Reliability of Supply and Quality of Delivered Electricity Performance Report 2017 - 18029
Contents Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 Landsnet’s transmission system in 2017. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 Key figures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 Statistics from operations – entire country . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 Grid disturbances, curtailments and energy consumption by region and major users. 8
Main operational disturbances to the transmission network. . . . . . . . . . . . . . . . . . 10 Security of supply. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 Index of Reliability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Average Outage Duration Index, outage minutes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Power Interruption Index . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Outage minutes in various regions of the country . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . System Minutes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Curtailments to sheddable load customers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Energy produced by backup power generators. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Summary of the supply from the transmission net . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
14 14 17 17 19 20 20 21
Impact on security of supply. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 Grid disturbances. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 Number of faults. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
Voltage and frequency quality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 Frecuency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 Voltage. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
Appendix 1: About Landsnet. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36 Appendix 2: Definition of Indexes for Security of Supply: . . . . . . . . . . . . . . . . . . . . 37 Appendix 3: Definition of Incident Classification Scale . . . . . . . . . . . . . . . . . . . . . . 39 Appendix 4: Landsnet’s transmission lines at year-end 2017 . . . . . . . . . . . . . . . . . 40 Appendix 5: Landsnet’s substations at year-end 2017 . . . . . . . . . . . . . . . . . . . . . . . 42 Appendix 6: Indices for sheddable load and average curtailment load. . . . . . . . . 44 Appendix 7: Grid disturbances and faults. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45 Appendix 8: Voltage quality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50 Appendix 9: Tables and graphs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
A section about economic cost due to disturbances is not included in this report due to errors in the calculation of macroeconomic costs, based on information and data from the Start Group (a workgroup focusing on operational disturbances: www.truflun.is).
3
4
Introduction
Landsnet defines five main key performance indexes, all linked to the promises Landsnet has given their stakeholders, which are customers, owners, the community and its employees. They are: Index Promise Trust
In harmony with society and the environment
Minutes of energy not supplied
Safe supply of electricity – quality and safety of the transmission system
Required return on equity
Efficient use of funds- effective operations
Work satisfaction
Positive work environment
Accident rate (H value)
Positive work environment
The Performance Report is a summary of information on the Icelandic transmission system in 2017, including statistics and a ten-year comparison. The Report assesses Landsnet’s performance with regard to the quality and secure delivery of electricity, in accordance with the obligations set out by Regulation 1048/2004 as well as the company’s internal objectives. The number of registered grid disturbances in 2017 was similar to the preceding year. There were 711) grid disturbances in 2016, compared with 74 in 2017. The number of registered grid disturbances in substations increased in 2017, from 872) in 2016 to 893) in 2017, but the number of grid disturbances in high-voltage power lines decreased. The 10-year average for grid disturbances is 64 per year. The total number of grid disturbances leading to curtailment of load was 39 compared with 35 in the previous year. Energy not supplied to priority consumers due to grid disturbances was 1,495 MWh in 2017. The calculated outage duration was therefore 42.5 minutes and has not been higher since 2012. The year’s goal of 50 minutes or less was achieved. Regulation No. 1048/2004 on the quality and secure delivery of electricity requires electricity companies to measure voltage characteristics in accordance with the ÍST EN 50160 Standard. Landsnet is obligated to take sample measurements from at least 6 points of supply, at various substations every year. Quality requirements were met in all 6 substations in 2017. The Regulation also stipulates that delivery voltage must be within a +/-10% margin. More stringent requirements are made with regard to the supply voltage to power-intensive industries. Landsnet has defined these limits as -9% and +5%. These set limits are used when voltage quality in the 220kV system is assessed. The results of continuous measurements in the energy management system, conducted throughout the year, show that values were within these limits, with the exception of Bolungarvík and Ísafjörður. The same regulation states that the target system frequency should be 50 Hz. The average operating frequency under normal operating conditions and measured over 10 seconds must be within the following limits: 50 Hz ± 1% Hz = 99.5% of the time 50 Hz +4/-6% = 100% of the time The average operating frequency in 2017 was within these limits 99.9962% of the time. Internal objectives regarding the quality of frequency require that measured values be within the set limits of Hz +/- 0.2 Hz (over a ten second period) 99.5% of the time, each month. The quality of frequency in 2017 was within these limts 99.79% of the time.
1. Corrected figure: The figure was 72 in the 2016 report. 2. Corrected figure: The figure was 85 in the 2016 report. 3. Of these 89 faults; 5 faults are registered as normal responses from the security systems which are designed to respond in this manner in order to prevent a complete system failure.
5
Landsnet’s transmission system in 2017
Kópasker Bolungarvík Ísafjörður
Bakki
Breiðidalur
Lindarbrekka Húsavík Dalvík
Þeistareykir
Mjólká Vopnafjörður
Laxá
Sauðárkrókur
Keldeyri
Krafla Rangárvellir Laxárvatn Lagarfoss
Varmahlíð
Geiradalur Blanda
Seyðisfjörður
Eyvindará Glerárskógar
Neskaupstaður Hrútatunga
Grundarfjörður
Eskifjörður
Hryggstekkur
Vogaskeið
Fljótsdalur
Ólafsvík
Stuðlar
Vegamót
Fáskrúðsfjörður
Teigarhorn Vatnshamrar
Andakíll
Brennimelur Klafastaðir Akranes Hnoðraholt
Korpa Nesjavellir
Reykjanes
Höfn
Sigalda
Sog Búrfell
Geitháls Hamranes Svartsengi Þorlákshöfn
Hólar
Vatnsfell
Flúðir
Öldugata Stakkur Fitjar Rauðimelur
Sultartangi Búðarháls Hrauneyjafoss
Kolviðarhóll
A12
Transmission lines:
Hveragerði
220 kV 132 kV
Selfoss Hella Hvolsvöllur
66 kV
Prestbakki
33 kV Substations:
Rimakot
Power-intensive users:
Vestmannaeyjar
Key figures
Objectives for security of supply Index of Reliability (AS)
2017
Target
99.992%
Over 99.9905%
Average Outage Duration Index, outage minutes (SMS)
42.5
Below 50
Power Interruption Index (SRA)
0.931)
Below 0.85
One disturbance longer than 10 system minutes (see Fig 13)2)
No disturbance longer than 10 system minutes
System Minutes (KM)
The key figures show Landsnet’s objectives with regard to the security of supply as well as real figures for 2017. The objective of 99.99% reliability within the transmission system was achieved in 2017 whereas the objective of less than 0.85% power interruption was not achieved. This can mainly be attributed to human error which resulted in tripping and subsequently grid disturbances on the 18th of January. Energy not supplied to priority consumers was just over 600 MW during these grid disturbances and surpassed 10 system minutes. This meant that Landsnet could no longer achieve its goal of ‘no grid disturbances over 10 system minutes’. However, the goal for outage minutes was achieved. This can be attributed to the rapid response of the smart grid3) as well as those responsible for the operation of the electricity system.
1 Goal was not achieved. See Figure 8 and Appendix 2. 2 See Chapter on security of supply (page 19). 3 A smart grid is an electricity network based on digital technology that is used to supply electricity to consumers via two-way digital communication.
6
Statistics from operations – entire country
Transmission system total feed-in
18,512 GWh
Highest average power of feed-in (hour value)
Transmission system total load
2,350 MW
18,140 GWh
15. December at 11 o’clock
Thereof 513 GWh to secondary load
?
? Highest average power of load (hour value)
Transmission losses
Number of grid disturbances
2,298 MW
373 GWh
74
Number of faults
Number of faults leading to curtailment
89
39
15. December at 11 o’clock
Number of grid disturbances leading to curtailment
39
Of these 89 faults, 5 are registered as normal responses from the security system, designed to prevent a complete system failure
Total energy not supplied to primary load customers due to faults
Reserve fossil fuel generation due to faults
Total energy not supplied to curtailable secondary load customers due to faults
1,495 MWh
312 MWh
16,281 MWh
7
Grid disturbances, curtailments and energy consumption by region and major users West
West Fjords
MWh
Northwest
MWh
Northeast
MWh
MWh
1
204,153
1
206,942
1
98,421
1
256,988
2
0.1
2
7.6
2
2.6
2
9.7
3
0.0
3
207.2
3
1.2
3
1.0
4
0.0
4
63.5
4
0.0
4
22.4 en ts ilm
5/5
Cu rta
en ts ilm
ilm Cu rta
Cu rta
en ts
en ts ilm Cu rta
s ce an
s ce an
s ce an
s ce an
2/3
b ur
b ur
b ur
b ur
17 / 57
st Di
st Di
st Di
st Di
2/1
Major users
ts en ilm
rta
0.0
rta
ts ilm en Cu
Cu
ts ilm en
4
es
rta
1.0
nc
Cu
3
a rb
tailm
1,330
u st
s
es
Cur
14,869,950
10 / 39
South
MWh
East
MWh
MWh
1,363,704
1
236,352
1
483,108
1
451,675
2
21.5
2
28.8
2
59.8
2
34.9
3
0.5
3
0.8
3
15,785.2
3
285.4
4
0.0
4
0.0
4
215.9
4
10.2
1
Total load in the region (primary and secondary load)
2
Total energy curtailment to secondary load due to grid disturbances
3
Total energy curtailment to primary load due to grid disturbances
4
Backup power production
Figure 1.
8
20 / 18
Suรฐurnes
MWh 1
ce
nc
Capital
n ba
a rb
s
ce
5/4
1 2
Di
u st
n ba
13 / 4
ur st Di
Di
ur st Di
ents
MWh
9
Main operational disturbances to the transmission network
There were 74 grid disturbances in 2017 and 891) faults occurred in connection with these grid disturbances (more than one fault occurred in some grid disturbances).
Number of registered grid disturbances 2017
Energy not supplied to priority consumers, due to grid disturbances, was 1.4952) MWh
3
or 42.53) outage minutes (99.992% security of supply). Landsnet’s ‘incident classification scale’ which defines the severity of disturbances is partly based on the guidelines outlined by ENTSO-E4). The classification of disturbances
18
in Landsnet’s transmission system in 2017 is shown in Figure 2 (colour classification according to severity)5).
