2017 // June - August 06

Precast fins - panels installation commenced on site. // Tonality is difficult to control so some of the panels were of different tones from each other. For such cases, the affected panels would be dismounted & reinstalled for review & approval.

07

Propping for the podium staircase finally removed - the trumpet form is finally revealed. (see pg. 13 for detail drawings)

08

For most parts, architectural & M&E mock-up works have begun.

08

Detail drawing // Precast Panels