OSR Project List March 2012

Page 1

P r o j e c t S tAt u S

03.12 PROJECT STATUS

Athabasca Region Industrial Heartland Region Cold Lake Region

Sourced from company releases, the energy resources conservation Board and the Daily Oil Bulletin, with files from Strategy West. for changes and updates, please contact Deborah Jaremko at djaremko@junewarren-nickles.com. Disclaimer: oilsands review accepts no liability for errors or inaccuracies in the information provided in this report.

Peace River Region Northwestern Saskatchewan

CAPACITY

START-UP

SASkATCHEWAN REgION

SOUTH ATHABASCA REgION

INDUSTRIAl HEARTlAND REgION

COlD lAkE REgION

for even more details on all of these projects, visit www.oilsandsreview.com.

CURRENT PROJECT

NORTH ATHABASCA REgION

NEW EXPORT PIPElINES

PEACE RIVER REgION

REgUlATORY STATUS

NORTH ATHABASCA REgION — MININg

CURRENT PROJECT

NEW INfORMATION THIS MONTH

CAPACITY

REgUlATORY STATUS

START-UP

Suncor Energy Inc.

Canadian Natural Resources limited

Base Operations

Horizon

Updated: Nov 2011

Updated: Nov 2011

Suncor says that during the third quarter it completed construction and initiated commissioning of the

Canadian Natural says that SCO production safely resumed (post-January upgrader fire) in August,

hydrogen plant portion of the Millennium Naphtha Unit, and that the hydrotreater portion of the pro-

steadily growing to 108,000 barrels per day in October. Commissioning is underway on a third ore

ject was expected to be complete before the end of 2011. This project is designed to provide flexibility

preparation plant and associated hydrotransport, expected to increase reliability in 2012.

and boost sweet oil production, helping maximize profits. Suncor is also in the process of deploying

Phase 1 Phase 2A

TRO tailings management across its operations, to be complete by the fourth quarter of 2012.

135,000

2008

Operating

10,000

2014

Approved

Millennium Debottlenecking

2008

Operating

294,000

1967

Operating

180,000

2012

Construction

4,000

2007

Operating

Phase 2B

45,000

TBD

Approved

Millennium Mine

Phase 3

80,000

TBD

Approved

North Steepbank Extension Steepbank Debottleneck Phase 3

Imperial Oil limited

kearl

fort Hills

Updated: Jan 2012

Imperial says that Kearl Phase 1 is 87 per cent complete, and is progressing on schedule. Modules have

Debottleneck

assembly and integration into the plant facilities continues. Phase 2 sanctioned in December. 110,000

2012

110,000

2015

Construction

Phase 3 Debottleneck

70,000

2020

Approved

Jackpine

TBD 2016

Voyageur South Phase 1

Approved Approved Updated: Nov 2010

120,000

TBD

Application

Mildred lake/Aurora North & South

Updated: Jan 2012

The Canadian Environmental Assessment Agency is inviting public comment on a revised draft agreement to establish a joint panel for review of the Pierre River Mine project, as well as revisions to the existing joint panel agreement for the review of the Jackpine Mine Expansion project. Com-

Updated: Nov 2011

Canadian Oil Sands reports that front-end engineering and design is now complete for its $4.6-billion Mildred Lake mine train replacements. The target in-service date for the $1.6-billion Syncrude Emissions Reduction Project has now been extended into the first quarter of 2012.

ment is due February 24.

Aurora South Train 1

100,000

2016

Approved

Expansion

100,000

2017

Approved

Aurora South Train 2

100,000

2018

Approved

Phase 1A

100,000

2010

Operating

Base Mine Stage 1 & 2 Expansion

290,700

1978

Operating

Phase 1B

100,000

TBD

Approved

Stage 3 Expansion

116,300

2006

Operating

Commercial

155,000

2002

Operating

Expansion & Debottlenecking

115,000

TBD

Approved

Phase 1

100,000

2018

Application

Phase 1

Phase 2

100,000

TBD

Application

Joslyn South Mine

Muskeg River

Total E&P Canada ltd. Joslyn North Mine

SilverBirch Energy Corporation

Phase 1

frontier

Updated: Jan 2012

100,000

2018

Energy Corporation) with the former company’s in situ assets. Teck gains SilverBirch’s 50 per cent interest in Frontier.