The main disturbances leading to sheddable load in 2017 were as follows: 18.01.2017: Unforseen activity in protection equipment in the Fjarðaál Substation
53
caused a bus coupler circuit breaker to open in Landsnet’s substation in Fljótsdalur. Five turbines at the Fljótsdalur Station subsequently became isolated from the network and tripped due to over-frequency. This resulted in under-voltage at
Severity 0 Severity 1
Fljótsdalur and other areas of the network and the total load for Fjarðaál became
Severity 2 Severity 3
Figure 2.
under voltage. System protection equipment divided the system between Blanda and Hólar as a result of instability and extensive energy transmission, via the national network. The load in the North and East of Iceland tripped in a number of areas due to over- frequency and under- frequency. Voltage control in the East of Iceland was problematic until the first turbines came online at Fljótsdalur Station. Curtailments to primary load users reached a total of approx.848.5 MWh and system minutes reached a total of 22.66. Sheddable load customers experienced a reduction of 5.3 MWh. 08.02.2017: A fault resulted in tripping on Rimakotslína Line 1 (Hvolsvöllur – Rimakot). A transmission line tower caught fire when the cable became loose and set fire to it. Curtailments to primary load reached a total of approx. 44.2 MWh and 72.4 MWh for sheddable load users. 11.02.2017: A disturbance occurred when a line at Norðurál tripped, causing power fluctuations in the national network. System protection equipment divided the transmission system into two islands: Southwest Hólar and Northeast Blanda. The effects of these disturbances were widespread, affecting the Keldeyri area in the West Fjords, turbines in the Andakíl and Svartsengi stations. Other energy-intensive users in the southwest area experienced decreased load. Curtailments to primary load were reached a total of approx. 12.4 MWh and 1.3 MWh for sheddable load users. 14.02.2017: Unforseen activity in protection equipment at Landsnet’s substation in Hamranes resulted in tripping on Ísal Line 2 (Hamranes – Ísal). Hafnarfjörður Line 1 (Hamranes – Öldugata) experienced an outage when the line came back online. Curtailments to primary load reached a total of approx. 14.3 MWh. 05.04.2017: A fault in Vestmannaeyjastreng Cable 3 (Rimakot – Westmann Islands) caused tripping on the sub-sea cable. The fault occurred on a submerged section of the cable and repairs were time consuming. An especially equipped repair ship was needed to complete the work which could only be carried out when weather and sea conditions allowed. The cable was offline for 73 days. Curtailments to primary load reached a total of approx. 8.7 MWh and 15.593.6 MWh for sheddable load users. 26.04.2017: Tripping was experienced by sheddable load users in the East of Iceland. This was caused by maintenance work which shut down Krafla Line 1 (Krafla – Rangárvellir) which also disturbed the power flow to Blanda Line 2 (Blanda – Varmahlíð). Initially, human error was thought to have disabled the smart grid transmission system but this was not the case and the system caused tripping to sheddable load users in the East. Curtailments to sheddable load users reached a total of approx. 29.9 MWh. 26.04.2017: A bus coupler tripped in Landsnet’s substation in Sigalda during maintenance work. Krafla Line 1 (Krafla – Rangárvellir) also tripped due to maintenance work elsewhere and the transmission system was therefore divided into 2 islands: Soutwest Krafla and Northeast Sigalda. Energy-intensive users in the East and Southwest parts of the country experienced curtailments to primary load (approx. 65.2 MWh).
10
1 Of these 89 faults; 5 faults are registered as normal responses from the security systems which are designed to respond in this manner in order to prevent a complete system failure. 2. Curtailments to secondary load customers are not included. 3. Curtailments to secondary load customers are not included. 4. www.entsoe.eu. 5. Appendix 3 gives further information on Landsnet’s incident classification scale.
12.05.2017: A capacitor was due to be taken offline at Landsnet’s substation in Rangárvellir but human error meant that Rangárvellir Line 1 (Varmahlíð – Rangárvellir) went offline instead. The transmission system was divided into three islands: Southwest, North and Northeast at Rángárvöllum and Blanda and Hólar. 17.05.20171): A smelting pot leak incident at Norðurál required an emergency stop. System protection equipment divided the transmission system into two islands: Soutwest and Northeast in Sigalda and Blanda. Fluctuations in production and usage and the weak national network meant that neither of the islands were able to maintain stable operations and protection equipment on Fljótsdalur Line 2 (Fljótsdalur – Hryggstekkur) tripped. A number of operating units also subsequently tripped including Lagarfoss Line 1 (Eyvindará – Lagarfoss), Sigalda Line 4 (Sigalda – Prestbakki), Höfn Line 1 (Hólar – Höfn), as well as a number of production units located all over the country. The remaining systems short circuit power was too low to maintain the voltage due to the underground cable Stuðlar Line 1. As a result, the overvoltage damaged the surge arrestors connected to the cable at Stuðlar. Furthermore, as Fljótsdalur Line 2 was energised after the disturbance the cable appeared not to be fully disconnected from the system. As a result the tranformers in Fljótsdal tripped and the entire system from Siglada to Fljotsdal collapsed. 15.06.2017: Four turbines tripped at the Búrfell Station. The system protection equipment divided the transmission system into two islands: Southwest and Northeast at Hólar and Blanda. A shortage of spinning reserves led to curtailments to sheddable load users and energy intensive users. Curtailments to primary load reached a total of approx. 86.2 MWh and 12.6 MWh for sheddable load users. 30.06.2017: Lightning in the North of Iceland caused tripping on Kópasker Line 1 (Laxá – Kópasker). Lightening protection equipment was damaged and14 pylons were also damaged. Curtailments to primary load reached a total of 9.4 MWh. 10.08.2017: Maintenance work was carried out at Landsnet’s substation in Mjólká and island operation therefore became necessary in the West Fjord area. Human error disabled the smart grid in the West Fjords and island operations were therefore not successful. This resulted in outages in the West Fjord area. Curtailments to primary load reached a total of approx. 1.2 MWh. 22.08.2017: Mistakes were made during maintenance work which resulted in outages in the West Fjord area. Curtailments to primary load reached a total of approx. 2.3 MWh and 11.3 MWh for sheddable load users. 05.11.2017: Tripping occured as a result of lightning strikes affecting Suðurnes Line 1 (Hamranes – Fitjar) and a transformer tripped at Öldugata. Curtailments to primary load reached a total of approx. 74.6 MWh and 0.8 MWh for sheddable load users. 05.11.2017: Tripping occured as a result of lightning strikes, affecting Rimakot Line 1 (Hvolsvöllur – Rimakot). Curtailments to primary load reached a total of approx. 6.6 MWh and 13.7 MWh for sheddable load users. 23.11.2017: Tripping occurred on Eyvindará Line 1 (Hryggstekkur – Eyvindará) as a result of sand storms in the area. Tripping also occurred in two transformers in Stuðlar. This resulted in the load being transferred to another transformer at Stuðlar which became overloaded and tripped a few minutes later. The Eastern Fjords subsequently experienced electricity shortages. Curtailments to primary load reached a total of approx. 21.1 MWh and 49.4 MWh for sheddable load users. 07.12.2017: Unforseen activity in protection equipment in Landsnet’s substation at Öldugata resulted in tripping on Hafnarfjörður Line 1 (Hamranes – Öldugata) when the line was supposed to come back online after maintenance work was carried out on protective equipment. Curtailments to primary load reached a total of approx 10.7 MWh and 0.5 MWh for sheddable load users.
1. This fault is not included in Figure 2. Faults within Landsnet’s system are included whereas faults in other systems are not.
11
Figure 3 shows all curtailments by date – 2017. 848.5
Curtailments to primary load users in 2017 – by date
Curtailment MWh
200 Disturbances in other systems
Disturbances in the transmissions grid
150
100
50
0 1/5/17
2/5/17
3/5/17
4/5/17
5/5/17
6/5/17 Figure 3.
12
7/5/17
8/5/17
9/5/17
10/5/17
11/5/17
12/5/17
13
Security of supply
Landsnet’s security of supply is assessed on the basis of the following indexes and in accordance with Regulation No. 1048/2004 on the Quality of Voltage and Security of Electricity. Landsnet must outline specific objectives with regard to the first three: 1) Index of Reliability (AS)
4) System Minutes (KM)
2) Average Outage Duration Index, outage minutes (SMS) 5) Power Energy Curtailment Index (SSO) 3) Power Interruption Index (SRA)
6) Power Supply Average Curtailment per Disturbance (SMA)
These indexes have been calculated for 2017 and will be discussed below, including a ten year analysis (for comparison purposes). These calculations include all grid disturbances within the transmission system. The origin of the grid disturbance is also indicated; from Landsnet’s system or other systems (which subsequently have a knock-on effect). These may involve grid disturbances in the systems of both energy producers and energy consumers.
Index of Reliability
%
100.0000 99.9900
AS 99.9800 99.9700 99.9600 Landsnet’s system Landsnet’s system and others Landsnet’s goal
99.9500 99.9400 2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Figure 41).
Index of Reliability The Index of Reliability shows the reliability of the system as a proportion of the number of curtailed hours during the year and can be converted to percentages. Figure 4 shows the index of reliability converted into percentages as well as Landsnet’s objectives with regard to security of supply; that the reliability of supply from the transmission system should be more than 99.9905%. This is equal to 50 outage minutes per year or 0.833 curtailed hours. The National Energy Authority now requires the measurement of ther indices. These have no specific objectives but are described in Appendix 6.
Average Outage Duration Index, outage minutes Outage minutes are one of the main indicators used by Landsnet to assess the transmission system’s security of supply. Our goal is to ensure that outage minutes do not exceed 50 minutes per year. The total number of outage minutes in 2017 was 42.5 minutes or just within the set limit. Landsnet has only failed to stay within its set limit twice (2008 and 2012).
1. Table 5 in Appendix 9 shows the data which the graph is based on.
14
Outage minutes
Outage minutes due to operational disturbances
200 180
SMS
160 140 120 100 80 60 40 20 0 2008
2009
2010
Disturbances in other systems
2011
2012
2013
Disturbances in Landsnet’s system
2014
2015
2016
2017
Landsnet’s goal 5 year running average, Landsnet’s system
Figure 51).
Figure 5 shows the number of outage minutes due to grid disturbances in the transmission system. Curtailments due to disturbances in other systems such as production, distribution or energy intensive systems are not included in the main results. Some of these disturbances are shown in Figures 6 and 7. Energy not supplied to sheddable load customers is not included in these figures.
Outage minutes
Outage minutes - power intensive users
500
400
300
200
100
0 2008
2009
2010
Disturbances in other systems
2011
2012
2013
Disturbances in Landsnet’s system
2014
2015
2016
2017
5 year running average, Landsnet’s system
Figure 62).
Figures 6 and 7 show both outage minutes calculated for power-intensive industries and distribution systems. The total number of outages due to disturbances in the transmission system was low between 2009 and 2011 but increased in 2012 and decreased again in 2013. Outage minutes in general distribution systems have decreased significantly since 2012. The outage minute figure is normally higher for general distribution systems than for power-intensive industries as the voltage level is higher (less units and therefore fewer disturbances) whereas the voltage supplied to general distribution systems is generally either 66KW or 33KW.
