Young Lit & Phil 'Conversation Club' - Technology and Environment Report

Page 1

PETER WINTERBURN

W12020388

CONVERSATION CLUB YOUNG LIT + PHIL

TECHNOLOGY & ENVIRONMENT REPORT

KA0733



TECHNOLOGY&ENVIRONMENT

Introduction

[4]

2.1 Structure 2.2 Groundworks and Foundations 2.3 Envelope

[14-15] [16-17] [18-21]

1.1 1.2 1.3 1.4 1.5 1.6

Site Plan Ground Floor plan Front Elevation Section Aa Accessibility Strategy Fire Strategy

3.1 Environmental Performance 3.2 Internal Finishes

4.1 Health and Safety Strategy 4.2 Site Layout 4.3 Assembly Sequence References

Technical Appendix

[5] [5] [7] [8] [9-11] [12-13]

[22-25] [26-27] [28] [29] [30-41]

CONTENTS PAGE


INTRODUCTION

This report is intended to serve as a record and portfolio of the Technologies, Planning and Legislation which has both informed and regulation the design both Technologically and Environmentally of the Young Lit and Phil ‘Conversation Club’ design project.

The report outlines the detailing and requirements of the technologies utilised within the project and cover the areas of; planning, structural performance, environmental performance, accessibility, building regulations and guidance, health and safety and the construction process.

1.0 TECHNOL OGY

4


5

ENVIRONMENT 1.1

SITE PLAN 1:250


GROUND FLOOR PLAN 1:200

Aa

1.2 TECHNOL OGY

Enterance Ramp Open Air Theater Access to Bridge Hotel Waiting Area WCs 10 Person Lift

Contained Stairwell

Teared Seating

6


7

ENVIRONMENT 1.3

FRONT ELEVATION 1:150


SECTION Aa

1.4 TECHNOL OGY

8


ENVIRONMENT 1.5

ACCESSIBILITY STARATERGY PART 1

Each floor offers 2 “Single Stall” WCs and 1 Accessible WC. The accessible WC meets the guidelines outlined in the Approved Document Part M. Accessible WC features “Contour 21 Doc M Close Coupled Pack, Left Hand (S6966AC)” from Armitage Shanks.

1061

• Assistance alarm system provided (see Axo) 1500

• WC is located on an accessible route which is direct and unobstructed In addition to this, the Accessibler WC is locasted 4 meter from the Lift to aid access. 2203

1500

ø

00 15

• Outward opening door fitted with a horizontal closing bar 1099

2200

1500

ø

00 15

90 0

900

1241

90 0

1

• Wall-mounted grab rail provided (see Axo)

14 00

1600

• A 1500mm turning circle

14 00

1121

1500

9


ACCESSIBILITY STARATERGY PART 2

A textured finish is applied on tot the polished concrete stairs at the head of each staircase. This change in finish provided a “Harvard Warning” for users with visual impairments, this prevents loss of balance and injury. This has been designed in accordance with the Approved Document Part M

1.5 TECHNOL OGY

10

1061

1121

14 00

1600

A bright white paint has been applied to the edge of each tread of the step to further indicate the edge of the step to those with visual impairments. Emergency lighting is built into the handrail on both sides of eliminate the floor in the event of a fire.

1500

2203

1500

ø

00 15

1099

1500

2200

900

1241

1500

ø

00 15


11

ENVIRONMENT 1.5

ACCESSIBILITY STARATERGY PART 3

Wheelchair Users (Top)

4 Wheel chair space are provided in the front row of the Main Theatre, these allow for 1400x900mm of clearance which is sufficient for a wheelchair user to be moved into position by a carer or relative comfortable. Seating is provided between each space carers or relatives.

