Wilshire/Fairfax decking 2017

metro

metro.net/purplelineext

We’re building the future, right under your feet. purple line extension transit project

winter 2017

Wilshire/Fairfax Decking

Purple Line

A


B

metro

Larchmont Chronicle

Wilshire/Fairfax decking 2017

Wilshire/Fairfax Decking: What You Need to Know what is decking? The Purple Line Extension Transit Project has been engaged in construction activities along Wilshire Bl and Fairfax Av since May 2014. Work began with advanced utility relocation (AUR), followed by major subway construction in late 2016 with pile installation. The underground piles will provide structural support for the excavation of the subway station box at Wilshire/Fairfax. The next step following piling is decking. Decking is a construction process that entails excavating the street and sidewalks, and replacing them with temporary concrete deck panels on top. This will allow traffic to continue to flow, while maintaining access to sidewalks and driveways as construction continues underground. In the Wilshire/Fairfax area, decking will occur on Wilshire Bl stretching from Odgen Dr, thru the Fairfax Av intersection, to San Diego Wy. This work – excavating Wilshire Bl and placing steel beams and deck panels across the street – will occur over 18 weekends starting in February 2017. Sidewalk access will be maintained; however, some infrequent closures may occur depending on the nature of the work.

work is scheduled in three phases Phase 1: Wilshire Bl, Spaulding Av to Fairfax Av Phase 2: Wilshire Bl/Fairfax Av Intersection Phase 3: Wilshire Bl, Fairfax Av to Crescent Heights Bl

Rendering shows how the Wilshire/Fairfax Station might look.

typical weekend schedule february 2017 – spring 2017 Fridays

10am

> Wilshire Bl (Phase 1 and Phase 3) reduced to one lane in each direction > Fairfax Av (Phase 2) reduced to one lane in each direction Fridays

8pm

> Full Closure of Wilshire Bl (Phase 1 and Phase 3) > Wilshire Bl/Fairfax Av Intersection (Phase 2) Mondays

6am

> Streets open

note > Thru the weekend work will occur 24/7 > Decking will require approximately 18 weekend closures > Wilshire/Fairfax Station stats: > 800 ft long > 70 ft wide > 60 ft deep


Larchmont Chronicle

Wilshire/Fairfax decking 2017

metro

Local Access Routes

CRESCEN T HEIGHTS

detours

HIGHLAND

2ND

LA BREA

Eastbound & Westbound detour

3RD

> Westbound Wilshire: Northbound La Brea Av to Westbound 6th St to Southbound Fairfax Av to Westbound Wilshire Bl > Eastbound Wilshire: Northbound Fairfax Av to Eastbound 6th St to Southbound La Brea Av to Eastbound Wilshire Bl

4TH

6TH

additional lane reductions starting at 8pm leading to full closure

LA

8TH

MAN SFIE LD

BREA

HAUS ER

OGD EN

SPAU LDIN G

WILSHIRE

FAIR FAX

SAN DIEG O WY

LA CIENEGA

MARYLAN D DR

MARTEL

phase 1: wilshire bl, spaulding av to fairfax av (westbound/eastbound)

> Westbound Wilshire: Wilshire Bl reduced at Mansfield Av > Eastbound Wilshire: Wilshire Bl will remain two lanes up to Fairfax Av

9TH

OLYMPIC

Local access maintained

SAN VIC EN TE

Work zone PICO

note Local access on Wilshire Bl for business and residents will be maintained. The farthest that thru traffic can travel before needing to turn is: > Westbound Wilshire: Wilshire Bl at Spaulding Av > Eastbound Wilshire: Wilshire Bl at Fairfax Av

essentials

* Street signage will be provided

> In the work zone, Wilshire Bl reduced to one lane in each direction from Spaulding Av to Fairfax Av on Fridays from 10am – 8pm > In the work zone, full closure of Wilshire Bl, from Spaulding Av to Fairfax Av, starting at 8pm on Fridays until Mondays at 6am

phase 2: wilshire bl/fairfax av intersection (westbound/eastbound)

MARTEL

CRESCENT HEIGHTS

Local access maintained

HIGHLAND

2ND

LA BREA

Work zone

3RD

Westbound detour

4TH

additional lane reductions starting at 8pm leading to full closure

MANS FIEL D

BREA LA

HAUS ER

OGDE N

8TH 9TH

> Westbound Wilshire: Wilshire Bl reduced at Mansfield Av > Eastbound Wilshire: Wilshire Bl reduced beginning west of La Cienega Bl

OLYMPIC

SAN VICE NTE PICO

detours > Westbound Wilshire: Westbound Wilshire Bl to Southbound La Brea Av to Westbound Olympic Bl to Northbound San Vicente Bl to Westbound Wilshire Bl > Eastbound Wilshire: Eastbound Wilshire Bl to Southbound La Cienega Bl to Eastbound Olympic Bl to Northbound La Brea Av to Eastbound Wilshire Bl