1. Table 6 i Appendix 9 shows the figures in the graph. 2. Table 7 in Appendix9 shows data related to Figures 6 and 7.
15
Outage minutes
Outage minutes – distributors
550 500 450 400 350 300 250 200 150 100 50 0 2008
2009
2010
2011
Disturbances in other systems
2012
2013
2014
2015
2016
2017
5 year running average, Landsnet’s system
Disturbances in Landsnet’s system
Figure 71).
Tables 1 and 2 show an overview of curtailments as well as the calculated duration of outages experienced by customers in 2017, due to grid disturbances in Landsnet’s transmission system. The outage time is calculated from the ratio of energy not supplied and energy sales to each customer over the year. The year 2016 is shown for comparison purposes.
2017 2016
No. of events U nsupplied energy Outage duration
No. of events Unsupplied energy Outage duration
LN Other LN syst. syst. syst.
Other syst.
LN Other LN Other syst. syst. syst. syst.
(No.) (No.)
[MWh]
[d hh:mm]
[d hh:mm]
Power-intensive users total
24
Customer, Prm load
HS Veitur, Prm load Norðurorka, Prm load
[MWh]
8 1,330.33 156.583
6
1
LN Total syst.
(No.) (No.)
0 00:47
0 00:52
9
3
67.574
5.788
0 01:07
0 01:13
2
0
[MWh]
[MWh]
68.55 80.583 7.319
0
LN syst. [d hh:mm]
Total [d hh:mm]
0 00:02
0 00:05
0 00:06
0 00:06
0
0
0
0
0 00:00
0 00:00
2
0
1.682
0
0 00:07
0 00:07
10
0
7.642
0
0 00:42
0 00:42
36
0
14.969
0
0 00:59
0 00:59
Orkuveita Reykjavíkur, Prm load
0
0
0
0
0 00:00
0 00:00
1
0
3.397
0
0 00:01
0 00:01
RARIK, Prm load
14
2 89.666
33.735
0 00:53
0 01:14
26
0 73.588
0
0 00:32
0 00:32
Orkubú Vestfjarða, Prm load
Table 1.
Customer,
Sec load
2017 2016
No. of events U nsupplied energy Outage duration
No. of events Unsupplied energy Outage duration
LN Other LN syst. syst. syst.
Other syst.
LN Other LN Other syst. syst. syst. syst.
(No.) (No.)
[MWh]
[MWh]
[d hh:mm]
[d hh:mm]
LN Total syst.
[MWh]
[MWh]
[d hh:mm]
Total [d hh:mm]
HS Veitur, Sec load
8
1 1,5786.48
10.523
25 05:59
25 06:53
3
0
7.519
0
0 00:34
0 00:34
Norðurorka, Sec load
0
0
0
0
0 00:00
0 00:00
1
0
0.071
0
0 00:02
0 00:02
Orkubú Vestfjarða, Sec load
11
1
207.201
1.26
0 16:25
0 16:31
49
0 682.159
0
2 10:15
2 10:15
Orkuveita Reykjavíkur, Sec load
0
0
0
0
0 00:00
0 00:00
0
0
0
0
0 00:00
0 00:00
RARIK, Sec load
11
2
286.555 48.379
0 09:27
0 11:03
0
1
35.09
0.827
0 01:40
0 01:42
Table 2.
1. Table 7 in Appendix 9 shows data related to Figures 6 and 7.
16
(No.) (No.)
LN syst.
Power Interruption Index The Power Interruption Index for the transmission system was 0.93 in 2017. Landsnet’s goal of 0.85 was therefore not achieved. These interruptions can be attributed to a number of disturbances that led to curtailments (disturbances on the 18th of January, 17th of May and 15th of June). Figure 8 shows the transmission system’s ‘Power Interruption Index’ over the past 10 years.
Power Interruption Index
MW/MWyear
2.5
2.0
SRA 1.5
1.0
0.5
0.0 2008
2009
2010
Disturbances in other systems
2011
2012
2013
Disturbances in Landsnet’s system
2014
2015
2016
2017
Landsnet’s goal
Figure 81).
Outage minutes in various regions of the country The security of supply to general consumers varies according to region. Outage minutes are therefore calculated for each area of the country and are based on the load in each region. The outage minutes shown are therefore the outage minutes experienced by each separate region. The Reykjavík area experienced the least outage minutes or an average of 2 minutes per year, over the last five years. The Suðurnes area has experienced 20 outage minutes per year, over the last five years. The South, West, Northwest, Northeast and finally the East of Iceland have experienced an average of 40-70 outage minutes in the last five years. The security of supply is weakest in the West Fjords of Iceland with an average of 590 outage minutes per year, in the last five years. However, there has been a measurable decrease in outage minutes in this region as a result of the back-up power station located in Bolungarvík and the smart grid in the West Fjords area which generally responds within 90 seconds of a disturbance. The outage minutes in this region subsequently decreased in 2017 to 10% of the average outage minutes experienced every five years and the total is now in line with other regions. Figures 9 and 10 show the number of outage minutes experienced in 2017 (by region) as well as the five year average. The number of outage minutes is variable according to region and year and one large-scale disturbance can significantly alter these results. Outage minutes due to sheddable load were high in the south in 2017. This can be attributed to a fault in Westmann Island Line 3 which lasted for 73 days and had a negative impact on domestic heating utilities on the island as oil is used to supply the system in the absence of electricity. This could have created extensive problems for the island’s main industries, such as fishmeal production but the fish catch was low during this period. Outage minutes were high in the Suðurnes area in 2017 as a result of curtailments to energy- intensive industry load. The companies affected included United Silicon, Verne and Advania. 1. Table 8 in Appendix 9 shows the figures in the graph
17
Outage minutes
Outage minutes – general primary load by region
100 Average 2013-2017
90
2017
589
80 70 60 50 40 30 20 10 0 Capital
Suðurnes
South
West
West Fjords
Northwest Northeast
East
Total general primary load
Figure 91). Outage minutes
Outage minutes – total primary load by region
600 Average 2013-2017
500
2017
400 300 200 100 0
Capital
Suðurnes
South
West
West Fjords
Northwest
Northeast
East
Total primary load
Figure 102).
Outage minutes by cause
Number
200 Weather
180
Technical fault
Human error
Other
160 140 120 100 80 60 40 20 0 2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Figure 113).
Figure 11 shows the division of outage minutes by cause. The unusually high figure in 2017 can be attributed to human error and reflects the complexity of operating the transmission system. The development of protective systems has been rapid, with the aim of improving the management of a heavily loaded system. The national network is weak, causing instability and fluctuations between regions. The most serious disturbances in this category occurred on the 18th of January, 14th of February, 26th of April and 15th of June this year. Each incident was reviewed and the necessary improvements were implemented. Figure 12 shows how many curtailment cases occured within determined time limits in 2017. The first column shows the number of curtailments lasting between 0–3 minutes; the next column shows the number of curtailments lasting between 3–30 minutes, etc. Curtailment cases are categorised according to units e.g. lines and cables, substations and system 1. Table 9 in Appendix 9 shows the data used for the graph. 2. Table 10 in Appendix 9 shows the data used for the graph. 3. Table 11 in Appendix 9 shows the data used for the graph.
18
Number of curtailment events within set time limits 2017
Number 60 50 40 30 20 10 0
0-3 min
3-30 min
30-60 min
Substations
1-12 hours
12-24 hours
Lines and Cables
1-7 days
More
System failures
Figure 121).
failures. System failures include disturbances that are generally classified as system disturbances and not specific unit failures such as disturbances experienced as a result of actions within the smart grid and control centre. The disturbances that fall within this category are actually a defense response within the system in order to avoid an absolute system failure.
System Minutes The System Minutes Index shows how serious each case is. The severity of each case is categorised as follows: Category 0, instances are < 1 min
Category 2, instances are ≥ 10 and <100 min.
Category 1, instances are ≥ 1 and < 10 min
Category 3, instances are ≥ 100 and < 1000 min.
Number 60
Categorisation of disturbances 2008-2017 by outage minutes
50 40 30 20 10 0 2008
2009
2010
2011
Category 0
2012
2013
Category 1 Figure 132).
2014
2015
Category 2
2016
2017
Category 3
Landsnet’s goal is to ensure that no grid disturbance lasts for more than 10 system minutes. This goal has been achieved five times since 2008. One disturbance lasted more than 10 minutes in 2017. The disturbance occurred on the 18th of January and is described on page 10. Figure13 shows the division of system minutes into the above categories, over a period of 10 years.
1. Table 12 in Appendix 9 shows the data used for the graph. 2. Table 13 in Appendix 9 shows the data used for the graph.
19
Curtailments to sheddable load customers Curtailable transmission refers to the permitted curtailment of electricity due to instances outlined in Article 5.1 of Grid Code B5: Terms for Curtailable Transmission. Curtailments of secondary load have increased significantly over the last years due to the increased load on the transmission system. These curtailments are either enforced as a result of a request from Landsnetâ&#x20AC;&#x2122;s control centre or automatically initiated with circuit breakers. Landsnet has set up the automatic tripping of secondary load to increase operational security and to improve the utilisation of the transmission system. Curtailments of secondary load, due to grid disturbances, increased by 98% between 2013 and 2015 but decreased in 2016. Extensive curtailments were necessary in 2017 and can mostly be attributed to an outage on Vestmannaeyjastreng Line 3 which took over two months to repair. The estimated curtailment of sheddable load was 16,281 MWh which corresponds to 462 system minutes.The system minutes of the transmission system would have increased by the same amount in 2017 if the agreement on secondary load did not exist. Figure 14 shows the curtailment of secondary load for the last 5 years, due to disturbances in the transmission system.
Curtailments to sheddable load customers in Landsnetâ&#x20AC;&#x2122;s system 2013-2017
MWh
18000 16281 16000 14000 12000 10000 8000 6000 4667 4000 2000
1212
1989 725
0 2013
2014
2015
2016
2017
Figure 14.
Energy produced by backup power generators Distribution utilities have installed backup power generators to produce electricity when disturbances affect the supply. Landsnet has access to these power stations which are used to feed primary load during disturbances, and during any system maintenance. Starting up these power generators can take some time and the curtailment of primary load can therefore occur during disturbances, until the back-up energy is made available. Backup power generators accounted for 312 MWh in 2017 which is a decrease from the previous year. If Landsnet did not have access to these backup power stations, the system minutes for priority consumers would have been 51 minutes, instead of 42.5 minutes (an increase of 9 minutes). Figure 15 shows electricity generation by backup power stations due to disturbances in the transmission system over the last 5 years.
