Fit Out Briefing and Safety Induction

Page 1

FIT-OUT BRIEFING DATE: _________________________

TENANT: ________________________

Time: __________________________

LOT NO: _________________________

Attendance Name List:

No.

Name

I/C No.

Company Name

CMCO period are allow to work as follow: Noisy Works, Smelly, Bulky Item Transport & Hot works: 6am~10:00am FIT-Out (General) (To carry-out before the operation hours, it is not allowed during the Time allowed is night works from 10:30pm – 7:00am operation hours) Hoarding board to be constructed full height, 2 feet away from lease line, to cover on top of hoarding/ neighboring tenant sect ions At the door: To paste work permit, schedule and insurance cover notes Behind door: To paste oil approved drawings Flooring – to lay a layer of 0.25mm thk polythene sheet with overlapping 1m for all joint before screeding Sprinkler works must be carried out by panel Marak Teguh - Mr. Hairul: 012-7107627 Water proofing work Gas piping works must be carried out by panel contractor, R&Y Engineering and Construction Sdn Bhd Mr. Kenny Yong J.K: 012-302 3360 / 012-288 3087 Insurance Cover Note to cover Contractor All Risk (2M Third Public Liability) and Workmen Compensation. The Insurance shall maintain in the joint names of the Landlord, the Tenant, and the Main Contractor.(Please See Sample Attachment) To inform Fit-Out Dept. at least three (3) days in advance to arrange Hoarding Inspection, Close Ceiling Inspection, Water Ponding Test, and Pre-Opening Inspection, Final Inspection or etcs. To secure the lot by using numbering padlock and ensure it is locked when there’s no activities on site. To extend padlock number to Fit Out Dept. for monitoring and safety purpose Deliver - loading Iunloading pathway route (Loading Bay 2 / Loading Bay 5) Contractors to touch up and make good Landlord common area ceiling, wall and floor if damage found and caused by the renovation

M&E (Electricity) Power supply ·to install temporary distribution board All electrical installation work must be carried out according to the approved drawing No illegal electrical tapping is allowed to be carried out on the common area lighting and power supply Relocation of DB, POS, and TELEPHONE ·to submit drawing to Management for approval All electrical fitting must be installed with SIRIM approval All electrical conduits must be painted with electrical code orange and must use G.I metal conduit Lighting density must not exceed 18 watt/m2 M&E (ACMV) To install three phase supply to the FCU control unit by tenant No illegal air-conditioned duct tapping allowed to be carried out at common area air-conditioned duct system Fan coil unit is not allowed to be painted Tenant aircon contractor must carry out the air balancing work after the completion All existing ventilation air louvers must be relocated, if install with new back drop wall For the F&B tenant,the lot is supplied with chilled water point. Tenant need to install their own fan coil unit and the FCU control panel M&E (Plumbing) Water meter to be installed horizontally within eye level range 1.5m Temporary water supply direct from water inlet valve (inside lot). Make sure no water ponding inside the premises and to remain dry to avoid leaking to another floor


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.