1 minute read

MCCLENDON PARK WEST

TARGET COMPLETION WINTER 2023

BUDGET $2.3 million

Advertisement

DESIGN FIRM Pacheco Koch

PROJECT MANAGER James Fish

FUNDING SOURCE MPFDC/GF COs

CONTRACTOR The Fain Group

SUMMARY This project includes replacing the underutilized softball field with two new basketball courts and adding a splash pad, new restroom building and expanded parking

CURRENT UPDATE Construction continues to work towards the project closeout. The last several weeks have posed some challenges with weather delays due to rain, sleet, mud and freezing temperatures The basketball project is 95% complete with final electrical service and turf establishment still remaining. Mechanical, electrical and plumbing work inside the restroom pump house building is underway, and the walks and concrete surrounding the splash pad have been poured The block work for the restroom building has been delayed d h h S ff i ki i h b h l k h h d l