Argyle ISD Argyle West Elementary
•
•
•
Segment A: •
Gym : Painting ongoing; Window frames & glass installed; Coach’s office and storage sheet-rocked
•
Kitchen: Food Service hoods and walk-in freezer/refrigerator installed; Walls sheet-rocked, taped and bedded; Ceramic Tile has commenced
•
Cafetorium: Glass has been installed on the North; Frames installed on the South; Interior framing complete; Sheetrock installed on North wall; Standing seam roofing has commenced
Segment B: •
Admin: Sheetrock completed; Tape and bed has commenced; Masonry completed; Frames and glass installed
•
Classrooms: First floor framing complete; sheetrock has commenced; First floor window frames installed; Second floor rough carpentry on going for window frame installation; First and second floor exterior framing & sheathing completed; Steel framework for connecting corridor on going; stairs and handrails installed; Masonry has commenced on the East side; Roofing has commenced
Segment C: •
•
•
•
Construction Update
•
•
Interior framing complete
•
Exterior framing on going
2nd Floor •
Slab poured
•
Roof decking completed over classrooms;
•
MPE overhead on going
•
Interior and exterior framing on going
•
Stairs and handrails installed
•
Roofing has commenced
Segment D: •
•
1st Floor
1st Floor •
MP overhead installed
•
Interior framing complete
•
MPE wall rough-in on going
•
Exterior framing on going
2nd Floor •
MPE overhead 90% complete
•
Interior framing and exterior framing on going
•
Roofing to commence after Segment B/C
Library: •
Steel Framing and roof deck complete
•
Concrete paving completed at NW
•
Dumpster enclosure grade beams underway
•
Parking lot pole bases excavated and formed
Site: