LAUREN DI PIETRO MArch Architecture 2017 14033056 Management Report
2
3
Client appointment letter
letter
Client appointment
4
21st September 2016 Alzheimer’s Society 43-44 Crutched Friars London England EC3N 2AE
Dear Alzheimer’s Society, LEAZES PARK, NEWCASTLE New Respite Centre Thank you for the opportunity to meet. I confirm that we would be very pleased to provide architectural services in connection with the proposed development. I understand that you will require architectural design services including extensive project research, providing a business case for the proposal, various sketch proposals to further confirm the brief and develop the scheme, culminating with drawings sufficient for detailed planning permission of the proposal. We could then prepare technical drawings and specifications for approval under the Building Regulations, and for construction should you require these.
5
We enclose a booklet entitled ‘A Clients Guide to Engaging an Architect’ (see Appendix item 1), together with a copy of ‘Guidance for Clients on Fees’ (see Appendix Item 2), produced by the RIBA. These outline architects’ services with standard terms and conditions, and give an indication of fee levels for different types of work. The nature of the project, extent of our involvement, ‘the procurement route’ and the construction cost are all uncertain at present. If a normal service were required, based on the Plan of Work (pages 16 & 17) and a traditional contract, we would propose that fees are based on the indicative percentage scales (Class 4 – New works). We have assumed a construction budget of around £2 million for the works which would imply a percentage fee of 6.7% from the RIBA scales, but we would be happy to discount this to 5% in order to be competitive. This arrangement would allow for some flexibility in respect of changes to the brief, the costs and the scope of our work. Should the construction cost vary from our initial assumption as the project develops then the percentage arrangement allows our fees to vary accordingly.
letter
Client appointment
6
You will see that the process is broken down into a series of work stages with a proportion of the fee attributable to each. Fees would be charged upon completion of each work stage and, if at any time the project changes significantly or is abandoned, it allows us to submit an account up to that stage, and for you to terminate the arrangement if necessary.
Based on the above assumptions of construction costs, the following stage payments would be likely:-
£2,000,000 x 5% = £100,000 Stage 0 - 2
Appraisal, briefing, sketch proposals
15%
£15,000
Stage 3
Detailed proposals/planning
20%
£ 20,000
Stage 4
Final proposals/Building Regulations approval
20%
£ 20,000
Stage 5
Production information/tender
20%
£ 20,000
Stage 6
Mobilisation, construction to Practical Completion
22.5% £ 22,500
Stage 7
After Practical Completion
2.5% £ 2,500
7
It may also be necessary to appoint other consultants including Engineers and Specialists and, when we have defined the project more clearly, we would offer guidance on such appointments and potential costs.
We should also make you aware of the Construction Design Management Regulations 2015, in which the appointment of a Principal Designer is now mandatory on all projects. We are able to provide this service and would suggest that we are appointed in the first instance to issue the necessary information. This should take no more than a couple of hours and would be included in our fees. This project role involves managing and overseeing the health and safety of the project and managing risk assessments.
Expenses and disbursements properly incurred in connection with our appointment would be charged in addition to fees and would include the cost of printing, copying, travel and the purchase of any printed contract documentation. If we make payments on your behalf we will invoice you for these at net cost. VAT, where applicable will be charged on all architects fees and expenses. As you may be aware the Local Authority will make a charge for the planning application, and for building regulation approval.
letter
Client appointment
8
As a RIBA Chartered Practice we are required to obtain confirmation of all architectural appointments in writing. Subject to agreement of the terms, we would therefore ask that you sign and return a copy of this letter. We trust this is acceptable and hope to receive your instructions in due course, but do let us know if you require further information or clarification in the meantime.
Yours sincerely
Lauren Di Pietro
9
LEAZES PARK, NEWCASTLE New Respite Centre
Job No. 4532
We hereby appoint Pearce Bottomley Architects to provide Architectural Services for the proposed development in accordance with the terms of this letter dated 21st September 2016.
Signed………………………………………………………
Name……………………………………………………… Client
ALZHEIMER’S SOCIETY
Date…………………………….
RIBA plan of work 10
contents
11
STAGE 0 Core project requirements Client appointment Lease hold Site selection Business Case and Initial Risk Profile Design team Project programme Feedback from Previous Projects Sustainable strategy
12 14 16 18 20 24 26 28 30 32
STAGE 1 Developing the strategic brief Cost estimate and fees proposal Feasibility study Surveys required Tree survey
34 36 40 42 48 50
STAGE 2 Intial Schedule of Accommodation Developing the Schedule of Accommodation Adjacency diagram Final Schedule of Accommodation Concept design floor plans Outline Strategies and Programme Review Programme Review Technological Strategy Elemental cost plan
52 54 56 58 60 62 64 66 68 70
STAGE 3 National Planning Policy and the Trigger of Article 50 Local development framework Conservation area materials specification Design and Access statement
74 76 78 80 82
STAGE 4 Compliance with Building Regulations Invitation to tender Design Responsibility Matrix and Information Exchange Indicative construction programme Pre-construction Meeting
96 98 106 108 112 114
APPENDIX 1 - Client’s guide to engaging an architect 2 - Guidance to clients on fees 3 - Alzheimer’s Society financial report 4 - Leazes Conservation Management Statement 5 - Elemental cost breakdown 6 - Planning Applications
124 126 160 164 168 174 182
REFERENCES AND BIBLIOGRAPHY
200
12
13
stage
Strategic brief
14
The Alzheimer’s Society approached Pearce Bottomley
The PII also covers for any copyright infringements
Architects to envision a scheme which would enrich
that may arise if the client no longer wishes to
the lives of people living with dementia and their
pursue the project. Regardless of payment, Pearce
carers by creating a respite facility in the North East .
Bottomley Architects retains ownership of the
Pearce Bottomley Architects were appointed as they
copyrights for this project.
are a chartered practice and are covered by a company professional indemnity insurance. This covers the client if they provide inadequate advice, services or designs and provides cover for the legal costs and expenses in defending a claim, as well as compensation payable to the client to rectify the mistake.
15
Stage 0
16
The Alzheimer’s Society is run financially by a board of trustees who have received a grant from the Heritage Lottery Fund of £66,000 (see Appendix 3 - Alzheimer’s Society Financial Report 2015-2016) which they have ear-marked as a significant contribution to the realisation of this project. The initial project budget set aside by the Alzheimer’s Society for this project, based on the latest financial report, is £2.5 million including fees and VAT. This would suggest that they intend to complete the entire project with Pearce Bottomley Architects covering all stages.
17
Site acquirement
18
Extensive research was undertaken to justify the
The urban park was derived as the perfect setting
Miss Joan Silcox MBE, who was made an honorary
need for the project (see DP3 Report) and to
for a project of this type due to the calm and
freeman in 2006 in recognition of her unstinting
understand the history of dementia care and the
tranquil nature of the green spaces, whilst still
support for local charities, holds the Alzheimer’s
short falls of it’s current state. This work could
remaining an important part of the city centre
Society close to her heart.
then formulate the basis of the project brief
fabric.
She recognised the importance of this project in
to ensure that an innovative solution could be
Leazes Park is owned by the Freemen of
maintaining the ethos and position statements
achieved for the realisation of a new respite facility.
Newcastle, who have granted the Alzheimer’s
of the Alzheimer’s Society and has achieved the
Many sites across Newcastle City Centre were
Society a lease hold for the site of the, now
support of the Freemen of Newcastle to grant
explored for the realisation of this project (see
disused, Springbank Pavilion.
the lease hold to the Alzheimer’s Society for this
DP3 report p.102-121) finally settling on Leazes Park as the most suited site.
project.
19
Potential sites
20
Site 1 - 2340m2 Pros
Cons
• Good location next to
• Would
children’s playground • RVI close by
block
the
children’s playground and make it unsafe
• Family picnic area
Site 2 - 9720m2 Pros
Cons
• Close to a main road -
• Close to a main road -
access
noise • Lack of parking facilities along the East side of the park
21
Site 3 - 35,750m2 Pros
Cons
• Surrounded by residential
• Might overlook residences
• Close to RVI
• Furthest away from St James Park to use as a landmark • Vast area
Site 4 - 1550m2 Pros
Cons
• By the band stand - great
• Might be quite a busy area
music connections and
of Leazes Park - too busy?
events
Stage 0
22
Site 5 - 25,750m2 Pros
Cons
• RVI close by
• Cattle graze on this site
• Near
to
playground picnic
children’s and
area,
family
although
March - November safety? - For users of building as well as cattle.
blocked by trees and shrubs Site 6 - 3800m2
Cons
Pros
• A lot of trees on site cause
• Immediate
links
with
children’s playground, RVI and family picnic area • Can see St James Park • Close
to
Richardson
Road - parking available here
constraints or removal • Springbank
Pavilion
currently on site - needs to be removed
23
Site 7 - 22,700m2 Pros
Cons
• Immediate links to St
• Close to Listed buildings
James • Close to lake
in the conservation area stricter rules • Noise pollution
Business case
24
The business case for the project is set out in
Over a third of people with dementia living alone
It is often deemed difficult to obtain planning
DP3 Report. This was further justified by the
had to stop doing things they enjoy as a result of
permission for building within a conservation
Alzheimer’s Society’s position statement regarding
a lack of services (Alzheimer’s Society, 2013). This
area, however Section 71 of the Planning (Listed
carer support, in which increased respite care is
enables full justification for the proposed project
Building and Conservation Area) Act 1990 states
highlighted as an important strategy to invest in.
on the proposed site.
that the local authority has the responsibility to
Many carers would be unable to continue caring
The site proposed for this project poses the most
determine whether the proposal would be viable.
risk for the realisation of the respite centre.
Any new buildings in Leazes Conservation Area
Leazes Park is located within the Leazes
should be designed with reference to their
conservation area in Newcastle. This will need
surroundings and their impact on the character
careful consideration through the planning process
and appearance of the Leazes area which will be
and pre-application discussions may be needed
an important driver in the design of this proposal.
without respite care. However, one-third of carers of people with dementia had no access to respite and one-fifth found that respite care was not dementia friendly (Carers' Trust, 2013). The society also calls for the provision of services that allow people with dementia to live independently in their own homes, and services that promote quality of life and prevent social isolation.
with Newcastle City Council with regards to the Town Planning Act.
25
Design team
26
Alzheimer’s Society Role in Stage 0: • Provide Business Case and other core project requirements and contribute to development of Strategic Brief as required Pearce Bottomley Architects Role in Stage 0:
Following the client appointment letter, Pearce Bottomley were appointed as both the architects and the CDM coordinator on this project, the role of which was set out in the appointment letter. As quality is the main design driver behind this project, a traditional project procurement method was selected. Consultants were selected to design specialist items, such as external works, lighting design, building services and structural engineering. The cost quotes for these services have been included in the elemental cost plan as provisional sums.
