Norfolk Capitol Projects Overview 2012

Page 1

Project Timeline • • • •

Notice to Award Contract: November 9, 2011 Notice to Proceed: February 27, 2012 Start of Construction: March 2012 Phase One (Main Structure) Estimated Completion: December 2013 • Phase Two (Connection to Jail) Estimated Completion: December 2015

“The courthouse touches every citizen multiple times in their lives. It is where you go for a marriage license, jury duty, traffic court, will probate and more. Norfolk residents deserve a comfortable place that fits their needs.” — City Councilman Andy Protogyrou

For more information please visit www.norfolk.gov/PublicWorks.

City of Norfolk Capital Project Overview

Consolidated Courts Complex

“Today’s milestone represents years of collaboration with clerks, judges, law enforcement and the Bar Association. The new consolidated courts complex, not only creates construction jobs but ultimately provides more efficient citizen service in an environment that best suits the justice system.” — Mayor Paul D. Fraim


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.