Estimation Portfolio- Mohammed Qureshi

Page 1

ESTIMATION PORTFOLIO Mohammed R. Qureshi


Strip Mall – Project Details


Strip Mall – Existing & Demolition Plan


Strip Mall – Demolition Plan


Strip Mall – Site Plan


Strip Mall – Foundation Plan


Strip Mall – Floor Plan


Strip Mall – Elevations


Strip Mall – Wall Details


Metals Quantities

Code

Description

Units

#

Length

Width

Height

Extension

Extension

Quantity

Units

125.36 32.24 33.08 136

L.F

Wt.per foot (pd)

Metals Columns W8x24

Extension

L.F

8 2 2 8

15.67 16.12 16.54 17

24 24 24 24 Total Height =

Beams W16x36

L.F

W10x22

L.F

8 4 2 4 2

22 18 20.39 18 16.39

36 36 36 22 22

176 72 40.78 72 32.78 Total Height =

Trusses; Bar Joist 28LH09

Tons

38

54

Frames

#

1

3

Steel-Dumpster Pad

S.F

6

Steel Studs

L.F

282

Galvanized Coping

S.F

Galvanized Cover Plate

S.F

1

18.4

326.68 L.F

L.F

393.56 18.87

Tons

0.145

7

1

#

6dia

6

56.52

S.F

17

4794

L.F

400

4

1600

S.F

146

54

7884

S.F


Masonry Quantities Code

Description

Units

#

Length

Width

Height

Extension Extension Entension Quantity

0.042113133050.0

BRICK VENEER

54' 54' 180'

6' 13.33'

LIME STONE

4 2 8

10" 10"

0.044310850100.0

S.F S.F L.F

0.040516300200.0

C.M.U

S.F

400'

2.67'

1068

0.033529600700.0

EIFS SYSTEM

S.F

398'

10'

3980

1296 180

Units


Concrete Quantities Code

Description

*

CONCRETE Concrete Dumpster Pad Patio Curb and Gutter a) Curb & Gutter b) Typical Walk c) P.C.C Curb Side Walk

*

Ramp

*

Spread Footings F1 F2 F3

* * *

*

Units

#

Length

Width

Height

Extension

# cu.ft

1 2

10' 15'

12' 54'

0.6' 0.67'

72.Cu.F 1085.4Cu.F

L.F L.F L.F sq. foot

12 8 2 1 2 2 1

19' 19' 19' 146' 54' 15' 25'

7.3' 5' 15' 5'

2

18.5'

5'

Total 0.9'

228 L.F 152 L.F 38 L.F 1065.8SqF 540SqF 450SqF 125SqF 2180 SqF 166.5 SqF

12 4 4

6 5 4.5

6 5 4.5

1.5 1.4 1 Total=

648 Cu.F 140 Cu.F 84.64 Cu.F 872.64 800Cu.F

Cu.F Cu.F Cu.F

Cu. F S.F

1 1

400

2

1

*

Concrete Grade Beam WF1 Concrete Slab

*

Transformer

Cu. F

1

5

5

0.5

Extension Entension Quantity

Units

2.66 40.2

Cu.yard Cu.yard

418 24 12 94.5

L.F

Total =

80.77 6.17

Sq. Y Cu. Y

Total =

32.32

Cu. Y

29.6

Cu. Y

12.5

Cu. F


Demolition and Site work Quantities Code

Description

Units

#

Demolition and Site work Remove Trees

#

7

Remove Asphalt

S.F

Length

Width

Height

Extension

Extension

Entension

C.F

26 24 24 24 42

50 50 50 50 50

1.5

1 4.5 Total filling

Excavation Spread Footings F1 F2 F3

12 4 4

6 5 4.5

6 5 4.5

3.67 3.67 4

2' on each side

Total = Excavation Grade Beams

400

2

1

2" on each side along width Total =

Bitumious Pavement

S.F

Subbase for Slabs

cubic foot

Total =

1

146

54

0.33 Total =

Remove Curb & Gutter

sq. foot

Units

7

Total = Site Grading

Quantity

32247 3583 19.5 30 24 12 94.5 333.33 6.67 3875.52 719.32 676 195.21 932 34.51 32247 3583 2601.72 96.36 667