Approved Updated: Dec 2010

100,000

TBD

Phase 1

57,250

TBD

On Hold

Phase 2

57,250

TBD

On Hold

12,000

TBD

Northern lights Mine

Teck Resources will acquire SilverBirch Energy and a new company will be spun out (SilverWillow

Phase 1

80,000

2021

Application

NORTH ATHABASCA REgION — IN SITU

Phase 2

80,000

2024

Application

Athabasca Oil Sands Corp.

Phase 3

80,000

2027

Application

Phase 4 Equinox

40,000

2030

Application

38 OILSANDS REVIEW | march 2012

Updated: Nov 2011

Project partner Suncor Energy says that current capital expenditures are around geological, engineering, regulatory and environmental studies.

Pierre River

25,000 165,000

Syncrude Canada ltd.

Shell Albian Sands

Phase 1

Construction

Phase 2

Updated: Nov 2011

Current capital expenditures for Fort Hills are around design base memorandum engineering.

been reduced in size and permits for additional U.S. interstate highway routes have been received. RePhase 1

23,000

Updated: Nov 2010

Birch Phase 1

Announced

Updated: Jan 2012 Announced


P r o j e c t S tAt u S

CURRENT PROJECT

CAPACITY

REgUlATORY STATUS

START-UP

Dover West Clastics

Updated: Jan 2012

CURRENT PROJECT

12,000

Birchwood

2015

Pilot

Application

Phase 2

35,000

2019

Application

Phase 3

35,000

2020

Application

Dover West leduc Carbonates

Updated: Jan 2012

Phase 1 Demonstration

6,000

2014

Application

Phase 2 Demonstration

6,000

TBD

Application

Canadian Natural Resources limited

REgUlATORY STATUS

Updated: Sep 2011 12,000

2016

Announced

Oak Point Energy ltd. lewis

Updated: Nov 2011

Oak Point Energy reports that engineering and procurement is ongoing. Pilot

AOSC says that TAGD piloting will continue through the end of the first quarter of 2012.

1,720

2013

Application

Southern Pacific Resource Corp. STP-Mckay

Updated: Dec 2011

Southern Pacific says several key pieces of the central processing facility have recently been installed on site, including evaporator towers, steam generation boilers, cogen turbines, heat recovery

Birch Mountain

Updated: Sep 2011

Phase 1

60,000

2022

Announced

Phase 2

60,000

2026

Announced

steam generators and components of the pipe rack assembly. The project remains on track for first steam in Q2/2012. The expansion application was filed in November 2011. The environmental impact assessment was filed in December 2011.

Cenovus Energy Inc.

START-UP

Marathon Oil Corporation

Application for the 12,000-barrel-per-day Phase 1 was filed in December 2011. Phase 1

CAPACITY

Telephone lake Borealis

Updated: Jan 2012

Cenovus has filed the environmental impact assessment for a 90,000-barrel-per-day phase commercial project at Telephone Lake. Phase A

45,000

TBD

Application

Phase B

45,000

TBD

Application

Dover Operating Corp.

Phase 1

12,000

2012

Construction

Phase 2A

12,000

2015

Application

Phase 2B

12,000

TBD

Application

Suncor Energy Inc. firebag

Updated: Nov 2011

Stage 3 cogen plant is nearing completion. Volumes from Stage 3 are ramping up and expected to boost production in 2012, along with new infill wells. Construction of infastructure, well pads, and central plant and cogeneration facilities continues on Firebag Stage 4.

Dover

Updated: Oct 2011

Cogeneration and Expansion

25,000

2007

Operating

Application

Stage 1

35,000

2004

Operating

Application

Stage 2

35,000

2006

Operating

Stage 3

62,500

2011

Operating

PetroChina has exercised its right to purchase the remaining 40 per cent of the MacKay River

Stage 3-6 Debottleneck

23,000

TBD

Application

project from former partner Athabasca Oil Sands Corp., marking the first time PetroChina will act as

Stage 4

62,500

2013

Construction

Stage 5

62,500

2018

Approved

Stage 6

62,500

2019

Phase 1 Subsequent Phases

50,000

2015

200,000

TBD

Mackay River

Updated: Jan 2012

project operator in the oilsands. ERCB project approval was granted in January 2012. Phase 1

35,000

2014

Approved

Phase 2

40,000

2017

Approved

lewis

Phase 3

40,000

2019

Approved

Phase 1

40,000

TBD

Application

Phase 4

35,000

TBD

Approved

Phase 2

40,000

TBD

Application

E-T Energy ltd.

Mackay River

Poplar Creek

Updated: May 2011

E-T has announced a deal (undisclosed value) with Total E&P Canada for ongoing testing, as well as

first quarter of 2012 are expected to offset natural declines. MR2

40,000

2016

Application

Phase 1

33,000

2002

Operating

Phase 1

10,000

2014

Application

Phase 2

40,000

2016

Announced

Sunshine Oilsands ltd.

1,000

2007

Operating

Harper

Updated: Jan 2012

Sunshine Oilsands is launching an initial public offering on the Hong Kong Stock Exchange, expected

Husky Energy Inc.

Updated: Nov 2011

Suncor says that new wells coming on stream at MacKay River in the fourth quarter of 2011 and the

$6.86 million in funding from the Climate Change and Emissions Management Corporation.

Pilot

Approved Updated: Dec 2010

Sunrise

Updated: Jan 2012

Husky says Phase 1 engineering remains on schedule and budget, the majority of the equipment has been purchased, more than 50 per cent of the well pairs are complete, piling for the central plant is underway, the 1,500-person construction camp is in progress, and contractors for the central plant and field facilities are on site. Design basis memorandum for Phase 2 has been awarded.

to raise up to $600 million. John zahary, former president and CEO of Harvest Operations Corp., has been appointed Sunshine’s new president and CEO. Carbonate Pilot

1,000

2011

legend lake

Operating Updated: Nov 2011

Sunshine Oilsands has filed its application for the Legend Lake SAGD project.

Phase 1

60,000

2014

Construction

Phase 1

10,000

2016

Application

Phase 2

50,000

2016

Approved

Phase 2

10,000

TBD

Announced

Phase 3

50,000

TBD

Approved

Phase 2 Expansion

10,000

TBD

Announced

Approved

Phase 3

20,000

TBD

Announced

Phase 3 Expansion

10,000

TBD

Phase 4

50,000

TBD

Ivanhoe Energy Inc. Tamarack

Updated: Nov 2011

Thickwood

Announced Updated: Nov 2011

Ivanhoe says that Alberta regulators have completed their initial review of the project application.

Sunshine Oilsands has submitted the regulatory application for its Thickwood SAGD project,

Answers to the first round of supplemental information requests were to be delivered to regulators

anticipating project start-up in 2015.

in Q4/2011. Project sanction remains subject to regulatory approval and financing.

Phase 1

10,000

2015

Phase 1

20,000

2013

Application

Phase 2

20,000

2017

Application Announced

Phase 2

20,000

TBD

Application

Phase 2 Expansion

20,000

2020

Announced

march 2012 | OILSANDSREVIEW.COM 39


P r o j e c t S tAt u S

CURRENT PROJECT

CAPACITY

START-UP

West Ells

REgUlATORY STATUS

CURRENT PROJECT

Updated: Jan 2012

Phase 3

Sunshine has received regulatory approval to proceed with a 10,000-barrel-per-day SAGD project at West Ells.

Pilot

START-UP

REgUlATORY STATUS

30,000

TBD

Announced

500

2011

Operating

CAPACITY

Canadian Natural Resources limited

Phase 1

5,000

2012

Approved

Phase 2

5,000

2013

Approved

Phase 3

40,000

2018

Announced

Phase 4

40,000

2024

Announced

Total E&P Canada ltd.

gregoire lake Phase 1

2024

grouse

Announced Updated: Nov 2011

Regulatory application is targeted for Q1/2012. Alberta Environment has issued its final terms of reference for the Grouse environmental impact assessment.

Joslyn

Updated: Dec 2010

Phase 2

Updated: Sep 2011 60,000

10,000

2006

Suspended

Value Creation Inc.

Commercial

40,000

2017

kirby (North)

Announced Updated: Jan 2012

CNRL has submitted the environmental impact assessment for all phases at Kirby North and South.

Terre de grace

Updated: Dec 2010

Phase 1

50,000

2016

Phase 2

30,000

2019

Application

Phase 1

40,000

TBD

Announced

Phase 2

40,000

TBD

Announced

Pilot

10,000

TBD

Approved

Canadian Natural says construction remains on track and on budget. The company has submitted

Alberta Oilsands Inc. Clearwater West

Updated: Dec 2011

Alberta Oilsands anticipates approval for the Clearwater West pilot in 2012, with construction to follow. Shabir Premji has retired as chairman and CEO, replaced by interim CEO Michael Lee and chairman Jack Crawford.

Pilot

Application Updated: Jan 2012

the environmental impact assessment for all phases of expansion at Kirby North and South.

SOUTH ATHABASCA REgION — IN SITU

Phase 2

kirby (South)

Phase 1

45,000

2013

Construction

Phase 2

15,000

2020

Application

30,000

2020

leismer Commercial

Updated: Dec 2010 Announced

Cenovus Energy Inc. 25,000

2016

Announced

4,350

2012

Application

Christina lake

Updated: Nov 2011

Construction of Phase D is 65 per cent complete, Cenovus reports, ahead of schedule and on budget. Construction has started on Phase E and earthworks is underway for Phase F.

Athabasca Oil Sands Corp. Updated: Jan 2012

Phase 1A

10,000

2002

Operating

AOSC says the engineering design basis memorandum is complete and certain long-lead items have

Phase 1B

8,800

2008

Operating

been procured, such as evaporators and boilers. Construction is targeted to start in late 2012.

Phase C

40,000

2011

Operating

Hangingstone

Phase 1

12,000

2014

Application

Phase D

40,000

2012

Construction

Phase 2

35,000

2017

Announced

Phase E

40,000

2013

Approved

Phase 3

35,000

2019

Announced

Phase F

40,000

2016

Approved

Phase G

40,000

2017

Approved

Phase H

40,000

2019

Hangingstone East Halfway Creek Exploratory Program

10,000

2014

Hangingstone Pilot Experimental Combustion Pilot

Approved Updated: Aug 2011

1,000

TBD

Application

Announced Updated: Nov 2011

Earthworks is nearing completion for Phases F-H. Detailed engineering, the installation of metal pilings and the pouring of concrete continue. Several pipe and equipment rack modules for Phase F are

BlackPearl Resources Inc.

foster Creek

Blackrod

Updated: Jan 2012

Alberta Environment is preparing the final terms of reference for the commercial project phases. BlackPearl says production at the pilot is now over 250 barrels per day with an instantaneous SOR

currently being assembled at Cenovus’ Nisku yard, with the first one already delivered to site. Phase A Phase B Debottleneck

24,000

2001

Operating

6,000

2003

Operating Operating

of just over 3:1. Expectations are production will reach between 500 and 800 barrels per day later

Phase C Stage 1

10,000

2005

this year.

Phase C Stage 2

20,000

2007

Operating

Phase 1

20,000

2016

Announced

Phase D

30,000

2009

Operating

Phase 2

30,000

TBD

Announced

Phase E

30,000

2009

Operating

SAGD well pads and pipelines specialists Learn more at projex.ca 40 OILSANDS REVIEW | march 2012


P r o j e c t S tAt u S

CURRENT PROJECT

Phase F

CAPACITY

45,000

START-UP

REgUlATORY STATUS

2014

Construction

CURRENT PROJECT

Pike

REgUlATORY STATUS

Updated: May 2011

Phase G

40,000

2015

Approved

Phase H

40,000

2016

Approved

the first half of 2012.

Phase I

45,000

2017

Announced

1A

35,000

2016

Announced

Updated: Nov 2011

1B

35,000

2017

Announced

1C

35,000

2017

Announced

with company expectations. Regulatory application is anticipated for the first phase of the project in

Cenovus and partner ConocoPhillips Canada anticipate a response from the ERCB regarding the Narrows Lake application in the second quarter of 2012.

grizzly Oil Sands Ulc

Phase 1

43,333

2016

Application

Phase 2

43,333

TBD

Application

Grizzly’s first phase is now under construction. Detailed engineering and design are complete, all

Phase 3

43,334

TBD

Application

to commence in Q1.

Pelican lake grand Rapids

Algar lake

Updated: Jan 2012

equipment is procured, Ledcor has commenced module assembly and SAGD well pair drilling is set

Updated: Jan 2012

Cenovus has filed the environmental impact assessment for a commercial project at Pelican-Grand Rapids.

Phase 1

5,650

2013

Construction

Phase 2

5,650

2014

Approved

Harvest Operations Corp.

Phase A

60,000

2017

Application

Phase B

60,000

TBD

Application

Harvest president and CEO John zahary has stepped down and will be replaced Myunghuhn yi as

Phase C

60,000

TBD

Application

600

2011

Operating

Pilot

Blackgold

Updated: Jan 2012

part of the transition of ownership to Korea National Oil Corporation.

Connacher Oil And gas limited

START-UP

Devon reports successful completion of 135 appraisal wells on its Pike lease, with results consistent

Narrows lake

CAPACITY

Phase 1

10,000

2014

Construction

Phase 2

20,000

2015

Application

Husky Energy Inc.

great Divide

Updated: Jan 2012

McMullen

Updated: Nov 2011

Connacher chairman and CEO Dick Gusella has relinquished his post. The company’s board has

Facilities commissioning is complete, and steam injection (the first phase of the process) began in

announced the initiation of a process to examine all potential strategies for the company going

September of 2011.

forward.

Air Injection Pilot-Experimental

755

2012

Construction

Algar Pod 2

10,000

2010

Operating

Japan Canada Oil Sands limited

Expansion

24,000

2014

Application

Pod 1

10,000

2007

Operating

JACOS owner Japan Petroleum Exploration is delaying a decision on an expansion at Hangingstone

Updated: Jan 2012

until mid-2012 due to a delay in regulatory approval.

ConocoPhillips Canada limited Surmont

Updated: Aug 2011

ConocoPhillips says it has received regulatory approval to increase production capacity of Phase 2 to 109,000 barrels per day, up from the previously approved 83,000 barrels per day.

Expansion

35,000

2015

Hangingstone Pilot

Application Updated: Aug 2011

JACOS owner JAPEX says regulatory approval for expansion is anticipated this fall, and an investment decision will follow.

Phase 1

27,000

2007

Operating

Phase 2

109,000

2015

Construction

1,200

1997

Operating

Pilot

Hangingstone

Pilot

11,000

1999

Operating

laricina Energy ltd. germain

Updated: Dec 2011

Civil site construction is complete. Well pair drilling has commenced. Procurement, engineering and

Devon Canada Corporation Jackfish

Updated: Dec 2011

Devon reports that Jackfish 3 construction is now underway, and that Jackfish 2 volumes are ramping up ahead of plan and on target to reach capacity of 35,000 barrels per day by late 2012.

module fabrication continues. Laricina has commenced an expansion of its camp to support project construction. Laricina has submitted the environmental impact assessment for its 150,000-barrelper-day expansion at Germain. 5,000

TBD

Construction

Phase 1

35,000

2007

Operating

Phase 1 Commercial Demonstration Phase 2

30,000

2015

Application

Phase 2

35,000

2011

Operating

Phase 3

60,000

TBD

Application

Phase 3

35,000

2015

Construction

Phase 4

60,000

TBD

Application

Putting rock theory Putting rock theory into practice into practice Discover how we transform seismic to success.

oilsandsimaging.com | 400, 736-8 Ave SW Calgary | 1.403.237.6686

Discover how we transform seismic to success.

oilsandsimaging.com | 400, 736-8 Ave SW Calgary | 1.403.237.6686 march 2012 | OILSANDSREVIEW.COM 41


P r o j e c t S tAt u S

CURRENT PROJECT

CAPACITY

REgUlATORY STATUS

START-UP

Saleski

Updated: Nov 2011

Laricina says the Saleski pilot sold 26,300 barrels of bitumen as of the end of Q3 in 2011. Pilot testing continues with an additional steam cycle added to each operating pair. The company has received regulatory approval for the addition of a second steam generator. The Phase 1 application continues to move through the regulatory process, and now first steam is targeted for early 2014 rather than late 2013. Phase 1 Pilot

10,700

2014

Application

1,800

2011

Operating

MEg Energy Corporation Christina lake

On Hold

Pilot

1,900

2006

Suspended

May River

Updated: Jan 2012

Public hearing to be held in March. Regulatory approval anticipated in mid-2012. Engineering, timelines and internal approval to be finalized post-regulatory approval.

Corner

40,000

2015

Approved

Corner Expansion

40,000

TBD

Application

Hangingstone

20,000

TBD

Application

Leismer Commercial

10,000

TBD

Approved

Application

Leismer Demonstration

10,000

2010

Operating

Application

Leismer Expansion

20,000

TBD

Approved

Updated: Dec 2010

Leismer Northwest

20,000

TBD

Application

20,000

TBD

Application

Phase 2B

35,000

2013

Construction

2016

Application

2018 2020

Statoil kai kos Dehseh

Updated: Aug 2011

Phase 1

50,000

2018

Announced

Leismer South

Phase 2

50,000

TBD

Announced

Thornbury

40,000

TBD

Application

Thornbury Expansion

20,000

TBD

Application

Updated: Aug 2011

Suncor Energy Inc.

40,000

TBD

N-SOlV Corporation Dover

N-Solv and partner Suncor Energy have been granted funding from the Government of Canada under Sustainable Development Technology Canada to develop the N-Solv pilot. Demonstration Plant

500

2012

Announced

Nexen Inc.