• Collate comments and facilitate workshops to discuss Business Case and develop Strategic Brief with project team members • Discuss initial considerations for assembling the project team • Establish Project Programme • Collate Feedback from previous projects • Contribute to preparation of Strategic Brief • Comment on project Programme • Provide Feedback from previous projects • Contribute to preparation of Strategic Brief • Discuss project with appropriate planning authority • Provide Feedback from previous projects • Contribute Cost Information to preparation of Strategic Brief
27
Project Roles Table
Client Client adviser Project lead Lead designer Construction lead Architect Civil and structural engineer Building services engineer Cost consultant Contract administrator Health and safety advisor Access consultant Acoustic consultant Archaeologist BREEAM assessor Cladding specialist Catering consultant Facilities management (FM) advisor Fire engineer Highways consultant Information manager Interior designer Landscape architect Lighting designer Masterplanner Operational lead Party wall surveyor Planning consultants Security advisor Signage designer Sustainability advisor Technical advisor Other additional project role 1 Other additional project role 2
Alzheimer's Society
Alzheimer's Society
Alzheimer's Society
Alzheimer's Society
Alzheimer's Society
Alzheimer's Society
Alzheimer's Society
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
Alzheimer's Society [Not required]
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
R Barker Builders
R Barker Builders
R Barker Builders
[Not required]
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
[Not decided]
[Not decided]
[Not decided]
Howard Marsdon
Howard Marsdon
Howard Marsdon
Howard Marsdon
Howard Marsdon
[Not decided]
Arup
Arup
Arup
Arup
Arup
Arup
Arup
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
[Not required]
[Not required]
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Arup
Arup
Arup
Arup
Arup
Arup
Arup
Arup
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
Arup
Arup
Arup
Arup
Arup
Arup
Arup
Arup
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
E2 Consultants
E2 Consultants
E2 Consultants
E2 Consultants
E2 Consultants
E2 Consultants
E2 Consultants
E2 Consultants
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
Pearce Bottomley Architects
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not decided]
[Not decided]
Robinson Landscape Design
Robinson Landscape Design
Robinson Landscape Design
Robinson Landscape Design
Robinson Landscape Design
Robinson Landscape Design
[Not decided]
[Not decided]
[Not decided]
Apollo Lighting
Apollo Lighting
Apollo Lighting
Apollo Lighting
Apollo Lighting
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
Newcastle City Council
Newcastle City Council
Newcastle City Council
Newcastle City Council
Newcastle City Council
Newcastle City Council
Newcastle City Council
Newcastle City Council
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
[Not required]
with the client sees the working drawings completed after the planning application has been determined. This does however mean that there will be no work completed for the 8 week determination period from the planning application submission date. There may be scope to begin working on the working drawing package before the final determination of the planning application, however this would be at risk to the client if the planning was rejected.
Working drawings and schedules Building Regs Application Tender period Tender Acceptance Mobilisation Contract period (On site) Practical Completion
14 Weeks
27/02/2017
20/02/2017
13/02/2017
06/02/2017
30/01/2017
23/01/2017
16/01/2017
09/01/2017
31/10/2016
24/10/2016
17/10/2016
10/10/2016
03/10/2016
TASK Client Appointment Brief Development Project Research Precedent Studies Site Selection Programme Development Initial Designs Developed Designs Final Designs In Planning Determination of Planning
26/09/2016
The project programme as initially discussed
Week Commencing
Stage 0
28
12 Months 11/09/2018
04/09/2018
04/09/2017
28/08/2017
21/08/2017
14/08/2017
07/08/2017
31/07/2017
24/07/2017
17/07/2017
10/07/2017
03/07/2017
26/06/2017
19/06/2017
12/06/2017
05/06/2017
29/05/2017
22/05/2017
15/05/2017
08/05/2017
01/05/2017
24/04/2017
17/04/2017
10/04/2017
03/04/2017
27/03/2017
20/03/2017
13/03/2017
06/03/2017
29
Springbank ‐ New Respite Centre ‐ Project Programme
30
Dyneley House GP Surgery, Skipton, UK
Precedents
Brief: Refurbishment of the existing waiting area and offices to include dementia friendly design initiatives. Architects: Pearce Bottomley Architects Procurement Method: Traditional building contract with negotiated tender. Review of Project: The main issue with this project was the short time frame in which the architects had to achieve it from conception to completion. This led to a negotiated tender opportunity due to the tight time constraints. This meant that costs couldn’t be as competitive as if tender had gone out in the traditional way. It is therefore important through the realisation of Springbank Respite Centre that although quality is the main design ambition, costs can be kept competitive through sticking with the project programme.
31
Alzheimer’s Respite Centre, Dublin, Ireland
Brief: New build facilities to provide respite and accommodation for 11 clients.
Architects: Niall McLaughlin
Procurement Method: Traditional building contract with Government Departments and Local Authorities Contract (GDLA 82 with Quantities)
Review of Project: The project cost £2.7million and was 1392m2. This makes the building roughly about £2000 per m2 which provides a good estimate for the initial costing of this project.
Stage 0 32
33
The design and construction process of tree care will be considered from the offset of this project. During the feasibility stages a topographical survey, soil assessment and detailed tree survey will be undertaken. This will allow a further tree categorization to determine which trees will be retained and which trees will be removed for the building works. This will also allow the RPAs (Root Protection Areas) to be calculated. The proposed landscaping will then be explored through stage 3 - developed design, alongside this a tree protection report will also be produced.
stage
36
Stage 1
Principal Objectives: •
Respite Centre for people with dementia
•
Maximise the panoramic views of the surrounding Leazes Park
•
Utilise the trees on site in the form of the building
Budget: •
£2million initial project budget – including fees, vat on fees and project contingencies.
•
£1.6 initial construction budget - no VAT on construction costs due to new build
•
Further cost analysis required following determination of proposals
Programme: •
Land is acquired.
•
Project to progress as soon as possible to minimise building in winter months.
Quality: •
Although budget is important, programme and quality are to be the priority.
•
The designs and specifications should be based on the premise that the centre will be a long term investment – rather than a development
opportunity to be sold on in the short term using the guidelines as discussed in DP3 Report.
37
38
Stage 1
Procurement: •
The project will proceed on the assumption that the works will be procured in the traditional way – by competitive tendering of the works and
with a traditional building contract. Style: •
External materials as the conservation area requirements
•
Dementia friendly finishes internally
Services: •
Underfloor heating
•
Drainage – Assumed connection to mains system.
Room Notes: •
Programme to be developed through initial design phases and brief preparation
Structure: •
Timber frame construction considered
External: •
No requirement for parking
•
Mobility Scooter store
•
Sensory gardens
39
40
Cost estimate
The fees proposal are set out in the Client Appointment Letter (see page. 6).
The estimated prices are based on building prices per square metre (sqm). The prices are given on a scale range which varies with quality. As design quality is key throughout this project, prices have been estimated using the higher costs in these ranges (Aecom, 2016). Although Niall McLaughlin’s precedent study saw that the building was roughly £2000 per sqm, these figures are significantly lower. This will be looked at in detail further in the elemental cost analysis, however it is not concerning at this stage as the total estimated construction cost falls below budget, which allows for some scope to add some cost where needed.
The building functions are based upon the finalised schedule of accommodation (see page. xxxx). The model has been prepared on the assumption that ground conditions are good and that minimal site preparation is required.
Demolition costs have been estimated based upon demolishing a single storey building approximately 500m3.
External works have been calculated at approximately 15% of the total build works.
41
Demolition costs
single storey building approximately 500m3
£20 per cubic m
£10,000
Fell and removing trees
2 No. trees on site to remove prior to work commencing.
Girth 500mm-1500mm £26 per tree Staff Offices and Reception Area - approx. 50 sqm Uniclass D3 Administrative Offices for owner occupation Low rise - air conditioned £1275 - £1600 per sqm Accommodation - 10 rooms - approx. 50 sqm per room Uniclass D4 Accommodation for the Elderly £850 - £1075 per sqm Rest Room - approx. 40 sqm Reminiscent Room - approx. 50 sqm Art and Activity Room - approx. 50 sqm Music and Film Room - approx. 50 sqm Uniclass D4 Medical Day Centres £1125 - £1425 per sqm Public Cafe - approx. 100 sqm to include; Kitchen approx. 25 sqm and Public WC approx. 25 sqm Uniclass D5 Recreational £1125 - £1425 per sqm External works
£52 £80,000 £537,500
£270,750 £213,750
Total
£166,808
£1,278,808
Stage 1 42
43
Stage 1 44
45
Stage 1 46
47
Stage 1
48
The site lies within the Newcastle conservation
A CAT scan can be undertaken to determine
An assessment of a tree’s age classification is made
area boundary, and thus careful site surveys and
exactly where the tree roots lie.
in terms of it maturity within the site’s landscape.
detailing need to be undertaken.
Each tree should be checked for degradation
An assessment of a tree’s physiological condition is
An extensive levels survey was undertaken
every year for five years after completion of the
to be made as good, fair, poor, dead.
measuring the change in levels at each 100mm
development.
The root protection areas of these trees can then
incline. Levels survey equipment was used to plot
Trunk/stem diameters are measured at 1.5 metres
be calculated as a circle with a radius 12x the stem
the change in incline.
above ground level, or immediately above the root
diameter (Reference).
A tree survey was also carried out to understand
flare for multi- stemmed trees.
the condition of the trees and the constraints that
Estimate branch spread is taken in metres from
these will pose to the site.
the centre of the trunk, at the four cardinal
GPS locations of trees were plotted to accurately
points of a compass, to achieve an accurate
locate the existing trees on site.
representation of crown shape.
Tree species were identified by twigs, leaf buds, bark texture, fallen leaves and seeds.
49
n w
e s
distance from eye to base of stick= a length of stick = b
distance from eye to base of tree = c
height of tree
=
b(c/a)
measure the canopy at all 4 cardinal points
Stage 1
50
An extensive level survey and tree survey was
It was found from the tree survey that all of the
undertaken throughout the feasibility stage.
trees on site were deemed good quality, except
The Tree Survey has been undertaken within the
for two which were significantly leaning and had
recommendations of British Standards 5837:2005
gashes to the bark. Planning permission to remove
and current good arboricultural practice.
these two unhealthy trees will therefore be sought.
The survey entailed a visual inspection from
It will be a design initiative to try and keep all of
ground level of all trees.
the remaining trees on site, and build around them
Due to variations of existing ground levels through
without causing any damage to them, or removing
the site, height dimensions are estimated and are
any unnecessarily.
given in metres.
