DRAWING LIST A0.0 A1.0 A1.1 A2.0 A3.0 A5.0 A9.0
ARTIST STUDIO
COVER SHEET SITE PLAN FIRST FLOOR PLAN ELEVATIONS BUILDING SECTION DETAILS MATERIAL PALETTE
182 NORTH AVENUE, ANNAPOLIS, MARYLAND Project No.
ACH240
FALL 2021 SEMESTER PROFESSOR HOFMANN
CONSTRUCTION DOCUMENT PHASE
CONCRETE MASONRY UNIT CONCRETE GRAVEL, WASHED STONE EARTH PLYWOOD ROUGH LUMBER FINISH LUMBER GYPSUM WALLBOARD RIGID INSULATION BATT INSULATION STEEL BRICK BUILDING SECTION DETAIL DOOR SYMBOL WINDOW TYPES
ABBREVIATIONS ACCES. ACOUS. A.C.T. A.F.F. ALUM BLDG. B.O.F. CLG. CONC. CONST. CONT. CMU DN DWG EL. ELEV. EX. EXIST. FIN FL. FLR. GWB H.M. HT. INSUL. N.I.C. O.C. PL. LAM. POLY PTD. PT. P.T. Q.T. REF. REQ'D R.O. S/S STL SUSP T&G T.O.M. T.O.P. T.O.W. TYP. WP W.W.F.
ACCESSORY ACOUSTICAL ACOUSTICAL CEILING TILE ABOVE FINISH FLOOR ALUMINUM BUILDING BOTTOM OF FOOTING CEILING CONCRETE CONSTRUCTION CONTINUOUS CONCRETE MASONRY UNIT DOWN DRAWING ELEVATION EXISTING FINISH FLOOR GYPSUM WALLBOARD HOLLOW METAL HEIGHT INSULATION NOT IN CONTRACT ON CENTER PLASTIC LAMINATE POLYETHYLENE PAINTED PRESSURE TREATED QUARRY TILE REFERENCE REQUIRED ROUGH OPENING STAINLESS STEEL STEEL SUSPENDED TONGUE AND GROOVE TOP OF MASONRY TOP OF PLATE TOP OF WALL TYPICAL WATERPROOF WOVEN WIRE FABRIC
VICINITY MAP
PROJECT INFORMATION THIS PROJECT CALLED FOR THE DESIGN OF AN ARTIST STUDIO SPACE NO LARGER THAN 600 SQUARE FEET, WITH A HALF BATH AND AN 8FOOT-WIDE OPENING TO EASILY MOVE LARGE ITEMS IN AND OUT OF THE SPACE. THE CONCEPT IS A SPACE FOR A HORTICULTURIST OR FLORIST TO CULTIVATE, ORCHESTRATE, AND OPERATE THEIR PLANT ARTISTRY. THE DESIGN IS BASED ON THE PASSIVE HOUSE APPROACH. IT CONSISTS OF SOLAR POSITIONING, THERMAL MASS, THE GREENHOUSE EFFECT, A WOOD BURNING FIREPLACE, OPTIMIZED INSULATION, AND STRATEGICALLY PLACED FENESTRATION FOR VENTILATION. DOING SO ELIMINATES THE NEED FOR ADDITIONAL HEATING OR COOLING SYSTEMS, RESULTING IN ENERGY SAVINGS. IN ADDITION TO THERMAL MASS, THE MATERIALS WERE CHOSEN BASED ON ENERGY CONSUMPTION DURING PRODUCTION, TRANSPORTATION, AND INSTALLATION AS WELL AS AESTHETIC VALUE, COST AND PERFORMANCE.
PROJECT TEAM ARCHITECT STEPHANIE BERG ANNE ARUNDEL COMMUNITY COLLEGE ACH 240 - CONSTRUCTION DOCUMENTATION ARNOLD MARYLAND SNBERG@MYMAIL.AACC.EDU
No.
Description
Date
ACH240 ARTIST STUDIO COVER SHEET ACH240 12/14/2021 BERG HOFMANN
Project number Date Drawn by Checked by
A0.0 Scale
1" = 1'-0"
4/29/2022 3:13:04 PM
SYMBOLS
6' - 0"
"E 24' 00 N 77° 80' 80.
8' - 0" 7' - 0" ACK SETB
7' - 0"
60' - 1
FALL 2020 SEMESTER PROFESSOR HOFMANN
ACK SETB
"
"E 36' 00 S 12° .75' 135
"W 36' 00 N 12° .75' 135
Y STOR ONE G IN EXIST LING L DW E
FRAM
E
RCH ED PO R E V O ING C EXIST
No.
Description
Date
ING EXIST ETE R CONC S P STE
ACH240
ACH240 11/12/2021 BERG HOFMANN
Project number Date Drawn by Checked by
1
A1.0
ARCHITECTURAL SITE PLAN 1" = 10'-0" Scale
1" = 10'-0"
11/15/2021 2:20:13 PM
ARTIST STUDIO ARCHITECTURAL SITE PLAN
"W 24' 00 S 77° 80' 80.
