GERTIE BARRETT PARK
TARGET COMPLETION WINTER 2023
BUDGET $2 3 million
Advertisement
DESIGN FIRM Dunaway
PROJECT MANAGER James Fish
FUNDING SOURCE Park Fees/GF COs
CONTRACTOR The Fain Group
SUMMARY New neighborhood park for the northwest quadrant that includes a playground, splash pad, restrooms, parking, walking trail and open natural spaces.
CURRENT UPDATE Construction continues to work towards the project closeout The last several weeks have posed some challenges with weather delays due to rain, sleet, mud and freezing temperatures. Mechanical, electrical and plumbing work inside the restroom pump house building is underway, and the walks and concrete surrounding the splash pad have been poured. The block work for the restroom building has been delayed due to the weather, but is 95% complete The improvements to the private drive are underway as well Due to weather delays, the project completion will likely be extended into March.