Plains Producer $1.40
Wednesday June 29, 2011
STAR OF THE NORTH
Sock ‘n’ Roll
n THE gang at Balaklava football and netball clubs have been “sock’n’rolling” with a fun-filled few days. On Saturday night after the club’s home game against Hamley Bridge, it was a “back to the 80s night” with some interesting costumes. Cheeky Pecker Daniel Butterfield appears to be portraying a footballer from another era. But the big questions are ...who do those legs belong to – and why the socks? Who is the odd one out. Do you know her? See Page 2 for the answer.
$6 million questions Report to council probes Port Wakefield CWMS
A REPORT into the contract compliance of Wakefield Regional Council (WRC) during the construction of the Port Wakefield Community Wastewater Management Scheme has outlined several shortcomings by the various parties involved. Consultant, Martin Harvey, presented his report to council at last Wednesday evening’s council meeting. “The Contract Compliance Review was commissioned by the chief executive officer of Wakefield Regional Council in order to establish the state of compliance and adherence to the terms and conditions of the contracts by the various contracting parties engaged for the Port Wakefield CWMS project,” he told council in his presentation.
Les Pearson reports: Mr Harvey said the review also was to demonstrate council’s transparency and document the lessons learned from the controversial project, which regularly drew the ire of a number of Port Wakefield’s residents. Amongst Mr Harvey’s lengthy list of findings, he highlighted council’s tendering process and the subsequent blow out of the total cost of the project through variations to the original contract. “If one takes the variation submissions as a stand-alone, they would appear to be excessive – and we’re talking about 60 per cent of the original contract value,” Mr Harvey said.
“It is important to note, however, a large number of those variation submissions were actually anticipated works that had not been formulated in terms of final design at the time the contract was put out to tender. “(This included) such things like the vacuum pump station relocation, storage lagoon and subsequently the revision of the connection point policy.” The report said the original contract was quoted at about $3.5 million when the tender was awarded to design, construction and engineering firm, Wallbridge and Gilbert (W&G). With the variations, the total contract value blew out to nearly $6 million, the report said.
Mr Harvey said W&G were not responsible for the exorbitant increase in the project cost. “Had there been sufficient opportunity for Wallbridge and Gilbert and the contractor to undertake a detailed site investigation, it is my belief the additional works paid out as variations would have been identified at tender stage,” he said. “I do not contend the additional works and the amounts thereto would have been avoided, what I’m saying is if such detailed site investigations had taken place during preliminary and final design process, the tender pricing would have been more comprehensive and would have covered those items to a great degree.”
BUY FROM THE BUTCHER & SAVE $ Chuck Stewing Steak
Rump Steak
Lamb 4/4 BBQ Chops
7
$
95
Per Kg
1250
$
Per Kg
850
$
Per Kg
Specials valid from Wednesday June 29 to Saturday July 2
HURRY! ENDS ON FRIDAY
material handling world leader Inventor of the rough terrain forklift truck, Manitou offers today the most comprehensive range to meet all specific handling and personal lifting requirements! Sales / Rentals
W.S.B. DISTRIBUTORS 198 Main North Rd, CLARE 8842 2177 Phil Stanway 0419 828 802
Adelaide Main North Road WSB Dist.
Victoria Rd
Marc’s Meats
Only local Australian Meat at Marc’s. No imported meats used. And no minimum weight at the butcher
n CONTINUED PAGE 4
SHOP Locally AND WIN