14 00

90 0

Hearing Loops (Bottom)

14 00

90 0 1099

14 00

90 0

14 00

2203

90 0

Approved Document Part M required that sufficient measures are put in place to aid users with hearing impairments. A hearing loop will be installed in the main auditorium to aid in the users. (Induction Loop indicated in red) “A hearing loop is a special type of sound system for use by people with hearing aids. The hearing loop provides a magnetic, wireless signal that is picked up by the hearing aid when it is set to ‘T’ (Telecoil) setting.” (What is a hearing loop?, 2012) Enterance

The building is accessed by a wide ramp with a 1:10 incline in accordance with BS 9266:2013 900

Both way swing doors can be electronicaly opened with push button opening on both sides of the door, laser sensors built into the frame prevent the doors from closing onto users, these doors will automatically open in event of a fire. internal doors feature power assist functionality. Step free access into the Bridge Hotel.


FIRE STRATERGY

1.6 TECHNOL OGY

12

Means of Warning and Escape

B1. The requirements of B1 will be met if

10900

a) there are routes of sufficient number and capacity, which are suitably located to allow persons to escape to a place of safety in the event of a fire; 9470

ø 1061

13 73 1

1600

1500

1500

1862

3100

39m

3622

1500

UP

00 15

1241

0 00 11

1500

238

900

16.5m

fire drawing ground

fire lowe

1 : 200

1 : 200

1099

2203

(Approved Document B: Fire Safety, 2013)

11156

Approved Document part B (volume 2) provides guidance on how to comply with the building regulations relating to fire safety in buildings other than dwellings. (Communities and Government, 2013)

ø

2200

d) the exits are suitably signed

It is imperative that an early warning is provided to all occupants in the event of a fire. Due to the scale of the building and estimated number of occupants, smoke detectors must be fitted within 7.5m of the entry point of each habitable space, and a suitable electrically operated alarm system must be fitted; sufficient sounders must be provided and be clearly audible throughout the building.

00 15

00 35

c) the routes are adequately lit;

Detection & Warning

1121

b) the routes are sufficiently protected from the effects of fire where necessary;

14 00


13

ENVIRONMENT 1.6

MEANS OF ESCAPE

The building entrance features doors which will automatically open in the event of a fire In the event of a fire, fire curtains will deploy on the connection between the bridge hotel and the young lit and phil to prevent fire from spreading the adjacent structure.

178 25

228 25

In order to prevent building users from becoming trapped in the building in the event of fire/smoke, alternative means of escape are in place from all parts of the building.

36m

DN 0 60 16

0 60 17

3100

34m

32 05

9569

424 2

3384

587 1

4400

53 46

00 98

DN

fire lower ground 1 : 200

2197

2738

11335

2384

DN

34m

first fire 1 : 200

00 98

All escape routes have clear signage and lower level lighting will be employed to aid in escape if heavy smoke is present. Wheelchair refuge points are located in the protected stairwell on each floor. 1500x900mm of refuge has been provided. These zones do not affect the means of escape for other users. Design Amendment

To reduce the travel distance on the first floor a second staircase could be added towards the front of the building which would cut the travel distance to an exit by more than half.


STRUCTURE - WALLS

2.1 TECHNOL OGY

In-Situ Cast Construction The structure is entirely Concrete elements. Due several steps have been and performance of this

comprised of In-Situ Cast to the nature of the design taken to increase the strength method of construction.

At wall joins and floor joints KSN Anchors have been cast into the concrete in which rebar is screwed of bonded into them. This allows for the concrete to shrink creating a movement joint. This also removed the need for exteriors rebar jutting out of the walls which may cause injury. Cemex CEMEX MicroTech - Fibre Reinforced Concrete has been used through the building to add strength epically in large spans. A range of advanced concretes, carefully formulated with microsilica and the latest admixture technology to produce high performance concretes with exceptional levels of durability in the harshest of environments.

The technology used in the formulation of CEMEX MicroTech ensures a high strength, low permeability concrete with enhanced resistance to sulfate and chloride attack. Coupled with increased levels of flexural strength and improved resistance to impact and abrasion, the product is a high performance concrete that will deliver in the most challenging of environments. Holedeck formwork has been uses to create voids within the floors allowing for spans of up to 12 meters. This system also allows services to be laid inside the voids removing the need for a suspended ceiling.

