1 minute read
Jail Renovation
Total Project Cost: $1.2M
Project Status: Continuing
PROJECT DESCRIPTION
This project includes renovating the dorm rooms in the Jail, upgrading HVAC systems, replacing boilers, repairing roof drainage systems, and improving the docket area used for booking inmates by constructing work stations and replacing flooring throughout multiple areas on the first floor.
Work began at the Jail in the Fall of 2019 and is currently ongoing. Various improvements throughout the facility have been performed by both design-bid-build contracting and existing cooperative contracts.
FUNDING SOURCES
• Cash-to-Capital - $0.9M
• Grant Funds - $0.3M
PROJECT MILESTONES
• Construction upgrades began in FY 20.
• Construction is scheduled to be completed in FY 24.