20
Backup station energy usage due to disturbances in Landsnetâ&#x20AC;&#x2122;s system 2013-2017
MWh
3000
2061 2000
878
1000 198
368
312
2016
2017
0 2013
2014
2015 Figure 15.
Summary of the supply from the transmission net The increased load in the transmission system and a rise in grid disturbances have led to an increase in the use of back up generators/stations. Curtailments on sheddable load have also increased. There are numerous examples of how smart grid solutions and the rapid response of Landsnetâ&#x20AC;&#x2122;s control centre have minimised or prevented curtailments to priority consumers. Landsnet has achieved its delivery targets in the last few years, despite the high number of disturbances. Table 3 and Figure 16 shows the total amount of back up power produced and converted to system minutes. The influence of these factors on the security of supply is evident and highlights the importance of backup power sources and permitted curtailments. Otherwise, the total number of system minutes would be 519 instead of the 42.5 recorded in 2017. Outages, curtailments to sheddable load users and back-up energy use
MWh
SMSin mins
Outages-priority consumers
1,495
42.5
Outages due to grid disturbances in other systems
196
5.6
Back-up energy use due to grid disturbances
312
8.9
16,281
462.2
18,285
519.1
Curtailments to sheddable load Total (outages, curtailments & back-up energy use) Table 3.
21
Curtailments to primary load users due to disturbances in Landsnet’s system 2013-2017
MWh
1600
1495
1400 1200 1000
600
856
748
800 595
400 170
200 0
2013
2014
2015
2016
2017
Figure 16.
MWh
Curtailments due to other system disturbances 2013-2017
400
365
358 350 300 250
196
200 150
149
148
100 50 0 2013
2014
2015
2016
2017
Figure 17.
Summary of security of supply in transmission system – disturbances 2013-2017
Outage minutes
600 500 400 300 200 100 0
2013
2014
2015
Curtailment to primary load Production backup stations Landsnet’s goal Figure 18.
22
2016
2017
Curtailment due to other systems Curtailment to secondary load customers
23
Impact on security of supply
The underlying cause of many grid disturbances in Iceland’s transmission system can be attributed to the limited capacity of the national network. The 132 kV line from Brennimelur to Hvalfjörður, across the north and east of the country and southwards to Sigalda was constructed almost forty years ago. A summary has been compiled of the number of incidents caused by restrictions to the national network over the last 10 years. Grid disturbances to the Vestur Line, from Hrútatunga to Mjólká, are not included in these figures as the line is unnafected by power fluctuations and stability issues between regions. Table 4 shows a summary of all curtailments due to faults that can be directly traced to the state of the national network. These faults would probably not have occurred in a stronger transmission system. These faults are accompanied by a higher percentage of outages than other disturbances to the transmission system as they are often more widespread1). Curtailments as a result of these faults are often more extensive than those enforced in other grid disturbances and therefore have a greater effect on energy consumers. A review of individual years shows that a large proportion of these curtailments can be traced to the restrictions of the national network. An estimated 80% of curtailments could be traced to these restrictions in 2014 and 50% in 2008 and 2009. Nine faults were experienced this year, due to the weak national network which subsequently led to 30% of all curtailments to primary load users. Faults caused by the weak national network were five times more likely to cause curtailment within the system in 2017 than other faults.
Year
Number faults
Curtailments
Lost sales
All Other Weak All Weak All Weak faults grid faults grid faults grid LN LN LN Number Number Number MWh MWh MWh MWh
2008
130 114 16 2,242 1,316 0 0
2009
60 56 4 1,824 920 0 0
2010
55 48 7 843 227 0 0
2011
64 63 1 842 0 0 0
2012
108 98 10 5,809 439 0 0
2013
79 70
9 744 167 1,213 314
2014
103
80
23 1,106 840 2,359
94
2015
139
119
20 1,221 283 4,947
64
2016
106 101
5 317 109 729
2017
108
9 1,691
Total
952
99 848
511 16,341
104 16,639 4,812 25,589
7 216
695
Percentage, % 10.9 28.9 2.7 Table 4.
Faults and curtailments that can be traced directly to the weak national network have been assessed alongside the total number of faults and curtailments within the system each year. There have been 950 faults in Landsnet’s transmission system over the last ten years, including faults as a result of grid disturbances in other systems or an average of 95 faults per year. A total of 104 of these faults can be traced to the weak national network. Figure 19 shows the the percentage of faults traced to the weak national network as well as the overall number of faults and curtailments in the system. The results show that on average, 11% of these faults can be traced to the weak national network as well as 29% of the total number of curtailments. However, these percentages vary between years and have reached up to 80%.
1. Approx. 29% of curtailments to users during this time period can be attributed to these faults as well as 3% of reduced sales to sheddable load users.
24
%
Percentage of faults and curtailments due to weak 132 kV system
100
Number of faults due to weak 132 kV system Curtailment of energy due to weak 132 kV system
90 80 70 60 50 40 30 20 10 0 2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Figure 19.
25
26
Grid disturbances
A grid disturbance is an unexpected event that can cause automatic or manual disconnection of a unit in the transmission system or in the event of a failed reconnection after a malfunction. Each grid disturbance, therefore, may involve more than one fault. This means that the number of faults will always be equal to or greater than the number of grid disturbances. Each fault is classified when a grid disturbance is registered e.g. according to type, the unit that caused the failure and the cause. There was an increase in grid disturbances in 2016 and 2017 or a total of 74 disturbances involving 891) faults. The average number of grid disturbances over the last 10 years (compared with a transmission system similar in size) was 64 with an average of 79 faults. Figure 20 shows the number of grid disturbances in the transmission system over the past 10 years. Disturbances are categorised according to location, i.e. in substations, on lines/cables or whether system faults are involved. Figure 21 shows the division of grid disturbances by cause.
A system disturbance is defined as follows: A forced outage which results from system effects or conditions and is not caused by an event directly associated with the component or unit being reported. If, e.g. voltage fluctuations or deviations in frequency cause units to disconnect from operation or if consumers are disconnected, then the event is a system disturbance. However, Non-selective tripping at customers for these reasons are, however, not considered system malfunctions.
Number of operational disturbances
Number
100 90 80 70 60 50 40 30 20 10 0 2008
2009
2010
2011
2012
Substations
2013
2014
Lines and cables
2015
2016
2017
2016
2017
System faults
Figure 202).
Number of disturbances â&#x20AC;&#x201C; by cause
Number
100 90 80 70 60 50 40 30 20 10 0 2008
2009
2010 Weather
2011
2012
2013
Technical fault
2014 Human error
2015
Other
Figure 213).
1. Of these 89 faults; 5 faults are registered as normal responses from the security systems which are designed to respond in this manner in order to prevent a complete system failure. 2. Table 14 in Appendix 9 shows the data used for the graph. 3. Table 15 in Appendix 9 shows the data used for the graph.
27
Number of faults The total number of faults in 2017 was 891) compared with 84 in the previous year. The following figures show the number of faults over the last 10 years. A comparison is shown according to the different categories.
Number of disturbances in the transmission system
Number
140 120 100 80 60 40 20 0 2008
2009
2010
2011
Substations
2012
2013
2014
Lines and cables
2015
2016
2017
System faults
Figure 222).
Average number
Number of faults in the transmission system by month â&#x20AC;&#x201C; average 10 year total
14
2008-2017 12 10 8 6 4 2 0 Jan
Feb
Mar
Apr
May
Substations
June
July
Aug
Lines and cables
Sep
Oct
Nov
Dec
System faults
Figure 233).
28
1. Of these 89 faults; 5 faults are registered as normal responses from the security systems which are designed to respond in this manner in order to prevent a complete system failure. 2. Table 16 in Appendix 9 shows the data used for the graph. 3. Table 17 in Appendix 9 shows the data used for the graph.
Number of faults in transmission system – by voltage
Number
140 120 100 80 60 40 20 0 2008
2009
2010
2011
220 kV
132 kV
2012
2013
66/33 kV
2014 11 kV
2015
2016
2017
Minus voltage
Figure 241).
Categorisation of faults – by duration
Number
35 Average 2008-2017
2017
30 25 20 15 10 5 0 0-3 min
3-30 min
30-60 min
1-12 hours
12-24 hours
1-7 days
More
Figure 252).
Number
Number of faults in the transmission system 2017 – by month
16 14 12 10 8 6 4 2 0 Jan
Feb
Mar
Apr
May
Substations
June
July
Aug
Lines and cables
Sep
Oct
Nov
Dec
System faults
Figure 263).
1. Table 18 in Appendix 9 shows the data used for the graph. 2. Table 19 in Appendix 9 shows the data used for the graph. 3. Table 20 in Appendix 9 shows the data used for the graph.
29
Number of faults in the transmission system â&#x20AC;&#x201C; by cause
Number
140 120 100 80 60 40 20 0 2008
2009
2010 Weather
2011
2012
2013
Technical fault
2014
2015
Human error
2016
2017
Other
Figure 271).
Number of faults â&#x20AC;&#x201C; by unit No unit Cables Lines Station, other Thyristor Surge protectors Busbars Circuit breaker Disconnector Control and support systems Transformer
Average 2008-2017
2017
Capacitor 0
10
20
30
40
50 Number
Figure 282).
1. Table 21 in Appendix 9 shows the data used for the graph. 2. Table 22 in Appendix 9 shows the data used for the graph.
30
31
Voltage and frequency quality
Frequency quality 2017 - ratio of measured values
%
40 35 30 25 20 15 10 5 0 49.00
49.20
49.40
49.60
49.80
50.00
50.20
50.40
50.60
50.80
51.00
Hz Figure 29.
Frequency The Regulation on the Quality of Voltage and Security of Electricity permit variations in frequency not exceeding 1% above and below 50 Hz under normal operating conditions. The mean value of fundamental, measured over 10 seconds must be within the following limits: 50 Hz ± 1 % (i.e. 49.5 – 50.5 Hz) 99.5% of the time 50 Hz +4 / -6 % (i.e. 47 – 52 Hz) 100% of the time Landsnet monitors frequency and voltage quality in the entire transmission system, throughout the year in the company’s energy management system. The system automatically registers frequency values every two seconds. Results for measurements at Geitháls have been processed (Figure 29). The number of measurement values is 3,146,398, the average frequency value is 50.00016 Hz and the standard deviation of measurement values is 0.04427. Total frequency excursion exceeding the 1% limit in 2017: >50.5 Hz = 14.83 min (0.00283 % of the time) <49.5 Hz min (0.00102 % of the time) Frequency was therefore within the set limit 99.99615% of the time. Landsnet has set internal goals on frequency quality: To ensure that 99.5% of measurement values are within the limit (50 Hz +/- 0.2 Hz ) every month. A 10-second average value is used. Frequencies were within these limits for eleven months of the year 2017 with the exception of July. The yearly average was 99.78757%.