14


15

ENVIRONMENT 2.1

STRUCTURE - FLOORS

Holedeck formwork has been uses to create voids within the floors allowing for spans of up to 12 meters. This system also allows services to be laid inside the voids removing the need for a suspended ceiling.

The Formwork has be used in a linera patern to emphasise the building intersecting angles. Concrete consumption and self weight are decreased, using conventional concrete and steel without the need for specialist labour. Savings of up to 55% of the volume of concrete and up 20% of the total built volume are possible, with the consequent carbon footprint reduction. (Holedeck, 2014)

The Holedeck system is also an improvement in terms of acoustic performance. The reverberation time is reduced to 1/5 with respect to a flat concrete slab. (Holedeck, 2014) The standardised formwork is manufactured with high-resistance polypropylene, meaning it can be used up to 50 times and recycled at the end of its life-cycle. (Holedeck, 2014)


FUNDATION AND GROUND WORK DETAIL 1:10

100mm Cast Concrete Outer Skin 150mm Insulation

250mm Cast Concrete Outer Skin

490mm Sustainable Urban Drainage System 80mm Granite Slab 50mm Laying Course Inbitex Membrane 100mm Sub-base 100mm Sub-base 5mm SC Intergrid 50mm Sub-base Inbitex Membrane

Concrete Pad

Sand Binding

300mm Insulation Earth

2.2 TECHNOL OGY

16


17

ENVIRONMENT 2.2

EXTERNAL STEPPED SEATING DETAIL 1:20

Custom Granite Steps with 1 degree slope Drainage Channel Concrete Pad Foundation Sand Binding

SUDs (Opposite Page) Earth


WALL DETAIL 1:10

2.3 TECHNOL OGY

18mm Rebar Underfloor Heating System KSN Rebar Anchors

150mm Insulation Holedeck Formwork 100mm Cast Concrete Outer Skin 250mm Cast Concrete Inner Skin

18


19

ENVIRONMENT 2.3

ROOF TO WALL DETAIL 1:20

Roofing Membrane

150mm Insulation

Holedeck Formwork 100mm Cast Concrete Outer Skin 250mm Cast Concrete Inner Skin


GLAZING TO CONCRETE DETAIL 2:1

Concrete Wall

Aluminium U Channel with Flanges Glazed Outer Leaf GRP Spacer/Endcap Glazing Inner Leaf Silicone Sealant

2.3 TECHNOL OGY

20


21

ENVIRONMENT 2.3

GLAZING SYSTEM DETAIL 1:2

Aluminium Capping Strip Glazed Outer Leaf

GRP Spacer/Endcap Glazing Inner Leaf Insulation Extruded Aluminium Frame


ENVIROMENTAL PERFORMANCE VENTILATION

The auditorium is the only space within the building which uses Mechanical ventilation. Duct work runs through the hollows within the Holedeck Slab from the plant room tot eh auditorium and enters through trickle vents between the layers of seating.

The depth of waffle slab roof deck creates a ‘reservoir’ of hot air. This additional depth is required in order to properly ventilate the upper floors; it raises the ‘neutral plane’ and prevents hot air from being forced out of the atrium into these spaces. (King, 2009) A Toilet stack vent runs behind the WCs which leads out via a protected roof vent. The WCs have mechanical ventilation to provide fresh air intake and fowl air is exhausted.

All other areas in the building are ventilated through trickle vents built into the glazing and external doors and are exhausted through non-return vents in the roof glazing.

3.1 TECHNOL OGY

NATURAL VENTILATION

MECHANICAL VENTILATION

22


23

ENVIRONMENT 3.1

ENVIROMENTAL PERFORMANCE THERMAL MASS

The building has a large thermal mass thanks in part of the dense 250mm internal concrete skin. The bare concrete acts as a thermal store which absorbed and releases heat into the building. This process of heat exchange would be eliminated or servery reduced if surface finishes and flooring were applied.

