MIT.nano BUILDING FACTS SQUARE FEET OF INTERIOR WALLS
25,000
27,000
SQUARE FEET OF INTERIOR STONE CLADDING
800,000 POUNDS
35.6 MILES
OF SHEET METAL DUCTWORK
OF PIPING
190 MILES
OF ELECTRICAL WIRING
3,385
AVERAGE PIECES INSTALLED PER DAY
AVERAGE WEIGHT PER PIECE OF POUNDS STRUCTURAL STEEL
TOTAL SQUARE FEET OF EXTERIOR WALL CLADDING
62,000
FEET OF PROCESS PIPING
22
AVERAGE TON PER DAY
22,000
40,000
640,000 CUBIC FEET PER MINUTE OF SUPPLY AND
EXHAUST AIR
TOTAL SQUARE FEET OF METAL WALL AND SOFFIT EXTERIOR WALL CLADDING
2,101
FEET OF FIRE PROTECTION PIPING
FEET OF PLUMBING PIPING
68
PIECES OF STRUCTURAL STEEL
100,000
20,000
60,000
300,000
STRUCTURE
PLUMBING AND WIRING
FEET OF HVAC PIPING
6,000
53,000
OF SITE UTILITY LINEAR PIPING
TOTAL SQUARE FEET OF GLASS CURTAIN EXTERIOR WALL CLADDING
1.4
EQUIVALENT MARATHONS OF PIPING
TOTAL SQUARE FEET OF STONE EXTERIOR WALL CLADDING
LABOR
EXCAVATION AND FOUNDATION
1,500,000 TOTAL PROJECT WORKER ONSITE MAN-HOURS
1,040
530,000 LINEAR FEET OF REBAR
350
TOTAL CUBIC YARDS OF CONCRETE IN THE ENTIRE PROJECT
ON SITE JOBS CREATED
3,000 TRUCKS AVERAGE NUMBER OF WORKERS PER DAY ON-SITE
12,000
530 MAXIMUM NUMBER OF WORKERS PER DAY ON -SITE
REMOVING SOIL
40,000 SQUARE FEET OF SLURRY WALL
9.9 MINUTES PER TRUCK LEAVING SITE ON PEAK DAY
1,400,000 CUBIC FEET OF SOIL REMOVED
550,000 LBS. OF STEEL BRACING TO TEMPORARILY SUPPORT SLURRY WALL DURING EXCAVATION