51
Tree Reference
Species Common Name
Species Scientific Name
UK Provenance
Presence of TPO or Conservation Area Protection
Approx Height (m)
Age Class*
Branch Spread North (m)
Branch Spread East (m)
Branch Spread South (m)
Branch Spread West (m)
Physiological and Structural Condition (Health and Physical Defects) Good/Fair/Poor/Dead
42
Horse Chestnut
Aesculus Hippocastanum
Non‐Native
CAP
4.6
315.0
10.03
80
Young
2.3
3.45
4.025
2.3
Good
43
Sycamore
Acer pseudoplatanus
Native
CAP
6.0
925.2
29.45
59
Young
5.75
5.75
3.45
4.6
Good
44
Osier Willow
Salix viminalis
Native
CAP
5.1
570.9
18.17
36
Middle Aged
3.45
2.3
2.3
3.45
Good
45
Common Box
Buxus sempervirens
Native
CAP
3.7
244.1
7.77
16
Middle Aged
3.45
5.75
3.45
5.75
Good
46
Common Box
Buxus sempervirens
Native
CAP
4.2
315.0
10.03
20
Middle Aged
3.45
5.75
3.45
5.75
Good
47
Common Box
Buxus sempervirens
Native
CAP
4.5
393.7
12.53
25
Middle Aged
3.45
5.75
3.45
5.75
Good
48
Whitebeam
Sorbus aria
Native
CAP
4.9
315.0
10.03
30
Middle Aged
4.6
5.75
3.45
2.3
Good
49
Aspen
Populus tremula
Native
CAP
6.2
354.3
11.28
23
Middle Aged
0.575
2.3
1.15
0.575
Good
50
Aspen
Populus tremula
Native
CAP
6.1
354.3
11.28
23
Middle Aged
0
2.3
2.3
1.15
Good
51
Field Maple
Acer campestre
Native
CAP
5.1
689.0
21.93
99
Middle Aged
2.3
6.9
9.2
4.6
Poor ‐ Leaning NorthWest @ 45 degrees from vertical
52
Sycamore
Acer pseudoplatanus
Non‐Native
CAP
5.3
925.2
29.45
118
Middle Aged
4.6
5.75
3.45
5.75
Poor ‐ Leaning SouthEast @ 35 degrees from vertical
54
Ash
Fraxinus excelsior
Native
CAP
5.1
629.9
20.05
80
Middle Aged
1.15
3.45
9.2
5.75
Good
55
Field Maple
Acer campestre
Native
CAP
5.3
669.3
21.30
96
Middle Aged
4.6
2.875
8.05
2.3
Good
57
Ash
Fraxinus excelsior
Native
CAP
5.0
551.2
17.54
70
Middle Aged
2.3
2.3
3.45
2.3
Good
59
Copper Beech
Fagus sylvatica f. purpurea
Non‐Native
CAP
5.5
826.8
26.32
105
Mature
5.75
5.75
5.75
5.75
Good
60
European Silver Fir
Pseudotsuga menziesii
Non‐Native
CAP
4.1
433.1
13.79
103
Young
3.45
3.45
3.45
3.45
Good
61
Sycamore
Acer pseudoplatanus
Non‐Native
CAP
5.1
590.6
18.80
75
Young
1.15
1.725
3.45
2.875
Good
62
Ash
Fraxinus excelsior
Native
CAP
5.6
598.4
19.05
76
Middle Aged
3.45
1.15
2.3
5.75
Good
63
Aspen
Populus tremula
Native
CAP
5.7
393.7
12.53
25
Middle Aged
0.575
0.575
1.15
0.575
Good
64
Alder Buckthorn
Frangula alnus
Native
CAP
4.2
629.9
20.05
40
Mature
1.15
1.15
2.3
2.3
Good
65
Field Maple
Acer campestre
Native
CAP
4.8
393.7
12.53
56
Young
2.3
2.3
2.3
1.15
Good
66
Midland Hawthorn
Crataegus laevigata
Native
CAP
4.6
439.0
13.97
42
Middle Aged
2.3
3.45
4.6
2.3
Good
Circumference of Stem Diameter Approximate Stem (inches) (inches) Age
stage
Stage 2
54
The quality of this project must be of
Design quality is the principle objective of this
exceptionally high standard in order to
project with cost and time following this.
incorporate designing for dementia guidelines
The building must reflect the values of the
in order to ease the use of the building by all,
Alzheimer’s Society throughout every aspect of
through the use of colour, light, texture and
the design. The spaces need to relate to each
architectural features to enrich the environment.
other to ensure ease of use of the building as well
The internal environment should be comfortable
as creating individual safe and secure spaces.
in relation to lighting, heating, air quality and acoustics, as well as allowing physical comfort in the furnishings. It is important that individual users can also control the internal quality of their environment.
55
Stage 2
56
As a result of the need for high design quality, a
The project will also need full demolition and
traditional procurement route is sought for the
planning permission to remove the disused
realisation of the project. Although there are
Springbank pavilion which is currently on site.
cost benefits with design and build contracts,
Although a sustainable strategy could argue that
the traditional route is preferred for this project
the existing structure would be better retained
as it is considered to be a low risk method of
than a new build, it was deemed that the pavilion
contracting for the client, as the contractor takes
was disused and was insufficient for the new
the financial risk for construction.
proposed use.
57
58
Stage 2
Outline Specification
Substructure - Pad foundations Superstructure - Timber frame construction with beam and block flooring Cladding (including external windows and doors) - Timber cladding and natural sandstone with timber vertical sliding sash windows and timber door. Roofing - 35 degree pitched roof with natural welsh slate Internal walls and partitions - Timber stud walls and internal glazed partitions with manifestations for user safety Internal doors - Timber internal doors with coloured frames Ceilings - Skim on plasterboard Flooring - Beam and block construction with carpet, vinyl and wood floor finishes Finishes - Paint on skim on plasterboard wall finishes Building services (including lighting, heating, ventilation and air conditioning, water supply and drainage and other special installations). Fixtures and fittings (such as sanitary fittings). Landscape.
59
Stage 2
60
The entrance and reception area should be clear
It will be implemented where possible to use
to occupants as well as accessible and welcoming.
locally sourced materials in order to improve
The building should have minimal impact of
the sustainability of materials, as well as using
the surrounding environment, whilst providing
renewable, reused or recycled materials.
good quality views and overlooking the natural
The building materials will also be to a high quality
landscape of the park.
standard to ensure that they have a long life span
The internal layout of the building will provide a
to enable the design to be durable.
flexible layout for future planning.
Energy consumption and pollution, both in
The building aims to enhance the local community
construction and in use will be kept as minimal as
and enriching the lives of people with dementia.
possible.
61
Stage 2 62
63
The concept design of the building is based up the idea that all of the existing trees that are in good condition should remain on site and thus the development should happen in the vacant spaces within the trees and between the root protection areas. After the critique of existing care homes as well (see DP3 Report) it was also important to reduce the conventional ‘corridor’. This has been explored in great detail through the concept design by making corridors within the plan multifunctional, or given the ability to open up so that they are not just a transition point from A to B. Closed loop circulation has also been explored in depth, using the spaces around the trees as circulation space and creating loops around the trees.
Stage 2
64
Acoustic strategy
Building control strategy
As the project has progressed from the initial brief
The acoustic strategy will apply the most in the
A local improved inspector will be used for
and client appointment, the programme has been
accommodation cluster. However one design
building control services. Although this often
delayed to ensure that the design is of the highest
requirement will be to ensure that the noise
costs slightly more than a local authority building
quality and functions as it should. The extension
generated by St James Park during match days is
control service, it is often deemed that an
in design time was discussed with the clients
controlled, to be heard in some of the spaces but
improved inspector can spend more time on site
and they were happy to proceed with this as the
not all.
and understand the project to a greater extent
quality is more important to the design than the
and thus improve the overall quality.
programme.
Maintenance and Operational strategy
The cafe will operate during usual working hours,
It was also decided that as the project grew
but will give residents at the respite centre the
through concept design that the construction
opportunity to work within this serving and
period should also be extended to be more
running the cafe business.
realistic to the scale of the project. This has increased from 12 months to 24 months.
65
66 Moment in
Programme Development Initial Designs Developed Designs Final Designs In Planning Determination of Planning Working drawings and schedules Building Regs Application Tender period Tender Acceptance Mobilisation Contract period (On site) Practical Completion
14 Weeks
24/04/2017
17/04/2017
10/04/2017
03/04/2017
27/03/2017
20/03/2017
13/03/2017
06/03/2017
27/02/2017
20/02/2017
13/02/2017
06/02/2017
30/01/2017
23/01/2017
16/01/2017
09/01/2017
31/10/2016
24/10/2016
17/10/2016
10/10/2016
03/10/2016
26/09/2016
TASK Client Appointment Brief Development Project Research Precedent Studies Site Selection
Week Commencing
Time
24 Months 16/01/2019
09/01/2019
09/10/2017
02/10/2017
25/09/2017
18/09/2017
11/09/2017
04/09/2017
28/08/2017
21/08/2017
14/08/2017
07/08/2017
31/07/2017
24/07/2017
17/07/2017
10/07/2017
03/07/2017
26/06/2017
19/06/2017
12/06/2017
05/06/2017
29/05/2017
22/05/2017
15/05/2017
08/05/2017
01/05/2017
67
Stage 2
68
Technological strategy
Pad foundations are deemed the most appropriate
Site clearance and demolition works will be
as they will have minimal impact on the existing
carried out first (demolishing the existing pavilion
ground. Micro piles can also be considered,
and clearing the site of shrubbery).
however access for machinery will be limited due
Root protection areas can then be marked and
to root protection areas.
fenced off in accordance with the Tree Protection Method Statement. The building is proposed to be built in timber frame to create a lightweight structure. Trusses will be used to support the 35 degree pitched roof.
69
70
Preparatory Works (e.g. demolition) for whole site:
Demolish Springbank Pavilion
Remove shrubbery and clear site
Felling and removing 2No. trees External Works for Cafe site:
Site preparation clearing site vegetation
Excavation and filling
Substructure for Cafe use:
£6,726.74 £17,784.94 £27,182.69
Foundations
Beam and Block floor
Drainage Superstructure for cafe use
Wall members
Roof construction
Truss system
Flooring Dry-lining Stairs
External cladding
External windows and doors
Internal doors
Internal walls and partitions
£110,885.10
71
Internal finishes for cafe use:
Floor finishes
Decoration Fixtures and fittings for cafe use:
Client supply furniture
Kitchen fittings
Sink
Basins and urinals
M&E Services
Contractors designed portion
Provisional sum included
£32,951.12 £6,644.77 £20,000.00
Specialist Items
Contractors overheads and profits
Professional and Statutory Fees
Water, gas and electrical connection to mains services
Architects and engineers fees
Planning application costs
Building control fees
Desktop studies
Value Added Tax
N.B VAT @ 0% due to the construction of new buildings used by charities
(HM Revenues and Customs, 2017).
£73,137.77
72
Provisional sums Staff Offices and Reception Area - approx. 50 sqm Uniclass D3 Administrative Offices for owner occupation Low rise - air conditioned Accommodation cluster 10 rooms - approx. 50 sqm per room Uniclass D4 Accommodation for the Elderly Activity cluster Rest Room - approx. 40 sqm Reminiscent Room - approx. 50 sqm Art and Activity Room - approx. 50 sqm Music and Film Room - approx. 50 sqm Uniclass D4 Medical Day Centres Apollo Lighting Design Robinson Landscape Design E2 Consultants - building services engineer
[For full cost breakdown please see appendix item 5]
£80,000
£1275 - £1600 per sqm
£850 - £1075 per sqm
£537,500
£270,750
£1125 - £1425 per sqm
£1000 £10,000
Total
£500
£1,195,583.12
Elemental pricing has been broken down into 3 sections; café use; activity cluster; accommodation and staff area cluster. This allows for each area to be broken down into elemental costs, based upon the building functions which were used to create the estimated costs based on building square metre for each function. Demolition has been cost as a whole as this isn’t specific to the building use.
There are some discrepancies with the elemental costing when compared with the costing estimates; • The accommodation will be better placed on the first storey, which was not accommodated for in the initial costing; • The plans are not yet finalised and thus could simplify the proposed structure from the elemental costing and reduce some costs; • Walls have been calculated as the perimeter of the building as window and door positions are not yet finalised - this will reduce costs of timber members and dry lining, but may increase costs based on glazing and windows; • Patent glazing has been included to accommodate for a roof light however this may need to be removed as part of the planning conditions within the Leazes Conservation Area; • There is the potential for the re-use of some materials from Springbank pavilion, mainly welsh slates and timber members, however this hasn’t been included as a cost reduction as the condition of the materials will need to be explored before they can be determined for re-use; • Inflation forecast at 1.89% for March 2017 (Trading Economics, 2017), meaning that the prices for these costed items could fluctuate before the contractor purchases them.