The diagram opposite indicated upto an 8 degree difference in temperature between a concrete based wall system and a traditional timber framed building. The thermal mass of concrete has the following benefits and characteristics: • • • • • •

Delays peak loads Reduces peak loads Reduces total loads in many climates and locations Works best in commercial building applications Works well in residential applications Works best when mass is exposed on the inside surface • Works well regardless of the placement of mass


ENVIROMENTAL PERFORMANCE GEOTHERMAL HEAT PUMP

Geothermal heat as GeoExchange, ter-source heat 1940s. They use as the exchange temperature.

pumps (GHPs), sometimes referred to earth-coupled, ground-source, or wapumps, have been in use since the late the constant temperature of the earth medium instead of the outside air

The system is comprised of an exchanger which takes heat from a fluid (generally Glycol or Anti-Freeze) this is done by passing two loops across one another allowing the heat to transfer throught the heat exchanger similar to a common refrigerator. A persentage oif the heat exchanged is passed on to a Hot Water heater to be used for plumbing use whilst the remainder is passed throught the building underfloor heating system. The system can be run in reverse to provide a cooling tot he building. The technology canbe used as part of an Air-based heating system if required.

Due to the low hot water demands of this building, an system with intergrated water heating will be required.

Summe System

Exchanger

Water Heater

3.1 TECHNOL OGY

Winter System

Exchanger

Water Heater

24


25

ENVIRONMENT 3.1

ENVIROMENTAL PERFORMANCE UNDERFLOOR HEATING/COOLING

The underfloor heating and cooling system will be powered by the Geothermal heat pump using Glycol heated on an indemendent loop to tthe Glycol used in the undefround pipework.

Exchanger

The system is comprised of a vast network of GRP pipework which is secured onto silicone or aluminium covered ridged insulation, this is then topped with a concrete floor screed. The screed allows the heat to disapate evenly.

Manifold

The Glycol is passed throught a Manifold which has a built in pump to fource the fludic round the system. Each floor will have its own manifold and each floor can be independantly controlled.

The system maintains its temperature using the Geothermal Heat Pump System, this can be supplimented if reuired using a small heating element inside the manifold.

The system willl be used to offset the effect of solar gain by absorbing the heat from the sun and transphering it into the ground.

Exchanger

Manifold


INTERNAL FINISHES

CEMEX MicroTech - Fibre Reinforced Concrete

A range of advanced concretes, carefully formulated with microsilica and the latest admixture technology to produce high performance concretes with exceptional levels of durability in the harshest of environments. The technology used in the formulation of CEMEX MicroTech ensures a high strength, low permeability concrete with enhanced resistance to sulfate and chloride attack.

Coupled with increased levels of flexural strength and improved resistance to impact and abrasion, the product is a high performance concrete that will deliver in the most challenging of environments.

3.2 TECHNOL OGY

26


27

ENVIRONMENT 3.2

INTERNAL FINISHES

Marshalls Galatea Granite (Fine picked)

Galatea Fine Picked Granite is suitable for both pedestrian or vehicular trafficked areas.

A very light silver grey stone it is also available in flamed and polished finish. Available for all product areas such as paving, setts, kerbs, tactile, steps, water management, street furniture or other bespoke specialised masonry items such as veneers for planters or furniture. Produced to ISO9001 quality assurance standards. All Marshalls Granites are fully tested to the appropriate standards in the UK and are all CE marked in accordance with the latest legislation. Granites are generally hard wearing, strong and durable landscaping materials.


HEALTH AND SAFETY

All works on site must comply with CDM (Construction Design and Management) Guidance, in additon to HSG150 and “Construction hazardous substances: Cement” Guidelines from the Health and Safety Executive. Facilities Provided

Site Management (Office) Changing Facilities Washing Facilities Rest Facilities

Car Parking (Below)

4.1 TECHNOL OGY

Construction hazardous substances: Cement

Cement based products, like concrete or mortar, can cause serious skin problems such as dermatitis and burns. This page tells you how to control these risks and why.