TBD

Disclosed

Operating

Surmont

1,900

Application

2009

50,000

Updated: Oct 2011

Expansion

TBD

22,000

Phase 3C

Conklin (Whitesands)

2013

Phase 2A

50,000

Petrobank Energy And Resources ltd.

10,000

Operating

Phase 3B

REgUlATORY STATUS

90,000

2008

50,000

START-UP

Subsequent Phases

3,000

Phase 3A

CAPACITY

Phase 1

Updated: Nov 2011

MEG says that production at Christina has quickly bounced back to capacity following a turnaround. It has completed the connections for two new steam generators and the tie in of two infill wells and four new well pairs to existing operations. Detailed engineering on Phase 2B is 84 per cent complete and construction is 22 per cent complete, remaining on time and on budget. Phase 1 Pilot

CURRENT PROJECT

long lake

Updated: Jan 2012

Nexen CEO Marvin Romanow and EVP Canada Gary Nieuwenburg have stepped down. Kevin

Chard Phase 1 Meadow Creek Phase 1

40,000

TBD

Approved

Phase 2

40,000

TBD

Approved

TriStar

Long Lake South (Kinosis) Phase 1

40,000

TBD

Approved

Long Lake South (Kinosis) Phase 2

40,000

TBD

Approved

Phase 1

72,000

2008

Operating

Phase 2

72,000

TBD

Approved

COlD lAkE REgION — IN SITU

Phase 3

72,000

TBD

Application

Canadian Natural Resources limited

Phase 4

72,000

TBD

Announced

Paramount Resources ltd.

Updated: Jan 2011

Value Creation is providing the ERCB with additional information supporting its application. Pilot

1,000

2012

Primrose/Wolf lake

Application

Updated: Nov 2011

Canadian Natural plans five new pads at Primrose East and three new pads at Primrose South

Hoole

Updated: Nov 2011

Paramount is spinning off its oilsands assets, including Hoole and carbonate leases, into a new firm called Pixar Petroleum Corp. The company says the majority of work necessary for the Hoole regulatory application has been completed, together with preliminary front-end engineering and design, reservoir modelling and simulation.

42 OILSANDS REVIEW | march 2012

Announced Updated: Dec 2010

Value Creation Inc.

Reinhart, previously CFO, will become interim president and CEO.

Commercial

Updated: Dec 2010

35,000

2015

Announced

in 2012. Primrose East

32,000

2008

Operating

Primrose North

30,000

2006

Operating

Primrose South

45,000

1985

Operating

Wolf Lake

13,000

1985

Operating


P r o j e c t S tAt u S

CURRENT PROJECT

CAPACITY

START-UP

REgUlATORY STATUS

Husky Energy Inc.

Updated: Nov 2010 10,000

TBD

Tucker

Approved Updated: Jan 2012

Production at Tucker has increased significantly, exiting 2011 at over 9,000 barrels per day versus 4,000 barrels per day the previous year. Phase 1

30,000

2006

Updated: Jan 2012

Cold Lake established a production record in 2011, averaging 160,000 barrels a day, compared to the previous annual record of 154,000 barrels a day in 2007.

Phase 11-13 Phase 14-16

110,000 30,000 30,000

1985 2002 2015

Updated: Jan 2012

reservoir modelling for a proposed horizontal cyclic steam stimulation pilot at Sawn Lake, concluding the project would yield commercial viable extraction. Deep Well is currently preparing a pilot plan and options for capitalization. CSS Pilot

700

TBD

Approved

Dawson

development is being considered, targeting regulatory filing in Q3. Phase 2

Operating

THAI Demonstration-Experimental

Approved

Updated: Jan 2012

Petrobank says the Dawson THAI pilot is 75 per cent complete and will be complete in Q2. Full field 10,000

TBD

Announced

TBD

TBD

Construction

Royal Dutch Shell plc Peace River

gemini

Updated: Nov 2011

impact assessment report for the Carmon Creek expansion. Cadotte Lake

10,000

TBD

Application

Carmon Creek - Phase 1

1,200

TBD

Application

Carmon Creek - Phase 2

Osum Oil Sands Corp.

Updated: Dec 2011

Alberta’s environmental assessment director has deemed complete Shell Canada’s environmental

on February 22, 2012.