73
stage
Stage 3
76
National and Local Policy and Guidance
The Prime Minister has stated that Article 50 will
This means that products and specifications
This proposal contributes to the achievement
be triggered by March 2017 at the latest. From
purchased by the contractor for the works
of sustainable developments as set out in the
this point a series of negotiations will take place
may not be subject to the same regulations
National Planning Policy Framework on all three
over a two year period. This will result in the UK’s
and standards as originally specified, (if the
key dimensions set out in the guidance, providing;
independence from the EU after two years.
specification is written before the UK leaves).This
an economic role, creating income from the cafe
Although the trigger of Article 50 will not
is because the UK Parliament will have greater
to support the running of the building and The
apply any changes to the procurement of this
scope to re-evaluate regulations once the UK has
Alzheimer’s Society; a social role, supporting
project, it may however, affect the product and
left the EU.
strong, vibrant and healthy communities
environmental standards of the development as
with accessible local services that reflect the
the construction progresses. According to the
community’s needs and support its health, social
project programme the UK will leave the EU
and cultural well-being; and an environmental
during the construction phase of this project.
role, contributing to protecting and enhancing the natural environment.
NB. The Party Wall Act does not apply to this development.
77
Stage 3
78
Leazes Park was added to English Heritage
Green Flags are the national standard for
Due to the conservation area status of the
Register of Parks and Gardens of special historic
excellence for parks and recognise excellent use
site and the nature of the works a planning
interest in 1992 and thus English Nature are to be
of green space, well maintained facilities and high
application for full planning permission and
consulted when the works are planned.
standards of safety and security. Judges awarded
relevant demolition to an unlisted building in a
Although healthcare and respite buildings are not
the flags after deeming the parks welcoming,
conservation area, as well as an application for tree
mentioned in Newcastle’s Local Development
healthy and safe, clean and well-maintained, as well
works: notification of proposed works to trees in
Framework, Leazes Park is mentioned as having
as being areas which are sustainable and involve
a conservation area, will need to be submitted to
been granted a green flag status. Leazes Park is
the local community.
Newcastle City Council (see appendix 6 - Planning
also included under the Leazes Conservation Area.
Although the development should qualify for the
Applications and Drawing Issue List). This would
Although this doesn’t restrict development in the
Community Infrastructure Levy, as it is a new
be submitted with the relevant drawings and fees
area, it will be imperative to remain sensitive and
development which creates net additional floor
with the expectation of a decision in 8 weeks from
conservative to the surrounding context.
space of 100 square metres or more, there may
validation.
be some relief from this as the building will be run and managed by a charity.
79
Stage 3
80
The management plan forms a supplementary
Adequate planning permission will be acquired
planning document [SPD] to the Local
for any relevant works to trees around the site, in
Development Framework [LDF] (see Appendix
accordance with section 5.3.
3 - Leazes Conservation Area Management Plan
The preservation of the natural habitats of the
for map of the area) and complies with key issues
local wildlife and bat population will be maintained
PH4, LE2, TLC1, D1 and D2 of the LDF Key Issues
throughout the development of this project.
report [April 2004].
The management plan sets out key materials that
The proposal will be sympathetic to all issues of
should be used within Leazes Park Conservation
vulnerability within the document to ensure that
Area for any development. Materials must be
the nature and character of the conservation area
traditional and sympathetic to the history of
remain as so. The proposal does not affect any
Leazes Conservation Area.
transport links or parking issues within Leazes
The original pattern of gardens and the presence
Conservation Area in accordance with section 4 of
of trees greatly contributes to the character of
the management report.
Leazes Conservation Area and should be retained.
Walls Natural Sandstone - colour to remain unchanged Brick Stucco - colour BS 08 B17 Windows Timber frame vertical sliding sash windows Roofs Natural Welsh Slate Rainwater Goods Cast iron with gutters on brackets Boundary Treatments to remain unchanged Advertisements should be sympathetic to the historic character of the area Rooflights should be in a ‘conservation’ style in design, materials and size
81
82
83
Design and Access
statement
84
Introduction
This statement has been prepared in support of an application for Planning Permission and for relevant demolition of an unlisted building in a conservation area in accordance with the Town and Country Planning Act 1990. The proposal seeks to demolish the existing timber frame pavilion building located on the East of Leazes Park, adjacent to Richardson Road, Newcastle and propose a new build respite facility for people with dementia in it’s place, incorporating a public cafe within this scheme. The application also determines the scale and massing of the proposed respite centre, and details the access to the site, layout, appearance and landscaping of the proposal.
85
Introduction
The site lies within the Newcastle conservation area boundary, and thus careful site surveys and detailing have been undertaken. An extensive levels survey was undertaken measuring the change in levels at each 100mm incline. A tree survey was also carried out to understand the condition of the trees and the constraints that these will pose to the site. Trunk/stem diameters are measured at 1.5 metres above ground level, or immediately above the root flare for multi- stemmed trees. Estimate branch spread is taken in metres from the centre of the trunk, at the four cardinal points of a compass, to achieve an accurate representation of crown shape. An assessment of a tree’s age classification is made in terms of it maturity within the site’s landscape. An assessment of a tree’s physiological condition is to be made as good, fair, poor, dead.
86
Landscaping
The site is currently set within Leazes urban park landscape in Newcastle City Centre, characterised by mature trees, grazing land, the lake and recreational facilities. The flat land is punctuated by planted trees and boundary edges are contained within a metal rail fence, often complimented by hedgerows and self-set trees. It is proposed that the external appearance of the settlement will remain complementary to the existing park and as is consistent with the conservation area. The amenity space will be contained within the curtilage of the park, where it is mainly obscured from public view. Hard landscaping surrounding the property will be simple in form. Planting will be low level and largely imperceptible from outside the site.
87
Landscaping
After the tree survey was undertaken it was determined that all trees except two, were of good health and quality and could remain in place, however the two that were deemed poor quality would have to be removed for the construction of the building. The removal of these trees will be one of the initial works along with the demolition of the existing pavilion. The shrubbery at the rear of the site will also need to be cleared for the proposal. After the site is cleared the RPA can be marked off and fenced off to determine where diggers can pass and foundations can be laid out. This shows the area that can be used for building works whilst protecting the root protection areas. This will inform routes which a digger and other machinery can pass on the site.
88
Scale
The scale of the proposal in the context of its plot is respectful of the character and scale of the surrounding landscape, and respects the traditional vernacular courtyard form which is prevalent in rural settlements in this area. The development does not impose itself upon any surrounding properties and will fit in well to the nature and character of this particular location. The proposed development is designed as a series of clusters which provide internal courtyard spaces. This arrangement has several advantages; - The historic vernacular form of the settlement is restored. - The buildings form an enclosure, providing shelter from the elements in an otherwise exposed landscape.
89
Layout Internally the development has been designed to provide well proportioned accommodation arranged over two floors, whilst still respecting the construction and spatial qualities of the public areas. The design of the development places the circulation and existing trees in the centre of the plan. The cafe cluster is located adjacent to the family picnic area; the activity cluster is located adjacent to the children’s playground and the Leazes Park is 50,900sqm
accommodation cluster is to the north of the site on the second storey to maintain maximum
The proposed site is 3800sqm The proposed development is approx. 900sqm The proposed development looks to occupy only 0.02% of the land in Leazes Park making it a small scale development.
privacy.
Grid reference NZ243649
90
Use The conversion proposes the building to be used as a respite facility incorporating a public cafe area. The use class lie under ‘mixed use’ and includes the creation of class A3 - Food and Drink, B1 - Business, C2 - Hotels, Hostels and Dwelling Houses,D1 Public Services and D2 - Entertainment and Leisure. The present combined footprint of the existing pavilion is 120m2. The existing pavilion is disused and poorly constructed for the new purpose, with little of no insulation as the function of the pavilion was changing rooms for the deceased bowls club. It is therefore more economical to demolish this and build a new structure in it’s place which will serve a public function as well as the respite centre, including a cafe area. This will also make better use of the family picnic area nearby. The proposed curtilage area is 3800m2. The proposed cafe development has a total footprint of 390 m2.
91
Use Staff Offices 50sqm to accommodate approx. 20 full time staff working admin jobs, management and running activities as well as providing care to residents and working with the Alzheimer’s Society Reception area Rest Room 40sqm To be used by staff and clients as a separation area away from the main activity spaces if some space and time is needed during a visit or stay. Ancillary Storage for mobility scooters Laundry Accommodation 500sqm 5x single rooms (20sqm) with en-suite (10sqm) 3x couple rooms (25sqm) with en suite (15sqm) 2x accessible rooms for couple or single (50sqm) Hoists available in these rooms No living room or kitchen accommodation to encourage residents to spend more time in the public realm of the building rather than in their rooms
92
Use
Art and Activity room 50sqm Arts and crafts Drawing/Painting Jewellery making Knitting Games - dominoes/bingo/cards etc Acoustic requirements will be designed to allow some external noise to listen to the football from St James Park Music and Film Room 50sqm Capacity for approx. 15 people inc. residents and staff Acoustic requirements Listening; record player; tape machine; CD player; MP3; Spotify - generational - future proofing Playing Public Cafe 100sqm Kitchen 25sqm Cooking/baking Chance for residents to work here Serving snacks and hot meals and drinks No alcohol licence needed Where the residents will eat their meals too
Public WC 25sqm
93
Use
Sensory Gardens Plants to attract wildlife - animal therapy Scented and edible plants Sculptures Sculpted handrails Multisensory Tactile objects Bright colours Interesting sounds Exercise classes within these garden spaces Yoga/dance/Tai Chi etc. Gardening Raking leaves Planting flowers/ seeds Picking herbs/weeding Reminiscent Room 50sqm Reading ‘Chatting’ Old Newspapers World map - spark memories of travel
94
Access
Access to the development is from the existing footpath track along the west side of the development site. Passage along the track to beyond is also preserved. The design allows for this existing access to be both pedestrian and continues further to provide access for deliveries to the cafe/ kitchen area. The track is currently used for access to Leazes Park and this will continue to be the case, thus change of use for the access has not been sought. The development benefits from the same public transport provision as is existing. Given it’s location adjacent to the RVI, this is plentiful along Richardson Road. Parking will be “on street� and in Leazes Park car park as existing. Access is via level approach and a level threshold. The development has an accessible WC at entry level. Door opening widths and circulation within the principal storey comply with part M requirements.
95
Apperance
The development will take aesthetic inspiration from the park environment and conservation area guidelines. The design of the buildings is of a high quality and has regard to the character and appearance of the surrounding buildings and landscape. The buildings adhere to the local vernacular. The design is intended to preserve and enhance the character of the existing landscape.
stage
98
structure
Part a
A1
B2 buildings other than swelling houses
fire safety
Part b
Loading The building will be constructed so
A2
Ground Movement The building will be constructed
A3
Disproportionate collapse The
building
shall
be
that the combined dead, imposed
so that ANY ground movement
constructed so that in the
and wind loads are transmitted
will not impair the stability of
event of an accident the
to the ground safely and without
the building.
building will not suffer collapse
causing deformation of any parts
disproportionate
of this or another other building.
cause.
from
the
B1: Means of warning and escape
The building shall be designed and constructed so as to provide
B2: Internal fire spread (linings)
reasonable facilities to assist firefighters in the protection of
B3: Internal fire spread (structure)
life. Richardson road is the closest main access to the site.
B4: External fire spread
Similar provisions will be made for this development as the
B5: Access and facilities for the fire service
existing provisions for Springbank Pavilion.
Design for vertical escape will apply to the accommodation cluster of the building. Design for horizontal escape will apply to all. Smoke and heat alarms to BS EN, 14604 will be installed and mains-operated and inter-linked with standby power to conform with approved document B2.
99
The red circles in the diagram opposite denote indicative fire exits in the cafe cluster. The dotted red lines show distances for escape. The plan complies with fire regulations that the distances in one direction do not exceed 18m and 45m in more than 1 direction.
All habitable rooms on upper and lower ground floor open up to hall leading to a suitable exit, or contain an escape window. All habitable rooms on the first floor open up to a hall leading to a protected stairway in
compliance
document B2.
with
approved
100
Part c
C1
Preparation of site and resistance to contaminants
site preparation
Site vegetation will be cleared at the commencement
Resistance to Moisture The walls floor and roof will be constructed to
of the works and has been included for in the
provide adequate protection from ground moisture,
elemental costing plan. This includes the felling and
precipitation, condensation and spillage.
removal of 2No. trees.
No part of the building works will contain or use any toxic substances. Insulating
material
inserted into a cavity wall will have reasonable precautions
taken
to
prevent permeation of any toxic fumes.
Part e resistance to sound
toxic substances
Part d
C2
E1: Protection against sound from the building and adjoining building
This does not apply as there are no adjoining buildings.
E2: Protection against sound within a dwelling house
This does not apply as the building is not a dwelling house.
E3: Reverberation in common parts of buildings for residential purposes.
This will only apply to the accommodation cluster of the development. The
building will be constructed to ensure that reverberation around the common areas is no more than is reasonable. E4: Acousitc conditions in schools - does not apply
101
ventilation
Part f
Adequate
ventilation
will
be provided throughout the building, via both active and passive strategies.
Mechanical ventilation to be provided to all wet and sanitary accommodation as follows:
Kitchens - 30 l/sec extract rate if in cooker hood, or 60 l/sec if independent.
Bathrooms
-
15
l/sec
automatically operated with minimum 15 minute over run on light switch.
102
There will be suitable installation and provision of drinking water,
softened water to wash basins, showers and sanitary conveniences, and wholesome water to any sink. This will apply to the cafe cluster for the public WCs and kitchen area. G2: Water efficiency
Fixtures and fitting will be installed to prevent any undue consumption
of water.
Part h
drainage
This will apply to the cafe cluster for the public WCs and kitchen area. G4 Sanitary conveniences and washing facilities Adequate sanitary provisions will be provided in bathrooms and
kitchens. This will apply to the cafe cluster for the public WCs and kitchen area. G5: Bathrooms
G5 applies to dwellings and buildings containing one or more rooms
for residential purposes. This will apply to the accommodation cluster of the development. A bathroom will provide a washbasin and either a fixed shower or bath. G6: Kitchens and food preparation areas
water will be connected to the mains sewage. H2:
Wastewater
treatment
systems and cesspools - does not apply as connection is to mains
There will be sufficient supply of heated wholesome water washbasins,
showers, baths and sinks for food preparation.
H1: Foul water drainage - all foul
sewage.
G3: Hot water supply and systems
A sink must be provided in any area where food is prepared.
Part k
protection from falling
sanitation
Part g
G1: Cold water supply
K1: Stairs, ladders and ramps will be designed, constructed and installed to be safe. Ramps will be designed to be accessible for wheelchairs, which means the incline must be maximum 1:12 ratio of rise:going up to 2m going.
103
the buildings. Any hard landscaping will provide adequate run off drainage to the mains system. H4: Building over sewers - does not apply. H5: Separate systems of drainage - Any system for discharging water into the mains sewer will be separate from that provided for the conveyance of foul water from the building. H6: Solid waste storage - Adequate provision shall be made for the storage of solid waste.
Part j fuel storage
H3: Rainwater drainage - Cast iron gutters and rainwater pipes will carry water from the roof of
Does not apply as no fuel will be stored in the building. There
will
be
no
fixed
combustion appliances or oil storage tanks.
K2: Protection from falling - stairs and ramps will be provided with balustrades. K3:Vehicle barriers and loading bays - does not apply. K4: Protection against glazing: glazing will be obscured or hold manifestations to ensure that injuries are not sustained from people moving around the building (this will be particularly important for people with dementia as visual perception difficulties is a common symptom of the condition); protection from collision with opening windows; safe opening and closing of windows; safe access for cleaning windows. K5: Protection against impact from and trapping by doors; provision will be made to prevent any door from falling on a person or trapping a person; provision shall also be made for any power assisted door to be opened in the event of a power failure.
104
Conservation of fuel and power in new buildings other than dwellings For the purposes of this project the following values will be an initial guideline for fabric U-values: External walls - 0.35 w/ m2 k Floor - 0.25 w/ m2 k Roof - 0.25 w/ m2 k External doors and Windows - 2.2 w/ m2 k
Design air permeability at 50pa- 10.0m3/hr.m2
P
art m M1
access and use
S tage 4 fuel and power
P
art l L2A
Reasonable provision will be made for people to access and use the building and its facilities.
Entrances to the building will be over level threshold.
Lifts and ramps will be provided where necessary so that people, regardless of disability, can access all parts of the building.
Main heating system - boiler system with underfloor heating comprising of gas fired system boiler with
Passing places must be 1.8m wide
minimum efficiency of 88%
minimum.
Low energy lights
Floor finishes will be firm, durable
Percentage of fixed lights with low energy fittings = 100%
and slip resistant.
105
electrical
protect
the
items
will
persons
operating, maintaining or altering installations from fire or injury.
materials and workmanship
Regulation 7
Does not apply to buildings other buildings.
than
dwelling
Part r
communications
of
Part q
security
electrical safety
Part p
The design and installation
*Effective January 2017 The new building will have the
necessary
physical
in-building
infrastructure
to
enable connections to superfast broadband.
The suitability of materials for a specific purpose must adhere to a minimum British Standards. Compliance with CE standards would be preferred, however these regulations may change with the trigger of article 50 as discussed previously
Invitation to tender
106
Dear Sirs LEAZES PARK Erection of 1 No. Respite Centre
We note that you wish to tender for these works. We enclose: •
A CD containing: Preliminaries, Specifications & Schedule of Works, the tender drawings,
Pre-construction Information and the Form of Tender •
an addressed envelope in which to return the tender
The completed form of tender, sealed in the envelope provided, should reach this office not later than 12 noon on Friday 01st September 2017.
107
Please note that: 1.
Drawings and details may be inspected at Pearce Bottomley Architects.
2.
The site may be inspected by arrangement with the clients. Please contact Pearce
Bottomley Architects to make arrangements. 3.
Any queries should be raised with Pearce Bottomley Architects at this office.
4.
The building owner reserves the right to accept any tender from those submitted or to
refuse them all.
Please confirm that you have received this letter and enclosures and that you are prepared to tender in accordance with these instructions.
The contract to be prepared will be a JCT Intermediate Building Contract with Contractors Designed Portion of Mechanical and Electrical Works.
108 Design Responsibility Matrix incorporating Information Exchanges 2 - Concept Design
Aspect of design Classification
Title
3 - Developed Design
Design team
4- Technical Design
Design team Level of information Design responsibility (LOI)
4 - Technical Design
Design team
Level of detail (LOD)
Level of information (LOI)
Design responsibility
Contractor
Design responsibility
Level of detail (LOD)
Level of detail Level of (LOD) information (LOI)
Design responsibility
Level of detail (LOD)
Level of information (LOI)
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Stage 4
Ss_15 - EARTHWORKS Ss_15_10_30
Excavating and filling systems
Ss_15_30_90
Timber repair and renovation systems
Ss_20 - STRUCTURAL SYSTEMS Ss_20_05_65
Piling systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_20_10_70
Shelter systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_20_10_75
Structural framing systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25 - WALL AND BARRIER SYSTEMS Ss_25_10_20
Curtain walling systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_10_30
Framed partition systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_10_32
Framed wall structure systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_10_35
Framed glazed systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_12_80
Structural glass wall systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_13_33
Glass wall systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_14_63
Post, rail and board fence systems
Robinson Landscape Design
2
2
Robinson Landscape Design
3
3
Robinson Landscape Design
4
4
R Barker Builders
4
4
Ss_25_14_67
Post, wire and mesh fence systems
Robinson Landscape Design
2
2
Robinson Landscape Design
3
3
Robinson Landscape Design
4
4
R Barker Builders
4
4
Ss_25_15_60
Robinson Landscape Design
2
2
Robinson Landscape Design
3
3
Robinson Landscape Design
4
4
R Barker Builders
4
4
Ss_25_20_08
Pedestrian safety barrier and guarding systems Board cladding systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_20_85
Stone cladding systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_25_85
Stone lining systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_30_20
Door, shutter and hatch systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_30_95
Window systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_32_35
Gate systems
Robinson Landscape Design
2
2
Robinson Landscape Design
3
3
Robinson Landscape Design
4
4
R Barker Builders
4
4
Ss_25_36_95
Vehicle access point control systems
Robinson Landscape Design
2
2
Robinson Landscape Design
3
3
Robinson Landscape Design
4
4
R Barker Builders
4
4
Ss_25_38_20
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_45_02
Door, window and gate hardware systems Acoustic covering systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_45_70
Render and roughcast coating systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_45_72
Rendered insulation systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_45_85
Sprayed coating systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_45_88
Tiling systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_50_45
Louvre and shading systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_60_30
Fire stopping systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_60_35
Glazing systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_25_60_50
Metal sheet wall flashing and weathering systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_30 - ROOF, FLOOR AND PAVING Ss_30_10_30
Framed roof structure systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_30_20_70
Raised floor systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_30_20_90
Wood and composite unit flooring systems Wood strip and board fine flooring systems Rooflight and window systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_30_20_95 Ss_30_30_72
Ss_32 - DAMP-PROOFING, WATERPROOFING AND PLASTER FINISHING Ss_32_20_20
Damp-proof courses renewal and insertion systems Floor damp-proofing systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_32_20_30
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_32_20_95
Wall damp-proofing systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
109
Building contractor Contractor's designed portion
Collateral Warranty required?
