group 4
CSI i d e a
&
d e s i g n
p r o p o s a l
site observation
L A C K O F WAY F I N D I N G lifts do not go to each floor, but instead every 3rd floor floor number is not indicated on any of the floors this might cause residents to be confused at times about which floor they are on
site observation
L A C K O F WAY F I N D I N G units of the flats do not have unit number indicated can be seen on mailboxes @ ground floor
engagement on site
INTERVIEW Lifts do not show floor number. Residents get confused even he stayed there for a long time Usage of the stairs. Stairs are dirty and smelly. Many things can be found on the stairs: mattress, bottles, etc. Signage. Wants handmade and unique signages. Eg. the one way road signs looks boring. The playground looks incomplete. Should have more play structures for the children. Urban farming. Is ok with this idea. As of now, the vegetable garden is taken care by the person in charge of the refuse collection center. Mr Zul says the community could contribute money to upkeep the garden,
group 4
PROPOSAL
w a y fi n d i n g + g r e e n e r i e s
proposal
VERTICAL PLANTING FLOOR SIGNS combination of urban farming/greenery and wayfinding/signage ‘green signage’
proposal
G R E E N
S I G N A N G E
not only act as signage but also beautify each floor makes it lively and may contribute to more pleasant odour act as a community project as each residents of the specific floors need to work together to take care of the plants (e.g. schedule watering of plants) plants dying = floor residents not working together planter box are removable so it can be arranged and customized modular, easy to assemble
proposal
proposal
AROUND THE LIFT LOBBY
proposal
L O C AT I O N lift lobbies beside the lifts (right side when you exit from the lift)
Targeted floors: Ground floor, 8th floor, 12th floor
proposal
PLANT SUGGESTED mother in law tongue
proposal
Wire mesh (1000mm x 1400mm)
CONSTRUCTION D E TA I L
Timber frame (1045mm x 1445mm)
Nail
L-bracket screwed on timber frame as bracing
L-bracket screwed to wall and timber frame
proposal
Wire mesh
CONSTRUCTION D E TA I L Pots will be hooked on the wire mesh with pot clips.
L-bracket screwed to wall L-bracket screwed on timber frame
proposal
1000 mm
1400 mm
1200 mm
DIMENSIONS The outline of the number is painted on the wire mesh.
1400 mm
The location of the plants are marked with the diagonal box
8TH FLOOR (wooden block)
12TH FLOOR (paint)
GROUND FLOOR (plants)
proposal
E S T I M AT E D B U D G E T
QUANTITY
PRICE x QUANTITY
Timber (3m long, 45mmx18mm – RM 11)
7
RM 77.00
Wire mesh (0.5 inch x 0.5 inch) per meter
4
RM 46.00
Mother in law tongue plant (without pot) x 3
4
RM 40.00
Plastic pots (no hook)
12
RM 21.60
Nails, Screws and other adhesive (per packet)
2
RM 5.00
Bucket paint (per can)
2
RM 100.00
Shellac (per can)
1
-
ITEM
TOTAL
289.00
proposal
TIMELINE 28th May 2018 | Monday - Meet Ms Sze Ee for tutorial - Buy the materials - Cut wood at workshop (filming) - Ask for plants (Joy)
29th May 2018 | Tuesday (public holiday) - Assemble mock-up at studio (filming) - Framework + wire mesh + L brackets
30th May 2018 | Wednesday - Continue assembling mock up (filming) - Put plants in pots, Paint/Shellac job
1st June 2018 | Friday - Any amendment for the signage. To complete
3rd June 2018 | Sunday - Present to PPR residents - Filming footage for the video
group 4
chin man choong clara lee pei lin joy ann lim ee hsien kennett lim roong xiang shazleen shafiqah wong teck poh yee mae yuen
0324509 0324495 0327592 0325031 0324367 0327462 0328561