The QUAD - Kansas City Transportation Hub

Page 1

Kansas City QUAD Molly Knake & Jack Young ARCH 609 Kansas City Metro Station Hub


Kansas City Transit System

Hub Selection

Intersection of the Purple, Yellow, Green, and Inner Loop The station hub we selected is the intersection of four transit lines and also directly serving UMKC and Rockhurst University. This hub will be a destination point for many students, faculty, and residents of the neighboring communities. This will also be a critical intersection for commuters and for people switching transit lines.


Connection to Kansas City YELLOW LINE North-South 53 Miles

Overland Pk Conv.


Site Location The location we chose for this critical instersection in the Kansas City Transit system, is on the corner of 51st Street and Troost Avenue. This corner is centrally located in between two major universities in Kansas City: UMKC and Rockhurst University. Along with much of the hub’s traffic being comprised of students and faculty of the universities, this hub will also serve the neighboring residential communities.

49/63 Neighborhood Coalition • 10 local neighborhoods on both sides of Troost Avenue, a historical dividing line in the city. • 3,000 households • 8,000 residents UMKC • Student population: 16,019 Rockhurst University • Student Population: 2,185 Needs: • Only one local grocery store (Whole Foods on outer edge of community) • No local parks • Health market


Site Context

UMKC parking garage East of the site

Site

UMKC library & parking North of the site

Large elevation change on the site

UMKC house West of the site


Site Analysis

Tr oo

st

Av en

ue

t e tre

5

S t 1s


Design Proposal

Tr oo

st

Av en

ue

Bu sS top

e Rid

t e tre

re Sha

5

S t 1s


Site Location The location we chose for this critical instersection in the Kansas City Transit system, is on the corner of 51st Street and Troost Avenue. This corner is centrally located between two major universities in Kansas City: UMKC and Rockhurst University. Along with much of the hub’s traffic being comprised of students and faculty of the universities, this hub will also serve the neighboring residential communities. Troost Avenue is one of the major bus routes for Kansas City. With the planned routes of each line, the Red & Green line will run East and West along 51st Street. The Purple and Yellow Line will run North and South along Troost Avenue.


Cutaway View


Cutaway View


Concept Diagram

Site Selection

This hub will be serving primarily the two neighboring universities and surrounding neighborhood communities. The corner of 51st Street and Troost Avenue is a central point in the community and was selected to ensure equitable access to the transit system.

Site Conditions

The two main entries to the hub are located from Troost Avenue and 51st Street, directly adjacent to the major bus stops and ride share drop off. The corner condition needs to maintain a clear visual connection for cars entering onto Troost Avenue from 51st Street. The entrance into the stations will be located directly above the intersection of the two station boxes.

Station Considerations

The Purple and Yellow lines will run North/South along Troost Avenue; the Red and Green lines will run East/West along 51st Street. With four transit lines running through the hub, we will condense the lines to share only two station boxes. There is also existing parking surrounding that could be used for a park and ride system for commuters.

Hub Concept

This Hub will become the central meeting point for students of UMKC, Rockhurst University, the surrounding neighborhoods, and the Kansas City area. As many universities have a main Quad for students to gather, this project will serve as a shared Quad for the universities and community.

Concourse, Platform, and Appendages Locations

The Red & Green Lines station box will be stacked on top of the Purple & Yellow Lines station due to the large elevation change that occurs in the North/South axis. This will allow the Purple & Yellow lines to stay at a more consistent elevation underground. Additional entrances are located on either side of 51st Street and Troost Avenue to provide direct access to the stations from expected arrival points.

The Quad

From intersecting all of the communities that will participate in this hub, the Quad was then placed on the site as a base for the hub.


Form Development

Maximizing Use of the Site

Axial Organization

Form Development

The Quad was then stretched back into the site to maximize use of the area. With the large elevation change within the site, a second level was created to match the top topograophy line. The second level will be used for amenities such as restaurants, bars, and green space.

The programming and circulation of the hub is all centered around the 45 degree axis that was created from mirroring the hub between two universities. By creating this symmetrical layout, we are immulating the idea of equal access for all in the community.

The facade was then peeled up from the corner of the site to reveal the main circulation happening inside. That curve then extends back to enclose the hub.

Skin System

Structural System

Natural Lighting

The facade will be a layered system of glass and perforated zinc panels. The use of transparent glass and perforated zinc panels was chosen to allow plenty of natural light to enter into the hub.

The primary structure of the hub will be glu laminated timber construction. The construction of the upper level of the hub will be repetitive arch ways that continue to the front atrium space. The structure will then radiate into the atrium to create a beautiful open space.

To highlight the primary circulation and axial organization, the zinc panels will be completely removed down the axis of the hub with a large skylight directly above the main circulation to the stations.



Section Along Top Station Box: Red & Green Line Station


Section Along Top Station Box: Red & Green Line Station


Section Along Axis and Circulation


Section through Restaurants and Back of House


Section through Main Atrium


Hub Ground Level

51st Street

10

TRASH ROOM

11

Troost Avenue

HEALTH 2 MARKET

8 OFFICE RESTROOM

3

8

ELEC. 6

HM STORAGE

3 RESTROOM

5

MECH.

10

3 3 MECH. 5 CAFE

1

9 B/R STORAGE 8

4 KITCHEN

12 CAFE 8 STORAGE

8 B/R STORAGE

Hub Ground Level

1 2 3 4 5 6 7 8 9 10 11 12

Cafe Health Market Restroom Kitchen Mechanical Room Electrical Room Office Storage Service Elevator Bus Stand Trash Room Service Corridor


Hub Level Two

5

6

2 3 .,7&+(1

5

6(59,&( 4

1 2

3 .,7&+(1 1 6(59,&( 4

1

1 6

1 2 3 4 5 6

Bar Restaurant Kitchen Service Mezzanine Garden


Main Atrium Space


Cafe


Corridor to Bars and Restaurants


Level Two Green Space


Station Boxes : Red & Green Line Concourse


1 2 3 4 5 6

Paid Area Free Area Ticket Booth Fire Stair Platform Exhaust Electrical Room

7 8 9 10 11 12

Plenum Emergency Fan Room Plenum Ancillary Power Room Fan Room Traction Room Fire Stair

10

1

2 3

4

5

6

7

8

9

11

12


1 2 3 4 5 6

12

11

10

9

Free Area Paid Area Ticket Booth Fire Stair Platform Exhaust Ancillary Mechanical Room

7 8 9 10 11 12

Electrical Room Plenum Emergency Fan Room Plenum Auxillary Power Room Fan Room Traction Power

8

5

7

4

2

1 3

6


Station Boxes : Red & Green Line Platform


1 2 3 4 5

Platform Fire Stair Custodial Room Under Platform Exhaust Gap Breaker Room

6 7 8 9 10

Sump Pump Room Ejector Rooom Cable Room Auxillary Power Room Cable Room

6 2

3

4

5

7

10 8

9

9


1 2 3 4 5 6

Platform Elevator Fire Stair Under Platform Exhaust Custodial Room Auxillary Power Room

7 8 9 10 11

Gap Breaker Room Cable Room Sump Pump Room Ejector Room Fire Stair

9 11

8 10

7

6

5

4

3

2

1


Station Boxes : Purple & Yellow Line Concourse Electrical Room Plenum Emergency Fan Room Plenum Auxillary Power Room Fan Room Traction Power

11

7 8 9 10 11 12

12

Free Area Paid Area Ticket Booth Fire Stair Platform Exhaust Ancillary Mechanical Room

10

1 2 3 4 5 6

1 2 3 4 5 6

Paid Area Free Area Ticket Booth Fire Stair Platform Exhaust Electrical Room

7 8 9 10 11 12

Plenum Emergency Fan Room Plenum Ancillary Power Room Fan Room Traction Room Fire Stair

2

9

3 1

8

4

7

5

5

7

6

6 4

8

1 3 2

9 10 11 12


Station Boxes : Red & Green Line Concourse Gap Breaker Room Cable Room Sump Pump Room Ejector Room Fire Stair