WILSHIRE

SPAU LDIN G

SAN DIEGO

WY

6TH

FAIR FAX

LA CIENEGA

MARYLAND DR

HANCOCK PARK

1ST

FAIRFAX

Local access maintained

Eastbound detour

note Local access on Wilshire Bl for businesses and residents will be maintained. The farthest thru traffic can travel before needing to turn is: > Westbound Wilshire: Wilshire Bl at Spaulding Av > Eastbound Wilshire: Wilshire Bl at Crescent Heights Bl

essentials > In the work zone, lane reductions on Wilshire Bl and Fairfax Av will start on Fridays from 10am - 8pm > In the work zone, full closure of Wilshire Bl and Fairfax Av starting at 8pm on Fridays until Mondays at 6am

* Street signage will be provided

MARTEL

phase 2b: wilshire bl/fairfax av intersection (southbound/northbound) LA BREA

3RD

4TH

6TH

8TH

LA BRE A

HAU SER

SPA ULD ING

OGD EN

WILSHIRE

FAIR FAX

SAN DIEGO

WY

Work zone

CRESCENT HEIGHTS

MARYLAND DR

2ND

Northbound & Southbound detour

9TH

Local access maintained

OLYMPIC

SAN VIC EN TE

essentials > In the work zone, lane reductions on Wilshire Bl and Fairfax Av will start on Fridays from 10am – 8pm > In the work zone, full closure of Wilshire Bl and Fairfax Av starting at 8pm on Fridays until Mondays at 6am

detours > Southbound Fairfax: Southbound Fairfax Av to Eastbound 6th St to Southbound La Brea Av to Westbound Olympic Bl to Southbound Fairfax Av > Northbound Fairfax: Northbound Fairfax Av to Eastbound Olympic Bl to Northbound La Brea Av to Westbound 6th St to Northbound Fairfax Av

additional lane reductions starting at 8pm leading to full closure > Southbound Fairfax: Fairfax Av reduced at Maryland Dr > Northbound Fairfax: Fairfax Av reduced beginning south of Olympic Bl

note Local access on Fairfax Av for businesses and residents will be maintained. The farthest that thru traffic can travel before needing to turn is: > Southbound Fairfax: Intersection of Fairfax Av and 6th St > Northbound Fairfax: Intersection of Fairfax Av and 8th St * Street signage will be provided

C


metro

Wilshire/Fairfax decking 2017

Larchmont Chronicle

Local Access Routes phase 3: wilshire bl, fairfax av to crescent heights bl (westbound/eastbound) detours

MARTEL

CRESCENT HEIGHTS

3RD

4TH

Westbound detour MANS FIELD

BREA

8TH

LA

HAUS ER

OGDE N

WILSHIRE

SPAU LDIN G

WY

6TH

SAN DIEGO

HIGHLAND

LA BREA

2ND

Work zone

FAIR FAX

MARYLAND DR

HANCOCK PARK

1ST

FAIRFAX

Local access maintained

9TH OLYMPIC

ROSSMORE

BEVERLY

LA CIENEGA

> Westbound Wilshire: Westbound Wilshire Bl to Southbound Fairfax Av to Westbound San Vicente Bl to Westbound Wilshire Bl > Eastbound Wilshire: Eastbound Wilshire Bl to Southbound La Cienega Bl to Eastbound Olympic Bl to Northbound La Brea Av to Eastbound Wilshire Bl

additional lane reductions starting at 8pm leading to full closure > Westbound Wilshire: Wilshire Bl will be reduced to one lane at Ogden Dr > Eastbound Wilshire: Wilshire Bl reduced beginning west of La Cienega Bl

SAN VICE NTE

note

PICO

Eastbound detour REDO NDO BL

Local access to Wilshire Bl for businesses and residents will be maintained. The farthest that thru traffic can travel before needing to turn is: > Westbound Wilshire: Wilshire Bl at Fairfax Av > Eastbound Wilshire: Wilshire Bl at Crescent Heights Bl * Street signage will be provided

essentials > In the work zone, Wilshire Bl reduced to one lane in each direction from Fairfax Av to Crescent Heights Bl on Fridays from 10am – 8pm > In the work zone, full closure of Wilshire Bl, from Fairfax Av to Crescent Heights Bl start at 8pm on Fridays until Mondays at 6am

How to Stay Involved and Give Input 213.922.6934 purplelineext@metro.net

Construction is a dynamic process and information is subject to change without notice. Detour routes are subject to change at the discretion of the Department of Transportation.

metro.net/purplelineext twitter.com/purplelineext

closures and detours updates

facebook.com/purplelineext

For closures and detour updates, please visit metro.net/purplelineext. Metro bus stops may be relocated. For information changes to Metro service, please call 323.go.metro or visit metro.net/advisories.

17-1347dd ©2016 lacmta

D


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.