UNDERGROUND STORAGE TANKS DIVISION 5 PERMIT FEES Fees for Special Services are $337 / hour Effective July 21, 2022 L.A.M.C. 57.105.7.8 Tank Installation: Plan Check, Inspection, Soil Report Review

Tank Abandonment by Removal: Plan Check, Inspection, Soil Report Review

Tank Abandonment-in-Place: Plan Check, Inspection, Soil Report Review

Tank System Major Modification or Repair, Add to Alter: Plan Check, Inspection, Soil Report Review

$4,044 12 hr. minimum* $3,033 9 hr. minimum* $1,002 for each addt’l tank 3 hr. minimum* $3,033 9 hr. minimum* $1,011 for each addt’l tank 3 hr. minimum* $4,044 12 hr. minimum*

Tank Entry Relining Repairs: Plan Check, Inspection, Soil Report

$2,022 6 hr. minimum*

Tank System Minor Modification or Repair: Plan Check, Inspection

$1,011 3 hr. minimum*

Tank System Minor Repair Performed During Routine Inspection

$337 1 hr. minimum*

Soil Report Review: Business Initiated Reports or Business Requests for No Further Action (Inspector Review of File)

$3,033 9 hr. minimum*

Expedite Plan Check or Site Assessment: In addition to D5 permit

Contractor Changes, Additional Plan Check (L.A.M.C. 57.105.7.8.2)

$480 4 hr. minimum** Addition to original permit $337 1 hr. minimum*

*If additional time is required for Fire Department processing, the responsible party will be billed at the current hourly rate in effect. ** Expedite hourly rate is $120 / hour If additional time is required for Fire Department processing, the responsible party will be billed at the current hourly rate in effect.