Oilsands Review Project Status May 2013

Page 1

P R O J E C T STATUS

project status

05 13

Athabasca Region Industrial Heartland Region Cold Lake Region

Sourced from company releases, the Energy Resources Conservation Board and the Daily Oil Bulletin, with files from Strategy West. For changes and updates, please contact Deborah Jaremko at djaremko@junewarren-nickles.com. Disclaimer: Oilsands Review accepts no liability for errors or inaccuracies in the information provided in this report.

Peace River Region Northwestern Saskatchewan

For more detailed project data, visit oilsandsreview.com. To explore projects in the Athabasca oilsands region using our interactive web tool, visit the Canadian Oilsands Navigator at navigator.oilsandsreview.com.

CURRENT PROJECT

CAPACITY

START-UP

REGULATORY STATUS

NORTH ATHABASCA REGION

SASKATCHEWAN REGION

SOUTH ATHABASCA REGION

INDUSTRIAL HEARTLAND REGION

COLD LAKE REGION

NEW Export Pipelines

PEACE RIVER REGION

CURRENT PROJECT

New information this month

CAPACITY

START-UP

REGULATORY STATUS

NORTH ATHABASCA REGION — MINING

­

Canadian Natural Resources Limited

Suncor considers Voyageur South to be a “longer-term” project and has not confirmed a start-up date.

Horizon

Updated: Mar 2013

Canadian Natural says reliability at the Horizon plant continues to steadily improve. The company continues its strategy of staged, flexibly scheduled expansion to 250,000 barrels per day and work remains on track. Projects currently under construction are trending at or below estimates.

­

Voyageur South Phase 1

Updated: May 2012 120,000

TBD

Application

Syncrude Canada Ltd. Mildred Lake/Aurora

Updated: Mar 2013

­

Phase 1

135,000

2008

Operating

Canadian Oil Sands Limited says Syncrude is expected to produce between 105 million and 115 million barrels in 2013, incorporating a planned turnaround of Coker 8-1 in the second half of the year.

­

Phase 2A

10,000

2014

Construction

­

Base Mine Stage 1 & 2 Expansion

­

Phase 2B

45,000

TBD

Approved

­

Stage 3 Expansion

­

Phase 3

80,000

2017

Approved

­

­

Tranche 2

5,000

2012

Operating

­

290,700

1978

Operating

116,300

2006

Operating

Aurora South Train 1

100,000

2016

Approved

Aurora South Train 2

100,000

2018

Approved

Teck Resources Limited

Imperial Oil Limited Kearl

Frontier

Updated: Mar 2013

Updated: Mar 2013

­

Phase 1

110,000

2013

Construction

­

Phase 2

110,000

2015

Construction

Teck says it received the final supplemental information requests relating to the Frontier regulatory application in Q3/2012 and filed its responses in January 2013. The Canadian Environmental Assessment Agency estimates the federal review schedule for the project application to be approximately two years, so 2015 would be the earliest approval would be granted. A field exploration program is being developed for 2013 to acquire additional resource delineation and geotechnical information to support future engineering studies.

­

Phase 3 Debottleneck

70,000

2020

Approved

­

Phase 1

75,000

2021

Application

­

Phase 2

80,000

2024

Application

­

Phase 3

80,000

2027

Application

A decision from the federal joint review panel on the Jackpine project is expected in 2013.

­

Phase 4 Equinox

40,000

2030

Application

­

Phase 1A

100,000

2010

Operating

Total E&P Canada Ltd.

­

Phase 1B

100,000

TBD

Approved

­

Expansion

100,000

2017

­

Muskeg River

­

Commercial

155,000

2002

­

Expansion & Debottlenecking

115,000

TBD

­

Pierre River

Imperial Oil says construction on Phase 1 is complete and start-up activities are underway. The project is now expected to cost $12.9 billion, a $2-billion increase from previous estimates. At the end of Q4/2012, the company said Kearl Phase 2 was 27 per cent complete.

Shell Albian Sands ­

Jackpine

Updated: Dec 2012

Application Updated: Nov 2012

Joslyn North Mine

­

Phase 1

Operating

NORTH ATHABASCA REGION — IN SITU

Approved

Athabasca Oil Corporation

Updated: Aug 2012

­

Birch

A joint review panel of the Canadian Environmental Assessment Agency and ERCB has been established to review the proposed Pierre River mine project. The timeline for the joint review panel to submit its report is 550 days (18 months) from coming into force in July 2012.

­

Phase 1

Dover West Carbonates (Leduc)

­

Phase 1

100,000

2018

Application

­

Phase 2

100,000

TBD

Application

Suncor Energy Inc. •

Base Operations

Updated: Mar 2013

In March 2013, Suncor and Alberta Environment reported a release of process-affected water from its oilsands base plant into the Athabasca River, the result of a frozen and broken pipeline. The company says the incident is unacceptable and is investigating.

TBD

Updated: Dec 2012 Announced Updated: Mar 2013

AOS says it has completed a third production phase at its Dover West TAGD pilot, confirming the production of bitumen from between the two horizontal wellbores, indicating good mobilization at temperatures around 90 degress Celsius. AOS says it is very encouraged by these results and will seek corporate sanction of the demonstration project as soon as regulatory approval (anticipated this year) is received. ­

Phase 1 Demonstration

6,000

2015

­

Phase 2 Demonstration

6,000

TBD

­

Dover West Sands & Clastics

Application Application Updated: Dec 2012

4,000

2007

Operating

23,000

2008

Operating

In 2012, AOS acquired approximately 30,000 acres of oilsands leases contiguous to its existing Dover West assets. The company says its Dover West Sands project could now eventually support development up to 270,000 barrels per day. Regulatory approval and internal sanction for the first 12,000-barrel-per-day phase are expected in 2013. AOS says it is leveraging work done on FEED for its Hangingstone project for Dover West.

Operating

­

Phase 1

12,000

2015

Application

­

Phase 2

35,000

2018

Announced

­

Phase 3

35,000

2020

Announced

Steepbank Debottleneck Phase 3

­

Millennium Debottlenecking

­

North Steepbank Extension

180,000

2012

Fort Hills

Updated: Mar 2013

A sanction decision on Fort Hills is expected in the second half of 2013.

Debottleneck

12,000

Approved

Operating

­

­

2018

1967

Millennium Mine

Phase 1

100,000

294,000

­

­

Updated: Mar 2013

Project partner Suncor Energy says an updated timing for the Joslyn sanction decision will be made available when it is ready.

165,000

2016

Approved

­

Phase 4

35,000

2022

Announced

25,000

TBD

Approved

­

Phase 5

35,000

2024

Announced

MAY 2013 | OILSANDSREVIEW.COM 43


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Oilsands Review Project Status May 2013 by JWN | Trusted energy intelligence - Issuu