Caretakers' Roadmap

Page 13

“we are living in a generation of lack of maintenance. golden lane is falling apart; barbican centre is falling apart. the museum of london is falling apart...”

caretaker’s roadmap

4

Business as usual

reference:

“Full Circle to Reuse”, Elliott Wood, accessed May 31, 2023, https://online. flippingbook.com/view/915371497/.

“Façade Leasing pilot project at TU Delft” , TU Delft, accessed May 31, 2023, https://www.tudelft.nl/bk/onderzoek/projecten/green-buildinginnovation/facade-leasing/facade-leasing-pilot-project-at-tu-delft.

Pre-Design

0

Existing building structure

2

Architect develops brief with client Desk study

Dimensional Survey

Architect options drive structural investigations

Structural scheme (assumptions)

4

Targeted structural investigations

Knock-down and rebuild Building Plan of Work
Stage
Strategic Definition
Preparation & Briefing
Conceptual Design
Spatial Co-ordination
Business as usual
Pre-Design
0
1
2
3
Technical Design
&
5 Manufacturing
Construction
Existing building structure Demolition Contractor
Demolition Contractor
Refurbishment Building Plan of Work
Stage
Strategic
Definition
& Briefing
1 Preparation
Conceptual
Design
3 Spatial Co-ordination
Technical Design
5 Manufacturing & Construction

Proposed Caretakers’ Strategy

Workers Shortage

Supply Chain Crisis

Property Value

Local Authority

Local Authority Funding

Community Infrastructure Levy

City of London

Climate Action Team

User Productivity

Energy Savings

VATchargedonDemolition

Environmental Taxes

Material Extraction Tax

C&DWasteManagement

Carbon as Currency

Initial Production Cost

Material Embodied Value

Profit on products & services

Product Suppliers

Material Resellers

Client

Down payment

Building

Product-as-a-Service

Products

Products

Periodicservicefee

Facade-as-a-Service

Insulation-as-a-Service

Finishes-as-a-Service

Opening-as-a-Mechanism

Threshold-as-a-Mechanism

Joint-as-a-Mechanism

Services

Caretakers Team

Services

Contractor

Service Suppliers

Building-as-a-Product

Pre-Development - Pilot Site

TOWN AND COUNTRY PLANNING (DEVELOPMENT MANAGEMENT PROCEDURE) ORDER 2023 Proposed Development/Works at: 140-150 London Wall London EC2Y 5DN give notice that London Caretakers is applying to the City of London for planning permission for the following Deconstruction of the existing buildings to engage local community as part of the Building Caretaking Strategy under Greater London Authority guidelines. The development would enable the rejuvenation and extension of existing buildings. Given the current COVID-19 situation, you will not able to view plans in the Guildhall, however you may inspect copies of the application, the plans and any other documents submitted with it on-line at https://www.planning2.cityoflondon.gov.uk quoting reference 20/00951/LBC. If you are finding it difficult to access the on-line documents or you require paper documents please contact us by email at plans@cityoflondon.gov.uk or telephone 020 7332 1710. Anyone who wishes to make representations about this application should do so by the below date online https://www.planning2.cityoflondon.gov.uk or by email to PLNComments@cityoflondon.gov.uk quoting reference 20/00951/LBC. The deadline for commenting on this application is 28 days from the date of this notice. Please note that all representations will be made available for public inspection and will be displayed on the website, together with your name and address. Representations that do not include a name and address cannot be taken into account in the determination of an application. For the purposes of data protection we will not reveal the e-mail address, telephone number or signature of private individuals. See www.cityoflondon.gov.uk/privacy for full details. Dated: 28/05/2023 Rosy Tam - Department of the Built Environment
Public Notice
1_ Caretakers’ Flat
1
Museum of London and Bastion House
Team Meeting at Caretakers Terrace
H7 1 2 3 4 5 6 7 A B C D E F G H I J K L M

A RE A

DIRE C T O R Y

MO L_ LV 03 _ H 7

Location: Museum of London Level 03 (22.7 Highwalk Level)

Structural Grid - H7

Component Directory:

STO_LIM_001

Grey Limestone Walling Slabs

300 x 1200mm

STO_LIM_002

Grey Limestone Flooring Slabs

200 x 700mm

300 x 600mm

400 x 600mm

CLA_GLA_001

Glazed White Ceramics Tiles

95 x 195mm

BRI_CLA_001

Earth-coloured Semi-Engineering Brick

105 x 215mm

STR_SUS_001

Suspended Canopy Ceiling

DOO_SLI_001

Sliding Entrance Door

Project

140 - 150 London Wall Museum of London and Bastion House

Drawing No

230409-AA-DIP14-10001

©Self-Assisted Unbuilders

8 9 10 11 12 A B C D E F G H I J K L M

STO_LIM_001

Grey Limestone Walling Slabs

300 x 1200mm

STO_LIM_002

Grey Limestone Flooring Slabs

200 x 700mm

300 x 600mm

400 x 600mm

Reinforced Concrete Structure

(Cement / Aggregate Ratio 1:4.5 to 1:6)

