Maloney renovation plans

Page 1

Francis T. Maloney High School City of Meriden May 5, 2011


Team Introductions: Maloney High School

Fletcher Thompson:

Joe Costa, AIA, LEED AP – Principal KK-12 Curt Krushinsky, RA, LEED AP – Project Manager Angela Cahill, AIA AIA,, LEED AP – Assistant PM Dan Davis, AIA, LEED AP – Director of Design Mike Berger, LEED AP – Senior Designer

Blades and Goven:

Earl Goven, ASLA – Landscape Architect

Leach Consulting, LLC

Kevin Leach, P.E. – Estimator

May 5, 2011


Program Analysis

Design Approach: High School – Programming

Drawing on Our Expertise/Research/Tools Communicating/Listening/Implementing Program: Foundation of a Successful School Avoiding Facilities That Are Not Needed Space Allocation/Distribution Critical Program Approved on April 7th

TOTAL: 271,553 SF

May 5, 2011


Design Approach:

Maloney High School – Existing School Plan

1970’s

Original Building 1958 Addition 1970s Code/Safety Issues Hazardous Materials Facility Needs Modernization Enabling a 21 Century Curriculum

1958

May 5, 2011


Design Approach:

Maloney High School – Existing School Plan

May 5, 2011


Design Approach:

Maloney High School – Challenges and Opportunities

Site Configuration Entrance Drive/Fields/Parking Loop Circulation Patterns Distribution of Large Spaces Community Uses of Facility Construction Phasing Construction Phasing Coordination with Platt HS Modernize Facility d i ili May 5, 2011


Design Approach:

Maloney High School – Concept Design (Work in Progress)

Site Influences Building Design

FIELDS

Entry/Graduation/Service Zoning: Public/Private

GALLERY

Loop Circulation Patterns Display History/Learning Library/Media Center Library/Media Center

FIELDS

Freshman Academy/Bridge Natural Light Throughout GRADUATION

May 5, 2011

Improve Curb Appeal


Main Level Plan

M i L lT l Main Level Total:

160,949 sf

May 5, 2011


Upper Level Plan

U Upper Level Total: L lT l

38,422 sf

May 5, 2011


Pool Level Plan

P lL lT l Pool Level Total:

48,344 sf

May 5, 2011


Lower Level Plan

L Lower Level Total: L lT l

19,534 sf

May 5, 2011


Building Area Summary Upper Level:

38,422 sff

Main Level:

160,949 sf

Pool Level:

48,344 sf

Lower Level: Lower Level:

19,534 sf

Building Total: 267,249 sf May 5, 2011


Building Design

May 5, 2011


Building Design

May 5, 2011


Building Design

May 5, 2011


Building Design

May 5, 2011


Phasing Plan

EXISTING CLASSROOM WING TO REMAIN PHASES 1 ‐ 4

May 5, 2011


Phasing Plan

PHASE 1 • ACADEMIC CR WING ADDITION • CORRIDOR BRIDGE (STAIR & ELEV.)

May 5, 2011


Phasing Plan

PHASE 2 • FRESHMAN ACADEMY RENOVATIONS • STAIR ADDITION

May 5, 2011


Phasing Plan

PHASE 3 • • • •

NATATORIUM RENOVATIONS PHYSICAL ED RENOVATIONS PHYSICAL ED ADDITION NEW ELEVATOR NEW ELEVATOR

May 5, 2011


Phasing Plan

PHASE 4 RENOVATIONS & ADDITIONS: • CAFETERIA • KITCHEN / SERVERY • CUSTODIAL • ART • TECHNOLOGY ED • AUDITORIUM • MUSIC • VOCATIONAL ED

May 5, 2011


Phasing Plan

PHASE 5 RENOVATIONS & ADDITIONS: • ADMINISTRATION • HEALTH CLINIC • GUIDANCE • LIBRARY • FRESHMAN SCIENCE • GALLERY

May 5, 2011

DEMOLISH EXISTING CLASSROOM WING


Site Design

May 5, 2011


Site Design

May 5, 2011


Project Schedule: Maloney High School

Design Documents Completed

Aug 2012

BSF Submission

Nov 2012

Bidding & Award

Feb 2013

Start Construction

Mar / Apr 2013

Phase Ph 1 – Construction: C i Academic A d i Classroom Cl Addition Addi i

Apr A 2013 1 – Aug A 2014 1

Phase 2 – Construction: Freshman Academy Renovations

June 2014 – Aug 2015

Phase 3 – Construction: Natatorium & PE Renovations / Add

June 2014 – Aug 2015

Phase 4 – Construction: Cafe, Vocational Ed, Auditorium & Art

June 2015 – Aug 2016

Phase 5 – Construction: Admin, Heath, Library, Science, Gallery

June 2016 – Aug 2017

Project Completed

September 2017

May 5, 2011


Cost / Budget Analysis: Maloney High School

Hard Cost Phase 1 – Academic Classroom Addition Phase 2 – Freshman Academy Renovations Phase 3 – Natatorium & PE Renovations / Additions Phase 4 – Cafeteria, Kitchen, Art, Tech Ed, Auditorium Music & Vocational Education Renovation / Addition y Science, Galleryy Addition Phase 5 – Admin, Health Clinic, Library, Subtotal: Site Work

$27,668,642 $ 7,959,221 $18 112 910 $18,112,910 $22,780,339 $14,438,846 $90,959,958 $ 6,377,042

Hard a d Cost Subtotal: Subtota :

$97,337,000 $9 ,33 ,000

Fees, Expenses, Bonding, Printing, FF&E Owner’s Contingency (5%)

$ 13,634,342 $ 5,548,659

Soft Cost

May 5, 2011

Subtotal:

$19,183,000

Total Project Budget:

$116,520,000


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.