View with images and charts Environmental Impact Assessment of Jamuna Bridge after construction and its Mitigation measures. INTRODUCTION 1.1.
Background
The economic development and social unity largely depend on the communication facilities. Improvement of national highway network in Bangladesh has been obstructed due to three mighty rivers: The Ganges (Padma), Meghna and the Jamuna (Brahmaputra). Jamuna is one of the world’s largest river divides Bangladesh into two regions: North West region and the other part of the country. The major transport barrier between the east and west part of Bangladesh is Jamuna Bridge. The river poses an impediment to economic development and social integrity between these two parts. There has long been desire to improve the transportation network and the energy transfer between these two parts of the country. The Jamuna Multipurpose Bridge (JMB) within the length of 4.8 km has been constructed connecting the capital city, Dhaka with the North West part of the country. Jamuna Multipurpose Bridge replaced the Tangail-Sirajgong gas and electricity transmission; telecommunication has been made in this Bridge. The largest bridge of the country made direct road network with 17 districts of north-west region and International road network with India and Nepal through Lalmonirhat-Burimari-Ranigong. On the other hand, there was no rail way network to connect these two regions. Govt. of Bangladesh (GOB) made new rail network from Jaydebpur of Dhaka to Vill: Jhawal at Sirajgong. Jamuna Bridge carries a two lane connecting roads on each side, 230 kv electric power line, telecommunication cable and gas pipe the construction of the main components of the project including the main bridge, river training work bridge connecting roads, bridge connecting rail network and some other facilities at the bridge end side involve massive construction activities which have both positive and negative impacts on the components of the environment. 1.2.
Objectives
The study was carried out with the objectives – I.
To identify the positive and negative impacts after the construction of the Jamuna Multipurpose Bridge (JMB) over the Jamuna;
II.
To make recommendations for possible Mitigation of the negative impacts and enhance the positive impacts.
METHODOLOGY OF THE STUDY 2.1. Data Collection Information concerning the EIA of the project is mainly based on the available secondary and primary data. The secondary data pertaining to the study were collected from different sources like Bangladesh Water Development Board (BWDB), Local Government Engineering Department (LGED), Bangladesh Agriculture Development Corporation (BADC), Department of Roads and Highway (RHD), Bangladesh Railway (BR), Department of Public Health Engineering (DPHE), Department of Land Record Survey (DLRS), Petro