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Notes
110
Ss_32_46_50 Ss_32_46_65
Metal lathing and anchored mesh reinforcement systems Plaster coating systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_35 - STAIR AND RAMP SYSTEMS Ss_35_10_25
External stair and ramp systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_35_10_40
Internal stair and ramp systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_40 - SIGNAGE, FITTINGS, FURNISHINGS AND EQUIPMENT SYSTEMS
Stage 4
Ss_40_10_25 Ss_40_10_30
External signage and interpretation systems Fire and safety signage systems
Ss_40_10_40
Internal architectural signage systems
Ss_40_15_25
Catering FF&E systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_40_15_35
General and joinery FF&E systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_40_15_46
Laundry FF&E systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_40_15_75
Sanitary appliance systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_40_20_30
External public realm FF&E systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_40_90_60
Painting and clear finishing systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_40_90_95
Wood preservative and fire retardant treatment systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_45 - FLORA AND FAUNA SYSTEMS Ss_45_10_10
Bird and vermin control systems
Pearce Bottomley Architects
2
2
E2 Consultants
3
3
E2 Consultants
4
4
R Barker Builders
4
4
Ss_45_10_95
Vegetation control systems
Pearce Bottomley Architects
2
2
E2 Consultants
3
3
E2 Consultants
4
4
R Barker Builders
4
4
Ss_45_35_05
Pearce Bottomley Architects
2
2
E2 Consultants
3
3
E2 Consultants
4
4
R Barker Builders
4
4
Ss_45_40_95
Amenity and ornamental planting systems Vertical planting systems
Pearce Bottomley Architects
2
2
E2 Consultants
3
3
E2 Consultants
4
4
R Barker Builders
4
4
Ss_45_70_05
Animal conservation systems
Pearce Bottomley Architects
2
2
E2 Consultants
3
3
E2 Consultants
4
4
R Barker Builders
4
4
Ss_50 - DISPOSAL SYSTEMS Ss_50_30_02
Rainwater drainage systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_50_30_04
Above ground waste water drainage Pearce Bottomley Architects systems Below ground gravity drainage systems
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Below ground pumped drainage systems Land drainage systems
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Pearce Bottomley Architects
2
2
Pearce Bottomley Architects
3
3
Howard Marsdon
4
4
R Barker Builders
4
4
Ss_50_30_08 Ss_50_30_10 Ss_50_30_45
Ss_60 - HEATING, COOLING AND REFRIGERATION SYSTEMS Ss_60_40_15
Combined heating, cooling and power
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
R Barker Builders
4
4
Ss_60_40_17
Cooling systems
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
R Barker Builders
4
4
Ss_60_40_36
Heat pump systems
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
R Barker Builders
4
4
Ss_60_40_37
Heating systems
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
R Barker Builders
4
4
Ss_60_60_15
Cold room systems
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
R Barker Builders
4
4
Ss_65 - VENTILATION AND AIR CONDITIONING SYSTEMS Ss_65_40_33
General space ventilation systems
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
R Barker Builders
4
4
Ss_65_40_80
Smoke extract and control systems
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
R Barker Builders
4
4
Ss_65_40_94
Vehicular space ventilation systems
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
R Barker Builders
4
4
Ss_65_80_05
Central air conditioning systems
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
R Barker Builders
4
4
Ss_65_80_45
Local air conditioning systems
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
[Not decided]
R Barker Builders
4
4
Ss_70 - ELECTRICAL SYSTEMS Ss_70_10_80
Solar power generation systems
Pearce Bottomley Architects
2
2
Apollo Lighting
3
3
Apollo Lighting
4
4
R Barker Builders
4
4
Ss_70_30_45
Low-voltage systems
Pearce Bottomley Architects
2
2
Apollo Lighting
3
3
Apollo Lighting
4
4
R Barker Builders
4
4
Ss_70_30_80
Small power systems
Pearce Bottomley Architects
2
2
Apollo Lighting
3
3
Apollo Lighting
4
4
R Barker Builders
4
4
Ss_70_80_25
External lighting systems
Pearce Bottomley Architects
2
2
Apollo Lighting
3
3
Apollo Lighting
4
4
R Barker Builders
4
4
Ss_70_80_33
General space lighting systems
Pearce Bottomley Architects
2
2
Apollo Lighting
3
3
Apollo Lighting
4
4
R Barker Builders
4
4
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
111
112
15
26
37
48
59
10 6
11 7
12 8
18/09/2017
Week Commencing 25/09/2017
04/09/2017 02/10/2017
11/09/2017 09/10/2017
18/09/2017 16/10/2017
25/09/2017 23/10/2017
02/10/2017 30/10/2017
09/10/2017 06/11/2017
16/10/2017 13/11/2017
23/10/2017 20/11/2017
Drainage Drainage 1st Fix Plumbing 1st Fix Plumbing Plastering Plastering 2nd Fix Joinery 2nd Fix Joinery 2nd Fix Electrical2nd Fix Electrical
2nd Fix Plumbing2nd Fix Plumbing Tiling Tiling Decorating Decorating External Works External Works Handover and Clean Handover and Clean Snagging Snagging
14 1115 1216 1317 14 18 913 10
13/11/2017 11/12/2017 20/11/2017 18/12/2017 27/11/2017 25/12/2017 04/12/2017 01/01/2018
4
06/11/2017 04/12/2017
3
30/10/2017 27/11/2017
2
11/09/2017
TASK TASK Site set up Site set up Excavation Excavation Foundation preparation Foundation preparation Setting out substructure Setting out substructure Superstructure Superstructure 1st Floor joists 1st Floor joists Roof timbers Roof timbers Roof coverings Roof coverings 1st Fix Joinery 1st Fix Joinery 1st Fix Electrical 1st Fix Electrical Windows and Doors Windows and Doors
1
04/09/2017
Week Commencing
Stage 4
Springba
36 33 37 34 38 35 39 36 40 37 41 38 42 39 43 40 44 41 45 42 46 43 47 44 48 45 49 46 50 47 51 48 52 49 50 51
14/05/2018 23/04/2018 21/05/2018 30/04/2018 28/05/2018 07/05/2018 04/06/2018 14/05/2018 11/06/2018 21/05/2018 18/06/2018 28/05/2018 25/06/2018 04/06/2018 02/07/2018 11/06/2018 09/07/2018 18/06/2018 16/07/2018 25/06/2018 23/07/2018 02/07/2018 30/07/2018 09/07/2018 06/08/2018 16/07/2018 13/08/2018 23/07/2018 20/08/2018 30/07/2018 27/08/2018 06/08/2018 13/08/2018 20/08/2018
27 24 28 25 29 2630 27 31 2832 2933 30 3431 35 23 32
07/05/2018 16/04/2018
30/04/2018 09/04/2018
23/04/2018 02/04/2018
19/03/2018 16/04/2018 26/03/2018
19/02/2018 19/03/2018 26/02/2018 26/03/2018 05/03/2018 02/04/2018 12/03/2018 09/04/2018
12/02/2018 12/03/2018
26 22
05/02/2018 05/03/2018
21 18 22 19 23 20 24 21 25 15 19 1620 17
29/01/2018 26/02/2018
22/01/2018 19/02/2018
15/01/2018 12/02/2018
08/01/2018 05/02/2018
01/01/2018 29/01/2018
25/12/2017 22/01/2018
11/12/2017 08/01/2018 18/12/2017 15/01/2018
113
ank ‐ New Respite Centre ‐ Construction Programme Springbank ‐ New Respite Centre ‐ Construction Programme
meeting
Pre-construction
114
SECTION 1 – RELEVANT PERSONNEL
Contract Title:
Silver Street – New Dwelling
Employer: The Alzheimer’s Society 43-44 Crutched Friars London England EC3N 2AE Main Contractor:
R Barker Building Contractors
487 Leeds Road Scholes Leeds LS15 4DA Tel: 07967 650989
E-Mail: rbarkerbuilders@hotmail.com
115
Structural Engineer:
Howard Design Associates
24 Glovers Crescent
Ripon HG4 2TB Tel: 01765 692 686
Fax: 01765 677005
E Mail : howard.marston@unicombox.co.uk
Contact: Howard Marston
Architect: Pearce Bottomley Architects Roman Ridge Main Street Aberford Leeds LS25 3AW Tel: 0113 2812000
Fax: 0113 2812911
Contact: Lauren Di Pietro
Stage 4
116
SECTION 2 – CONTRACT
ACTION
P2.01 Contract Details:
Date of Possession:
09th October 2017
Date for Completion: 23rd January 2019
Contract Period:
Contract Sum:
104 weeks
ÂŁ1,600,000
P2.02 Possession:
Possession of Site to be taken by Contractor on 09th October 2017.
P2.03 Contract documents:
The contract is to be JCT Intermediate Building Contract 2011.
The contract will be executed under hand.
Contract Documents comprise: Form of contract (as above); Specification and Schedule
of Work; Drawings as attached drawing issue sheet.
Contract documents to be prepared by PBA and handed to contractor for signing.
To be returned to PBA for forwarding to client. Client to countersign and return to PBA for safekeeping.
117
P2.04 Defects Liability
Period: 12 months.
P2.05 Liquidated Damages:
£1,000 per week or part thereof.
P2.06 Insurance Cover:
Clause 5.3 Public Liability Insurance cover for any one occurrence or series of
occurrences arising out of one event - £1M To be held by the contractor. Evidence of this insurance has been issued by contractor to PBA.
Clause 5.4 Insurance of the works:
Option B applies. Insurance of the works by the Contractor in joint names.
P2.07 Valuations:
Valuations at one-month intervals. The certificate to be used will by RIBA Certificate
of Progress Payment. Payment to the main contractor will be within 14 days of the certificate being issued by the Architect. Date of first valuation to be two weeks from start on site. Invoices to be made out to The Alzheimer’s Society.
Stage 4
118
SECTION 3 – INFORMATION P3.01 Architect’s Instructions:
Instructions are to be given only by Pearce Bottomley Architects. It is necessary for all
variations to be costed and the co-operation of the main contractor is requested. Only written instructions by the Architect are valid and all oral instructions are to be confirmed in writing. The contractor should promptly notify the Architect of any written confirmations outstanding. P3.02 Information to Contractor
2 no copies of construction drawings to be issued following revisions.
P3.03 Information to Client
1 no. copy of construction drawings to be issued following revisions.
P3.04 Information to Architect
Copies of M&E sub-contractors design proposals and programme.
P3.05 Drawings/Documents
Distribution Requirements: Unless otherwise stated – information to be issued
electronically.
119
P3.06 Provisional Sums:
Provisional Sums as listed in Specification and Schedule of Work to be expended in due
course by issue of Architects Instructions. P3.07 Contractor’s Quality Plan:
Contractor is not QA certified under BS EN 9001 – 9003. It is the main contractor’s
responsibility to ensure quality control and to supervise the progress of the works. P3.08 Programming/
Phasing:
Principal contractor to prepare a detailed programme for monitoring
throughout the contract period. Programme must include for and be agreed by the sub – contractors. It must contain adequate separate work elements to measure progress. The Contractor is to allow for ordering of windows/doors/ etc within programme.The programme is to include for cleaning and commissioning prior to handover. P3.9 Information Required:
Contractor to advise consultants as soon as possible for any information required. The
contractor’s information required from consultants must relate to the programme of works and must be kept up to date and must allow reasonable time.
Stage 4
120
SECTION 4 – HEALTH AND SAFETY P4.01 Records:
Records should be kept of materials, services, etc., to facilitate the preparation of the
Building Manual upon completion. The Building Manual is to be in place at Practical Completion or soon thereafter. P4.02 Responsibility:
It is important that it is recognised that the health and safety on site is the responsibility
of the Principal Contractor. The contractor is to define working areas. P4.03 Asbestos
Thought to be none on site. All removals to be carried out strictly in accordance with
all relevant regulations. 14 days notice required by HSE. P4.04 Contamination
Any contaminated ground uncovered to be notified to CA.
P4.05 Avoidance of Nuisance:
In accordance with legislation. Main contractor to limit disruption, as far as is reasonably
practicable, to adjoining properties. Noise to be kept within acceptable limits.
121
Disruption to existing roads and footpaths to be kept to a minimum.
P4.6 Emergency Procedures:
Contractor to ensure that employees, sub-contractors and any visitors to site are made
aware of all emergency procedures.
SECTION 5 – SITE ORGANISATION P5.01 Site Records:
Main contractor to maintain site records.To include site diary and accident book/visitor
book. P5.02 Signboard:
For delivery purposes
P5.03 Materials/Delivery/Storage:
Main contractor to notify architect of any problems in materials delivery as soon as they
become apparent. P5.04 Facilities / Use of Services:
Contractor to arrange own facilities and arrange for any temporary supply service
required. Contractor to provide on-site phone – this will be Bob’s mobile. Contractor to bring temporary WC to site. Site cabin. Possibly a container.
Stage 4
122
P5.05 Security Arrangements:
Site security to be responsibility of contractor for duration of contract.
Authorised persons with access to the site:-
Employers Architect P5.06 Working Hours:
Generally 8.00am to 4.30pm Monday to Friday. Occasionally, and by agreement with
Client, Saturday 8.00am to 1.00pm.
SECTION 6 – AUTHORITIES P6.01 Local Authority Consents:
a) Planning consent granted.
Copy issued to contractor. No conditions require
discharging.
b) Building Regulations approval. Copy issued to Contractor to notify at key stages.
Inspection fee to be invoiced to Client. P6.02 Statutory Undertakers:
Contractor to liaise with statutory authorities at appropriate points. Details passed to
Contractor.