1 2 3 4 5

Platform Fire Stair Custodial Room Under Platform Exhaust Gap Breaker Room

6 7 8 9 10

Sump Pump Room Ejector Rooom Cable Room Auxillary Power Room Cable Room 2

1

3 4 6

7

2

5 8

5

4

3

9

8

7

6

9

10

10

9

7 8 9 10 11

11

Platform Elevator Fire Stair Under Platform Exhaust Custodial Room Auxillary Power Room

1

1 2 3 4 5 6


Descending into Transit Stations


First Concourse


Purple & Yellow Concourse


Purple & Yellow Platform


Hub & Station Box Ventilation Diagram


Hub & Station Box Circulation Diagram


Tunnel Ventlation Diagram


Atrium Wall Section GLASS & ZINC STEEL CONNECTORS

STEEL CABLES

ZINC PANELS

5 A114

LOW E GLASS

GLU LAM BEAMS

OO STEEL CURTAIN WALL SUPPORT

GLU LAM COLUMN

4 A114

LOW E GLASS

STEEL KNIFE PLATE CONNECTOR

FORMED METAL BASE

1" ANCHOR BOLTS

DOUBLE GLAZED SILL

GROUND LEVEL 103' - 4"

3" PVC DRAINAGE PIPE STEEL PLATE CLADDING GRAVEL RIGID INSULATION RAIN / VAPOR BARRIER

HUB LEVEL 2 118' - 4"

24" CONCRETE BEAM

CABLES FOR DISPLAY SUPPORT

3 A114

5

Detail 0 1" = 1'-0"

2

Atrium Wall Section - Callout 1 1" = 1'-0"

OO 2 A114

GROUND LEVEL 103' - 4"

GALLERY DISPLAY BOARDS

NN

LOW E GLAZING

OPERABLE DOUBLE HOPPER WINDOW

STEEL FLOOR PLATES SUPPLY FLOOR VENT

RAISED ACCESS FLOORING

HUB LEVEL 2 118' - 4"

HUB LEVEL 2 118' - 4"

9 PLY CLT FLOORING

HVAC RETURN VENT

STEEL PLATE CLADDING

30" GLU LAM BEAM

SPRINKLER SYSTEM 9 PLY CLT

LED LIGHTING

GLU LAM BEAM

STEEL CURTAIN WALL SUPPORT

RG CONCOURSE 72' - 10"

3

Atrium Wall Section - Callout 3 1" = 1'-0"

4

Atrium Wall Section - Callout 4 1" = 1'-0"


Rear Hub Wall Section ZINC END CAP

STEEL CONNECTOR PLATE

BOLTED CONNECTION

STEEL COLUMN

3 A123

Sim

4 A123

Sim

2 A123

Sim EPDM ROOFING MEMBRANE

6" EXTERIOR RIGID INSULATION FLUID APPLIED A&W BARRIER

GUTTER SYSTEM

3/4 INCH SHEATING 1/2" FURRING STRIPS 5 PLY CLT ROOF

"

6

Short Section - Bars & Restaurants - Callout 4 4 1" = 1'-0"

7

Level 3 134' - 0"

EPDM ROOFING MEMBRANE AT 1/8" / 1' SLOPE

m

5

Short Section - Bars & Restaurants - Callout 5 1" = 1'-0"

CONCRETE FIBER CLADDING ALUMINUM FRAME FOR CLADDING FLUID APPLIED AIR & WATER BARRIER 3" EXTERIOR RIGID INSULATION 3 PLY CLT WALL STEEL FLOOR PLATES ALUMINUM FRAME WALL CONNECTOR

HUB LEVEL 2 118' - 4"

RAISED ACCESS FLOOR SYSTEM

CONCRETE PANELS RAISED ACCESS FLOOR

SUPPLY DUCT 3" EXTERIOR RIGID INSULATION

5" CONCRETE SLAB

CONCRETE BEAM

6 A123

6

Sim

Short Section - Bars & Restaurants - Callout 6 1 1/2" = 1'-0"

CONCRETE FOOTING FOR STEEL COLUMN

GROUND LEVEL 103' - 4"

PLANTER BOX

ion - Bars & Restaurants Copy 1 2

Short Section - Bars & Restaurants - Callout 1 1" = 1'-0"