2017 TRANSPORTATION FORUM

SOUTHERN BELTWAY Pennsylvania Turnpike Commission Steven J. Hrvoich, P.E. Construction Engineering Manager

April 5, 2017


Southern Beltway

(Findlay Connector) PA-60 to US-22 (Completed July, 2006)

Section

Bid

Contractor

54A

$

35,953,665.70

Dick Corp., Large

54B

$

64,898,184.30

Mashuda Corp.

54C

$

46,520,309.55

St Paul/ Mashuda


Southern Beltway facts: • Total construction cost estimate for the entire 13 mile US22 to I-79 project is over $710,000,000. • Anticipated 7 Major Section Contracts • The PTC intends to open the Southern Beltway to traffic in late 2019, and finish work on I-79 interchange in 2020. • CDR Maguire is the Commission’s Construction Manager.


Southern Beltway Map


Southern Beltway; 55A1-1, Dual Bridges over US-22, Completed March, 2015 Mosites Construction Company, $14,400,000.


Southern Beltway; 55W Wetlands Mitigation for Southern Beltway Cast & Baker, Inc., $954,000


Southern Beltway: Section 55A1 3.7 miles of Mainline, 7 Bridges, 7 Local Roads, New Interchange

• • • • • • •

Bids Opened November 9, 2016 Independence Excavating, Inc.: $90,621,870.00 Excavation –5,400,000 CY (various classes) Pipe –40,000 LF (various types/classes) Inlets –340 ea. 6 –Mainline and 1 –Overhead bridges New Beech Hollow Connector Road and Interchange Cashless Tolling Gantry


Southern Beltway: Section 55A1 3.7 miles of Mainline, 7 Bridges, 7 Local Roads, New Interchange


Southern Beltway: Section 55B 3 miles of Mainline, 2 Bridges, 5 Local Roads

• • • • • • •

Bids Opened December 14, 2016 Joseph B. Fay Co.: $90,621,870.00 Excavation –5,700,000 CY (various classes) Pipe –26,000 LF (various types/classes) Inlets –230 ea. 2 –Mainline (Dual bridges –1,500’ long/110’ tall) over SR 980. New Reissing Road and new alignment to existing Laurel Hill Rd. Cashless Tolling Gantry


Southern Beltway: Section 55B 3 miles of Mainline, 2 Bridges, 5 Local Roads


Southern Beltway: Section 55C1-1 1.7 miles of Mainline, 4 Bridges, 4 Local Roads, New Interchange

• • • •

Advertisement - Current Excavation –1,000,000 CY (various classes) Pipe –32,000 LF (various types/classes) Inlets –270 ea. 2 –Mainline (Dual bridges –1,015’ long/100’ tall) over SR 50 and W&LE Railroad. • New Cecil Sturgeon Connector Road and Interchange • New Connector Road and Bridge to SR 50


Southern Beltway: Section 55C1-1 1.7 miles of Mainline, 4 Bridges, 4 Local Roads, New Interchange


Southern Beltway: Section 55C2-2 1 mile of Mainline, 2 Bridges, 4 Local Roads, Roundabout

• • • • • •

Advertisement – Fall 2017 Excavation –1,000,000 CY (various classes) Pipe –10,000 LF (various types/classes) Inlets –95 ea. New Morganza Road Alignment and Roundabout at Morgan Rd New Morgan Road Bridge over I-79 New Baker Road Bridge over mainline Southern Beltway


Southern Beltway: Section 55C2-2 1 mile of Mainline, 2 Bridges, 4 Local Roads, Roundabout


Southern Beltway: Section 55A2 3 miles of Mainline, 5 Bridges, 4 Local Roads, New Interchange

• • • •

Advertisement – Spring 2018 Excavation –3,300,000 CY (various classes) Pipe –38,000 LF (various types/classes) Inlets –285 ea. 2 Mainline Curved Girder Bridges, 1,800’ long over Noblestown Road and the Panhandle Trail • 2 Mainline, 180’ long bridges at the new Ft Cherry Interchange • 1 Local, 100’ long bridge over the Panhandle Trail


Southern Beltway: Section 55A2 3 miles of Mainline, 5 Bridges, 4 Local Roads, New Interchange


Southern Beltway: Section 55C1-2 3 miles of Mainline, 1 Bridge, 2 Local Roads

• • • • •

Advertisement – Early 2018 Excavation –2,000,000 CY (various classes) Pipe –9,500 LF (various types/classes) Inlets –55 ea. 1 Bridge–Hickory Grade Road Over Mainline 72” RCP Culvert


Southern Beltway: Section 55C1-2 3 miles of Mainline, 5 Bridges, 4 Local Roads, New Interchange


Southern Beltway: Section 55C2-1 3 miles of Mainline, 3 miles of I-79, 6 Bridges, 4 Local Roads, New Interchange

• • • • •

Advertisement – Spring 2018 Excavation –9,000,000 CY (various classes) 4 –I-79 structures including widening into the median 2 – Mainline Ramp structures including 1 curved girder New interchange at Morganza Road with extensive ramps


Southern Beltway: Section 55C2-1 3 miles of Mainline, 3 miles of I-79, 6 Bridges, 4 Local Roads, New Interchange


Southern Beltway: Additional Projects • Section S; Signing, Advertisement – Spring 2018 • Section T; Cashless Tolling, Advertisement –1stQ of 2018 • Section M; Maintenance Facility, Advertisement – Fall 2017


Southern Beltway Challenges • Extensive Utility Relocations • Regional Environmental Factors

• Acid Mine Drainage • Pickle Liquor Sludge / Coal Refuse

• Geotech – Deep Mine Grouting • Abandoned Gas & Oil Wells • Community Coordination & NCOTA • 3 New Local Interchanges and Local Road Impacts • Multi County/Agency Coordination (Local/State/Federal)


Southern Beltway Sustainablility Measures • 12” PCC/Long Life Concrete Pavement • Drainage: ATPBC, dual pavement base drain system • Type A Rock Slope Armor • ASTM A-588 Steel Bridge Girders • AAAP Concrete Bridge Decks • Triple Drop Linestriping


Southern Beltway Links • https://www.patpconstruction.com/southern_beltway

• https://ebs.paturnpike.com/generalinformation/bids/bid_ schedule.aspx?type=Advertised