Sawn lake

Operating

The ERCB will hold a public hearing on the proposed Gemini project in Cold Lake, Alta.,

Pilot

REgUlATORY STATUS

Company owner Deep Well Oil & Gas says DeGolyer & MacNaughton Canada has completed its

koch Exploration Canada Corporation

Commercial

START-UP

Petrobank Energy And Resources ltd.

Cold lake

Phase 1-10

Operating

Imperial Oil limited

CAPACITY

Northern Alberta Oil ltd.

Caribou Demonstration

CURRENT PROJECT

12,500

1986

Operating

40,000

2015

Application

40,000

TBD

Application

Southern Pacific Resource Corp.

Taiga

Updated: Jan 2012

Red Earth

Updated: Nov 2011

Osum has completed a $500-million private placement. The company has raised in excess of $1 billion

Southern Pacific reactivated the project earlier this year and is currently testing three different

in private equity since inception.

wellbores with different cyclic steam stimulation configurations.

Phase 1

23,000

2014

Application

Commercial

10,000

TBD

Announced

Phase 2

22,000

2016

Application

Pilot

1,000

2009

Operating

Pilot Expansion

3,000

TBD

Announced

Pengrowth Energy Corporation lindbergh

Updated: Nov 2011

Surface engineering and procurement are underway. Drilling of two SAGD well pairs has begun, with first steam planned for January 2012. Submission of regulatory application for the commercial project is anticipated in late 2011 or early 2012. Commercial Pilot

12,500

TBD

Announced

1,200

2012

Approved

Oilsands Quest Inc.

Axe lake

Orion

Updated: Dec 2010

Phase 1

10,000

2007

Operating

Phase 2

10,000

TBD

Approved

Updated: Jan 2012

Oilsands Quest has entered into a solicitation process looking for offers to acquire or restructure the company. Commercial

Royal Dutch Shell plc

TBD

On Hold

Reservoir Test

30,000 600

2008

On Hold

SAGD Pilot

TBD

TBD

On Hold

NORTH ATHABASCA REgION — UPgRADER Canadian Natural Resources limited

PEACE RIVER REgION — IN SITU

Horizon

Andora Energy Corporation Sawn lake

Updated: Nov 2011

Andora Energy majority owner PanOrient Energy Corp. says the previously announced strategic review continues, but no bids have been received either to purchase the company or to farm in to the asset. The process continues. SAGD Demonstration

SASkATCHEWAN REgION — IN SITU

1,400

TBD

Approved

Updated: Nov 2011

Canadian Natural says that SCO production safely resumed (post-January upgrader fire) in August of 2011, steadily growing to 108,000 barrels per day in October. Commissioning is underway on a third ore preparation plant and associated hydrotransport, expected to increase reliability in 2012. Phase 1 Phase 2A

114,000

2009

Operating

10,000

2014

Approved

march 2012 | OILSANDSREVIEW.COM 43


P r o j e c t S tAt u S

CURRENT PROJECT

CAPACITY

START-UP

REgUlATORY STATUS

CURRENT PROJECT

Shell Albian Sands

Phase 2B

45,000

TBD

Approved

Phase 3

80,000

TBD

Approved

Ivanhoe Energy Inc. Tamarack

Updated: Nov 2011

34,784

2014

Application

Base Operations

Updated: Nov 2011

Suncor says that during the third quarter it completed construction and initiated commissioning of the hydrogen plant portion of the Millennium Naphtha Unit, and that the hydrotreater portion of the project was expected to be complete before the end of 2011. This project is designed to provide flexibility and boost sweet oil production, helping maximize profits. Suncor is also in the process of deploying TRO tailings management across its operations, to be complete by the fourth quarter of 2012.

Millennium Vacuum Unit U1 and U2

97,000

2008

35,000

2005

225,000

1967

fort Hills

Operating Operating Operating Updated: Nov 2011

Current capital expenditures for Fort Hills are around design base memorandum engineering. Phase 1

145,000

TBD

Approved

Phase 2 & 3

145,000

TBD

Approved

Voyageur Upgrader 3

Updated: Nov 2011

Current capital expenditures are around remobilizing the workforce, confirming current design and modifying project execution plans.