Crushed Penlee Granite used as Aggregate

1200 30
700 600 30 600 40 0 STO_LIM_002 20
STO_LIM_001

COMPONE N T

D IR E C T O R Y

CLA_GLA_001

C L A _ G WT_00 1

Element: Glazed White Tiles

Dimension: 195 x 95 x 12.5

800 mm Ø

Concrete Column with Bush-Hammering Effect

FLO_PAR_001

Parquet Flooring

70 x 230mm

Location: Building Envelope Museum of London

CLA_GLA_001

Glazed White Ceramics Tiles 95 x 195mm

⚠Proceed ONLY with induction.

General Instructions:

No. of Workers: 1 Time: 30 min./ m²

Personal Protective Tools: Hammer, Chisel, Mallet, Disk Machine, Protective Gloves, Wire Brush, Protective Eyewear, Mask, Safety Shoes

Notes:

This document shall be read in conjunction with all other associated project information including models and related consultants documents

If in doubt ASK.

BRI_CLA_001

Earth-coloured

Semi-Engineering Brick

105 x 215mm

140 - 150 London Wall Museum of London and Bastion House

Project Drawing No

230409-AA-DIP14-90001

©Self-Assisted Unbuilders

9 195 BRI_CON_001
5 215
10
Local Community - Self-Assisted Unbuilders Lead Skilled Caretaker - If in doubt ASK Call 08000650858 1:4 team ratio | Sign up @ www.caretakersscheme.org.uk

grout

glazed white tiles

cement mortar Outside

waterproofing membrane

concrete

material life spanwell-maintained concrete structure - up to 100 years glazed ceramic tiles - 50 - 100 years; depending on wear and uses

8cm 0
Understanding building layers
Inside
1:2 Detail

 

Building on Collective Knowledge and Skills

 
From Extraction

3mm expansion joint

expansion joint to structural slab vapour barrier

100mm

internal stone pavers 1:4 Details
To Reuse
material life spannatural stones - over 100 years / almost indefinitely stone is being created continually through a series of geologic processes; crushing into aggregate diminishes its value greatly

Step by Step Unbuild Made Easy

Stone / Carpet Tile to Internal Partition

metal stud wall metal stud wall
MDF skirting
1:8 Details
1:8 Details
internal
stone paver
carpet tile 1:8 Details 1:8 Details Reclaiming material, building and space
Material processing and storage at the Museum of London
1 2
1_ Material storage & exchange market Caretakers’ Team
2_ Processing area & workshop space
3_
From the Museum of London offices to the Caretakers Common Terrace
4_ Bastion House
Transformation in Progress 4 3
from a “stranded asset” to a catalyst

Crescent House | Golden Lane Estate existing envelope

existing sapele timber frame | repair existing glass | single glazed unit

existing structure

existing sapele timber frame | repair

existing glass | single glazed unit

existing structure

Golden Lane Estate Refurbishment

0 8cm 2
Existing

existing sapele timber frame | repair

new hardwood frame | sourcing abroad

new insulation | aerogel

new glass | double glazed unit

existing structure

existing sapele timber frame | repair

new hardwood frame | sourcing abroad

new insulation | aerogel

new glass | triple glazed unit

existing structure

existing sapele timber frame | repair

new hardwood frame | sourcing abroad

new insulation | aerogel

new glass | triple glazed unit

existing structure

0 8cm 2
Crescent House | Golden Lane Estate window refurbishment option 2
Option 1 Option 2

Proposed Caretakers’ Roadmap

Pre-Development

Pilot Site

Museum of London and Bastion House

Introduction of Caretakers

Sign Up

Existing Building Structure Audit

New Construction

Compulsory

Lead Caretakers

Self-Assisted

Unbuilders

Local Community

Caretakers Pilot Team

Deconstruction

Transport & Logistics

Training

Shearing Layers

Step-by-step

Reuse Made Easy

Caretakers’ Collective Knowledge and Skills

Craftsmanship

Form Follows Availability

Inventory & Storage

New Construction

Material Bank

Demolition Contractor
Design Input

Maintenance Refurbishment

Building Network

Uses and Wear

Maintenance Works

Repair Works

Caretaking as Currency to Claim Ownership

More Homes and Workplaces

Energy Performance Insulation and Facade Leasing

Adaptation and Use of Space

Turn static files into dynamic content formats.