Interior Construction Drawing

Page 1

CONSTRUCTION PACKAGE

Bachelor of Arts in Interior Design

Final Major Project

Coursework 2

Wai See Hui

002BA17ID2107

April 2022

Lecturer's Name: Carlo Joson


Table of Content PAGE A

DRAWING TITLE TABLE OF CONTENT

SCALE N.T.S

SIZE A3

B 1

PERSPECTIVES LOCATION PLAN

N.T.S N.T.S

A3 A3

N.T.S

A3

SITE PLAN 2 GENERAL ARRANGEMENT PLANS 3 FIRST FLOOR GENERAL ARRANGEMENT PLAN

1:250

A3

4 5

SECOND FLOOR GENERAL ARRANGEMENT PLAN THIRD FLOOR GENERAL ARRANGEMENT PLAN

1:250 1:250

A3 A3

6

ROOF TOP GENERAL ARRANGEMENT PLAN

1:250

A3

FRONT ELEVATION

1:200

A3

SIDE ELEVATION 1

1:200

A3

SIDE ELEVATION 2

1:200

A3

GENERAL SECTION 1 GENERAL SECTION 2 11 FOCUS AREA 1: SOCIAL AREA, F&B AREA, COMMUNAL KITCHEN

1:200 1:200

A3 A3

ISSUE DATE

REMARKS

GENERAL ELEVATIONS 7 8 9 GENERAL SECTIONS 10

FIRST FLOOR SETTING OUT PLAN

1:150

A3

SECOND FLOOR SETTING OUT PLAN FIRST FLOOR FURNITURE LAYOUT PLAN

1:150 1:150

A3 A3

SECOND FLOOR FURNITURE LAYOUT PLAN

1:150

A3

FIRST FLOOR REFLECTED CEILING PLAN SECOND FLOOR REFLECTED CEILING PLAN

1:150 1:150

A3 A3

FIRST FLOOR FLOOR FINISHES PLAN SECOND FLOOR FLOOR FINISHES PLAN

1:150 1:150

A3 A3

FOCUS AREA 1: JOINERY DETAILS 20 J-02: WALL & BAR SEATING AREA DETAIL

1:40

A3

J-02: WALL & BAR SEATING AREA DETAIL J-03: WALL & DINING AREA 1 DETAIL

1:10 1:40

A3 A3

J-03: WALL & DINING AREA 1 SECTION DETAIL J-04 WALL & DINING AREA 2 DETAIL

1:10

A3 A3

12 13 14 15 16 17 18 19

21 22 23 24 25 26 27 28 29

J-04 WALL & DINING AREA 2 DETAIL J-04 WALL & DINING AREA 2 SECTION DETAIL J-06: DINING AREA ARC WALL DESIGN DETAIL

A3 A3

J-09: COMMUNAL KITCHEN COUNTER DETAIL J-09: COMMUNAL KITCHEN COUNTER SECTION DETAIL

1:20 1:10

A3 A3

31 32 33

SETTING-OUT PLAN

1:50

A3

FURNITURE LAYOUT PLAN

1:50

REFLECTED CEILING PLAN FLOOR FINISHES PLAN

1:50 1:50

A3 A3

FOCUS AREA 2: JOINERY DETAILS 34 J-11: MERCHANDISE DISPLAY

40 41 42

A3

1:15 / 1:30 / 1:100

A3

1:30 1:15

A3 A3

1:40 1:25

A3 A3

FOCUS AREA 1 FIRST FLOOR WALL DETAILS FOCUS AREA 1 & 2 FLOOR DETAILS

1:5 1:5

A3

FOCUS AREA 1 CEILING DETAILS FOCUS AREA 1 CEILING DETAILS

1:8 1:25 / 1:15

A3 A3

J-12: RETAIL SHELVING 1 DETAIL J-12: RETAIL SHELVING 1 SECTION DETAIL

37 J-14: RETAIL SHELVING 3 DETAIL 38 J-14: RETAIL SHELVING 3 DETAIL TYPICAL DETAILS: WALL, CEILING & FLOOR 39

A3

1:15 1:40

FOCUS AREA 2: RETAIL AREA 30

35 36

1:40 1:40

A3

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

TABLE OF CONTENT

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

00


SCHEDULES: FOCUS AREA 1 & 2 43

DOOR SCHEDULE

N.T.S

A3

44 45

WINDOW SCHEDULE MATERIAL & FINISHES SCHEDULE FURNITURE & EQUIPMENT SCHEDULE

N.T.S N.T.S

A3 A3

LIGHTING SCHEDULE

N.T.S N.T.S

A3 A3

ROOM FINISHES SCHEDULE

N.T.S

A3

50 52 53

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

TABLE OF CONTENT

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

00


GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

PERSPECTIVES

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

B


LA JA K

AK A ME L

RA PE

LA N

N

JALA

JA

TU

JALAN MELAYU

N PAN

N AM G

GATE BLRT MASJID JAMEK

AN

H

G

P AM

NA NA S

BO

LE

JA

LA

N

TU N

H

SL

EE

JA L

AN

BU

KIT

MASJID JAMEK MRT

LA N

GE

RE

JA

JALAN

RAJA

AN CHUL

JA

LA

N

HA

NG

LE

KIU

JA

ER RIV

EN

KL

TA

AN

NG

G

AH

AHKAM

UKIT M

B JALAN

NB LA JA

H

JALAN RAJA CHULAN

JA

G

AN

LA N

P AM

BO

LE

TU N

PE

1 1

JA

ME DA

LA N

NP

TU

AS

N

H

AR

SL

EE

RA K

LOCATION PLAN SCALE N.T.S

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

NORTH SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

LOCATION PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

01


CCP CAR PARK

ES TR

IA

N

W

AY

TM OFFICE TOWER

BU

JA LA N

TU

JA LA N

N

H

PE D

S

BU KI TN

LE E

AN AS

TM OFFICE TOWER

IL

D

IN

G

PE D

ES TR

LE KI U

IA N

AY

JA

LA

HA NG

N

G

ER

LA N JA

W

Y

EJ

IAN

WA

TR ES

D PE

A

BANGUNAN ASIA INSURANS

N JALA

LAN

HU JA C

RA

N JALA

H KAMA H A TM BUKI STARCOM MALAYSIA

BANGUNAN YEE SENG

1 2

SITE PLAN SCALE N.T.S NORTH

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

SITE PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: JULY 2021

DATE: 20-04-2022 SCALE: NTS

SHEET:

02


GENERAL ARRANGEMENT PLANS


A

B

C

D

E

F

G

H

I

J

K

L

M

L

M

61620 18210

3285

3285

3285

3285

3285

3285

3285

3240

4160

9775

9775

2990

1

3240

1 11

3130

2 3

UP

8400

SOCIAL AREA 104

1 10

F&B AREA 105

UP

KICHEN AREA 106

LIBRARY 103

DN

2660 6330

5

33335

4

UP

RETAIL AREA 107 MAIN ENTRANCE 100 OUTDOOR PERFORMANCE AREA 110

6

SECURITY ROOM 101

RECEPTION AREA 102 UP

UP

MALE TOLIET

9825

108

FEMALE TOLIET 109

7

1 3

FIRST FLOOR GENERAL ARRANGEMENT PLAN

2 3

SCALE 1:250

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

FIRST FLOOR MEZZANINE LEVEL SCALE 1:250

NORTH

DRAWING TITLE:

FIRST FLOOR GENERAL ARRANGEMENT PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:250

SHEET:

03


A

B

C

D

E

F

G

H

I

J

K

L

M

61620 18210

3285

3285

3285

3285

3285

3285

3285

3240

2990

1

3240

9775

STORAGE 206

3130

2

4160

3

1 11

COMMUNAL KITCHEN 205

DN

209 STORAGE

8400

LIBRARY 201 CAFE AREA 202

1 10

DN UP DANCING STUDIO 208

2660

DINING AREA 207

6330

5

33335

4

SERVER 212 ROOM WORKSHOP AREA 203

6

DANCING ROOM 210

IT ROOM 211 PRAYER ROOM 213

9825

UP

UP

MALE 216 TOLIET

STORAGE 204 FEMALE TOLIET 217

CLEANER ROOM 214

STORAGE 215

7

1 4

SECOND FLOOR GENERAL ARRANGEMENT PLAN SCALE 1:250 NORTH

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

SECOND FLOOR GENERAL ARRANGEMENT PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:250

