Francis T. Maloney High School City of Meriden May 5, 2011
Team Introductions: Maloney High School
Fletcher Thompson:
Joe Costa, AIA, LEED AP – Principal KK-12 Curt Krushinsky, RA, LEED AP – Project Manager Angela Cahill, AIA AIA,, LEED AP – Assistant PM Dan Davis, AIA, LEED AP – Director of Design Mike Berger, LEED AP – Senior Designer
Blades and Goven:
Earl Goven, ASLA – Landscape Architect
Leach Consulting, LLC
Kevin Leach, P.E. – Estimator
May 5, 2011
Program Analysis
Design Approach: High School – Programming
Drawing on Our Expertise/Research/Tools Communicating/Listening/Implementing Program: Foundation of a Successful School Avoiding Facilities That Are Not Needed Space Allocation/Distribution Critical Program Approved on April 7th
TOTAL: 271,553 SF
May 5, 2011
Design Approach:
Maloney High School – Existing School Plan
1970’s
Original Building 1958 Addition 1970s Code/Safety Issues Hazardous Materials Facility Needs Modernization Enabling a 21 Century Curriculum
1958
May 5, 2011
Design Approach:
Maloney High School – Existing School Plan
May 5, 2011
Design Approach:
Maloney High School – Challenges and Opportunities
Site Configuration Entrance Drive/Fields/Parking Loop Circulation Patterns Distribution of Large Spaces Community Uses of Facility Construction Phasing Construction Phasing Coordination with Platt HS Modernize Facility d i ili May 5, 2011
Design Approach:
Maloney High School – Concept Design (Work in Progress)
Site Influences Building Design
FIELDS
Entry/Graduation/Service Zoning: Public/Private
GALLERY
Loop Circulation Patterns Display History/Learning Library/Media Center Library/Media Center
FIELDS
Freshman Academy/Bridge Natural Light Throughout GRADUATION
May 5, 2011
Improve Curb Appeal
Main Level Plan
M i L lT l Main Level Total:
160,949 sf
May 5, 2011
Upper Level Plan
U Upper Level Total: L lT l
38,422 sf
May 5, 2011
Pool Level Plan
P lL lT l Pool Level Total:
48,344 sf
May 5, 2011
Lower Level Plan
L Lower Level Total: L lT l
19,534 sf
May 5, 2011
Building Area Summary Upper Level:
38,422 sff
Main Level:
160,949 sf
Pool Level:
48,344 sf
Lower Level: Lower Level:
19,534 sf
Building Total: 267,249 sf May 5, 2011
Building Design
May 5, 2011
Building Design
May 5, 2011
Building Design
May 5, 2011
Building Design
May 5, 2011
Phasing Plan
EXISTING CLASSROOM WING TO REMAIN PHASES 1 ‐ 4
May 5, 2011
Phasing Plan
PHASE 1 • ACADEMIC CR WING ADDITION • CORRIDOR BRIDGE (STAIR & ELEV.)
May 5, 2011
Phasing Plan
PHASE 2 • FRESHMAN ACADEMY RENOVATIONS • STAIR ADDITION
May 5, 2011
Phasing Plan
PHASE 3 • • • •
NATATORIUM RENOVATIONS PHYSICAL ED RENOVATIONS PHYSICAL ED ADDITION NEW ELEVATOR NEW ELEVATOR
May 5, 2011
Phasing Plan
PHASE 4 RENOVATIONS & ADDITIONS: • CAFETERIA • KITCHEN / SERVERY • CUSTODIAL • ART • TECHNOLOGY ED • AUDITORIUM • MUSIC • VOCATIONAL ED
May 5, 2011
Phasing Plan
PHASE 5 RENOVATIONS & ADDITIONS: • ADMINISTRATION • HEALTH CLINIC • GUIDANCE • LIBRARY • FRESHMAN SCIENCE • GALLERY
May 5, 2011
DEMOLISH EXISTING CLASSROOM WING
Site Design
May 5, 2011
Site Design
May 5, 2011
Project Schedule: Maloney High School
Design Documents Completed
Aug 2012
BSF Submission
Nov 2012
Bidding & Award
Feb 2013
Start Construction
Mar / Apr 2013
Phase Ph 1 – Construction: C i Academic A d i Classroom Cl Addition Addi i
Apr A 2013 1 – Aug A 2014 1
Phase 2 – Construction: Freshman Academy Renovations
June 2014 – Aug 2015
Phase 3 – Construction: Natatorium & PE Renovations / Add
June 2014 – Aug 2015
Phase 4 – Construction: Cafe, Vocational Ed, Auditorium & Art
June 2015 – Aug 2016
Phase 5 – Construction: Admin, Heath, Library, Science, Gallery
June 2016 – Aug 2017
Project Completed
September 2017
May 5, 2011
Cost / Budget Analysis: Maloney High School
Hard Cost Phase 1 – Academic Classroom Addition Phase 2 – Freshman Academy Renovations Phase 3 – Natatorium & PE Renovations / Additions Phase 4 – Cafeteria, Kitchen, Art, Tech Ed, Auditorium Music & Vocational Education Renovation / Addition y Science, Galleryy Addition Phase 5 – Admin, Health Clinic, Library, Subtotal: Site Work
$27,668,642 $ 7,959,221 $18 112 910 $18,112,910 $22,780,339 $14,438,846 $90,959,958 $ 6,377,042
Hard a d Cost Subtotal: Subtota :
$97,337,000 $9 ,33 ,000
Fees, Expenses, Bonding, Printing, FF&E Owner’s Contingency (5%)
$ 13,634,342 $ 5,548,659
Soft Cost
May 5, 2011
Subtotal:
$19,183,000
Total Project Budget:
$116,520,000