San Diego Community College District Proposition S and Proposition N Overview

Page 1

SAN DIEGO COMMUNITY COLLEGE DISTRICT PROPOSITION S AND PROPOSITION N OVERVIEW PRESENTED TO AGC – SAN DIEGO CHAPTER MEET YOUR OWNER - JUNE 11, 2009

David Umstot, PE Vice Chancellor Facilities Management


Bond Measures  Proposition S (2002)

$685 Million

Proposition N (2006)

$870 Million

Total

$1.555 Billion


Impact of State Budget Crisis

 All

projects are locally funded funded.

 State

budget g does NOT impact construction.


Props S and N Projections and Actuals


Propositions S and N Budget


Construction Contracts


San Diego City College • Seven new teaching and learning facilities • Seven major renovations • Campus Camp s e expansion pansion will ill provide facilities/programs to accommodate eventual enrollment of 25,000 students


San Diego City College General Purpose p Classroom Building g Estimated Construction Start: Summer 2010 Estimated Construction Cost: $37.7 million Delivery Method: Design/Build Design/Builder: Sundt Sub Opportunities: Major trade subcontractors have been selected for MEP, Structure, and Concrete. M lti l ttrade Multiple d contracts t t will ill b be solicited in late Spring of 2010.


San Diego City College Arts & Humanities/Business Technology Complex


San Diego City College Arts & Humanities Building g

Estimated Construction Start: Summer 2010 Estimated Construction Cost: $62 million Delivery Method: CMMP

CM: Turner Construction

Sub Opportunities: Multiple trade bid packages will be solicited in late Spring of 2010.


San Diego City College Business Technology gy Building g

Estimated Construction Start: Summer 2010 Estimated Construction Cost: $62 million Delivery Method: CMMP

CM/GC: Turner Construction

Sub Opportunities: Multiple trade bid packages will be solicited in late Spring of 2010.


San Diego City College Science Building g Estimated Construction Start: Fall 2010 Estimated Construction Cost: $34 million Delivery Method: CMMP CM: Rudolph & Sletten Sub Opportunities: Multiple trade bid packages will be solicited in late Summer of 2010.


San Diego City College 16th Street Sewer Project j Estimated Construction Start: Winter 2010 Estimated Construction Cost: $2 million Delivery Method: Design-Bid-Build E i Engineer: AB E Engineering i i Sub Opportunities: This project will likely bid to heavy civil or wet utilities general contractors.


San Diego City College Central Plant Upgrade pg

Estimated Construction Start: Winter 2010 Estimated Construction Cost: $6 million Delivery Method: Design/Build Sub Opportunities: TBD


San Diego Mesa College

• Five projects completed under Propositions p S and N • Four projects currently under construction •Three projects currently in design; six more remaining as part of campus expansion


San Diego Mesa College Student Services Building g Estimated Construction Start: February 2010 Estimated Construction Cost: $47 2 million $47.2 Delivery Method: CMMP CM: PCL Construction Sub Opportunities: All Trades


San Diego Mesa College Math and Science Building g Estimated Construction Start: F b February 2011 Estimated Construction Cost: $92 million Delivery Method: CMMP CM: McCarthy Sub Opportunities: Trades, MEP and skin as Design/Build; balance of trades


San Diego Mesa College Muir Design g Center

Estimated Construction Start: February 2010 Estimated Construction Cost: $1.3 million Delivery Method: Design-Bid-Build Sub Opportunities: All Trades


San Diego Miramar College

• Ten completed projects • Infrastructure project & two classroom buildings currently y in construction • Campus expansion will accommodate eventual enrollment of 25,000


San Diego Miramar College Library y Learning g Resource Center

Estimated Construction Start: November 2009 Estimated Construction Cost: $31.9 Million Delivery Method: CMMP

CM: Sundt

Sub Opportunities: Multiple Trade packages will be solicited in July 2009


San Diego Miramar College College Student Campus Center & Cafeteria/Bookstore


San Diego Miramar College Student Campus Center & Cafeteria/Bookstore Estimated Construction Start: July 2010 Estimated Construction Cost: $23.5 million Delivery Method: CMMP CM: CW Driver Sub Opportunities: Multiple trade packages will be solicited in April 2010; MEP trades as designbuild in late summer 2009