SHEET:

04


A

B

C

D

E

F

G

H

I

J

K

L

M

61620 18210

2990

1

3240

3285

3285

3285

3285

3285

3240

4160

9775

OUTDOOR AREA 310

STORAGE 302

1 11

STORAGE 309

3

33335

1 10

RECEPTION AREA 307

VOID

ART STUDIO 301

ACTIVITY AREA 308

2660

8400

DN

4

EXHIBITION 303

6330

5

3285

3130

2

3285

6 9825

DN

MEETING 305 ROOM

DN

DIRECTOR ROOM 306

MALE TOLIET 311

FEMALE TOLIET 312

ADMINISTRATION AREA 304

7

1 5

THIRD FLOOR GENERAL ARRANGEMENT PLAN SCALE 1:250 NORTH

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

THIRD FLOOR GENERAL ARRANGEMENT PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:250

SHEET:

05


A

B

C

D

E

F

G

H

I

J

K

L

M

61620 18210

3285

3285

3285

3285

3285

3285

3285

3240

4160

9775

2990

1

3240

3130

2

1 11

6330

5

33335

4

1 10

2660

8400

3

9825

6

7

1 6

ROOF TOP GENERAL ARRANGEMENT PLAN SCALE 1:250 NORTH

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

ROOF TOP GENERAL ARRANGEMENT PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:250

SHEET:

06


GENERAL ELEVATIONS


A

B

C

D

E

F

G

H

I

J

K

L

M

61620 18210

3240

3285

3285

3285

3285

3285

3285

3285

3240

4160

9775

ROOF APEX +18.72

7970

CLAY ROOF TILES WITH TIMBER ROOF

PLASTER ARCHITRAVE

18325

THIRD FLOOR FFL +10.75

5090

FROSTED GLASS WINDOW WITH STEEL FRAME PLASTER ORNAMENTATION

SECOND FLOOR FFL +05.66

5265

BRICK WALL WITH ORNAMENTED CAPITALS

FIRST FLOOR FFL +00.40 NGL +00.00

1 7

FRONT ELEVATION SCALE 1:200

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FRONT ELEVATION

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:200

SHEET:

07


1

2

3

4

5

6

7

33335 2990

3130

8400

2660

6330

9825

ROOF APEX +18.72

7970

CLAY ROOF TILES WITH TIMBER ROOF TRUSS PLASTER ARCHITRAVE

18325

THIRD FLOOR FFL +10.75

5090

PLASTER ORNAMENTATION FROSTRED GLASS WINDOW WITH STEEL FRAME

5265

SECOND FLOOR FFL +05.66

FIRST FLOOR FFL +00.40 NGL +00.00

1 8

SIDE ELEVATION 1 SCALE 1:200

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

SIDE ELEVATION 1

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:200

SHEET:

08


7

6

5

4

3

2

1

33335 9825

6330

2660

8400

3130

2990

ROOF APEX +18.72

7970

CLAY ROOF TILES WITH TIMBER ROOF TRUSS

PLASTER ARCHITRAVE

5090

18325

THIRD FLOOR FFL +10.75

SECOND FLOOR FFL +05.66

5265

PLASTER ORNAMENTATION

FROSTED GLASS WINDOW WITH STEEL FRAME

FIRST FLOOR FFL +00.40 NGL +00.00

1 9

SIDE ELEVATION 2 SCALE 1:200

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

SIDE ELEVATION 2

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:200

SHEET:

09


GENERAL SECTIONS


A

B

C

D

E

F

G

H

I

J

K

L

M

61620 18210

3240

3285

3285

3285

3285

3285

3285

3285

3240

4160

9775

ROOF APEX +18.72

7970

THIRD FLOOR FCL +14.28

ART STUDIO 301

RECEPTION AREA 307

ACTIVITY AREA 308

18325

THIRD FLOOR FFL +10.75 DANCING STUDIO 208

COMMUNAL KITCHEN 205

5090

LIBRARY 201

SECOND FLOOR FFL +05.66

SOCIAL AREA 104 LIBRARY 103

5265

F&B AREA 105 VOID VOID

FIRST FLOOR FFL +00.40

VOID

NGL +00.00

1 10

GENERAL SECTION 1 SCALE 1:200

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

GENERAL SECTION 1

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:200

SHEET:

10


7

6

5

4

3

2

1

33336 6330

9825

2660

3130

8400

2990

ROOF APEX +18.72

7970

THIRD FLOOR FCL +14.28

ACTIVITY AREA

THIRD FLOOR FFL +10.75

5090

18325

308

DANCING ROOM

DANCING STUDIO

210

208

SECOND FLOOR FFL +05.66

5265

RETAIL AREA 107

KITCHEN AREA 106

FIRST FLOOR FFL +00.40

F&B AREA 105

NGL +00.00

1 11

GENERAL SECTION 2 SCALE 1:200

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

GENERAL SECTION 2

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:200

SHEET:

11


FOCUS AREA 1: SOCIAL AREA, F&B AREA, COMMUNAL KITCHEN


C

D

E

F

G

H

I

J

K

L

M

L

M

40170 3285

3285

3285

3285

3285

3285

3285

3240

4160

9775

9775

W01

2990

1 W01

W01

W01

W01

W01

W01

W01

2 3130

D02

W01

W01

W01

14520

3 SOCIAL AREA 104

W01

8685

10630

10630

2770

A

8400

B A

A

7585

F&B AREA

A

A

105 UP

D03

2130

UP

A

106

3230

650 KITCHEN AREA

W01

C DN

D01

A

A

1635

A

1485

A

1347

A

1635

4 W02

W02

W02

W02

W02

W02

W02

W02

FIRST FLOOR SETTING OUT PLAN

1 12

2 12

SCALE 1:150

FIRST FLOOR MEZZANINE LEVEL SETTING OUT PLAN SCALE 1:150

LEGEND EXISTING WALL

E

200MM DRY WALL PARTITION

NEW WALL

F

100MM DRY WALL PARTITION

GLASS WALL

G

100MM BLOCK PARTITION WALL

A

100MM CONCRETE WALL

H

150MM BLOCK PARTITION WALL

B

200MM CONCRETE WALL

D00

DOOR CODE REFER TO SCHEDULE

C

150MM CONCRETE WALL

W00

WINDOW CODE REFER TO SCHEDULE

D

200MM FIRE-RATED BRICK WALL

ROOM NAME 506

ROOM NAME & NUMBER

NOTE: REFER TO SCHEDULE FOR SPECIFICATION & DRAWING DRAWINGS FOR DETAILS

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FIRST FLOOR SETTING OUT PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:150

SHEET:

12


C

D

E

F

G

H

I

J

K

L

30395 3285

3285

3285

3285

3285

3285

3285

3240

4160 W01

2990

1 W01

W01

W01

W01

W01

W01

W01

W01 3600

2

E

H

A

600

COMMUNAL KITCHEN

3

D 2670

3130

1970

D03

D

204

2690

8430

14520

D

SOCIAL AREA 104

10372

H

DN

2470

8400

D

D UP

D

11022

F G

F G

G

D

A D01

4

1420 W02

1 13

D04

W02

W02

W02

W02

W02

W02

W02

A

SECOND FLOOR SETTING OUT PLAN SCALE 1:150

LEGEND EXISTING WALL

E

200MM DRY WALL PARTITION

NEW WALL

F

100MM DRY WALL PARTITION

GLASS WALL

G

100MM BLOCK PARTITION WALL

A

100MM CONCRETE WALL

H

150MM BLOCK PARTITION WALL

B

200MM CONCRETE WALL

D00

DOOR CODE REFER TO SCHEDULE

C

150MM CONCRETE WALL

W00

WINDOW CODE REFER TO SCHEDULE

D

200MM FIRE-RATED BRICK WALL

ROOM NAME 506

ROOM NAME & NUMBER

NOTE: REFER TO SCHEDULE FOR SPECIFICATION & DRAWING DRAWINGS FOR DETAILS

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

NORTH KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

SECOND FLOOR SETTING OUT PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:150

