Oilsands Review Project Status June 2012

Page 1

PROJECT STATUS

06.12 PROJECT STATUS

Athabasca Region Industrial Heartland Region Cold Lake Region

Sourced from company releases, the Energy Resources Conservation Board and the Daily Oil Bulletin, with files from Strategy West. For changes and updates, please contact Deborah Jaremko at djaremko@junewarren-nickles.com. Disclaimer: Oilsands Review accepts no liability for errors or inaccuracies in the information provided in this report.

Peace River Region Northwestern Saskatchewan

NORTH ATHABASCA REGION

For even more details on all of these projects, visit www.oilsandsreview.com.

CURRENT PROJECT

CAPACITY

START-UP

SOUTH ATHABASCA REGION

INDUSTRIAL HEARTLAND REGION

COLD LAKE REGION

NEW Export Pipelines

PEACE RIVER REGION

REGULATORY STATUS

CURRENT PROJECT

NORTH ATHABASCA REGION — MINING

­

Voyageur South

Canadian Natural Resources Limited

­

Phase 1

­

Horizon

Updated: Apr 2012

Canadian Natural reports that it has successfully completed unplanned maintenance on the fractionating unit in its primary upgrading facility and started up operations. The outage lasted from February 5 to March 13. ­

Phase 1

135,000

2008

Operating

­

Phase 2A

10,000

2014

Approved

­

Phase 2B

45,000

TBD

Approved

­

Phase 3

80,000

TBD

Approved

­

Tranche 2

5,000

2012

Operating

Imperial Oil Limited •

Kearl

Updated: May 2012

Imperial Oil says that construction of Kearl Phase 1 is 90 per cent complete and is progressing to expected start-up in late 2012. ­

Phase 1

110,000

2012

Construction

­

Phase 2

110,000

2015

Construction

­

Phase 3 Debottleneck

70,000

2020

Approved

Shell Albian Sands ­

Jackpine

Updated: Jan 2012

The Canadian Environmental Assessment Agency recently invited public comment on a revised draft agreement to establish a joint panel for review of the Pierre River mine project, as well as revisions to the existing joint panel agreement for the review of the Jackpine mine expansion project.

2016

Approved

100,000

2018

Approved

­

Base Mine Stage 1 & 2 Expansion

290,700

1978

Operating

­

Stage 3 Expansion

116,300

2006

Operating

Teck Recources Limited ­

Frontier

­

Phase 1

75,000

2021

Application

­

Phase 2

80,000

2024

Application

­

Phase 3

80,000

2027

Application

­

Phase 4 Equinox

40,000

2030

Application

Total E&P Canada Ltd. •

Joslyn North Mine

­

Phase 1

­

Joslyn South Mine

­

Phase 1B

100,000

TBD

­

Phase 1

Muskeg River

­

2002

­

Expansion & Debottlenecking

115,000

TBD

­

Pierre River

­

Phase 1

100,000

2018

Application

­

Phase 1

­

Phase 2

100,000

TBD

Application

Dover West Clastics

­

Millennium Mine

­

North Steepbank Extension

­

Steepbank Debottleneck Phase 3

Fort Hills

Approved Updated: Dec 2010

100,000

TBD

Birch

155,000

Millennium Debottlenecking

2018

Announced

Athabasca Oil Sands Corp.

Commercial

­

100,000

NORTH ATHABASCA REGION — IN SITU

­

Suncor is now mining volumes from the North Steepbank Extension. The company expects that its Millennium Naphtha Unit (MNU) project will be fully operational by mid-year. In April, Suncor announced its upgrader had successfully returned to normal operations following a brief shutdown due to a fractionated performance issue. Suncor has started commissioning assets associated with its tailings reduction operations infrastructure project and anticipates to start using these assets during Q2.

Updated: May 2012

Project partner Suncor Energy says that current capital expenditures are around further design work, drilling and site preparation. The partners plan to submit development plans to their respective boards of directors for sanction in 2013.

Operating

Updated: May 2012

Updated: Apr 2012

The Canadian Environmental Assessment Agency has announced that a period of public comment is underway and participant funding is being allocated. Comments are being accepted until June 4.

Approved

Base Operations

Updated: May 2012

100,000

2010

Suncor Energy Inc.

Application

Aurora South Train 2

2017

Approved

TBD

Aurora South Train 1

100,000

Updated: Jan 2012

Updated: Nov 2010 120,000

­

100,000

Operating

REGULATORY STATUS

­

Phase 1A

Shell has purchased a 1,820-acre tract of land near Grand Prairie, Alta., to conserve as boreal forest habitat on behalf of its oilsands operations. It will be called the Shell True North Forest.

START-UP

Mildred Lake/Aurora North & South

Expansion

Approved

CAPACITY

Construction is underway on a number of major projects including mine train replacement and relocation, the Aurora North Tailings Management Project, the Syncrude Emissions Reduction Project and the Centrifuge Tailings Management Project.

­

Updated: May 2012

New information this month

Syncrude Canada Ltd.

­

SASKATCHEWAN REGION

Updated: Apr 2012

AOSC says the updated contingent resources on its Birch holdings total 1.9 billion barrels. The company plans to submit its Birch regulatory application in late 2012 based on additional drilling and 3-D seismic. 12,000

TBD

Announced Updated: May 2012

AOSC says construction of an all-weather access road to the Dover West area is 85 per cent complete, with one bridge remaining to be built. Completion is expected in Q3. ­

Phase 1

12,000

2015

Application

­

Phase 2

35,000

TBD

Announced

­

Phase 3

35,000

TBD

Dover West Leduc Carbonates

Announced Updated: May 2012

2008

Operating

AOSC says production testing continues while it works on the TAGD pilot. An update from the TAGD proof of concept is expected in Q2. The company has responded to the first round of supplemental information requests from regulators and has launched work on its design basis memorandum.

294,000

1967

Operating

­

Phase 1 Demonstration

6,000

2014

Application

180,000

2012

Operating

­

Phase 2 Demonstration

6,000

TBD

Application

4,000

2007

Operating

BP p.l.c. 10,000

TBD

23,000

Updated: May 2012

­

Terre de Grace

Suncor says current work on Fort Hills includes progressing design basis memorandum engineering, site preparation and procurement for long-lead items. The company and its partner plan to submit development plans to their respective boards of directors for sanction in 2013.

­

Pilot

­

Debottleneck

­

Phase 1

Updated: Mar 2012 Approved

Canadian Natural Resources Limited ­

Birch Mountain

25,000

TBD

Approved

­

Phase 1

60,000

2022

Updated: Mar 2012 Announced

165,000

2016

Approved

­

Phase 2

60,000

2026

Announced