Gloves – gloves should be waterproof and suitable for use with high pH (alkaline) substances; eg marked with EN374:2003 and tested for use with “alkalis and bases” (class K) – some nitrile or PVC gloves may be suitable. Breakthrough time and permeation rate should also be suitable for the type and duration of the work. Gloves should be long and /or tight fitting at the end to prevent cement being trapped between the glove and the skin. Footwear – suitable footwear, such as wellington boots, should be used where large concrete pours are taking place. If standing in cement, these should be high enough to prevent cement entering the top of the boot. Waterproof trousers – when kneeling on wet products containing cement, appropriate waterproof trousers should be worn or, if screeding, use appropriate waterproof knee pads or knee boards. Minimise any time spent kneeling. Wear trousers over the top of boots. This stops cement getting into them.

Washing – wash off any cement on the skin as soon as possible. Workers should be encouraged to wash exposed skin at breaks and after work. Good washing facilities are essential. There should be hot and cold or warm running water, soap and towels. Basins should be large enough to wash forearms. Showers may be needed in some situations where workers could get heavily covered in cement. Use emergency eyewash to remove any cement that gets into eyes. Skin care products – these can help to protect the skin. They replace the natural oils that help keep the skin’s protective barrier working properly.

28


29

ENVIRONMENT 4.2

SITE LAYOUT

Material Storeage Area Secure Internal Store

Site Facilities 2400mm Go-Hoard™ Vehicle Gates 2400mm Go-Hoard™ Site Hoarding

DN

DN

2400mm Go-Hoard™ Site Hoarding


ASSEMBALLY SEQUENCE 1

1. Hoarding Errected and Temporary Site Building Installed.

2. Site Cleared in preperation for works.

3. Land Graided into site to create a service ramp for machine access. 4. Bridge Hotel Underpinned

4.3 TECHNOL OGY

30


31

ENVIRONMENT 4.3

ASSEMBALLY SEQUENCE 2

1. Land removed for foundations. 2. Steel Piles Installed with Ground Source Heat Pipework Installed within them. 3. Raft Foundation Cast.


ASSEMBALLY SEQUENCE 3

1. Additional land cleared. 2. Retaining Wall cast.

3. Temporary ramp created into site.

4.3 TECHNOL OGY

32


33

ENVIRONMENT 4.3

ASSEMBALLY SEQUENCE 4

1. External and Spine Walls cast. 2. Interiror Walls Cast


ASSEMBALLY SEQUENCE 5

1. Spine Wall Cast

2. Formwork Errected for Cast Upper Floor.

4.3 TECHNOL OGY

34


35

ENVIRONMENT 4.3

ASSEMBALLY SEQUENCE 6

1. Upper Floor Cast

2. External and Spine Walls cast. 3. Interiror Walls Cast

4. Ramp created from external ground level.


ASSEMBALLY SEQUENCE 7

1. Canterliveered Wall Cast

4.3 TECHNOL OGY

36


37

ENVIRONMENT 4.3

ASSEMBALLY SEQUENCE 8

1. Upper Floor Cast

2. External and Spine Walls cast. 3. Interiror Walls Cast

4. Ramp created from external ground level.


ASSEMBALLY SEQUENCE 9

1. Upper Floor Cast

2. External and Spine Walls cast. 3. Interiror Walls Cast

4.3 TECHNOL OGY

38


39

ENVIRONMENT 4.3

ASSEMBALLY SEQUENCE 10

1. Upper Walls Cast

2. Form work errected for casting roof


ASSEMBALLY SEQUENCE 11

1. Roof Cast In.

2. Curtain Glazing Installed over atrium. 3. Roof covering applied

4.3 TECHNOL OGY

40


41

ENVIRONMENT 4.3

ASSEMBALLY SEQUENCE COMPLETED



REFERENCES Approved Document B Fire Safety Buildings Other Than Dwellinghouses Vo. (2013). 1st ed. London: RIBA Publishing. C1 site preparation and resistance to contaminants, C2 resistance to moisture. (2013). [Place of publication not identified]: RIBA.

