1 minute read
ASSEMBLY SEQUENCE
11.
14. The facade assembly concludes with the mounting of the horizontal cladding panels. The horizontal panels are installed as the last element since the scaffolding structure is secured in the hole designated for this element. By synchronizing the dismantling of the scaffolds with the placement of the horizontal panels. Installed manually from the exterior with the help of scaffolding.
Advertisement
15. Sealing of the joints with rubber band tape to ensure the third line of defense of the facade against rain and for aesthetic reasons. Installed manually from the exterior with the help of scaffolding.
16. Once the installation of the façade is completed, the installation of the floors of the interior spaces is continued. The first step consists of the placement of hard insulation on the