123
SECTION 7 – ANY OTHER BUSINESS P7.01 Handover requirements:
Allow time for snagging and cleaning.
P7.02 Site Meetings:
Dates for site meetings provisionally set as:
Tuesday 24th October 2017 at 9.30am
Tuesday 21st November 2017 at 9.30am
Tuesday 19 December 2017 at 9.30am
Tuesday 16 January 2018 at 9.30am
Tuesday 13 February 2018 at 9.30am
Tuesday 13 March 2018 at 9.30am
These will coincide with valuations.
124
125
Appendix
126
127
Appendix 1
A clients guide to
engaging an architect
Appendix 128
129
Appendix 130
131
Appendix 132
133
Appendix 134
135
Appendix 136
137
Appendix 138
139
Appendix 140
141
Appendix 142
143
Appendix 144
145
Appendix 146
147
Appendix 148
149
Appendix 150
151
Appendix 152
153
Appendix 154
155
Appendix 156
157
Appendix 158
159
160
161
Appendix 2
Guidance for clients on fees
Appendix 162
163
164
165
Appendix 3 Alzheimers Society financial report
166 48
Alzheimer’s Society
Trustees’ report and annual accounts 2015/16
Appendix
19. Consolidated statement of financial activities For the period ended 31 March 2015 Incorporating an income and expenditure account
Notes
Restricted funds £’000
Unrestricted funds £’000
2015 Group Total £’000
Incoming and endowments from Donations and legacies
2a
Charitable activities
9,020
43,425
52,445
4,770
29,168
33,938
Other trading activities
7c
30
3,360
3,390
Investment income
2b
–
964
964
Other
–
8
8
Total
13,820
76,925
90,745
Less gross incoming resources from joint venture Total incoming resources
–
–
–
13,820
76,925
90,745
Expenditure on Costs of generating funds Raising funds Charitable activities Total
Operating surplus Net gains/(losses) on investments Net income/(expenditure)
3 & 7c
960
15,016
15,976
3
11,869
64,923
76,792
12,829
79,939
92,768
(3,014)
(2,023)
2,971
2,971
991 – 991
(43)
948
Other recognised gains and losses Net interest in joint venture operating result Net movement of funds Funds balance at 1 April 2014 Funds balance at 31 March 2015
–
(8)
991
(51)
(8) 940
9,708
32,587
42,295
10,699
32,536
43,235
In line with the requirements of FRS 102 SORP, the above note shows the split of comparative information between the Funds. The option to prepare a separate note has been taken, over the integration within the existing SOFA (i.e. the six column approach).
20. Related Party Transactions In 2015–16, Alzheimer’s Society charged £129k (2014–15 £321k) to Alzheimer’s Trading Ltd for the provision of staff and the purchase of goods. The balance owed to Alzheimer’s Society at 31st March 2016 was £1,085k. (31st March 2015 £616k). Alzheimer’s Society collected legacy income on behalf of The Alzheimer’s Foundation, to the value of £130k. (2014–15 £99k). The balance owed to The Alzheimer’s Foundation at 31st March 2016 was £23k (31st March 2015 £107k).
167 Alzheimer’s Society
Trustees’ report and annual accounts 2015/16
49
168
169
Appendix 4
Leazes conservation management plan
170 DRAFT LEAZES CONSERVATION AREA MANAGEMENT PLAN
Appendix
CONTENTS
1.
Aims, Context and Introduction 1.1 Aims of the Management Plan 1.2 Context of the Management Plan 1.3 Introduction to the Leazes Conservation Area
2.
Significance, characteristics, key issues and vulnerabilities in the Conservation Area 2.1 Leazes Terrace 2.2 Leazes Crescent 2.3 St Thomas Estate 2.4 St James Terrace and St James Street (West) 2.5 Leazes Park Road East Side 2.6 Leazes Square 2.7 Strawberry Place, Barker & Stonehouse and Benefit Agency Offices 2.8 Percy Street 2.9 Leazes Park
3.
Development Issues within Leazes Conservation Area
4.
Transport Issues within Leazes Conservation Area
5.
Planning Procedures within Leazes Conservation Area
6.
Future Management – 6.1 SWOT Analysis 6.2 Key Points
7.
Future Management – Protection and Enhancement of Leazes Conservation Area
Leazes Conservation Area Management Plan – NC - Nov 2005 (aef) – Version 2
1
171 SECTION SEVEN FUTURE MANAGEMENT – PROTECTING AND ENHANCING LEAZES CONSERVATION AREA This element of the Management Plan provides guidance for the conservation of the historic fabric of Leazes Conservation Area and is to be read in conjunction with the Planning Procedures contained within Section Five of the Management Plan. 1.
Alterations and Extensions
These should not dominate an existing building’s scale or alter the composition of its main elevations. Any alterations, including partial demolition, should respect an existing building and its materials. All new work should complement the old in quality, texture and colour as well as method of construction. Artificial wall claddings and coatings or artificial roof slates will not generally be allowed on any elevation. No more than one externally mounted alarm box will be allowed on an elevation and this should be unobtrusive in both location and colour. 2.
Materials
Planning permission will include conditions to ensure that traditional materials, appropriate to a particular building or site are used. Historically the predominant building materials and finishes within Leazes Conservation Area are natural sandstone, brick and stucco. 3.
Roofs
The roof is one of the most important parts of a property as it makes the building wind and watertight and can bring harmony to a townscape. The original roof material, ridge tiles and hip tiles should be retained and repaired or replaced on a like for like basis. Within the Leazes Conservation Area Welsh Slate is the predominant roofing material. Imitation slates are a poor substitute in quality and appearance for natural slate and detract from the character of a building and would not be allowed on Listed Buildings nor encouraged on unlisted buildings within the Conservation Area. 4.
Dormer Windows and Rooflights
The conversion of loft space and the installation of inappropriate dormer windows and/or rooflights have a negative impact on the appearance of a building and detract from the character of a roofscape. If there is a precedent the host terrace they may be acceptable. Dormer Windows must be of a modest size, have pitched roofs and be built in traditional materials and designs. Rooflights should be a ‘conservation style’ in design, materials and size. 5.
Masonry, Brickwork and Pointing
When repairing a building in a Conservation Area the original character of masonry and/or brickwork walls should be maintained by paying particular attention to the size, shape, colour and surface texture of any new materials and to the style, colour and texture of the mortar pointing Leazes Conservation Area Management Plan – NC - Nov 2005 (aef) – Version 2
38
172 6.
Windows and Doors
Appendix
Windows and doors are important components of a building and any alteration or replacement can significantly alter the character and appearance of a building. Wherever possible the original windows and doors should be retained and repaired in order to keep the integrity of the original design so preserving the character and proportions of the building. The efficiency (thermal capacity and soundproofing) of the windows can be increased through the use of appropriate secondary glazing. Imitation replacement window styles and inappropriate replacement window materials (such as UPVC) are poor alternatives for traditional single pane, timber, vertical sliding sash windows. Mock sliding sash windows generally have heavy top opening casements for the opening section, while UPVC windows have thicker, cruder frames than timber windows. These unsuitable styles and materials impact on the proportions and overall appearance of a window and a building. The character of a building is then changed, which has a detrimental impact on the overall appearance of a townscape and a conservation area. 7.
Chimney Stacks and Other Architectural Details
The shape, height and variety of chimney stacks and other architectural details on buildings in a Conservation Area contribute greatly to the local character and should be retained and repaired. 8.
Rainwater Goods
Original cast iron rainwater goods, such as gutters on brackets, downcomers and hoppers contribute to the character and appearance of buildings in a Conservation Area. UPVC rainwater goods attached to fascia boards have a negative impact on the appearance of a traditional house. Where possible original rainwater goods should be retained and repaired, or replaced on a like for like basis. 9.
Colour and Painting
The architectural unity of Leazes Conservation Area, in whole or part, may depend on the use of specific colours for the decoration of external rendered walls, joinery or railings. Therefore original colour schemes should be retained, such as the colour of the exterior stucco on Leazes Crescent which should be BS 08 B 17. Walls and stone detailing which have traditionally not been painted should remain undecorated. 10.
Aerials, Satellite Dishes and Alarm Boxes
Aerials, satellite dishes and alarm boxes can have a detrimental impact on the appearance of a building. Where possible they should be situated inside or to the rear of a property or carefully located to minimise the impact on the character of the building. 11.
Gardens, Grounds and Trees
The original pattern of gardens and grounds and the presence of trees contribute greatly to the character of Leazes Conservation Area and should be retained.
Leazes Conservation Area Management Plan – NC - Nov 2005 (aef) – Version 2
39
173 12.
Boundary Treatments
Original boundary treatments, such as walls, railings and hedges play and important part in the character and appearance of a Leazes Conservation Area and should be retained and maintained or reinstated where possible. Where reinstated or replaced, original walls and railings should be replicated in terms of material, proportions and design. 13.
Advertisements
All advertisements within Leazes Conservation Area should be sympathetic to its historic character. New advertisement displays will be strictly controlled and the removal of inappropriate signs pursued. There will be a presumption against internally illuminated projecting fascia signs and advertising above ground floor level. Advertisement hoardings of any description will not be appropriate. 14.
New Buildings
There is little scope for new buildings within Leazes Conservation Area, with the exception of the car park sites. Any new buildings in Leazes Conservation Area should be designed with reference to their surroundings and their impact on the character and appearance of the Leazes area. Special attention should be paid to form, height, bulk, materials (style and colour), proportions of openings and detailing of roofs, windows and doors. 15.
Undoing Damage
The Council will use opportunities created through planning applications or other proposals within Leazes Conservation Area to negotiate improvements which remove unsympathetic alterations or additions from existing buildings and which secure the proper repair or restoration of buildings, other structures and the landscape. 16.
Monitoring
The Management Plan will be subject to a 5 year review commencing from the date of adoption and amended accordingly. This review will be undertaken through consultation with the local community and other consultees.
Leazes Conservation Area Management Plan – NC - Nov 2005 (aef) – Version 2
40
174
175
Appendix 5
Elemental cost breakdown
176
Springbank Respite Centre
Price per Unit
Unit
Amount
Value
NB. Elemental pricing has been broken down into 3 sections; café use; activity cluster; accommodation and staff area cluster. This allows for each area to be broken down into elemental costs, based upon the building functions which were used to create the estimated costs based on building square metre for each function. Demolition has been cost as a whole as this isn't specific to the building use. £6,726.74
Appendix
DEMOLITION WORKS Clear the site of rubbish and debris. Demolish all existing structures within the site boundary, up to and including the site boundary only, and remove from site.