C20society.org.uk. (2017). Dunelm House, Durham — The Twentieth Century Society. [online] Available at: http://c20society.org.uk/botm/dunelm-house-durham/ [Accessed 14 May 2017]. Construction Industry Research and Information Association and Sustainable Urban Drainage Scottish Working Party (2000). Sustainable urban drainage systems. 1st ed. London: Construction Industry Research and Information Association. Daley, R. (2017). Auditorium Building, Delft University of Technology, Delft, The Netherlands. [online] Brutalism.online. Available at: http://brutalism.online/ brutalist-buildings/40-the-netherlands/401-auditorium-building-delft-university-of-technology-delft-the-netherlands [Accessed 14 May 2017].

Dimplex.co.uk. (2017). RENEWABLE SOLUTIONS - GROUND SOURCE - HEATING AND HOT WATER. [online] Available at: http://www.dimplex.co.uk/products/renewable_solutions/heat_pump_ground_source/commercial/SI_TU_range/index.htm [Accessed 14 May 2017]. Foster, J. (2015). Mitchell's structure & fabric. [Place of publication not identified]: Routledge. Gorse, C., Johnston, D. and Pritchard, M. (2012). A dictionary of construction, surveying and civil engineering. Oxford: Oxford University Press.

Gov.uk. (2017). Fire safety: Approved Document B - GOV.UK. [online] Available at: https://www.gov.uk/government/publications/fire-safety-approved-document-b [Accessed 14 May 2017]. Henderson, N., Baldwin, N., McKibbins, L., Winsor, D. and Shanghavi, H. (2002). Concrete technology for cast in-situ foundations. London: CIRIA. Kind-Barkauskas, F. (2002). Concrete construction manual. 1st ed. Basel: Birkhauser.

Marshalls.co.uk. (2017). Galatea Granite Fine Picked Paving Setts and Kerbs. [online] Available at: https://www.marshalls.co.uk/ commercial/natural-stone/products/galatea-granite-fine-picked-webfa091830 [Accessed 14 May 2017].

Ribaproductselector.com. (2017). Armourplan PVC roof membrane product brochure. [online] Available at: https://www.ribaproductselector.com/armourplan-pvc-roof-membrane-product-brochure/19448/col369015/download.aspx. Ribaproductselector.com. (2017). CEMEX - Fibre Concrete. [online] Available at: https://www.ribaproductselector.com/cemex-fibre-concrete/21068/ col1521068/download.aspx [Accessed 14 May 2017].

Ribaproductselector.com. (2017). Commercial lift brochure. [online] Available at: https://www.ribaproductselector.com/commercial-lift-brochure/7050/ col207050/download.aspx [Accessed 14 May 2017]. Ribaproductselector.com. (2017). Kawneer Curtain Wall Systems Brochure. [online] Available at: https://www.ribaproductselector.com/kawneer-curtain-wall-systems-brochure/4373/col527996/download.aspx [Accessed 14 May 2017].

Ribaproductselector.com. (2017). Protective Street Furniture. [online] Available at: https://www.ribaproductselector.com/protective-street-furniture/4959/ col921483/download.aspx [Accessed 14 May 2017]. The Building Regulations 2010. (2011). [Place of publication not identified]: NBS.

Health and safety in construction HSG150. (2017). 1st ed. Health and Safety Executive.

Hse.gov.uk. (2017). Cement - Controlling hazardous substances - Managing occupational health risks in construction. [online] Available at: http://www.hse. gov.uk/construction/healthrisks/hazardous-substances/cement.htm [Accessed 9 May 2017].

Legislation.gov.uk. (2017). The Construction (Design and Management) Regulations 2015. [online] Available at: http://www.legislation.gov.uk/uksi/2015/51/contents/made [Accessed May 2017].



















Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.