Voltage The Regulation on the Quality of Voltage and Security of Electricity No. 1048/2004 stipulates that electricity companies must measure voltage characteristics in accordance with the ÍST EN 50160 standard. Landsnet is under obligation to conduct measurements at 6 delivery points each year. Specific measurements were taken in 2017, using precise quality measuring instruments, at the following delivery points: Akranes: 66 kV Eskifjörður: 66 kV Geiradalur: 132 kV Hamranes: 132 kV Hveragerð: 66 kV Korpa: 132 kV
32
Measurements were taken continuously for at least one week at each location and the relevant quality requirements were fulfilled in each case. Figures 40 to 47 show the voltage values for delivery points in the transmission system. An examination is made of the distribution of 5-minute values in all cases. The measurements are taken from the energy management system. According to the Regulation, voltage variations must be kept within the permissible limit ±10%. More stringent requirements are made to delivery voltage for power-intensive industries. In these cases, the limits of delivery voltage have been defined as +5%/-9%. These limits are therefore taken into account when the 220kV system is assessed. The results show that values were within the set limits in nearly all cases with the exception of the west of Iceland (Bolungarvík and Ísafjörður). These deviations can all be traced to lack of voltage due to faults or maintenance at the delivery point in question. The 66 kw system in the West Fjords is operated slightly below these limits, in cooperation with Orkubú Vestfjarða.
33
34
35
Appendix 1: About Landsnet
We are a responsible and progressive service company with a powerful team spirit and high level of community awareness. We strive to be at the forefront of the global energy industry.
Role Secure, uninterruptible electricity is one of the pillars of modern society and our role is to ensure the cost-efficient development and operation of the grid and a secure and uninterrupted electricity supply at any given time, within the electricity system.
Our future vision An electrified future, in line with society, is a key principle at the core of our future vision. Modern societies are increasingly reliant on the secure supply of electricity. We are committed to ensuring the secure supply of electricity for the future and to maintaining a balance between generation and consumption. We want to achieve a broad consensus in our future endeavours, are committed to considering the needs of society at any given time and to showing responsibility in environmental matters. We are also committed to promoting a healthy market environment within the electricity market and to the efficient use of funds.
Values Our values are responsibility, cooperation and respect and we incorporate these principles, both internally and externally. They shape our corporate culture, approach and behaviour, supporting professionalism and effective decision-making.
Policy pledges Our policy is based on six key pledges to society. These include the secure supply of electricity, a high quality service and secure transmission system for the future, operations in harmony with society and the environment, efficient operations, informed debate, and targeted management and organisation. Our promises include: • Secure electricity supply- a high-quality and secure transmission system for the future • In harmony with society and the environment • Efficient use of funds- effective operations • Clear image • Strategic management and organisation • Positive work environment
Organisational chart
President & CEO
Corporate Services & Communications
36
Finance
Technology & Developement
Stakeholder’s Forum
System Operations
Constructions & Grid Services
Appendix 2: Definition of Indexes for Security of Supply
Power Interruption Index This index is the ratio of the aggregate power curtailment and highest load on the system. The following equation applies to this index:
Where: Pi:
Power curtailment in curtailment i [MW]
PMax:
Maximum total feed-in of the year into the transmission system / distribution system [MW].
Average Outage Duration Index-Outage Minutes This index assesses how long the curtailment has prevailed based on energy curtailment and total energy delivery. The following equation applies to this index:
Where: Ei:
Energy curtailment in disturbance i [MWh].
ETotal:
Total energy delivery to customers [MWh].
System Minutes Index that indicates the severity of each case of curtailed energy delivery. The following equation applies to this index:
Where: E:
Energy curtailment in disturbance [MWh].
PMax:
Maximum load on the system, transmission system / distribution system [MW].
37
Power Energy Curtailment Index This index is the ratio of energy curtailment if the load had been unchanged over the whole curtailment period and the total load on the system. The following equation applies to this index:
MW hour / MW year
Where: Pi: Power curtailment MW, in curtailment i. Ti: Duration of curtailment, hours. PMax: Maximum load (one hour average) of feed-in, MW.
Power Supply Average Curtailment per Disturbance This index is an indication of the average curtailment of each disturbance. The following equation applies to this index:
MW / disturbance
Where: Pi: Load curtailment, MW, in disturbance i.
N: No. of disturbances.
Index of Reliability Index that shows the reliability of the system as a proportion of the number of hours during the year.
Where: Duration of outage is defined according to the Average Outage Duration Index, outage minutes.
38
Appendix 3: Definition of Incident Classification Scale The highest severity is read from # 1 and down to # 18 according to ENTSO-E1).
Transmission system incident classification scale (partially modelled on ENTSO-E Incident classification scale) Green (Scale 0) Anomaly
Yellow (Scale 1) Noteworthy incident
Incidents Classification
#9 L1
Outage of 5-15% of total power (ex. 110-330 MW)
LNFD0
Outage of < 2.5% of distribution utilities’ primary load (ex. < 9 MW)
LNFD1
Outage of 2.5 - 7.5% of distribution utilities’ primary load (ex. 9-27 MW)
LNFS0
Outage of < 5% of load to major users (ex. 80 MW)
LNFS1
Outage of 5 - 15% of load to major users (ex. 80-240 MW)
#18 T0
Outages or disconnections of units in the 220 kV system, without loss of transmission capabilities
#11 T1
Outage or disconnections of units affecting important areas (island operations, main 132 kV line outage)
#19 G0
Outage of generation which is <= the biggest generating unit in the system (each generator in Kárahnjúkar is 115MW)
#12 G1
Outage of generation which is > than the largest generating unit in the system (each generator in Kárahnjúkar is 115MW)
#21 OR0
Lack of >20% of defined reserves for 15-30 minutes
#15 OR1
Lack of >20% of defined reserves
#16 LT1
State estimator or substation out of commission for over 30 minutes
#14 OV1
Voltage standards continuously outside 0.9-1.1 p.u. for > 15 minutes at 110-300 kV
#10 F1
Δf is 0.25-0.5 Hz continuously for 20 minutes or Δf 0.5-1.2 Hz/without warning Δf >1.2 Hz for 10 minutes
#20 OV0
Voltage standards continuously outside 0.9-1.1 p.u. for 5 - 15 minutes at 110-300 kV
#17 F0
Continuous Δf 0.1-0.25 Hz for 20 minutes or continuous Δf 0.25-1.2 Hz for 10 minutes
Red (Scale 2) Extensive incident
Black (Scale 3) Major incident
#2 L2
Outage of 15-70% of total load (ex. 330-1500 MW)
#1 OB3
LNÁL2
>25% curtailment to one or more aluminum plants for an hour or more
>25% curtailment to LN- one or more aluminium ÁL3 plants for two hours or more
LNFD2
Outage of 7.5-35% of distribution utilities’ primary load (ex. 27-126 MW)
LNFD3
Outage of >7.5% of distribution utilities’ primary load for >5 hours (ex. > 27MW)
LNFS2
Outage of 15-70% of load to major users (ex. 240-1120 MW)
LNFS3
Outage of >15% of load to major users for >5 hours (ex. >240 MW)
#5 G2
Outage of generation which is >= the largest power plant in the system (Kárahnjúkar is 690 MW)
#8 LT2
EMS/Scada out for over 30 minutes
#3 F2
Continuous Δf 0.5-1.2 Hz/without warning Δf >1.2 Hz for 20 minutes
Total system failure
Scale 1. www.entsoe.eu.
39
1977 / 2006
BH1 2014 Búðarháls-HR1 (Langalda)
Búrfell Line 1
BU1 1969 Búrfell-Írafoss
Búrfell Line 2
BU2 1973 Búrfell-Kolviðarhóll
Búrfell Line 3 (partly built for 400 kV)
BU3 1992/1998 Búrfell-Hamranes
Fljótsdalur Line 3 (built for 400 kV)
FL3 2007
Fljótsdalur-Reyðarfjörður
49
Fljótsdalur Line 4 (built for 400 kV)
FL4 2007 Fljótsdalur-Reyðarfjörður
53
Geitháls-Brennimelur
58.6 5.6 60.8 86 119.07 0.07
Hamranes Line 1
HN1 1969 Geitháls-Hamranes
15.1
Hamranes Line 2
HN2 1969 Geitháls-Hamranes
15.1
Hrauneyjafoss Line 1
HR1 1982 Hrauneyjafoss-Sultartangi
19.5
Ísal Line 1
IS1 1969 Hamranes-Ísal
2.4
Ísal Line 2
IS2 1969 Hamranes-Ísal
2.4
Járnblendi Line 1
JA1 1978 Brennimelur-Járnblendivk
4.5 17.3
Kolviðarhóll Line 1
KH1 1973 Kolviðarhóll-Geitháls
Krafla Line 4
KR4 2017 Krafla-Þeistareykir
33
Norðurál Line 1
NA1 1998 Brennimelur-Norðurál
4.2
Norðurál Line 2
NA2 1998 Brennimelur-Norðurál
4
Sigalda Line 2
SI2 1982 Sigalda-Hrauneyjafoss
8.6 36.8
Sigalda Line 3
SI3 1975/2015 Sigalda-Búrfell
Sog Line 3
SO3 1969 Írafoss-Geitháls
35.8
Sultartangi Line 1
SU1 1982 Sultartangi-Brennimelur
121.6
Sultartangi Line 2
SU2 1999 Sultartangi-Búrfell
12.5
Sultartangi Line 3 (built for 400 kV)
SU3 2006 Sultartangi-Brennimelur
119
Vatnsfell Line 1
VF1 2001 Vatnsfell-Sigalda
5.8
Þeistareykir Line 1
TR1 2017 Þeistareykir-Bakki
40
Of which undergr. [km]
BR1
Búðarháls Line 1
Length [km]
First year in service
Brennimelur Line 1
Name
220
Voltage [kV]
KKS code
Connected substations
Appendix 4: Landsnet’s transmission lines at year-end 2017
28.3 Total 220 kV
917.9
0.07
132
Blanda Line 1
BL1 1977/1991 Blanda-Laxárvatn
32.7
Blanda Line 2
BL2 1977/1991 Blanda-Varmahlíð
32.4
Eyvindará Line 1
EY1 1977 Hryggstekkur-Eyvindará
27.5
Fitjar Line 1
MF1 1991 Rauðimelur-Fitjar
6.8
Fitjar Line 2
FI2 2015 Fitjar-Stakkur
8.5 8.5
Fljótsdalur Line 2
FL2 1978 Fljótsdalur-Hryggstekkur
Geiradalur Line 1
GE1 1980 Glerárskógar-Geiradalur
46.7
Glerárskógar Line 1
GL1 1983 Hrútatunga-Glerárskógar
33.5
Hafnarfjörður Line 1
HF1 1989 Hamranes-Öldugata
Höfn Line 1
HA1 1987/2014 Hólar-Höfn
Hnoðraholt Line 1
AD7 1990 Hamranes-Hnoðraholt
9.7 2
25 7
4 4 7 1.5
Hólar Line 1
HO1 1981 Teigarhorn-Hólar
75.1
Hrútatunga Line 1
HT1 1976 Vatnshamrar-Hrútatunga
77.1
Korpa Line 1
KO1 1974 Geitháls-Korpa
Krafla Line 1
KR1 1977 Krafla-Rangárvellir
Krafla Line 2
KR2 1978 Krafla-Fljótsdalur
Laxárvatn Line 1
LV1 1976 Hrútatunga-Laxárvatn
72.7
Mjólká Line 1
MJ1 1981 Geiradalur-Mjólká
80.8
6 0.3 82.1 123.2 0.1
Nesjavellir Line 1
NE1 1998 Nesjavellir-Korpa
32 16
Nesjavellir Line 2
NE2 2010 Nesjavellir-Geitháls
25 25
Prestbakki Line 1
PB1 1984 Hólar-Prestbakki
171.4
Rangárvellir Line 1
RA1 1974 Rangárvellir-Varmahlíð
87.5
Rangárvellir Line 2
RA2 2009 Rangárvellir-Krossanes
4.5 4.4
Rauðimelur Line 1
RM1 2006 Reykjanes-Rauðimelur
15
Rauðavatn Line 1
RV1 1953 Geitháls-A12
Sigalda Line 4
SI4 1984 Sigalda-Prestbakki
78.1
Sog Line 2
SO2 1953 Írafoss-Geitháls
44.4
3 1
2005
Of which undergr. [km]
SR1
Length [km]
First year in service
Stuðlar Line 1
Connected substations
KKS code
Name
Voltage [kV]
Hryggstekkur-Stuðlar
16
16
Suðurnes Line 1
SN1 1991 Hamranes-Fitjar
Svartsengi Line 1
SM1 1991 Svartsengi-Rauðimelur
4.9
Teigarhorn Line 1
TE1 1981 Hryggstekkur-Teigarhorn
49.7
Vatnshamrar Line 1
VA1 1977 Vatnshamrar-Brennimelur
30.7 0.1
20.2
Total 132 kV 66
1333.2
85.8
Akranes Line 1
AK1 1996 Brennimelur-Akranes
18.5 18.5
Andakíll Line 1
AN1 1966 Andakílsvirkjun-Akranes
Bolungarvík Line 1
BV1 1979/2014 Breiðidalur-Bolungarvík
17.1 1
Bolungarvík Line 2
BV2 2010/2014 Ísafjörður-Bolungarvík
15.3 15.3 36.4 0.8
34.85 1.3
Breiðidalur Line 1
BD1 1975 Mjólká-Breiðidalur
Dalvík Line 1
DA1 1982 Rangárvellir-Dalvík
39 0.1
Eskifjörður Line 1
ES1 2001 Eyvindará-Eskifjörður
29.1 0.3
Fáskrúðsfjörður Line 1
FA1 1989 Stuðlar-Fáskrúðsfjörður
16.8
Flúðir Line 1
FU1 1978 Búrfell-Flúðir
27.4 0.6
Grundarfjörður Line 1
GF1 1985 Vogaskeið-Grundarfjörður
35.4
Hella Line 1
HE1 1995 Flúðir-Hella
34.4 1.7
Hella Line 2
HE2 2015 Hella-Hvolsvöllur
Hveragerði Line 1
HG1 1982 Ljósafoss-Hveragerði
15.4 0.1
Hvolsvöllur Line 1
HV1 1972 Búrfell-Hvolsvöllur
45.1 0.25
Ísafjörður Line 1
IF1 1959/2014 Breiðidalur-Ísafjörður
Kópasker Line 1
KS1 1983 Laxá-Kópasker
Lagarfoss Line 1
LF1 1971 Lagarfoss-Eyvindará
Laxá Line 1
LA1 1953 Laxá-Rangárvellir
Ljósafoss Line 1
LJ1 2002 Ljósafoss-Írafoss
0.6 0.6
Neskaupstaður Line 1
NK1 1985 Eskifjörður-Neskaupstaður
18.2 1.9
Ólafsvík Line 1
OL1 1978 Vegamót-Ólafsvík
48.8
Rimakot Line 1
RI1 1988 Hvolsvöllur-Rimakot
22.2 0.1
Sauðárkrókur Line 1
SA1 1974 Varmahlíð-Sauðárkrókur
21.8
Selfoss Line 1
SE1 1981 Ljósafoss-Selfoss
20.3 2.7
Selfoss Line 2
SE2 1947 Selfoss-Hella
32 0.7
Selfoss Line 3
SE3 2016 Selfoss-Þorlákshöfn
28 28
Seyðisfjörður Line 1
SF1 1996 Eyvindará-Seyðisfjörður
19.8
13 13
13 3 83.3 0.1 28 6 58.4 0.7
Steingrímsstöð Line 1
ST1 2003 Steingrímsstöð-Ljósafoss
3.4 1
Stuðlar Line 2
SR2 1983 Stuðlar-Eskifjörður
18.2 2.4
Tálknafjörður Line 1
TA1 1985 Mjólká-Keldeyri
45.1
Vatnshamrar Line 2
VA2 1974 Andakílsvirkjun-Vatnshamrar
Vegamót Line 1
VE1 1974 Vatnshamrar-Vegamót
Vestmannaeyjar Line 3 (sub-sea cable)
VM3 2013 Vestmannaeyjar-Rimakot
Vogaskeið Line 1
VS1 1974 Vegamót-Vogaskeið
2 0.2 63.8 16 16 24.8
Vopnafjörður Line 1
VP1 1980 Lagarfoss-Vopnafjörður
Þeistareykir Line 2
TR2 2013 Þeistareykir-KS1 (Höfuðreiðarmúli)
Þorlákshöfn Line 1
TO1 1991 Hveragerði-Þorlákhöfn
Húsavíkur Line 1
HU1 1948 Laxá-Húsavík
26 0.1 16 16
58 0.15 11 11 19.3 0.1
Total 66 kV 33
Vestmannaeyjar Line 1 (sub-sea cable)
VM1 1962 Vestmannaeyjar-Rimakot
Vestmannaeyjar Line 2 (sub-sea cable)
VM2 1978 Vestmannaeyjar-Rimakot
Energy terms/abbreviations kV=kilovolt kW=kilowatt MW=megawatt=1000 kW kWh=kilowatt hour MWh=megawatt hour=1000 kWh GWh=gigawatt hour=1000 MWh
1033.8
127.5
16 15
Total 33 kV
58
Total 3343
31 244.4
41
42
Number of transformers
No. of switchyard bays
First year in service
Co-owner
Voltage [kV]
KKS code
Substations
Appendix 5: Landsnet’s substations at year-end 2017
Aðveitustöð 12 / Substation 12
A12
OR 132
Akranes
AKR OR 66 2016 4
Andakíll
AND OR 66 1974 3
0
Ásbrú
ASB 33 2011 8
0
2006 1
0 0
Bakki
BAK 220/33 2017 3/4
2
Blanda
BLA
0
Bolungarvík
BOL 66/11 2014 3/8
0
Breiðidalur
BRD OV 66 1979 4
0
Brennimelur
BRE
Búðarháls
BUD 220 2013 2
0 0
LV
RA
132 1991 5
220/132/66 1978 9/4/3
Búrfell
BUR
Dalvík
DAL RA 66 1981 1
0
Eskifjörður
ESK RA 66 1993 5
0
Eyvindará
EYV RA 132/66 1975 1/5
1
Fáskrúðsfjörður
FAS RA 66 1998 3
0
Fitjar
FIT HS 132 1990 5
0
Fljótsdalur
FLJ 220/132 2007 10/4
2
Flúðir
FLU RA 66 1995 3
0
Geiradalur
GED
0
Geitháls
GEH
220/132 1969 7/9
2
Glerárskógar
GLE
132 1980 3
0
OV
RA
220/66 1999 8/4
3
132 1983 3
Grundarfjörður
GRU RA 66 2017 3
Hamranes
HAM 220/132 1989 7/8
0 2
Hella
HLA RA 66 1995 4
0
Hnoðraholt
HNO OR 132 1990 2
0
Hólar
HOL
0
Hrauneyjafoss Hrútatunga
RA
132 1984 5
HRA
LV
220 1981 5
0
HRU
RA
132 1980 4
0
Hryggstekkur
HRY
RA
132 1978 6/5
Húsavík
HUS RA 33 1978 2
0
Hveragerði
HVE RA 66 1983 3
0
Hvolsvöllur
HVO RA 66 1995 4
0
Írafoss
IRA
Ísafjörður
ISA OV 66 2014 4
0 0
LV
220/132 1953 3/6
1
2
Keldeyri
KEL OV 66 1979 2
Klafastaðir
KLA 220/16 2013 1/4
1
Kolviðarhóll
KOL 220 2006 7
0
Korpa
KOR
Kópasker
KOP RA 66 1980 1
OR
LV
132 1976 6
Krafla
KRA
Lagarfoss
LAG RA 66 2007 5
Laxá
LAX
66/33 2003 6/1
1
Laxárvatn
LAV
132 1977 3
0
Lindarbrekka
LIN RA 66 1985 1
0
Ljósafoss
LJO
LV
66 1937 6
0
Mjólká
MJO
OV
132/66 1980 2/5
Nesjavellir
NES OR 132 1998 6
Neskaupstaður
NKS RA 66 1994 3
0
Ólafsvík
OLA RA 66 1980 1
0 0
RA
220/132 2017/1977 3/4
0 0 1 0
2 0
Prestbakki
PRB
RA
132 1984 3
Rangárvellir
RAN
RA
132/66 1974 8/7
Rauðimelur
RAU 132 2006 3
0
Reykjanes
REY HS 132 2006 3
0
2
Number of transformers
No. of switchyard bays
First year in service
Voltage [kV]
KKS code
RIM RA 66/33 1990 2/5
1
Sauðárkrókur
SAU RA 66 1977 3
0
Co-owner
Substations Rimakot
Selfoss
SEL RA 66 2005 5
0
Seyðisfjörður
SEY RA 66 1957 2
0
Sigalda
SIG
Silfurstjarnan
SIL RA 66 1992 1
LV
220/132 1977 7/1
1 0
Stakkur
STA 132 2016 3
1
Steingrímsstöð
STE
0
Stuðlar
STU RA 132/66 1980 3/5
2
Sultartangi
SUL
0
LV
66 1959 1
220 1999 6
Svartsengi
SVA HS 132 1997 4
0
Teigarhorn
TEH
RA
132 2005 3
0
Varmahlíð
VAR
RA
132/66 1977 3/1
1
Vatnsfell
VAF
220 2001 2
0
Vatnshamrar
VAT
132/66 1976 4/6
Vegamót
VEG RA 66 1975 4
0
Vestmannaeyjar
VEM HS 66/33 2017/2002 1/2
0
Vogaskeið
VOG RA 66 1975 3
0
Vopnafjörður
VOP RA 66 1982 1
0
RA
2
Þeistareykir
THR 220/66 2017/2013 5/1
1
Þorlákshöfn
TOR RA 66 1991 3
0
Öldugata
OLD 132 1989 3
0
RA=RARIK (Iceland State Electricity) OV=Westfjord Power Company HS=Sudurnes Regional Heating LV=Landsvirkjun OR=Reykjavík Energy
43
Appendix 6: Indices for sheddable load and average curtailment load The National Energy Authority now requires the measurement these indices which have no specific objectives.
Power Energy Curtailment Index The Power Energy Curtailment Index measures curtailed energy delivery, which is the ratio of energy curtailment if the power had been unchanged during the entire curtailment period and the total power in the system.
Power Energy Curtailment Index
MWh/MW year
3.0
SSO 2.5
2.0
1.5
1.0
0.5
0.0 2008
2009
2010
2011
2012
Landsnet’s system
2013
2014
2015
2016
2017
Landsnet’s system and others
Figure 301).
Power Supply Average Curtailment per Disturbance The Power Supply Average Curtailment per Disturbance Index measures the average curtailment of load, which is an indicator of the average curtailment in each disturbance. MW/fault
Power Supply Average Curtailment per Disturbance
90
SMA
80 70 60 50 40 30 20 10 0
2008
2009
2010
2011
2012
Landsnet’s system
2013
44
2015
Landsnet’s system and others Figure 312)
1. Table 23 in Appendix 9 shows the data used for the graph. 2. Table 24 in Appendix 9 shows the data used for the graph.
2014
2016
2017
Appendix 7: Grid disturbances and faults
Figure 32: Shows the average number of curtailments over a ten year period. Categorised by system component and within a set timeframe.
Average number of curtailment events 2008-2017 â&#x20AC;&#x201C; by duration Number 60 50 40 30 20 10 0 0-3 min
3-30 min
30-60 min Substations
1-12 hours
12-24 hours
Lines and cables
1-7 days
More
System failures
Figure 32.
Faults in Substations There were 54 faults in substations in 2017. Figure 33 shows the causes of faults in substations compared with the 10-year average. Figure 34 shows faults in substations categorised by stations as well as the 10-year average for comparison.
Number 40
Number of faults in substations â&#x20AC;&#x201C; by cause
35 Average 2008-2017
2017
30 25 20 15 10 5 0 External influence
Technical fault
Human error
Weather
User system
Unknown
Figure 331).
1. Table 25 in Appendix 9 shows the data used for the graph.
45
Faults categorised – by station Mjólká Fljótsdalur Sigalda - substation Brennimelur Eyvindará Hryggstekkur Blanda - substation Stuðlar Hamranes Eskifjörður Rangárvellir Geitháls Vatnshamrar Rimakot Flúðir Hólar Breiðidalur Vegamót Vestmannaeyjar Vogaskeið Stakkur Fitjar Írafoss - substation Hvolsvöllur Þeistarreykir Glerárskógar Akranes Öldugata Kolviðarhóll Steingrímsstöð - substation Hrauneyjarfoss - substation Búrfell - substation System disturbions Prestbakki Laxá - substation Krafla - substation Sauðárkrókur Varmahlíð Klafastaðir Ljósafoss - substation Hella Vopnafjörður Lagarfoss Neskaupstaður Fáskrúðsfjörður Teigarhorn Kópasker Hrútatunga Bolungarvík Ísafjörður Grundarfjörður Reykjanes Korpa - substation Selfoss Þorlákshöfn Sultartangi - substation Seyðisfjörður Bakki Silfurstjarnan Lindarbrekka Húsavík Bjarnarflag - substation Dalvík Laxárvatn Keldeyri Geiradalur Andakíll Ólafsvík Ásbrú Rauðimelur Svartsengi Hnoðraholt A12 Nesjavellir Hveragerði Búðarháls Vatnsfell - substation
Average 2008-2017
0
0.5
1
1.5
2
2.5
3
3.5
2017
4
4.5 Number
Figure 34.
46
Faults in Lines and Cables There were 32 faults in overhead lines and cables in 2017, compared with 46 faults in the previous year. These faults are divided between operating voltage (see Figure 35). Figure 36 shows the cause of line faults in 2017 including the the 10year average. Figures 37 to 39 show the average number of faults per year for every 100 km (for 220, 132 and 66 KW lines) over the past 10 years.
Number of faults on lines and cables per 100 km and per year
Number
16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0 2008
2009
2010 2011 33 kV
2012 66 kV
2013 2014 2015 132 kV 220 kV
2016
2017
Figure 351).
Number of faults on lines and cables â&#x20AC;&#x201C; by cause
Number
40 Average 2008-2017
2017
35 30 25 20 15 10 5 0 External influence
Technical fault
Human error
Weather
User system
Unknown
Figure 362).
1. Table 26 in Appendix 9 shows the data used for the graph. 2. Table 27 in Appendix 9 shows the data used for the graph.
47
Average number of faults per year on 220 kV lines per 100 km – 2008-2017 NA1, NA2 KH1 HR1 BU1 BU2 BR1 HN1, HN2 SO3 BU3 FL3 SU3 SU1 VF1 SU2 SI3 SI2 JA1 IS1, IS2 FL4 BH1 0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
Average number / 100 km / year
Figure 37.
Average number of faults per year on 132 kV lines per 100 km – 2008-2017 VA1 MJ1 FL2 GE1 HA1 GL1 SI4 SO2 HT1 SN1 SR1 NE1 TE1 LV1 PB1 KR2 KR1 NE2 EY1 RA1 BL2 SM1 RV1 RM1 RA2 MF1 KO1 HO1 HF1 FI2 BL1 AD7
0
2
4
6
8
10
12
14
Average number / 100 km / year
Figure 38.
48
Average number of faults per year on 66 kV lines per 100 km â&#x20AC;&#x201C; 2008-2017 BV1 HE2 TA1 SE2 VA2 IF1 LA1 FU1 GF1 OL1 SA1 BD1 SF1 FA1 AN1 RI1 HV1 VP1 KS1 HG1 NK1 SE1 ES1 BV2 VM3 SR2 TO1 VE1 VS1 LF1 TR2 ST1 SE3 LJ1 HE1 DA1 AK1
0
5
10
15
20
25
30
Average number / 100 km / year
Figure 39.
49
Appendix 8: Voltage quality Quality of voltage supply National network 132 kV
Quality of voltage supply 220 kV 70000
40000
60000
35000
50000
30000
GED GLE HOL HRU HRY LAV PRE TEH VAR
25000
40000
20000
BRE_AT
30000
HAM_AT
15000
FJA_AT
20000
10000
FJA_BT
10000
5000
0
0 144
146
142
140
138
136
134
132
130
128
126
124
122
120
118
234
232
230
228
226
222
224
220
218
216
214
212
210
208
204
206
202
200
Figure 40.
Figure 41.
Quality of voltage supply Southwest Region 132 kV
Quality of voltage supply West Region 66 kV 50000
40000
45000
35000
40000
30000
35000
25000
30000
20000 15000
FIT
25000
GEH
20000
HAM
10000
KOR
15000
OLD
10000
5000
SVA
5000
0
AND BRE GRU OLA VAT VEG VOG
0 146
144
142
140
138
134
136
132
130
128
124
126
122
118
120
59 60
Figure 42.
61 62 63 64 65 66 67 68 69 70
71
72 73
Figure 43.
Quality of voltage supply West Fjords 66 kV
Quality of voltage supply North Region 66 kV
70000
120000
60000
100000
50000
DAL
80000
LAX
40000
RAN
60000 30000
SIS
BOL
KOP
BRD
20000
LIN
40000
SAU
ISA
20000
KEL
10000
MJO
0
0 59 60 61 62 63 64 65 66 67 68 69 70 Figure 44.
71
72 73
59 60 Figure 45.
61 62 63 64 65 66 67 68 69 70
71
72 73
71
72 73
Quality of voltage supply South Region 66 kV
Quality of voltage supply East Region 66 kV 90000
60000
80000 50000
70000 60000
ESK
50000
EYV FAS
40000
HLA HVE
30000
HVO
LAG
30000
NKS
20000
SEY STU
10000
LJO
20000
RIM SEL
10000
TOR
VOP
0
0 59 60 Figure 46.
50
FLU
40000
61 62 63 64 65 66 67 68 69 70
71
59 60
72 73 Figure 47.
61 62 63 64 65 66 67 68 69 70
Appendix 9: Tables and graphs Year
Index Index
Year
Landsnet
Other systems
Landsnet Landsnet and Ratio other systems Ratio
2008
2.04 0.25
2009
0.37 0.64
2008
0.99987 0.99986
2010
0.54 0.55
2009
0.99994 0.99989
2011
0.42 0.06
2010
0.99998 0.99995
2012
0.81 0.12
2011
0.99995 0.99995
2013
0.60 0.23
2012
0.99966 0.99965
2014
1.16 0.72
2013
0.99997 0.99996
2015
0.81 0.39
2014
0.99996 0.99994
2016
0.37 0.17
2015
0.99995 0.99993
2017
0.93 0.22
2016
0.99999 0.99998
2017
0.99992 0.99991 General primary load
Table 5. Index of Reliability (AS). Data for Figure 4.
Year
Landsnet
Other systems
2008
66.9 9.0
2009
31.8 28.3
2010
10.3 17.1
2011
26.7 0.5
2012
180.4 3.3
2013
18.3 4.6
2014
23.0 11.0
2015
25.4 10.8
2016
5.1 4.4
2017
42.5 5.6
Table 6. Outage minutes due to grid disturbances Data for Figure 5.
Year
Table 8. Power Interruption Index (SRA). Data for Figure 8.