SHEET:

13


C

D

E

F

G

H

I

J

K

L

M

L

M

40170 3285

3285

3285

3285

3285

3285

3285

3240

4160

9775

9775

2990

1 2

TA-01

TA-01

TA-01

TA-01

J-04

3130

J-03

TA-01 CH-01

3

CH-01

DS-01

DS-01

14520

CH-01

J-01

SOCIAL AREA

J-02

CH-01

DS-02

J-05

CH-01 DS-01

DS-02

DS-02

DS-02

DS-01

104 CH-01

8400

SS-01

CH-01 UP

CH-01

J-06

F&B AREA DS-01

DS-03

DS-03

105

DS-01

KITCHEN AREA

CH-01

106

J-07

DS-04

UP

DS-04

DN

4

1 14

FIRST FLOOR FURNITURE LAYOUT PLAN

2 14

SCALE 1:150

LEGEND

LEGEND

FURNITURE CODE

JOINERY CODE

CH-01

BAR CHAIR

J-01

STAIR SEATING

J-06

DINING AREA ARC WALL DESIGN

DS-01

DINING SET 1

J-02

WALL & BAR SEATING AREA

J-07

KITCHEN COUNTER

DS-02

SQUARE DINING SET

J-03

WALL & DINING AREA 1

J-08

DINING SEATING

DS-03

SOFA DINING SET

J-04

WALL & DINING AREA 2

J-09

COMMUNAL KITCHEN COUNTER

DS-04

DINING SET 2

J-05

CAFE COUNTER

J-10

CUSTOM KITCHEN CABINET

TA-01

DINING TABLE

FIRST FLOOR MEZZANINE LEVEL FURNITURE LAYOUT PLAN SCALE 1:150

NOTE: REFER TO SCHEDULE FOR SPECIFICATION & DRAWING DRAWINGS FOR DETAILS

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FIRST FLOOR FURNITURE LAYOUT PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:150

SHEET:

14


C

D

E

F

G

H

I

J

K

L

30395 3285

3285

3285

3285

3285

3285

3285

3240

4160

2990

1 STORAGE 206

3130

2 COMMUNAL KITCHEN

3

J-08

J-09

J-09

14520

204

J-10 J-01 SOCIAL AREA

8400

104 J-09

J-09

DN

UP

4

1 15

SECOND FLOOR FURNITURE LAYOUT PLAN SCALE 1:150

LEGEND

LEGEND

FURNITURE CODE

JOINERY CODE

CH-01

BAR CHAIR

J-01

STAIR SEATING

J-06

DINING AREA ARC WALL DESIGN

DS-01

DINING SET 1

J-02

WALL & BAR SEATING AREA

J-07

KITCHEN COUNTER

DS-02

SQUARE DINING SET

J-03

WALL & DINING AREA 1

J-08

DINING SEATING

DS-03

SOFA DINING SET

J-04

WALL & DINING AREA 2

J-09

KITCHEN COUNTER

DS-04

DINING SET 2

J-05

CAFE COUNTER

J-10

CUSTOM KITCHEN CABINET

TA-01

DINING TABLE

NOTE: REFER TO SCHEDULE FOR SPECIFICATION & DRAWING DRAWINGS FOR DETAILS

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

SECOND FLOOR FURNITURE LAYOUT PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:150

SHEET:

15


C

D

E

F

G

H

I

J

K

L

M

L

M

40170 3285

3285

3285

3285

3285

3285

3285

3240

4160

9775

9775

1 2406

2590

2990

3000

650

2 3130

2200

3273

2460

3000 PA-01

CH=5294

2000

1522

1500

0

PA-02

CH=5294

40 R1

1273

DINING AREA PA-01

3105

2065 2406

0

2000

2000

40

R1

2000

0

2420

1472

2420

UP R1400

R140

600

2235

F&B AREA PA-01

2196

1000

8400

2420

2770

0

R75

825

2250

2965

1600

CH=5294

4930

CH=14100

2415

14520

0 R75 SOCIAL AREA

2030

1500

2016

6130

3

1568

4590

2460 4165

3630

2420

0

R75

CH=5294

4460

KITCHEN AREA PA-01

UP

DN

CH=2833

2331

4

1 16

1 42

FIRST FLOOR REFLECTED CEILING PLAN

2 16

SCALE 1:150

FIRST FLOOR MEZZANINE LEVEL REFLECTED CEILING PLAN SCALE 1:150

LEGEND SYMBOL

CODE

NAME

SYMBOL

CODE

NAME

L-01

LED DOWNLIGHT TYPE 1

L-06

BARRISOL TYPE 1

L-02

PENDANT LIGHT TYPE 1

L-07

BARRISOL TYPE 2

L-03

PENDANT LIGHT TYPE 2

PA-01

GYPSUM FALSE CEILING

L-04

WALL BRACKET LIGHT

PA-02

WOODEN FALSE CEILING

L-05

LED STRIP LIGHT

CH=0000

CEILING FINISH LEVEL (MM)

NOTE: REFER TO SCHEDULE FOR SPECIFICATION & DRAWING DRAWINGS FOR DETAILS

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FIRST FLOOR REFLECTED CEILING PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:150

SHEET:

16


C

D

E

F

G

H

I

J

K

L

30395 3285

3285

3285

3285

3285

3285

3285

3240

4160

1 1395

2990

1800

600 PA-02

985

1300

3150 COMMUNAL KITCHEN PA-01

1920

14520

600

600

CH=10255

1500

961

3280

3

R

0

2000

00

2870

40

2870

R1

2391

R14

R1

CH=10255

2080

00 14

2870

0 40

2870

3130

600

2

STORAGE PA-01

CH=10055 4260

2300

2480

PA-02

VOID 8400

4130

CH=14100

0

00

40

4 R1

1221

R1 1834

2000

2000

2000

2000

2000

1738

390

0

40

R1

950

4

1 17

R1

0 40 R1

1500

0

40

UP

2390

00

4 R1

2000

0

40

R1

1 42

SECOND FLOOR REFLECTED CEILING PLAN SCALE 1:150

LEGEND SYMBOL

CODE

NAME

SYMBOL

CODE

NAME

L-01

LED DOWNLIGHT TYPE 1

L-06

BARRISOL TYPE 1

L-02

PENDANT LIGHT TYPE 1

L-07

BARRISOL TYPE 2

L-03

PENDANT LIGHT TYPE 2

PA-01

GYPSUM FALSE CEILING

L-04

WALL BRACKET LIGHT

PA-02

WOODEN FALSE CEILING

L-05

LED STRIP LIGHT

CH=0000

CEILING FINISH LEVEL (MM)

NOTE: REFER TO SCHEDULE FOR SPECIFICATION & DRAWING DRAWINGS FOR DETAILS

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

SECOND FLOOR REFLECTED CEILING PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:150

SHEET:

17


C

D

E

F

G

H

I

J

K

L

M

L

M

40170 3285

3285

3285

3285

3285

3285

3285

3240

4160

9775

9775

2990

1

3130

2

14520

3 DINING AREA FL-03

FFL=+0.58 F&B AREA FL-02

FFL=+0.40

FFL=+0.40

8400

SOCIAL AREA FL-01

UP KITCHEN AREA FL-02

DINING AREA FL-04

FFL=+0.40

FFL=+3.33

UP

4

1 18

FIRST FLOOR FINISHES PLAN

2 18

SCALE 1:150

FIRST FLOOR MEZZANINE LEVEL FINISHES PLAN SCALE 1:150

LEGEND FL-01

1200X600MMRC.RE DARK GYR TILES

FL-02

1200X600MM CERAMIC TILES

FL-03

WHITE CARPET FLOOR

FL-04

1200X600MM EGO AVORIO R TILES

FL-05

900X900MM NEWDECO' PALL LIGHT TERRAZZO

NOTE: REFER TO SCHEDULE FOR SPECIFICATION & DRAWING DRAWINGS FOR DETAILS

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FIRST FLOOR FINISHES PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:150

SHEET:

