common terrace garden - porous facade enable light penetration into the corridors


Advertisement
06 07 08
2017 // June - August 06 Precast fins - panels installation commenced on site. // Tonality is difficult to control so some of the panels were of different tones from each other. For such cases, the affected panels would be dismounted & reinstalled for review & approval.
07 Propping for the podium staircase finally removed - the trumpet form is finally revealed. (see pg. 13 for detail drawings)
08 For most parts, architectural & M&E mock-up works have begun. Detail drawing // Precast Panels