CRITICAL TIMELINE

Preliminary Pre-Development Schedule

Key Activities

6-12 Month Pre-Development Activities

Targeted Start/ End Date

April 2016 Present feasibility study to City Council Planning and Public Safety Committee and discuss next steps

May/June 2016 Work with City Council to identify sources of preliminary funding during Budget Review Session

June/July 2016 Initiate conversations with critical property owners to validate property acquisition assumptions from feasibility study

June/Sept 2016 Perform site survey to determine ownership and property appraisals

July/Dec 2016 Negotiate 6 - 12 month assignable options on critical properties

July/Dec 2016 Engage Library and potential consultant on community-based programming process to determine uses, services and space needs

July/Dec 2016 Identify and formalize partnerships for redevelopment activities

Sept 2016 Bid out work for schematic design and preliminary engineering work

Nov 2016/Mar 2017 Perform schematic design and preliminary engineering work

Q4 2016/Q1 2017 Apply for and secure initial funding and financing for project