P R O J E C T S TAT U S
06 14 project status
Athabasca Region Industrial Heartland Region Cold Lake Region
Sourced from Alberta regulators and corporate disclosures. For changes and updates, please contact Deborah Jaremko at djaremko@junewarren-nickles.com. Disclaimer: Oilsands Review accepts no liability for errors or inaccuracies in the information provided in this report.
Peace River Region Northwestern Saskatchewan
CURRENT PROJECT
navigator.oilsandsreview.com
CAPACITY
START-UP
Suncor Energy Inc. Base Operations
For more detailed project data, visit oilsandsreview.com. To explore oilsands projects using our interactive web tool, visit the Canadian Oilsands Navigator.
Updated: Feb 2014
Suncor says that during the fourth quarter, maintenance was completed at its Upgrader 2 vacuum tower and related units. The company says that hot bitumen infrastructure commissioned in the third quarter of 2013 has increased the takeaway capacity of bitumen and unlocked additional mining production. Millennium Mine
294,000
1967
Operating
4,000
2007
Operating
Millennium Debottlenecking
23,000
2008
Operating
North Steepbank Extension
180,000
2012
Steepbank Debottleneck Phase 3 NORTH ATHABASCA REGION
SASKATCHEWAN REGION
SOUTH ATHABASCA REGION
INDUSTRIAL HEARTLAND REGION
COLD LAKE REGION
NEW EXPORT PIPELINES
PEACE RIVER REGION
NEW INFORMATION THIS MONTH
•
Fort Hills
CURRENT PROJECT
CAPACITY
START-UP
Suncor says that project activities in 2014 are expected to focus on the completion of detailed engineering, procurement across all areas of the project, and construction of mine and extraction infrastructure including pilings and foundations. Phase 1
160,000
2017
20,000
TBD
Voyageur South Phase 1
Horizon
Updated: Mar 2014
Canadian Natural says that Horizon achieved strong and reliable operating performance for all of 2013. The 2013 fourth-quarter production volumes of 112,273 barrels per day represent a 35 per cent increase from 2012 fourth-quarter levels, which the company says indicates a step-change in safe, steady and reliable production. The overall Phase 2/3 expansion is 34 per cent physically complete, and projects under construction continue to trend at or below cost estimates.
Phase 2A
Approved Updated: May 2012
120,000
TBD
Application
Syncrude Canada Ltd.
Canadian Natural Resources Limited
Reliability - Tranche 2
Construction
Suncor considers Voyageur South to be a “longer-term” project and has not confirmed a start-up date.
NORTH ATHABASCA REGION — MINING
Phase 1
Operating Updated: Feb 2014
Debottleneck REGULATORY STATUS
REGULATORY STATUS
•
Mildred Lake/Aurora
Updated: Apr 2014
Canadian Oil Sands Limited says that Syncrude Canada Ltd. has begun unplanned maintenance work on Coker 8-1 and it expects the work will overlap the turnaround of Coker 8-2 scheduled for the second quarter. Alberta has issued the final terms of reference for Syncrude’s MLX project. Base Mine Stage 1 & 2 Expansion
290,700
1978
Operating
Stage 3 Expansion
116,300
2006
Operating
TBD
Construction
135,000
2008
Operating
Centrifuge Tailings Management
5,000
2014
Construction
Aurora South Train 1
100,000
2016
Approved
12,000
2015
Construction
Aurora South Train 2
100,000
2018
Approved
TBD
2023
Announced
Phase 2B
45,000
2016
Construction
Phase 3
80,000
2017
Construction
Imperial Oil Limited Kearl
Updated: Feb 2014
Imperial Oil says that Kearl gross bitumen production continues to ramp up. Production was impacted during the fourth quarter by harsh winter weather and equipment reliability issues that are being addressed. Production rates of 100,000 barrels per day have been reached, and ongoing activities to stabilize performance at these higher levels are progressing. The Kearl expansion project was 72 percent complete at year-end and remains on target for a 2015 start-up. Phase 1
110,000
2013
Operating
Phase 2
110,000
2015
Construction
Phase 3
80,000
2020
Approved
Phase 4 Debottleneck
45,000
TBD
Approved
Shell Albian Sands
Mildred Lake Mine Extension (MLX) Teck Resources Limited Frontier
Updated: Dec 2013
Phase 1A
100,000
2010
Operating
Phase 1B
100,000
TBD
Approved
Expansion
100,000
2017
Approved
Muskeg River
Updated: Mar 2014
Minority partner Marathon Oil Corporation says its income from the Athabasca Oil Sands Project was significantly lower in the fourth quarter of 2013 compared to the third quarter of 2013, primarily as a result of lower price realizations. Commercial
155,000
2002
Expansion & Debottlenecking
115,000
TBD
Pierre River
Operating Approved Updated: Feb 2014
Shell has informed regulators that it is indefinitely halting work on the Pierre River project. The company has asked that the regulatory approval process be suspended.
Updated: Feb 2014
The Canadian Environmental Assessment Agency estimates the federal review schedule for the project application to be approximately two years, so 2015 would be the earliest approval would be granted. Teck says that an exploration program is planned at Frontier in the winter of 2014 to provide additional data to support the regulatory review process and ongoing engineering work. Phase 1
74,600
2021
Application
Phase 2
84,000
2024
Application
Phase 3
79,300
2027
Application
Phase 4 Equinox
39,400
2030
Application
Total E&P Canada Ltd. •
Joslyn North Mine
Updated: Apr 2014
A project amendment has been filed with the Alberta Energy Regulator and Alberta Environment to increase production to 157,000 barrels per day. Phase 1
Jackpine
TBD
100,000
2019
Approved
NORTH ATHABASCA REGION — IN SITU Athabasca Oil Corporation Birch
Updated: Mar 2014
Athabasca will be reducing its workforce by 15 per cent. The layoffs, focused primarily in its Calgary office, will largely affect employees directly or indirectly tied to projects that are not being funded in the near term. Phase 1
12,000
TBD
Dover West Carbonates (Leduc)
Announced Updated: Dec 2013
A fourth production cycle for the TAGD pilot test was scheduled for the fourth quarter of 2013. Athabasca had been encouraged by results so far. Phase 1 Demonstration
6,000
2016
Phase 2 Demonstration
6,000
TBD
Dover West Sands & Clastics
Approved Application Updated: Nov 2013
Athabasca Oil Corporation is awaiting regulatory approval for the Dover West Sands Phase 1.
Phase 1
100,000
TBD
On Hold
Phase 1
12,000
2016
Application
Phase 2
100,000
TBD
On Hold
Phase 2
35,000
2019
Announced