REgUlATORY STATUS

Updated: Dec 2011

2011. Engineers will now focus on improving operating efficiencies and adding capacity through debottlenecking. Alberta’s environmental impact assessment director has deemed complete the environmental impact assessment report for Shell Canada’s Quest carbon capture and storage project from the Scotford upgrader. Commercial

158,000

2003

91,000

2011

Scotford Upgrader 2

Operating Operating Updated: Nov 2010

Shell withdrew its application for all phases of Scotford Upgrader 2 in fall 2010. Phase 1

97,750

TBD

Cancelled

Phase 2

97,750

TBD

Cancelled

Phase 3

97,750

TBD

Cancelled

Phase 4

97,750

TBD

Cancelled

Statoil Strathcona

Updated: Mar 2010

Application withdrawn in December 2008. Phase 1

65,000

TBD

Cancelled

Phase 2

152,000

TBD

Cancelled

Total E&P Canada ltd. Northern lights

Updated: Nov 2010

Phase 1

127,000

2017

Approved

Previous project owner Synenco Energy withdrew the Northern Lights upgrader application in June

Phase 2

63,000

TBD

Approved

2008. Total purchased Synenco in August 2008.

Syncrude Canada ltd. Mildred lake/Aurora North & South

Updated: Nov 2011

Canadian Oil Sands reports that front-end engineering and design is now complete for its $4.6-billion Mildred Lake mine train replacements. The target in-service date for the $1.6-billion Syncrude Emissions Reduction Project has now been extended into the first quarter of 2012. Base Plant Stage 1 & 2 Debottleneck Stage 3 Debottleneck Stage 3 Expansion (UE-1)

250,000

1978

Operating

75,000

TBD

Announced

100,000

2006

Operating

Value Creation Inc. Terre de grace Phase 1 Phase 2 Pilot

Updated: Dec 2010 33,600

TBD

Announced

33,600

TBD

Announced

8,400

TBD

Approved

SOUTH ATHABASCA REgION — UPgRADER Nexen Inc.

Scotford Upgrader 1

Expansion

Suncor Energy Inc.

Millennium Coker Unit

START-UP

The first commercial production from the Scotford upgrader expansion was announced in May

Ivanhoe says that Alberta regulators have completed their initial review of the project application. Answers to the first round of supplemental information requests are being prepared, to be delivered to regulators in Q4/2011. Project sanction remains subject to regulatory approval and financing. Phase 1

CAPACITY

long lake

Updated: Jan 2012

Nexen CEO Marvin Romanow and EVP Canada Gary Nieuwenburg have stepped down. Kevin Reinhart, previously CFO, will become interim president and CEO. Phase 1

58,500

2008

Operating

Phase 2

58,500

TBD

Approved

Phase 3

58,500

TBD

Announced

Phase 4

58,500

TBD

Announced

Value Creation Inc.

50,600

TBD

Cancelled

Phase 2

50,600

TBD

Cancelled

Strathcona

Debottlenecking

46,000

TBD

Cancelled

Phase 1

138,000

TBD

Cancelled

Phase 2

87,000

TBD

Cancelled

Value Creation Inc. Heartland

840

TBD

Application

INDUSTRIAl HEARTlAND REgION — UPgRADER

Updated: Nov 2010

Construction was suspended in September 2008. Phase 1

46,300

TBD

On Hold

Phase 2

46,300

TBD

Approved

Phase 3

46,300

TBD

Approved

NEW EXPORT PIPElINES Enbridge Northern gateway

Updated: Dec 2011

The federal joint-review panel into the Northern Gateway project has confirmed the schedule for community hearings up to early April 2012. 525,000

Updated: Jan 2011

Value Creation is providing the ERCB with additional information supporting its application.

Updated: Dec 2010

Total says it will not proceed with its Strathcona upgrader.

Alberta to Kitimat, B.C.

TriStar

Pilot

Phase 1

plus 70,000

2017

Application

diluent line kinder Morgan Canada Trans Mountain Expansion (TMX)

Updated: Nov 2011

Expansion open season began on Oct. 20, 2011, and ended on Jan. 19, 2012.

North West Upgrading Inc.

Edmonton to Burnaby, B.C., Washington Expansion up

Redwater Upgrader

Updated: Sep 2011

Final sanction was anticipated to be late 2011 or early 2012. Alberta’s Industrial Heartland Association expects to see activity ramping up this fall, including moving project management trailers onto the site, improvements to the approaches to the site and some site grading.

State and offshore

to 700,000

n/q

Announced

TransCanada Pipelines keystone Expansion

Updated: Nov 2011

Phase 1

77,000

2013

Approved

Approval by U.S. Department of State delayed pending review of revised route. The decision is now

Phase 2

77,000

2018

Approved

not expected until 2013.

Phase 3

77,000

TBD

Approved

44 OILSANDS REVIEW | march 2012

Cushing, Okla., to U.S. Gulf Coast

500,000

TBD

Announced