S.F S.Y C.Y

C.Y C.Y C.F C.F C.F C.Y C.F C.Y S.F S.Y C.F C.Y S.F


Thermal Quantities Code

Description

Units

#

Length

Width

Height

Extension Extension Entension Quantity

THERMAL & MOISTURE PROTECTION

0.07211620132.0

Batt Insulator

S.F

1

398

10'

0.072510100401.0

Felt paper

S.F

1

398

1'

0.07251010047.0

Building Wrap

S.F

2 4

54' 146

1\2" 1\2"

0.07221610243.0

Plywood

S.F

0.0921163392.0

Studs

S.F

0.05422370404.0

Metal Canopy

Ea.

8

0.07050510442.0

Roofing Membrane

S.F

1

146'

0.0771231007.0

Downspouts

L.F

6

86'

0.071213200015.0

Rolled Bituthene

S.F

1

506

3980 398

15' 2'11"

1620 1752

398

5'

1990

398

9.5

3781

6"

8

1.625" 54'

7884 516 1'

506

Units


Job Overhead JOB OVERHEAD /GENERAL CONDITIONS Worksheet

ITEM

Include (1=yes)(2=no)

One time Unit for one Cost/Each or time cost #units

One time Cost

Cost per time Periods

Periods

Cost as a function of time

Cost per activity

Activity

Cost as Function of Activity

TOTAL

Personnel Superintendent

1

$1800/week

26 weeks

46800

Project Manager

1

$2000/week

26weeks

52000

Insurances Builders Risk

1

2400

Public Liability

1

7202

Performance Bond

1

8403

Equipment Floater

1

3001

Job Support Cost Job layout

1

Trailer 32' x 8'

1

per day

$1,100 $200

7 days

7700 5200

Computer CPM

1

$1,500

1500

Job photographs(per set)

1

$400

400

Clean up at the end of job

1

3001 137607

EQUIPMENT,TOOLS Forklift & Crew

$4000/month

6months

24000 TOTAL =

161607


Summary Division

(1=Yes) (2=No)

Labor $

Material $ Equipment $

Sum Labor,matl,Eq (Unadjusted)

Adjusted Labor Matl Eq Sum(for city)

TOTAL $

1 2 3 4 5 6

General Conditions Existing Conditions Concrete Masonary Metals Wood,Plastic,Components

1 1 1 1 1

25741.02 41611.22 18711.76 34238.85 68734.6

0 45950.98 14725.48 52935.13 39879.6

12707.42 1476.99 835.8 4127.73 0

38448.44 89039.19 34273.04 91301.71 108614.2

37833.26496 91265.16975 38180.16656 93310.34 114262.1384

37833.265 91265.1698 38180.1666 93310.34 114262.138

7

Thermal & Moisture protection

1

190322

13326.63

96.14

203744.77

210672.0922

41008.69

8 9 10 11 12 13 14 21 22 23 26 27 28 31 32 33 34 35 41

Openings Finishes Speacialities Equipment Furnishings Special Conditions Conveying Equipment Fire Supression Plumbing HVAC Electrical Communications Electronic Safety & Security Earthwork Exterior Improvements Utilities Transportation Waterway & Marine Material Processing

1 1

6787.68 5572

14143.32 1870.6

0 835.8

20931 8278.4

20763.55

20763.55 8278.4

44

Pollution Control Equipement

1 1 1 1

1 1

14,500 32639.76 54557.28 64648.8

15873.87

0

13784.13

29658

29658 22,000

Subcontracts General Conditions

161607

Company Overhead(markup)

57715

TOTAL/BID

882227.56

Company Characteristics Company Annual Volume(Labor,Material,Equipment, Sub,General Cond.)

$5,000,000

Annual Company Overhead Typical Average Project Duration Subcontracted Typical % of labor to Material Cost

$350,000 6 months 40% 50%

Profit (5%)

$44,111

$ AMOUNT

$101,827


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.