18


C

D

E

F

G

H

I

J

K

L

30395 3285

3285

3285

3285

3285

3285

3285

3240

4160

2990

1 STORAGE FL-05

FFL=+5.66

3130

2

14520

3 COMMUNAL KITCHEN FL-05

8400

FFL=+5.66

DN

UP

FL-01

FFL=+5.66

4

1 19

SECOND FLOOR FINISHES PLAN SCALE 1:150

LEGEND FL-01

1200X600MMRC.RE DARK GYR TILES

FL-02

1200X600MM CERAMIC TILES

FL-03

WHITE CARPET FLOOR

FL-04

1200X600MM EGO AVORIO R TILES

FL-05

900X900MM NEWDECO' PALL LIGHT TERRAZZO TILES

NOTE: REFER TO SCHEDULE FOR SPECIFICATION & DRAWING DRAWINGS FOR DETAILS GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

NORTH KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

SECOND FLOOR FINISHES PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:150

SHEET:

19


2 21

10630 1000

8130

1200

150

100

1 21

500

1200

600

150

2 20

J-02 WALL & BAR SEATING AREA PLAN

1 20

SCALE 1:40

10630 150

1000

750

1815

590

1815

590

1815

750

1200

150

600

908

908

908

760

500

R6

00

00 R5

150

FCL

350

05 R9

05 R9

05 R9

05

05

905

905

905

1639

1639

R9

1639

R9

3644

3744

4895

05

500

540

50

2545

R9

FFL

2 20

J-02 WALL & BAR SEATING AREA FRONT ELEVATION SCALE 1:40

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

NORTH SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-02 WALL & BAR SEATING AREA DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:40

SHEET:

20


500 300

600 100

150

500 450

100

300

600 100

150

450

20MM THK NEWDECO' PALL LIGHT TERRAZZO NEWDECO' PALL LIGHT TERRAZZO

50

100

30X50MM WOOD SUPPORT

1090

540

CONCRETE SUPPORT

PILOTAGE STACK

500

PLANTING, SOIL & LINING BY OTHERS

FFL

1 21

J-02 WALL & BAR SEATING AREA SIDE ELEVATION

J-02 WALL & BAR SEATING AREA SECTION DETAIL

2 21

SCALE 1:10

SCALE 1:10

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-02 WALL & BAR SEATING AREA DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:10

SHEET:

21


1 23

10630 1075

1000

1415

1000

1415

1000

675

550

1200

150

430

1000

100

4 22

430

1000

20 20

150

3 22

J-03 WALL & DINING AREA 1 PLAN

1 22

2 22

SCALE 1:40 10630 150 140 140

FCL

1000

450

625

1000

1415

1000

1000 1415

1000

675

100

450

1200

150

R6

00

100

SCALE 1:40

20 450

00

400

50100

350

250

4895

3470

R3

52

0

R3 620

R5

430

J-03 WALL & DINING AREA 1 ISOMETRIC

FFL

3 22

J-03 WALL & DINING AREA 1 FRONT ELEVATION

4 22

SCALE 1:40

J-03 WALL & DINING AREA 1 SIDE ELEVATION SCALE 1:40 NORTH

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-03 WALL & DINING AREA 1 DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:40

SHEET:

22


20

450

450 430

350

430

20

900

100

WOODEN BACKSEAT

50

50MM THK WESTERN RED CEDAR STACK

400

10MM SHADOW GAP

25X50MM WOOD SUPPORT 20MM THK CERAMIC TILES

FFL

1 23

J-03 WALL & DINING AREA 1 SECTION DETAIL SCALE 1:10

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-01 WALL& DINING AREA 1 SECTION DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:10

SHEET:

23


2 25

5140 3600 50

50

610

1280

610

50

450

50

50

1200

50

1000

FCL 400 540

50

400 540

429

50

450

50

50

2794

TA-01

TA-01

TA-01

450

TA-01

3 25

4994 450

5140

250 50 450

400

1000

50

TA-01

50

1 25

400

900

50

50

450

4065

900

1 26

900

2890

450

2 24

FFL

1 24

J-04 WALL & DINING AREA 2 PLAN SCALE 1:40

2 24

J-04 WALL & DINING AREA 2 SIDE ELEVATION 1

3 24

SCALE 1:40

J-04 WALL & DINING AREA 2 ISOMETRIC SCALE 1:40

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-04 WALL& DINING AREA 2 DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:40

SHEET:

24


3600 50

450

50

610

1280

3600 610

500

50

50

450

50

610

1280

5140 610

50

450

50

1000

50

4040

50

400

50 250 50

4994

4244

FCL

FFL

1 25

J-04 WALL & DINING AREA 2 FRONT ELEVATION

2 25

SCALE 1:40

J-04 WALL & DINING AREA 2 BACK ELEVATION

3 25

SCALE 1:40

J-04 WALL & DINING AREA 2 SIDE ELEVATION 2 SCALE 1:40

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-04 WALL& DINING AREA 2 DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:40

SHEET:

25


3500 50

350

260

1280

260

350

50

450

250

50MM THK WESTERN CEDAR STACK

750

50MM THK FABRIC BACKSEAT

50

50

450

400

SHADOW GAP

25X50MM THK WOOD SUPPORT 20MM THK CERAMIC TILES

FFL

1 26

J-04 WALL & DINING AREA 2 SECTION DETAIL SCALE 1:15

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-04 WALL& DINING AREA 2 SECTION DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:15

SHEET:

26


3 27

8785 2070

100

2070

100

2070

100

2075

100

100

2070

100

200

2570

100

2 27

J-06 DINING AREA ARC WALL DESIGN PLAN

1 27

SCALE 1:40

8785 2070

100

2070

100

2070

2 27

35

1035

1035

1035

1010

1010

1010

R10

R10

1035 1010

2435

2050

FFL

185

200

35

100

J-06 DINING AREA ARC WALL DESIGN FRONT ELEVATION SCALE 1:40 NORTH

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-06 DINING AREA ARC WALL DESIGN DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:40

SHEET:

27


4 28

1 29 200

800

200

1250 850

1025

675

300

100

80

700 230

300

1250

2 28

1080

800

150

50

80

3060

2 29

100

FFL

3 28

J-09 COMMUNAL KITCHEN COUNTER PLAN

2 28

SCALE 1:20

80

120

30

3060

600

3060

1630

30

390

390

925

50

600

600

5030

230

240

100

300

1080

670

1080

240

30

2030

150

600

SCALE 1:20

150

1 28

J-09 COMMUNAL KITCHEN COUNTER SIDE ELEVATION

FFL

3 28

J-09 COMMUNAL KITCHEN COUNTER BACK ELEVATION

4 28

SCALE 1:20

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

J-09 COMMUNAL KITCHEN COUNTER FRONT ELEVATION SCALE 1:20 NORTH NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-09 COMMUNAL KITCHEN COUNTER DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:20

SHEET:

28


1250 400

1250 350

300

80

20

100

130

300

20 30 2020

660

80

20

6MM THK LAMINATED PLYWOOD 150

50

20 40

20 30

90

25X50MM THK WOOD SUPPORT

20 30

20 30 20

STROVE WHITE MARBLE COUNTERTOP

220 20 220 20

20MM THK PLYWOOD DOOR WITH LAMINATED FINISH

100

170

20

20MM THK DRAWER SLIDE WITH LAMINATED FINISH 20MM THK LAMINATED PLYWOOD SHELD

260

405

20MM THK PLYWOOD DRAWER DOOR WITH LAMINATED FINISH

1080

20MM THK LAMINATED PLYWOOD SHELD

1080

1080

20

470

275

25X50MM THK WOOD SUPPORT

30

30

230

20MM THK PLYWOOD DOOR WITH LAMINATED FINISH

100

100

CERAMIC TILE FINISH SKIRTING

FFL

1 29

J-09 COMMUNAL KITCHEN COUNTER SECTION DETAIL 1

2 29

SCALE 1:10

J-09 COMMUNAL KITCHEN COUNTER SECTION DETAIL 2 SCALE 1:10

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-09 COMMUNAL KITCHEN COUNTER SECTION DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:10

SHEET:

29


FOCUS AREA 2: RETAIL AREA


L

M 9775

6090

4

A

A

LEGEND

A

D05

EXISTING WALL 1200

2660

NEW WALL

GLASS WALL

W01 A

100MM CONCRETE WALL

D00

DOOR CODE REFER TO SCHEDULE

W00

WINDOW CODE REFER TO SCHEDULE

ROOM NAME 100

ROOM NAME & NUMBER

5 W03

8975

8990

NOTE: REFER TO SCHEDULE FOR SPECIFICATION & DRAWING DRAWINGS FOR DETAILS

RETAIL AREA 107

6330

W01

W04

A

9510

A

6 1 30

SETTING OUT PLAN SCALE 1:50

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

NORTH SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

SETTING OUT PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:50

SHEET:

30


L

M 9775

4 LEGEND

J-13

JOINERY CODE MERCHANDISE DISPLAY

J-12

RETAIL SHELVING 1

J-13

RETAIL SHELVING 2

J-14

RETAIL SELVING 3

2660

J-11

5 LEGEND FURNITURE MD-01

NOTE: REFER TO SCHEDULE FOR SPECIFICATION & DRAWING DRAWINGS FOR DETAILS

J-12

8990

J-11

CUSTOM MERCHANDISE DISPLAY

RETAIL AREA 107

6330

MD-01

J-14

6 1 31

FURNITURE LAYOUT PLAN SCALE 1:50

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

NORTH SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FURNITURE LAYOUT PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:50

SHEET:

31


L

M

615

9775

940

4

LEGEND

500

2660

SYMBOL

982

2524

2524

L-01

LED DOWNLIGHT TYPE 1

L-02

PENDANT LIGHT TYPE 1

L-03

PENDANT LIGHT TYPE 2

L-04

WALL BRACKET LIGHT

L-05

LED STRIP LIGHT

L-06

BIG BULIT-IN-LAMPS TYPE 1

L-07

BIG BULIT-IN-LAMPS TYPE 2

956

5 2280

NAME

CODE

RETAIL AREA CH=5094

8990

NOTE: REFER TO SCHEDULE FOR SPECIFICATION & DRAWING DRAWINGS FOR DETAILS

2280 1791

651

6330

676

6 1 32

REFLECTED CEILING PLAN SCALE 1:50

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

NORTH SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

REFLECTED CEILING PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:50

SHEET:

32


L

M 9775

4 LEGEND FL-06

250X250MM CERAMIC TILES

2660

NOTE: REFER TO SCHEDULE FOR SPECIFICATION & DRAWING DRAWINGS FOR DETAILS

8990

5

RETAIL AREA FL-05

6330

FFL=+00.40

6 1 33

FLOOR FINISHES PLAN SCALE 1:50

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

NORTH SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FLOOR FINISHES PLAN

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:50

SHEET:

33


0 34

5550 240 20 240

50

240 20 240

50

240 20 240

50

240 20 240

50

240 20 240

50

240 20 240

50

240 20 240

50

240 20 240

50

240 20 240

50

240 20 240

50

560

3 34

20

600

20

50

J-11 MERCHANDISE DISPLAY PLAN

1 34

4 34

2 34

SCALE 1:30

J-11 MERCHANDISE DISPLAY ISOMETRIC SCALE 1:100

600 560

20

500

50

500

50

500

50

500

50

600 500

50

500

50

500

50

500

50

500

50

20

560

20MM THK ALUMINIUM SUPPORT

20MM ALUMINIUM SUPPORT

20

230 20

50

1300

1050

25X50MM WOOD SUPPORT

R250

R250

R250

R250

R250

R250

R250

R250

R250

R250

1300

20

250

250

500

230

5550 50

250

20

20

20MM THK NEWDECO'PALL TERRAZZO DARK

J-11 MERCHANDISE DISPLAY FRONT ELEVATION

3 34

SCALE 1:30

J-11 MERCHANDISE DISPLAY SIDE ELEVATION SCALE 1:30

FFL

20

2 34

760

FFL

5 34

J-11 MERCHANDISE DISPLAY SECTION DETAIL SCALE 1:15

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-11 MERCHANDISE DISPLAY DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: AS SHOWN

SHEET:

34


1 36

5224

1500

4 35

3 35

J-12 RETAIL SHELVING PLAN

1 35

SCALE 1:30

2 35

J-12 RETAIL SHELVING ISOMETRIC SCALE 1:30

5225 50

570

50

570

50

570

50

555

50

570

50

570

50

735

1500

20

50

360

50

390

50

735

0

50 500

385

50

2080

570

3000

545

R48

FFL

2 35

J-12 RETAIL SHELVING FRONT ELEVATION

4 35

SCALE 1:30

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

J-12 RETAIL SHELVING SIDE ELEVATION SCALE 1:30

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

NORTH DRAWING TITLE:

J-12 RETAIL SHELVING 1 DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:30

SHEET:

35


50

6MM THK LAMINATED PLYWOOD SHELF

50

570

3000

545

50

360

50

390

50

1500

385

25X40MM WOOD SUPPORT

500

20X50MM WOOD SUPPORT

FFL

1 36

J-12 RETAIL SHELVING 1 SECTION DETAIL SCALE 1:15 NORTH

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-12 RETAIL SHELVING 1 SECTION DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:15

SHEET:

36


2 38

9510

600

1 38 2 37

J-14 RETAIL SHELVING 3 PLAN

1 37

SCALE 1:40

9510 20

610

20

610

20

610

20

610

20

610

20

610

20

610

20

610

20

610

20

610

20

610

20

610

20

610

20

610

20

635

20

FFL

2 37

20 50

500

20

500

20

500

20

500

20

500

5065

1712

330

370

FCL

J-14 RETAIL SHELVING 3 FRONT ELEVATION

3 37

SCALE 1:40

J-14 RETAIL SHELVING 3 ISOMETRIC SCALE 1:40

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

J-14 RETAIL SHELVING 3 DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:40

SHEET:

37


3370 610

3370 2760

600

860

20

610

20

610

20

610

20

2416

370

FCL

20

20X20MM WOOD SUPPORT

20

4695

500

5065

5065

20MM THK LAMINATED PLYWOOD SHELF

500

20

500

20

500

20

500

50X50MM WOOD SUPPORT

1 38

50X50MM HARDWOOD FRAMING WITH LAMINATED PLASTIC FINISH

50

FFL

J-14 RETAIL SHELVING 3 SIDE ELEVATION

2 38

SCALE 1:25

GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

J-14 RETAIL SHELVING 3 SECTION DETAIL

KEYPLAN:

NO.

SCALE 1:25 DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad varierty cultural influences.

1 000

DRAWING NO. SHEET NO.

NORTH DRAWING TITLE:

J-14 RETAIL SHELVING 3 DETAIL

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:25

SHEET:

38


100

FCL

FCL SOFFIT OF CHOC FLOOR SLAB

'C' CHANNEL GALY STUD

'C' CHANNEL GALY STUD

FALSE CEILING TO DETAIL

RAMSET NAIL

12MM THICK NON COMBUSTIBLE GYPSUM BOARD

15

110MMX50MM HARDWOOD FRAME

6MM THICK CLEAR GLASS PANEL 10

42MMX15MM HARDWOOD BEADING

2500 CLEAR CEILING HEIGHT

INTERMEDIATE STUD

8MM THICK CLEAR GLASS

ALUM FRAME

RAMSET HALL

ALUM SKIRTING 100

12MM THICK HARDWOOD SKIRTING

'C' CHANNEL GALY STUD

FFL

FFL

1 39

FULL HT PARTITION DETAIL SCALE 1:5

2 39

HALF GLASS PARTITION DETAIL

3 39

SCALE 1:5

DETAIL OF FULL GLAZED PARTITION SCALE 1:5

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FOCUS AREA 1 FIRST FLOOR WALL DETAILS

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:5

SHEET:

39


10

15 60

75

8

POLISHED CEMENT FLOOR

67

CERAMIC TILE FLOOR

SCRATCHED CEMENT UNDERLAY

LIGHTWEIGHT SLAB OR FALSE FLOOR

1 40

CERAMIC FLOOR WITH POLISHED CONCRETE FLOOR DETAIL SCALE 1:5

ALUMINUM PROFILE PS-005 METINSA OR SIMILAR VINYL TILE FLOOR

POLISHED TERRAZZO FLOOR

POLISHED CEMENT FLOOR

TERRAZZO BASE

2 40

75

15

45

60

75

60

72

15

20 10

3

POLISHED CEMENT FLOOR

ALUMINUM PROFILE PS-005 METINSA OR SIMILAR

SCRATCHED CEMENT UNDERLAY

SCRATCHED CEMENT UNDERLAY

LIGHTWEIGHT SLAB OR FALSE FLOOR

LIGHTWEIGHT SLAB OR FALSE FLOOR

VINYL FLOOR WITH POLISHED CONCRETE FLOOR DETAIL

TERAZZO FLOOR WITH POLISHED CONCRETE FLOOR DETAIL

3 40

SCALE 1:5

SCALE 1:5

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FOCUS AREA 1 & 2 FLOOR DETAILS

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:5

SHEET:

40


20MM CONDUIT 10MM EXPANDING BOLT 20MM CONDUIT SLAB

TERMINAL BOX TERMINAL BOX

PLUG-IN TYPE CEILING ROSE STRUCTURAL SOFFIT

NYLON CABLE TIE (TYPICAL)

27MMX57MM ANGLE CLEATS 85°C HEAT RESISTANT FLEXIBLE WIRE

25MM WIDE MILD STEEL STRAP HANGERS AT 1200C/C 15MMX45MM MILD STEEL CHANNELS AT 1200C/C SLOTTED BOLT FIXINGS TO PROVIDE LEVELING ADJUSTMENT

THREADED ROD SUPPORT (MINIMUM 6MM)

PERIMETER CHANNEL

CEILING FINISH 80MMX26MM PRESSED STEEL CEILING SECTION AT 450C/C

1 OR 2 LAYERS OF 900MM WIDE X 12.5MM THK PLASTERBOARD SCREWED TO CEILING SECTION

LIGHT FITTING ABUTMENT WALL FALSE CEILING 600

1 41

SUSPENDED CEILING DETAIL

2 41

SCALE 1:8

SUSPENDED CEILING DETAIL SCALE 1:8

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FOCUS AREA 1 & 2 CEILING DETAILS

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: 1:8

SHEET:

41


2800 5050

200

50 100 50

200

50 100 50

200

50 100 50

200

50 100 50

200

50 100 50

200

50 100 50

200

5050

400 R1

3 42

CEILING DETAIL PLAN

1 42

2 42

SCALE 1:25

CEILING DETAIL ISOMETRIC SCALE 1:25

2800 50 50 50

100

50 50

100

50 50

100

50 50

100

50 50

100

50 50

100

50 50

100

50 50

100

50 50

100

50 50

100

50 50

100

50 50

100

50 50

100

50 50 50

50

FALSE CEILING 150

300

100

FCL

LED STRIP LIGHT

3 42

CEILING SECTION DETAIL SCALE 1:15

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FOCUS AREA 1 CEILING DETAILS

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: AS SHOWN

SHEET:

42


SCHEDULES


DOOR SCHEDULE D-01

D-02

D-03

D-04

D-05

DOUBLE LEAF LAMINATE FRAME TEMPERED GLASS DOOR SOCIAL AREA COMMUNAL KITCHEN 2

DOUBLE LEAF WOODEN DOOR TEMPERED GLASS DOOR

SINGLE LEAF WOODEN DOOR

SINGLE LEAF WOODEN DOOR TEMPERED GLASS DOOR

SINGLE LEAF WOODEN DOOR TEMPERED GLASS DOOR

SOCIAL AREA

KITCHEN AREA

COMMUNAL KITCHEN

RETAIL AREA

1

2

1

1

1400

1460

900

1000

1000

CODE DESCRIPTION AREA/ LOCATION QUANTITY

PLAN

1400 700

0

R65

1160

700

700

1460 1000

90

500 100

700

100

50

R2

200

500

200

700

FFL

SPEEDY DECOR WWW.SPEEDYDECOR.COM

FFL

SPEEDY DECOR WWW.SPEEDYDECOR.COM

50

50

R2

R2

FFL

SPEEDY DECOR WWW.SPEEDYDECOR.COM

R450

1600

500

1650

2150

2100 9090

2100

700 500

50

SUPPLIER

0

1000 50 R3

5 R2

R2

700

90

FFL

50

R2

700

2560

3260 2100

ELEVATION

450

00

R4

700

900

700

730

2100

730

FFL

SPEEDY DECOR WWW.SPEEDYDECOR.COM

SPEEDY DECOR WWW.SPEEDYDECOR.COM

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

DOOR SCHEDULE

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

43


DOOR SCHEDULE D-01

D-02

D-03

D-04

D-05

DOUBLE LEAF LAMINATE FRAME TEMPERED GLASS DOOR SOCIAL AREA COMMUNAL KITCHEN 2

DOUBLE LEAF WOODEN DOOR TEMPERED GLASS DOOR

SINGLE LEAF WOODEN DOOR

SINGLE LEAF WOODEN DOOR TEMPERED GLASS DOOR

SINGLE LEAF WOODEN DOOR TEMPERED GLASS DOOR

SOCIAL AREA

KITCHEN AREA

COMMUNAL KITCHEN

RETAIL AREA

1

2

1

1

1400

1460

900

1000

1000

CODE DESCRIPTION AREA/ LOCATION QUANTITY

PLAN

1400 700

0

R65

1160

700

700

1460 1000

90

500 100

700

100

50

R2

200

500

200

700

FFL

SPEEDY DECOR WWW.SPEEDYDECOR.COM

FFL

SPEEDY DECOR WWW.SPEEDYDECOR.COM

50

50

R2

R2

FFL

SPEEDY DECOR WWW.SPEEDYDECOR.COM

R450

1600

500

1650

2150

2100 9090

2100

700 500

50

SUPPLIER

0

1000 50 R3

5 R2

R2

700

90

FFL

50

R2

700

2560

3260 2100

ELEVATION

450

00

R4

700

900

700

730

2100

730

FFL

SPEEDY DECOR WWW.SPEEDYDECOR.COM

SPEEDY DECOR WWW.SPEEDYDECOR.COM

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

WINDOW SCHEDULE

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

44


MATERIAL SCHEDULE CODE

DESCRIPTION

IMAGE

SIZE / AREA

SUPPLIER

REMARKS

NIPPON PAINT SINGAPORE WWW.NIPPONPAINT.COM.SG

N.A.

1200X600MM FLOOR

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

1200X600MM FLOOR,JOINERY

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

900X900MM JOINERY

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

1200X600MM FLOOR

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

1200X1200MM JOINERY

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

1000X1000MM WALL

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

900X900MM JOINERY,WALL, FLOOR

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

250X250MM FLOOR

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

1410X1228MM FLOOR

HAFARY SINGAPORE WWW.HAFARY.COM.SG

EACH BLOCK 700X200MM, JOINTS ARE FILLED WITH MORTAR AND ARE 5MM IN WIDTH

3365X1500X12MM JOINERY

HAFARY SINGAPORE WWW.HAFARY.COM.SG

THICKNESS 12MM

3000X2149MM JOINERY, WALL

HAFARY SINGAPORE WWW.HAFARY.COM.SG

N.A.

PAINT FINISHES PA-01

VINILEX 5000 ACRYLIC PAINT COLOUR: WHITE FINISH: FLAT CODE: 1142

WALL AND CEILING TILES, STONE & CONCRETE

TL-01

TL-02

TL-03

TL-04

TL-05

TL-06

TL-07

TL-08

ST-01

ST-02

CR-01

GLAZED PORCELAIN TILE EGO AVORIO R FINISH: MATT CODE: 2546_14577 GLAZED PORCELAIN TILE CAPUCINO CERAMICS FINISH: HONED CODE: MTB601202PH GLAZED PORCELAIN TILE NEWDECO'PALL DARK FINISH: POLISHED CODE: 2261_12618 GLAZED PORCELAIN TILE RC.RE Drk Gy R FINISH: MATT CODE: 2792_16053 GLAZED PORCELAIN TILE MONO TERRAZZO FINISH: POLISHED CODE: 2332_16030 GLAZED PORCELAIN TILE PEARL RETT FINISH: POLISHED CODE: 2772_15911 GLAZED PORCELAIN TILE NEWDECO'PALL LIGHT FINISH: POLISHED CODE: 2261_12617 GLAZED PORCELAIN TILE CERAMICA VOGUE FINISH: POLISHED CODE: TO 203 OM STONE LIMESTONE, STAGGERED FINISH: ROUGH CODE: 2792_10053 SINTERED STONE- COUNTERTOP ARABESCATO MICHELANGELO LUX FINISH: POLISHED CODE: 2702_15650 CONCRETE POLISHED CONCRETE FINISH: POLISHED CODE: 2292_12223

LAMINATE & VENEER FINISHES LA-01

LA-02

LAMINATE IBIZA NOGAL MID-TONE CODE: WY 1244D

1200X2400MM FLOOR, JOINERY

LAMITAK SINGAPORE WWW.SG.LAMITAK.COM

N.A.