INC
INC
Remove roof timbers complete (inc. rafters purlins, ceiling joists, plates etc.) Load into skip; measured flat on plan NB. Not including coverings
£9.23
sqm
120
£1,107.60
Remove softwood floor structure. Withdraw nails ‐ set aside for re‐use Softwood flooring at ground level
£5.96
sqm
120
£715.20
Remove Fascia/Barge Board/Gutter; Load into skip
£10.27
m
54
£554.58
Remove doors and windows; Load into skip Remove solid timber door Remove door frame Window up to 3sqm
£7.30 £3.32 £19.23
item item item
4 2 18
£29.20 £6.64 £346.14
Remove roof coverings; Slates; Set aside for re‐use
£9.79
sqm
120
£1,174.80
Breaking up floor screeds; Up to 100mm thick unreinforced
£7.18
sqm
150
£1,077.00
Hack off wall finishes with chipping hammer; plaster to walls
£7.39
sqm
162
£1,197.18
Remove ceiling finishes; plasterboard and skim
£4.32
sqm
120
£518.40 £17,784.94
SITE CLEARANCE AND PREPARATION ‐ FOR CAFÉ USE Site clearance; fell and remove trees; girth 1500mm ‐ 3000mm
£75.77
item
2
£151.54
Clearing site vegetation; bushes, scrub, undergrowth, hedges, trees and tree shrubs not exceeding 500mm in girth
£1.33
sqm
300
£399.00
Excavating by hand (due to RPAs restricting machinery on site); max. depth not exceeding 4m
£1.13
cubic metres
860
£971.80
177
Filling obtained from excavated material by hand; average thickness over 50mm not exceeding 500mm
£18.91
cubic metres
860
£16,982.25
SUB‐STRUCTURE WORKS ‐ FOR CAFÉ USE Foundation to be sized as per Structural Engineer’s instructions and to a 1.4m as agreed with the Structural Engineer/Building Control Inspector to suit existing bearing strata and ground conditions. Particular care to be taken around trees. Small area with difficult access and limited headroom (inc. provisions of all equipment inc. rig for 50No. pad foundations) Pre‐stressed pre‐cast concrete beam and block floor at ground level; 225mm thick beams; up to 4.2m span
£2,475.00
item
0.33
£816.75
£41.45
sqm
390
£16,165.50
BELOW GROUND DRAINAGE ‐ FOR CAFÉ USE
£231.00
Check invert levels and positions of proposed drains, sewer outlet, inspection chambers and manholes to verify depths and outfall direction (where applicable) and report discrepancies.
INC
Excavate trenches for drains as indicated. PVC pipes with flexible joints, on granular bed and surround and backfill with selected excavated material, all laid strictly in accordance with manufacturer’s written instructions. Allow for all bends and fittings. Allow for concrete beds and surrounds to drains running under building and within 1m of foundations, including all necessary lintels and protection where drains pass through walls. Surface and foul runs are separate.
INC
NOTE: A provisional sum has been included to undertake a percolation test with may result in the design changing. For tender purposes assume the above specification and include all builders work required to achieve this installation. Allow for cleaning out and testing the new drainage system on completion.
£150.00
item
0.33
£49.50
£550.00
item
0.33
£181.50
ABOVE GROUND DRAINAGE ‐ FOR CAFÉ USE Allow for supply and fit of all waste pipework and drains. Allow for cleaning out and testing the new drainage system on completion. Supply and install cast iron rainwater goods to BS 416 (including half round gutters, RWP’s, and accessories) on brackets.
£9,969.44 £2,200.00
0.33
£726.00
113.5
£9,243.44
INC £81.44
m
SUPERSTRUCTURE ‐ FOR CAFÉ USE Supply and fix wall members 75mmx100mm Supply and fix roof members; pitched; 100mmx225mm
£16,262.60
£16,323.29 £7.45
m
113.5
£845.58
£16.60
sqm
390
£6,474.00
178
Supply and fix W type truss (fink); up to 45 degree pitch; 450mm eaves overhang; up to 7m span
£99.53
item
7
£696.71
Acoustic chipboard flooring
£21.30
sqm
390
£8,307.00 £5,990.10
Appendix
Dry‐Lining ‐ FOR CAFÉ USE Dry‐lining to ceiling with 12.5mm plasterboard fixed to 50mm insulation. Allow for skim coat plaster finish and primer to painted areas. Allow for all beadings, stops etc.
Dry‐lining on timber stud partitions with 12.5mm plasterboard as per drawings fixed with nails vertically along studs. Allow for skim coat plaster and primer to painted areas. Allow for framing to reveals to openings. Include for all beadings, stops etc.
£8.20
sqm
390
£3,198.00
£8.20
sqm
340.5
£2,792.10 £847.98
Stairs
Standard staircase; softwood parana pine; dog leg stair; 838mm wide; 2676mm going; 2600mm rise; 2No. Newel posts; with half space landing
Standard balustrade; wrought softwood
£686.12
item
1
£686.12
£161.86
item
1
£161.86
External Cladding
Timber cladding; western red cedar; tongue and groove; horizontal boarding (inc. battens on breather membrane)
£30,423.68
£89.35
Aluminium drip flashing at base of cladding
INC
Supply and fix insect mesh to all ventilation gaps. Allow for stop battens to perimeter of openings.
INC
NB Samples of board to be provided prior to any cladding works take place. All cladding rough sawn and untreated
INC
sqm
340.5
ROOF CONSTRUCTION ‐ FOR CAFÉ USE Natural welsh blue grey slate tiles to BS EN 12326 Part 2; 400mmx250mm slates; 7mm nominal thickness; uniform size; to 75mm lap; on 25mmx50mm battens and type 1F reinforced underlay EXTERNAL WINDOWS AND DOORS ‐ FOR CAFÉ USE
£30,423.68
£21,466.41
£60.13
cubic metres
357
£21,466.41 £34,780.12
179
Supply and install timber vertical sliding sash windows; nobars; complete with ironmongery 1200mmx2100mm 600mmx1050mm External doors; fire door; plywood faced; with half an hour fire rating; 838mmx1981mmx44mm
Standard plain glass to BS EN 14449; clear float panes; 0.15sqm ‐ 4sqm; 4mm thick; obscure patterned for safety Patent glazing; aluminium with alloy bars; 2.55m long at 622mm centres; fixed to supports; thermally broken with low‐e, double glazed, clear toughened; aluminium finished with RAL matte colour
£1,375.00 £700.00
item item
9 4
£12,375.00 £2,800.00
£241.98
item
6
£1,451.88
£79.68
sqm
170
£13,545.60
£383.97
sqm
12
£4,607.64 £105.60
INTERNAL WALLS / PARTITIONS ‐ FOR CAFÉ USE Construct timber non‐loadbearing partition walls as shown on drawings. Partition to comprise of 75 x 38 studs at 600mm ctrs vertically. 100mm compressed mineral wool insulation to be included as necessary and face each side with 12.5mm plasterboard with plaster skim finish and decoration described. Internal face of bathroom walls and WC to be lined with 12.5mm moisture resistant plasterboard to receive tiling described elsewhere.
Allow for forming door openings within all internal walls as indicated on drawings, suitable for door type.
£8.80
m
12
INC £967.92
INTERNAL DOORS ‐ FOR CAFÉ USE Internal doors and frames; fire door plywood faced with half an hour rating; 838mmx1981mmx44mm Include for all ironmongery.
£105.60
£241.98
item
4
£967.92
INC £6,644.77
FIXTURES, FITTINGS, AND MISCELLANEOUS ITEMS ‐ FOR CAFÉ USE Supply and fix floor units (with drawers) 500mmx600mmx870mm 600mmx600mmx870mm 1000mmx600mmx870mm
£197.38 £225.16 £331.81
item item item
10 2 2
£1,973.80 £450.32 £663.62
Sink unit 1000mmx600mmx870mm
£304.81
item
1
£304.81
180
£57.77
m
10
£577.70
Sink with sealant
£389.24
item
1
£389.24
Basin
£209.46
item
6
£1,256.76
Urinal
£342.84
item
3
£1,028.52
Appendix
Kitchen worktop 38mm thick; 600mm wide
£31,951.12
INTERNAL FINISHES ‐ FOR CAFÉ USE Door entrance mats 18mm thick 1800mmx3000mm 900mmx550mm
£1,963.91 £146.41
item item
1 1
£1,963.91 £146.41
Welsh slate floor tiles
£53.96
sqm
230
£12,410.80
Slip resistant vinyl flooring; 2m wide
£22.35
sqm
40
£894.00
£119.01
sqm
120
£14,281.20
£18.79
sqm
120
£2,254.80
Wood block flooring Seal and oil to wood block flooring N.B Include for all finishes as referred to on Finishes Schedule drawing.
INC £1,000.00
DECORATIONS ‐ FOR CAFÉ USE Prepare and apply 1 mist coat and 2 coats emulsion paint to all walls.
INC
To ceilings prepare and apply, 1 mist coat and 2 coats emulsion paint.
INC
Prepare, knot stop, prime and apply 1 no. coat undercoat and 2 no coats full gloss to all new internal joinery. (All windows to be pre‐finished.) (All internal doors to be pre‐finished.)
£920,750.00
Services Excavate for water, gas and electrical supply to end of site set in underground trench. Taken to end of hard landscaping as shown on drawings and capped/terminated in access chamber. Depth, surround and markers. Reinstate to existing surface level and finish.
£500.00
£500.00
181
Contractors Overheads and Profits Provisional Sums Mechanical and Electrical Services and Installation Accommodation based on building prices per sqm Activity cluster based on building prices per sqm Staff Offices based on building prices per sqm
Total Contract Sum
£12,000.00
£12,000.00
£20,000.00 £537,500.00 £270,750.00 £80,000.00
£20,000.00 £537,500.00 £270,750.00 £80,000.00
£1,122,945.35
Plus Other Project Costs Building control fees Architect's Fees Structural Engineers fees Planning Application Water connection Electricity connection Gas connection Desktop site survey Variation of Condition Application Discharge of conditions application Northern Powergrid charges Apollo Lighting Design Robinson Landscape Design Building Services Engineer Total
TOTAL PROJECT COST
£482.00 £56,147.27 £1,500.00 £288.00 £212.50 £198.00 £195.00 £97.00 £988.00 £102.00 £928.00 £1,000.00 £10,000.00 £500.00 £72,637.77
£1,195,583.12
Plus VAT @ 0%
182
183
Appendix 6
Planning applications and drawing issue list
Appendix 184
185
Appendix 186
187
Appendix 188
189
Appendix 190
191
Appendix 192
193
Appendix 194
195
Appendix 196
197
Appendix
198
Drawing Issue List for Planning Application
Location Plan Building Regulations Notes Topographical Survey GA Proposed Site Plan GA Floor Plans GA Sections VSO Sheet 1 GA Sections VSO Sheet 2 GA Elevations Substructure Details Site Layout with Drainage Details Root Protection Fence Locations
199
200
201
References and
bibliography
202
Aecom, (2016). Spon's architect's and builders' price book 2016. 1st ed. Oxon:Taylor and Francis.
Breeam.com. (2017). BREEAM. [online] Available at: http://www.breeam.com/ [Accessed 4 Mar. 2017].
Historic England. (2017). Conservation Areas. [online] Available at: https://historicengland.org. uk/advice/hpg/has/conservation-areas/ [Accessed 1 Mar. 2017].
Dqi.org.uk. (2017). DQI - Home. [online] Available at: http://www.dqi.org.uk/ [Accessed 6 Mar. 2017].
HM Revenues and Customs. (2017). VAT Notice 708: buildings and construction - GOV.UK. [online] Available at: https://www.gov.uk/government/publications/vat-notice-708-buildingsand-construction/vat-notice-708-buildings-and-construction [Accessed 12 Mar. 2017].
203
Kell, A. and Mordue, S. (2015). Levels of definition - Technical Support - NBS BIM Toolkit. [online] Toolkit.thenbs.com. Available at: https://toolkit.thenbs.com/articles/levels-of-definition [Accessed 5 Mar. 2017].
Newcastle City Council. (2006). Leazes Conservation Area Management Plan. [online] Available at:
https://www.newcastle.gov.uk/planning-and-buildings/planning-policy/supplementary-
planning-documents/leazes-conservation-area-management-plan-spd [Accessed 2 Jan. 2017].
RIBA (2013), “RIBA Plan of Work�. London: RIBA Publications
Trading Economics. (2017). United Kingdom Inflation Rate | 1989-2017 | Data | Chart | Calendar. [online] Available at: http://www.tradingeconomics.com/united-kingdom/inflation-cpi [Accessed 12 Mar. 2017].