San Diego Miramar College Automotive Technology gy Career Instructional Building Expansion Estimated Construction Start: September 2009 Estimated Construction Cost: $3.4 million Delivery Method: Design-Bid-Build Architect: Zagrodnik & Thomas Sub Opportunities: Underground Utilities, Block, Mechanical and Electrical


San Diego Miramar College Heavy y Duty y Advanced Transportation p Technology Center Expansion Estimated Construction Start: June 2010 Estimated Construction Cost: $6.6 million Delivery Method: CMMP Sub Opportunities: Multiple Trade packages will be solicited in March 2010


San Diego Miramar College College Aviation Maintenance Technology gy Center

Estimated Construction Start: January 2011 Estimated Construction Cost: $4.4 million Delivery y Method: Design-Bid-Build g


San Diego Miramar College Parking g Structure & Police Substation Estimated Construction Start: January 2010 Estimated Construction Cost: $13.8 million Delivery Method: Design /Build Design/Builder: McCarthy Sub Opportunities: TBA


Miramar College Parking Structure and Police Substation


San Diego Continuing Education

• Three projects completed • Construction completing for ECC Skills Center • Four Fo r projects in design • Total of eight projects to expand and modernize six Continuing Education sites


San Diego Continuing Education North City y Campus p Estimated Construction Start: November 2010 Estimated Construction Cost: $12.1 million Delivery Method: CMMP Sub Opportunities: All trades


San Diego Continuing Education Cesar Chavez Campus p Estimated Construction Start: October 2010 Estimated Construction Cost: $20 million Delivery Method: CMMP Sub Opportunities:


San Diego Continuing Education ECC Phase IIB – Wing g Expansion p Estimated Construction Start: M h 2011 March Estimated Construction Cost: $8 6 million $8.6 Delivery Method: TBD Sub Opportunities: All trades


San Diego Continuing Education Clairemont/Linda Vista Campus p Estimated Construction Start: March 2011 Estimated Construction Cost: $9.7 million Delivery Method: TBD Architect: SGPA Architecture and Planning Sub Opportunities: All trades


Lean Opportunities  

CMMP Design Design-Build Build opportunities MEP Trades  

Math and Science Building at Mesa College Cafeteria/Bookstore and Student/Campus at Miramar College Design-Build Selection Criteria      

Safety Record Price Past Performance Available Workforce Lif C Life Cycle l C Costs t BIM Experience


Prequalification All general and prime contractors must be pre-qualified to bid for construction contracts valued at more than $500,000. ď Ž

The District will not accept bids for contracts valued at more than $500 000 from Contractors who are not pre $500,000 pre-qualified. qualified ď Ž

Pre- and re-qualification forms and information are available online http://www.sdccdprops-n.com/Prequalification.aspx

Derek Contizano, Gafcon, Inc. (619) 231-6100, ext. 2207 dcontizano@gafcon.com


Labor Compliance 

Construction contracts for Proposition “S” and “N” projects are subject to California labor laws regarding “public public works” works projects.

Contractors must abide by the state labor laws, including payment of proper prevailing wage and utilizing apprentices.

The District will monitor all Proposition “S” and “N” projects for compliance with these requirements.

Use of LCP Tracker is required. Labor Compliance Program information is available online http://www sdccdprops n com/LaborCompliance aspx http://www.sdccdprops-n.com/LaborCompliance.aspx

Marty Glaske, Gafcon, Inc. (619) 231 231-6100, 6100 ext. t 1259 mglaske@gafcon.com


How to Track Opportunities Propositions S and N website http://www.sdccdprops-n.com/default.aspx The San Diego g Daily y Transcript p http://www.sddt.com/ Plan Rooms San Diego Contracting Opportunities Center (SDCOC) 4007 Camino del Rio South, #210 San Diego, CA 92108-4189 (619) 285-7020 http://www ptac-sandiego http://www.ptac sandiego.org/ org/

Black Contractors Consortium (BCC) 6125 Imperial Ave., San Diego, CA 92114 (619) 263-9791 http://www bcasd org http://www.bcasd.org

Associated General Contractors (AGC) 6212 Ferris Square San Diego, CA 92121 (858) 558-7444 http://www agcsd org/ http://www.agcsd.org/


SDCCD Contract Information

Cindy y Lasley, y, Contract Specialist p 3375 Camino del Rio South, Suite 125 San Diego, CA 92108 (619) 388-6546 clasley@sdccd.edu


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.