LAMINATE CHOC OREGON TEAK MID-TONE CODE: WY 1244D

1200X2400MM JOINERY

LAMITAK SINGAPORE WWW.SG.LAMITAK.COM

N.A.

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

MATERIAL & FINISHES SCHEDULE

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

45


MATERIAL SCHEDULE CODE

DESCRIPTION

IMAGE

SIZE / AREA

SUPPLIER

REMARKS

1/10" GAUGE TUFTED LOOP PILE JOINERY

ASRO INTERLINK PTE LTD WWW.ASROINTERIORS.COM

100% BCF SOLUTION DYED POLYPROPYLENE

225X60MM WALL

WALLHUB WWW.WALLHUB.COM.SG

MAX 10MM JOINT, GROUT TO MATCH TILE COLOUR

JOINERY

DONGFU PERFORATING WWW.PERFORATEDSHEETSMETAL.COM

BRUSHED ALUMINIUM TEXTURE

190X90X90MM JOINERY

LIAN WANG TRADING PTE LTD WWW.BRICKTILES.COM

N.A.

1500X50MM JOINERY

HAFARY SINGAPORE WWW.HAFARY.COM.SG

N.A.

1450MM WIDTH JOINERY

BODE WWW.BODE.COM.SG

N.A.

OTHERS CP-01

BR-01

PF-01

BR-01

WD-01

FB-01

EXP CARPET ROLL MODERN GREY CODE: QUADRA BRICK VENEER WHITE BRICKS CODE: BK-31 SERIES ALUMINIUM PERFORATED ALUMINIUM SHEET CODE: 2955_16554 FACING BRICK & REFRACTORY BRICKS PILOTAGE STACK CODE: M211 WOOD WESTERN RED CEDAR STACK CODE: WD10 FABRIC MISIA PARIS COLLECTION CODE: 2955

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

MATERIAL & FINISHES SCHEDULE

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

46


WALL FINISHES SCHEDULE CODE

DESCRIPTION

IMAGE

SIZE / AREA

SUPPLIER

REMARKS

5L

NIPPON PAINT SINGAPORE WWW.NIPPONPAINT.COM.SG

N.A.

1000X1000MM WALL

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

3000X2149MM WALL

HAFARY SINGAPORE WWW.HAFARY.COM.SG

N.A.

225X60MM WALL

WALLHUB WWW.WALLHUB.COM.SG

MAX 10MM JOINT, GROUT TO MATCH TILE COLOUR

900X900MM WALL

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

WALL FINISHES WL-01

WL-02

WL-03

WL-04

WL-05

VINILEX 5000 ACRYLIC PAINT COLOUR: WHITE FINISH: FLAT CODE: 1142 GLAZED PORCELAIN TILE PEARL RETT FINISH: POLISHED CODE: 2772_15911 CONCRETE POLISHED CONCRETE FINISH: POLISHED CODE: 2292_12223 BRICK VENEER WHITE BRICKS CODE: BK-31 SERIES GLAZED PORCELAIN TILE NEWDECO'PALL LIGHT FINISH: MATT CODE: 2261_12617

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

MATERIAL & FINISHES SCHEDULE

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

47


FLOOR FINISHES SCHEDULE CODE

FF-01

FF-02

FF-03

FF-04

FF-05

FF-06

DESCRIPTION

IMAGE

SIZE / AREA FLOOR FINISHES

GLAZED PORCELAIN TILE EGO AVORIO R FINISH: MATT CODE: 2546_14577 GLAZED PORCELAIN TILE CAPUCINO CERAMICS FINISH: HONED CODE: MTB601202PH GLAZED PORCELAIN TILE RC.RE Drk Gy R FINISH: MATT CODE: 2792_16053 GLAZED PORCELAIN TILE NEWDECO'PALL LIGHT FINISH: POLISHED CODE: 2261_12617 GLAZED PORCELAIN TILE CERAMICA VOGUE FINISH: POLISHED CODE: TO 203 OM EXP CARPET ROLL MODERN GREY CODE: QUADRA

SUPPLIER

REMARKS

1200X600MM

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

1200X600MM

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

1200X600MM

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

900X900MM

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

250X250MM

HAFARY SINGAPORE WWW.HAFARY.COM.SG

MAX 6MM JOINT, GROUT TO MATCH TILE COLOUR

1/10" GAUGE TUFTED LOOP PILE

ASRO INTERLINK PTE LTD WWW.ASROINTERIORS.COM

100% BCF SOLUTION DYED POLYPROPYLENE

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

MATERIAL & FINISHES SCHEDULE

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

48


CEILING SCHEDULE CODE

DESCRIPTION

IMAGE

SIZE / AREA

SUPPLIER

REMARKS

CEILING FINISHES PA-01

GYPSUM BOARD WITH WHITE PAINT FINISH

CUSTOM

PA-02

WOODEN FALSE CEILING IN DESIGN

CUSTOM

KOW YEE CIVIL & CONSTRUCTION PTE. LTD SINGAPORE WWW.KOWYEE.COM.SG HAFARY SINGAPORE WWW.HAFARY.COM.SG

N.A. WOOD DIMENSION 1200X2400MM

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

MATERIAL & FINISHES SCHEDULE

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

49


FURNITURE SCHEDULE CODE

DESCRIPTION

AREA/LOCATION

IMAGE

DIMENSION/SIZE

MATERIAL/FINISH/FABRIC

SUPPLIER

REMARKS

NATURAL ROMANIAN BEECH WOOD

COMFORT DESIGN WWW.COMFORT.COM.SG

N.A.

CHAIRS

CH-01

BAR CHAIR CODE: SH750

ROOM CODE: 105

W420 X D450 X H1010 MM

OTHERS

DS-01

DINING SET 1 CODE: RD600

ROOM CODE: 105

W915 X D315 X H750 MM W500 X D600 X H900 MM

TERRAZZO TABLE TOP FABRIC CUSHION SEAT

COMFORT DESIGN WWW.COMFORT.COM.SG

N.A.

DS-02

SQUARE DINING SET CODE: TR450

ROOM CODE: 105

W760 X D450 X H330 MM (PER N TABLE) W450 X D450 X H20 MM

LAMINATE TABLE TOP FABRIC CUSHIOIN

COMFORT DESIGN WWW.COMFORT.COM.SG

N.A.

DS-03

SOFA DINING SET CODE: 5500

ROOM CODE: 105

W1435 X D828 X H620 MM W950 X D350 X H265 MM

LAMINATE TABLE TOP FABRIC SOFA SEAT

BED AND BASICS WWW.BEDANDBASICS.COM.SG

N.A.

DS-04

DINING SET 2 CODE: TR200

ROOM CODE: 105

W915 X D315 X H750 MM W500 X D500 X H900 MM

TERRAZZO TABLE TOP FABRIC CUSHION SEAT

COMFORT DESIGN WWW.COMFORT.COM.SG

N.A.

MD-01

CUSTOM MERCHANDISE DISPLAY CODE: 3004

ROOM CODE: 107

W5645 X D650 X H570 MM

TERRAZZO COUNTERTOP

COMFORT DESIGN WWW.COMFORT.COM.SG

N.A.

JOINERY

J-01

STAIR SEATING

ROOM CODE: 104

CUSTOM

PERFORATED ALUMINIUM SHEET LAMINATE FINISH CAPUCINO CERAMICS TILE MONO TERRAZZO

BY CONTRACTOR

N.A.