FALL 2021 SEMESTER PROFESSOR HOFMANN
A2.0
1 A3.0
3
32' - 3" 12' - 8" 2' - 3"
14' - 4"
3' - 11" 0' - 7"
8' - 0"
6' - 0"
6' - 0" 14' - 4"
5' - 1"
A
2' - 8"
3' - 0"
7' - 0"
2' - 6"
2' - 10"
4' - 11" FIREPLACE
ENTRY 2
2' - 0"
6' - 2"
3' - 1"
26' - 1" 32' - 3"
4 A2.0
No.
Description
3' - 1"
ARTIST STUDIO FIRST FLOOR PLAN ACH240 12/14/2021 BERG HOFMANN
Project number Date Drawn by Checked by
1
Date
ACH240
5' - 2"
4' - 8"
4' - 11"
4
A2.0
9' - 0"
7' - 1"
8' - 0"
4' - 10"
2' - 10"
2' - 0"
3' - 11" GREENHOUSE
9' - 0"
7' - 2"
1
FIRST FLOOR PLAN 1/4" = 1'-0"
A1.1 Scale
1/4" = 1'-0"
4/29/2022 3:33:53 PM
2' - 0"
2' - 10" 1' - 0" 2' - 5"
7' - 1"
2' - 0"0' - 5"
4' - 10" 6' - 3"
2' - 11"
3' - 2" 1
1' - 0" 2' - 11"
5' - 9"
STUDIO SPACE
29' - 5"
B
14' - 6"
5
9' - 1"
CLOSET
9' - 1"
6
2' - 9"
3' - 2"
2' - 4"
2' - 9" 2' - 9"
8' - 9" 29' - 5"
2
2' - 2"
3
BATHROOM
A2.0
3' - 2"
PATIO
2' - 1"
6' - 0"
2' - 5"
19' - 8"
1
1' - 9" 14' - 0"
4' - 0"
ROOF LINE 12' - 0"
1' - 11"
8' - 3"
0' - 6" 2' - 5" 0' - 11" 1' - 6" 1' - 9"
1' - 9" 2' - 4"
B 4
BUILT IN LUMBER STORAGE BENCH
NORTH 1/4" = 1'-0"
1
FIRST FLOOR 0"
FALL 2021 SEMESTER PROFESSOR HOFMANN
FIRST FLOOR 0"
3
6' - 11"
STANDARD BRICK VENEER PAINTED WHITE W/ MATTE WATERPROOF FINISH
3
4' - 0"
BLACK MATTE ALUMINUM STANDING SEAM ROOF PANEL W/ 3' B/W SEAMS
4' - 0"
B
9' - 11"
B
4' - 1"
ROOF LINE 12' - 0"
14' - 0"
0' - 3" 2' - 9" 1' - 2"1' - 2" 2' - 0" 6' - 8"
6' - 11"
14' - 0"
5' - 1"
2' - 0"
A3.0
EAST 1/4" = 1'-0"
1
4' - 0" 14' - 0"
4' - 0"
8' - 0"
2' - 3" 1' - 0' 0"- 9" 1' - 0" 3' - 0"
1' - 6"1' - 3"1' - 1"1' -0'3"-1'2"- 0' 1" - 9"
1
No.
2' - 0"
FIRST FLOOR 0"
A
2' - 0"
STANDARD BRICK VENEER PAINTED WHITE W/ MATTE WATERPROOF FINISH
8' - 5"
14' - 0"
TEMPERED DOUBLE GLAZED 1/4" LOW-E EXTERIOR GLAZING CURTAIN WALL AND ROOF WITH MATTE BLACK ALUMINUM 1" VERTICAL AND HORIZONTAL MULLIONS
3' - 3"
5' - 7"
BLACK MATTE ALUMINUM STANDING SEAM ROOF PANEL W/ 3' B/W SEAMS
ROOF LINE 12' - 0"
Description
Date
FIRST FLOOR 0"
ACH240
WEST 2 1/4" = 1'-0"
ARTIST STUDIO ELEVATIONS ACH240 12/14/2021 BERG HOFMANN
Project number Date Drawn by Checked by
A2.0 Scale
1/4" = 1'-0"
4/29/2022 3:46:33 PM
SOUTH 4 1/4" = 1'-0"
ROOF LINE 12' - 0"
2' - 0" 1' - 8"
1' - 9" 2' - 6" 3' - 8" 2' - 0"
4' - 1"
8' - 0" 2' - 0"
14' - 0"
2' - 3" 1' - 9"
A3.0
FALL 2021 SEMESTER PROFESSOR HOFMANN MATTE BLACK STANDING SEAM ALUMINIUM ROOF PANELS ON 1 1/2" RIGID INSULATION 1/2" PLYWOOD W/ VAPOR BARRIER. VAULTED CEILING W/ CLOSED CELL SPRAY FOAM INSULATION B/W RAFTERS. CEILING FINISH TO BE 6" X 1/2" TONGUE AND GROOVE CEDAR PLANKS TO MATCH EXTERIOR SOFFIT.