Major users Distribution systems LN Other systems LN Other systems
2008
69.3 11.2 57.3 0.1
2009
4.6 34.8 149.0 0.4
2010
3.6 20.7 40.0 1.3
2011
10.9 0.2 96.6 1.6
2012
107.1 3.3 503.8 3.6
2013
5.6 4.2 74.8 6.2
2014
23.4 12.3 21.0 5.0
2015
19.8 10.3 48.9 13.0
2016
2.5 5.5 16.3 0.0
2017
47.0 5.5 23.8 5.7
Region 2017 Average 2013-2017 Capital
8.44 1.91
Suรฐurnes
66.41 20.54
South
79.37 47.68
West
0.37 39.76
West Fjords
41.63
Northwest
62.76 46.35
Northeast
21.53 54.09
East
77.52 69.47
Total general primary load
30.99
589.11
45.83
Table 9. Outage minutes for general primary load. Data for Figure 9.
Total primary load Region
2017
Average
2013-2017 Capital
5.76 1.15
Suรฐurnes
446.49 89.42
South
79.37 47.68
West
12.74 11.74
West Fjords
93.27
Northwest
166.87 67.17
Northeast
11.85 61.59
East
90.98 33.27
Total primary load
42.45
599.44
22.83
Table 10. Outage minutes for total primary load. Data for Figure 10.
Table 7. Outage minutes by users. Data for Figure 6 and Figure 7.
51
Year
Weather Technical Human error Other Total Curtailm. Curtailm. Curtailm. Curtailm. Curtailm. MWh MWh MWh MWh MWh
Year Substations Lines and System Total Number cables faults Number Number Number
2008 42.3
3.6
20.1
0.9 66.9
2008
28 49 1 78
2009 28.1
2.2
1.5
0.0 31.8
2009
11 33 0 44
2010 2.5 6.9 0.9 2.5 12.7
2010
8 21 0 29
2011 16.1 1.6
9.0 0.2 26.9
2011
17 33 0 50
2012 178.2 2.2
0.0
2012
11 70 0 81
2013 15.4 0.0
2.8 3.5 21.7
2013
6 42 0 48
2014 3.8 7.9 10.9 8.7 31.4
2014
15 49 4 68
2015 5.4 18.3 0.6 6.0 30.2
2015
22 68 5 95
2016 2.1
0.2 3.6 7.5
2016
22 45 4 71
2017 4.3 8.8 29.3 5.4 47.8
2017
36 32 6 74
1.7
2.4 182.8
Table 11. Outage minutes by cause. Data for Figure 11.
Table 14. The number of grid disturbances by subsystem. Data for Figure 20.
Substations Overhead lines System faults and cables
Year
Duration of A verage No. in Average No. in Average No. in curtailment 2008- 2017 2008- 2017 2008- 2017 2017 2017 2017
Weather Technical Human error Other Total Number Number Number Number Number
2008 35
30
9
4
78
2009 26
9
6
3
44
8
3
5 29
0-3 mín
3.5
6
11
0
0.7
1
2010 13
3-30 mín
15.5
30
33.1
10
5.2
16
2011 24 14
8
4 50
30-60 mín
3.8
7
6.9
5
1.2
1
2012 67
5
2
7 81
1-12 klst 5.6 8 9.9 12 1.3 10
2013 34
1
8
5 48
12-24 klst 0 0 1.9 0 0 0
2014 40
11
6
11 68
1-7 dagar 0.1 0 2.3 0 0 0
2015 58
18
7
12 95
Longer 0 0 0.1 0 0 0
2016 31 20
5
15 71
2017 20 26
18 10 74
Table 12. The number of curtailment events by duration. Data for Figure 12.
Year
Table 15. The number of grid disturbances by cause. Data for Figure 21.
Category 0 Category 1 Category 2 Category 3 Total. Number Number Number Number Number
Year Substations Lines and System Total Number cables faults Number Number Number
2008 44
6
2
0 52
2009 23
7
1
0
2010 18
3
0
0 21
2008
37 60 15 112
2011 22
4
0
0 26
2009
20 34 2 56
2012 42
9
4
0 55
2010
9 20 12 41
2013 27
4
1
0 32
2011
20 33 2 55
2014 44
5
0
0 49
2012
16 71 7 94
2015 39
6
0
0 45
2013
10 41 0 51
2016 33
2
0
0 35
2014
15 49 18 82
2017 29
9
1
0 39
2015
25 70 26 121
Table 13. Classification of disturbances by system minutes in 2007-2017. Data for Figure 13.
2016
22 46 16 84
2017
45 32 12 89
31
Table 16. The number of faults in the transmission system by subsystem. Data for Figure 22.
52
Month Substations Lines and System Total Number cables faults Number Number Number
Month Substations Lines and System Total Number cables faults Number Number Number
Jan
3.6 7.0 2.2 12.8
Jan
5 1 1 7
Feb
2.1 4.9 1.7 8.7
Feb
4 6 2 12
March
2.5 6.4 1.2 10.1
March
5 4 0 9
Apr
0.6 3.4 0.8 4.8
Apr
3 5 0 8
May
1.2 1.6 0.7 3.5
May
5 6 3 14
June
1.5 1.5 0.9 3.9
June
4 2 1 7
July
1.0 0.7 0.9 2.6
July
4 0 0 4
Aug
1.6 0.8 0.8 3.2
Aug
3 0 1 4
Sep
1.1 2.7 0.4 4.2
Sep
3 1 1 5
Oct
2.6 3.2 0.6 6.4
Oct
3 1 0 4
Nov
1.9 4.9 0.2 7.0
Nov
7 4 1 12
Dec
2.3 8.5 0.6 11.4
Dec
1 2 0 3
Table 17. The number of faults in the transmission system by months â&#x20AC;&#x201C; average of past ten years. Data for Figure 23.
Year 220 kV 132 kV 66/ 11 kV Without Total 33 kV voltage No. No. No. No. No. No. 2008
25 29 57 1
0 112
2009
6 16 35 0 0 57
2010
7 13 21 0 0 41
2011
7 17 31 0 0 55
2012
8 26 60 0 0 94
2013
2 19 30 0 0 51
2014
9 34 37 0 2 82
2015
13 51 53 0 4 121
2016
9 29 42 0 4 84
2017
15 33 36 1
4 89
Table 18. The number of faults in the transmission system by voltage level. Data for Figure 24.
Duration Average Total 2008-2017 2017 No./year 0-3 min
6.1
3
3-30 min
25.7
27
30-60 min
8.5
16
1-12 hours
22.7
30
12-24 hours
5.8
3
1-7 days
7.9
8
Longer 1.9 2 Table 19. Classification of faults by duration. Data for Figure 25.
Table 20. The number of faults in the transmission system by months in 2017. Data for Figure 26.
Year
Weather Technical Human error Other Total Number Number Number Number Number
2008 46
51
11
4 112
2009 26
20
8
3
2010 13 20
3
5 41
2011 24 19
8
4 55
2012 67
18
2
7 94
2013 34
4
8
5 51
2014 40 25
6
11 82
2015 59
43
7
12 121
2016 31 32
6
15 84
2017 20
18 10 89
41
57
Table 21. The number of faults in the transmission system by cause. Data for Figure 27.
Component type
Average 2008-2017 2017 Number Number
Capacitors
1.5 3
Power transformers
2.6
6
Control and support systems
21
32
Disconnectors
0.3 2
Circuit breakers
3.8
5
Bus bars
0.3
0
Surge protectors
0
0
Thyristors
0 0
Station. other
2
6
44.6
31
Overhead lines Cables No unit
1 1 3.6
3
Table 22. The number of faults in the transmission system by component type. Data for Figure 28.
53
Year Index Index Landsnet Landsnet and MWh/MW year other systems MWh/MW year 2008 0.97 1.10 2009 0.50 0.92 2010
0.15 0.42
2011
0.49 0.49
2012
2.73 2.78
2013
0.52 0.59
2014
0.91 1.52
2015
2.59 2.76
2016
0.40 0.47
2017
0.65 0.76
Table 23. Power Energy Curtailment Index (SSO). Data for Figure 30 in Appendix 6.
Year Index Index Landsnet Landsnet and MW disturbance other systems MW disturbance
220 kV 132 kV 66 kV 33 kV No/ No/ No/ No/ 100 km 100 km 100 km 100 km
2008
0.47 1.27 4.06 1.77
2009
0.00 1.03 2.08 1.77
2010
0.35 0.32 1.35 0.00
2011
0.24 0.87 2.08 0.00
2012
0.35 1.11 4.78 14.16
2013
0.00 1.14 2.53 1.37
2014
0.12 1.51 2.75 1.37
2015
0.47 2.19 3.66 1.37
2016
0.23 1.35 2.56 0.00
2017
0.23 0.30 2.56 0.00
Table 26. Number of faults in overhead lines and cables per 100km per year. Data for Figure 35 in Appendix 7.
Cause
Average 2008-2017 2017 Number Number
External influence
5.6
8
2008
80.76 81.43
Technical 4.9 4
2009
24.79 63.46
Human error
2010
36.05 75.27
Weather 34.5 19
2011
30.61 32.92
Userâ&#x20AC;&#x2122;s system
2012
28.16 30.61
Unknown 0.3
2013
33.99 44.01
Total
2014
41.48 51.58
2015
29.82 37.79
2016
19.70 26.04
2017
48.61 52.46
Table 24. Power Supply Average Curtailment per Disturbance Index (SMA). Data for Figure 31 in Appendix 6.
Cause
Average 2008-2017 2017 Number Number
External influence
0.2
1
Technical 22.3 37 Human error
6.9
15
Weather 1.5 1 Userâ&#x20AC;&#x2122;s system
0.9
0
Unknown 0.1 0 Total
31.9 54
Table 25. Number of faults in substations by cause. Data for Figure 33 in Appendix 7.
54
Year
0.3
0
0
0 1
45.6 32
Table 278. Number of faults in overhead lines and cables by cause. Data for Figure 36 in Appendix 7.
Reliability of Supply and Quality of Delivered Electricity Performance Report 2017 Authors: Kjartan Sigurjónsson, Daniel Leó Ólason, Kristveig Þorbergsdóttir, Jón Vilhjálmsson (Efla Consulting Engineers), Kolbrún Reinholdsdóttir (Efla Consulting Engineers) and Ingvar Baldursson (Efla Consulting Engineers) Project managers: Kjartan Sigurjónsson og Daniel Leó Ólason Abstract: The Performance Report is a summary of information on the Icelandic transmission system, including statistics and a ten-year comparison. The Report assesses Landsnet’s performance with regard to the quality and secure delivery of electricity. Translation: Hulda Kristín Jónsdóttir Supervision and layout: Athygli Photos: Landsnet Graphics: Effekt Landsnet –Report no. 18029 November 2018
55
LANDSNET HF. - GYLFAFLÖT 9 - 112 REYKJAVÍK - ICELAND - TEL. +354 563 9300 - LANDSNET@LANDSNET.IS