J-02

WALL & BAR SEATING AREA

ROOM CODE: 105

CUSTOM

CONCRETE WALL CERAMIC TILE TERRAZZO FINISH

BY CONTRACTOR

REFER TO DETAILS

J-03

WALL & DINING AREA 1

ROOM CODE: 105

CUSTOM

CONCRETE WALL WESTERN CEDAR STACK CERAMIC TILE

BY CONTRACTOR

REFER TO DETAILS

J-04

WALL & DINING AREA 2

ROOM CODE: 105

CUSTOM

FABRIC WESTERN CEDAR STACK CERAMIC TILE LAMINATE FINISH

BY CONTRACTOR

REFER TO DETAILS

J-05

CAFÉ COUNTER

ROOM CODE: 105

CUSTOM

CERAMIC TILE LAMINATE FINISH WESTERN CEDAR STACK

BY CONTRACTOR

N.A.

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FURNITURE & EQUIPMENT SCHEDULE

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

50


FURNITURE SCHEDULE CODE

DESCRIPTION

AREA/LOCATION

IMAGE

DIMENSION/SIZE

MATERIAL/FINISH/FABRIC

SUPPLIER

REMARKS

JOINERY

J-06

DINING AREA ARC WALL DESIGN

ROOM CODE: 105

CUSTOM

CONCRETE WALL CARPET FINISH

BY CONTRACTOR

REFER TO DETAILS

J-07

KITCHEN COUNTER

ROOM CODE: 106

CUSTOM

CERAMIC TILE LAMINATE FINISH

BY CONTRACTOR

N.A.

J-08

DINING SEATING

ROOM CODE: 204

CUSTOM

LAMINATE FINISH

BY CONTRACTOR

N.A.

J-09

COMMUNAL KITCHEN COUNTER

ROOM CODE: 204

CUSTOM

MARBLE COUNTERTOP LAMINATE FINISH FABRIC SEATING

BY CONTRACTOR

REFER TO DETAILS

J-10

CUSTOM KITCHEN CABINET

ROOM CODE: 204

CUSTOM

MARBLE COUNTERTOP LAMINATE FINISH

BY CONTRACTOR

N.A.

J-11

MERCHANDISE DISPLAY

ROOM CODE: 107

CUSTOM

MARBLE FINISH ALUMINIUM FINISH

BY CONTRACTOR

REFER TO DETAILS

J-12

RETAIL SHELVING 1

ROOM CODE: 107

CUSTOM

LAMINATE FINISH

BY CONTRACTOR

REFER TO DETAILS

J-13

RETAIL SHELVING 2

ROOM CODE: 107

CUSTOM

LAMINATE FINISH

BY CONTRACTOR

N.A.

J-14

RETAIL SHELVING 3

ROOM CODE: 107

CUSTOM

LAMINATE FINISH

BY CONTRACTOR

REFER TO DETAILS

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

FURNITURE & EQUIPMENT SCHEDULE

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

51


LIGHTING SCHEDULE CODE

DESCRIPTION

IMAGE

DIMENSION/SIZE

MATERIAL/FINISH/FABRIC

SUPPLIER

REMARKS

LIGHTING FITTINGS

L-01

DOWNLIGHT WITH VARIOUS WATTAGE CODE: LED IP65

SIZE: 108MM MATERIAL: ALUMINIUM LUX/WATT: 12W LIGHT COLOUR: WHITE

66

JUPITER LIGHTZ(S) PTE LTD WWW.JUPITERLIGHTZ.COM

HOLE SIZE 90-95MM, COLOUR TEMPERATURE 4500K

L-02

PENDANT LIGHT TYPE 1 CODE: 320792

SIZE: 500X500MM MATERIAL: ALUMINIUM LUX/WATT: 30W LIGHT COLOUR: WHITE

6

PHILLIPS ELECTRIC SG WWW.PHILLIP.COM.SG

COLOUR TEMPERATURE 4500K

L-03

PENDANT LIGHT TYPE 2 CODE: JDA-97873

SIZE: 150X300MM MATERIAL: METAL & GLASS LUX/WATT: 30W LIGHT COLOUR: GOLD

4

JUPITER LIGHTZ(S) PTE LTD WWW.JUPITERLIGHTZ.COM

COLOUR TEMPERATURE 3000K

L-04

WALL BRACKET LIGHT CODE: 84231

SIZE: 200X45MM MATERIAL: WOOD & ACRYLIC LUX/WATT: 20W LIGHT COLOUR: WHITE

3

JUPITER LIGHTZ(S) PTE LTD WWW.JUPITERLIGHTZ.COM

COLOUR TEMPERATURE 3000K

L-05

LED STRIP LIGHT CODE: 509N

SIZE: 5000MM MATERIAL: FLEXIBLE NEON PVC LUX/WATT: 50W LIGHT COLOUR: WHITE

24

DIRECTNINE SG WWW.DIRECTNINE.SG

CUTTABLE EVERY 1000MM

L-06

BARRISOL TYPE 1 (HIGH PERFORMANCE WIDE ANGLE LIGHT) CODE: PENTA WIDE IV CC

SIZE: 62X22X10.15MM MATERIAL: ALUMINIUM (HEAT SINK) LUX/WATT: 2.10W (PER PCS) LIGHT COLOUR: WHITE

15

ARISTO LIGHTING SOLUTION WWW.ARISTO-ENG.COM.SG

NOT FOR USE UNDER DIRECT SUN APPLICATION

L-07

BARRISOL TYPE 2 (HIGH PERFORMANCE WIDE ANGLE LIGHT) CODE: PENTA WIDE TWIN

SIZE: 86X22X10.15MM MATERIAL: ALUMINIUM (HEAT SINK) LUX/WATT: 2.50W (PER PCS) LIGHT COLOUR: WHITE

15

ARISTO LIGHTING SOLUTION WWW.ARISTO-ENG.COM.SG

NOT FOR USE UNDER DIRECT SUN APPLICATION

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

LIGHTING SCHEDULE

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

52


ROOM FINISHES SCHEDULE LEVEL 1: FOCUS AREA 1

LEVEL 2: FOCUS AREA 1

ROOM CODE

ROOM NAME

FLOOR FINISH

104

SOCIAL AREA

FF-03

105

F&B AREA

106

KITCHEN AREA

WALL FINISH

FF-01, FF02,FF-06 FF-02

WL-01, WL04 WL-01, WL02, WL-04 WL-03

CEILING FINISH

ROOM CODE

PA-02

205

PA-01

206

ROOM NAME

FLOOR FINISH

COMMUNAL KITCHEN FF-03, FF-04 STORAGE

FF-04

WALL FINISH WL-04,WL05, WL-01 WL-04,WL05

CEILING FINISH PA-02 PA-01

PA-01

LEVEL 1: FOCUS AREA 2 ROOM CODE

ROOM NAME

FLOOR FINISH

WALL FINISH

CEILING FINISH

107

RETAIL AREA

FF-05

WL-01

PA-01

NORTH GENERAL NOTES:

The contractor to be responsible for: Verifying all drawings, specifications, dimensions and measurements as well as site conditions and notifying the designer of all discrepancies and omissions before commencing the works. Submitting samples and shop drawings for review and approval by designer before commencing works. Ensuring that all works is keeping with all national building codes and regulations. All necessary repairs, patching and cleaning of site during and after completion of works. Verifying existing site conditions prior to submissions of quotations. Not starting the construction unless these drawings are signed approved. All work specified on all drawings and specifications and supplying all necessary materials and labour requried to complete all phases of work in accordance with the designer's standards.

SPECIFIC NOTES :

KEYPLAN:

NO.

DATE:

REVISIONS:

PROJECT TITLE:

BLDG A

SATU MALAYSIAN CENTRE A multicultural centre for Malaysian to acknowledge and balance the broad variety cultural influences.

1 000

DRAWING NO. SHEET NO.

DRAWING TITLE:

ROOM FINISHES SCHEDULE

NAME: WAI SEE HUI COURSE: B.A INTERIOR DESIGN - FINAL MAJOR PROJECT TERM: APRIL 2022

DATE: 26-05-2022 SCALE: N.T.S

SHEET:

53