2 A5.0
3 5/8" STANDARD BRICK VENEER PAINTED WHITE W/ WEATHER PROOF MATTE COATING ON 1 1/2" RIGID INSULATION W/ 1" AIR GAP. TIED TO 2" X 6" LIGHT WEIGHT STUD FRAMING FILLED WITH CLOSED CELL SPRAY FOAM INSULATION.
ROOF LINE 12' - 0" No.
CURTAIN PANEL WALL AND ROOF SYSTEM W/ TEMPERED DOUBLE GLAZED 1/4" LOW-E EXTERIOR FILLED WITH ARGON GAS, 1" X 1" MATTE BLACK ALUMINIUM MULLIONS TO MATCH EXTERIOR ROOF FINISH.
Description
Date
STUDIO SPACE
3 A5.0 GREENHOUSE COVERED PATIO
ACH240
1 A5.0
ARTIST STUDIO BUILDING SECTION ACH240 12/14/2021 BERG HOFMANN
Project number Date
1
SECTION 1/4" = 1'-0"
Drawn by Checked by
A3.0 Scale
1/4" = 1'-0"
4/29/2022 3:56:13 PM
FIRST FLOOR 0"
STANDARD 6" CONCRETE FLOOR ON 4" GRAVEL BASE W/ 1 1/2" PERIMETER SLAB INSULATION W/ FOOTING BELOW 32" FROST LINE, WRAPED VAPOR BARRIER, AND 6" DRAIN TILE
0' - 5" MASONRY CHIMNEY BEYOND SECTION CUT
3" / 1 '-
0"
VAPOR BARRIER
1' - 8"
STANDING SEAM METAL ROOF PANELS ON 1 1/2" RIGID INSULATION
2"X4" SUBFASCIA W/ METAL PANEL FASCIA TRIM AND FLASHING AT EAVE 1/2" PLYWOOD SHEATHING 6" X 1/2" CEDAR LAP SOFFIT
ROOF LINE 12' - 0"
2" X 6" DOUBLE TOP PLATE W/ 2" X 6" BLOCKING B/W RAFTER AND 7-1/2" BATT INSULATION 1 1/2" RIGID FOAM INSULATION 1" AIR BARRIER B/W MASONRY WYTHE AND RIGID INSULATION
1/2" GYPSUM BOARD INTERIOR FINISH 1/2" PLYWOOD SHEATHING 2' X 4" STUD WALL W/ CLOSED CELL SPRAY IN FOAM INSULATION VAPOR BARRIER 3 5/8" STANDARD BRICK VENEER PAINTED WHITE WITH WEATHER PROOF MATTE COATING TIED W/ CORRUGATED MASONRY TIES TO WOOD FRAME WALL
2
FALL 2021 SEMESTER PROFESSOR HOFMANN
CURTAIN WALL GREEN HOUSE ROOF HEAD AT FINISH
ENLARGED ROOF DETAIL 1 1/2" = 1'-0"
MATTE BLACK ALUMINIUM MULLION AT EAVE W/ SEALED PRESSURE EQUILIZATION CHAMBERS
MOMENT CONNECTION W/ BOLT FASTENER
DETERRENT SEALS
BLOCKING AS NEEDED TEMPERED DOUBLE GLAZED 1/4" LOW-E EXTERIOR GLAZING FILLED WITH ARGON GAS. CENTER SET.
1/2" JOINT SEALANT 6" SLAB ON GRADE W/ 4" GRAVEL BASE PATIO 1" ALUMINIUM FRAME W/ DOUBLE PANE LOW E GLAZING PANELS ON SLIDING TRACK W/ POCKET FRAME
FIRST FLOOR 0"
1/2" WOOD FINISH FLOORING 6" CONCRETE FLOOR ON 4" GRAVEL BASE W/ 1-1/2" PERIMETER SLAB RIGID INSULATION
1/2" FOUNDATION DRAINAGE BOARD
No.
MATTE BLACK ALUMINIUM MULLION SILL AT FINISH W/ SEALED PRESSURE EQUILIZATION CHAMBERS
EARTH FILL
Description
Date
FROST LINE
1/4" VAPOR BARRIER
2' - 6"
8" CONCRETE FOUNDATION WALL
6" DIAMETER PERIMETER DRAIN TILE 24" X 12" REINFORCED CONCRETE FOOTING W/ 2 CONT. HORIZ. #5 REBAR
CONTINIOUS BACKER ROD AND SEALANT BOTH SIDES
ACH240 ARTIST STUDIO DETAILS
TOP COURSE TO BE FULL WYTHE
ACH240 12/14/2021 BERG HOFMAN
Project number Date Drawn by
ENLARGED CURTAIN WALL DETAIL 3 6" = 1'-0"
ENLARGED FOUNDATION DETAIL 1 1 1/2" = 1'-0"
Checked by
A5.0 Scale
As indicated
4/29/2022 4:06:24 PM
2' BRICK CAVITY WALL W/ 2" GROUT FILL B/W WYTHES
FALL 2021 SEMESTER PROFESSOR HOFMANN No.
Description
Date
ACH240
ACH240 12/12/2021 BERG HOFMANN
Project number Date Drawn by Checked by
A9.0 Scale
12/12/2021 8:39:10 PM
ARTIST STUDIO MATERIAL PALETTE