Robinson Project 1 and Project 2 | 8/31/17

Page 1

Robinson Av. Street and Drainage Improvements Projects Project 1 and Project 2 Districts 1 August 30, 2017


Robinson Ave. Improvements Project Project Location (Project 1)

2


PROJECT BACKGROUND Existing Roadway Conditions • • • •

Predominant 80-ft R.O.W. Two-Way Traffic Corridor 20-ft Concrete Paved Section Narrow 10-ft Wide Lanes

Existing Roadway Typical Section


PROPOSED ROADWAY SECTION Proposed Roadway Improvements • Two 11-ft Lanes (CRCP) • 5-ft Parkway/Drainage Area • 12-ft Shared Use Path • 5-ft Sidewalk • New Rock Wall • New Landscaping • Safety Illumination

Proposed Roadway Typical Section


Robinson Avenue


Robinson Av. Phase 2


Robinson Avenue


PROJECT PROGRESS STATUS PROJECT 1 Maintain 2-wMaintain Trafficcomplete Phase 1 Status: Existing pavement 2-way demolition, ay Traffic concrete pavement from Piedmont to Sierra Crest, Robinson street open to traffic, Hike and Bike trail, concrete sidewalk and curb, drainage gabions, 2’ rock wall, installation of illumination poles and relocation of water and sewer lines. Outstanding items: Landscaping (in process), irrigation (in process), striping and electrical associated with illumination. Phase 2 Status: Existing pavement demolition, complete concrete pavement from Sierra Crest to Canyon Terrace, Robinson street open to traffic, Hike and Bike trail, concrete sidewalk and curb, drainage gabions, 2’ rock wall, installation of illumination poles and relocation of water and sewer lines. Outstanding items: Landscaping (in process), irrigation (in process), striping and electrical associated with illumination.


PROJECT PROGRESS STATUS PROJECT 1 Maintain 2-wMaintain Traffic relocation of Phase 3 Status: Existing pavement2-way demolition, ay Traffic sewer line, 16” water line, 2’ rock wall, drainage gabions completed. Outstanding items: Relocation of 12” water line (50%), concrete pavement (in process), Hike and Bike trail, concrete sidewalk and curb, installation of poles, landscaping, irrigation, striping, and electrical associated with illumination. Phase 4 Status: 2’ rock wall (95%) and gabions completed. Outstanding items: Relocation of water and sewer line, concrete pavement, box culvert, concrete sidewalk and curb, Hike and Bike trail, parking area at Rim/Robinson scenic overlook, installation of poles, landscaping, irrigation, striping, and electrical associated with illumination.


PROJECT PROGRESS STATUS PROJECT 1 Maintain 2-wMaintain 2-way Traffic ay Traffic


PROJECT PROGRESS STATUS PROJECT 1 Maintain 2-wMaintain 2-way Traffic ay Traffic


PROJECT PROGRESS STATUS PROJECT 1 Maintain 2-wMaintain 2-way Traffic ay Traffic


Robinson Av. Phase 2 Project 2 limits: Ochoa St to Piedmont Dr.

Project limits Piedmont Dr.

Project limits Ochoa St.


Robinson Av. Phase 2 • Negotiating Design Proposal • Expected award in September 2017 – Concept Report Phase expected in November 2017 – Preliminary Design Documents expected in January 2018 – 1st Community meeting expected in March 2018