SAN DIEGO COLLEGE
Propositions S and N Facilities and Master Plan Update Facilities and Master Plan Update
December 7 7, 2009
SAN DIEGO COLLEGE
Completed Propositions S and N Projects
Completed Propositions S and N Projects
Learning Resource Center (‘R’ Building) Project Budget: $3.4 million Completion Date: August 2007 p g Renovation to convert approximately 15,000 SF of parking garage space into faculty offices, student classrooms and support space. The LRC is the first Propositions S and N p j project to obtain LEED certification.
Completed Propositions S and N Projects
Academic Success Center (‘L’ Building Renovation) Project Budget: $10.8 million Completion Date: April 2009 p p Complete, major renovation of two‐story building totaling 28,700 square feet. The new ASC serves as one‐stop shopping for all student services, including tutoring, assessment, advising, and other student , g, support and student achievement programs.
Completed Propositions S and N Projects
‘P’ Building Renovation Project Budget: $11.3 million Completion Date: December 2009 Complete, major interior and exterior renovation of existing two‐story concrete gymnasium building. Includes enhanced ADA accessibility and parking upgrades. New facility includes work‐out rooms, locker rooms, training areas, classrooms and faculty and staff workspaces.
SAN DIEGO COLLEGE
Master Plan Update
16th S Street
Park k Blvd
City College Facilities Master Plan Facilities Master Plan 2008 Update Outline a Coordinated Development Strategy Validate Academic Program Needs Establish Building Sizes and dL Locations ti
B Street C Street
Broadway
Strategize Topography and Accessibilityy Updated Master Plan Area
SAN DIEGO COLLEGE
City College Facilities Master Plan Facilities Master Plan 2008 Update
T Building A Building
Academic Buildings • 6 new facilities • 2 modified buildings
L Building
B Street C Building
B Street
Structured Parking • 6 locations • 2,050 spaces Open Space Network
Broadway
16th Street
C Street
SAN DIEGO COLLEGE
P
5b
A Building
City College Facilities Master Plan Facilities Master Plan 2008 Update
P
5a L Building
B Street C Building
4b
B Street
P
1
C Career T h l Technology Center C t
2
Child Development Center
3
General Purpose Classroom Building
P 2
4a
4a Arts & Humanities 4b Business Technology
C Street
Broadway
3 16th Street
P
P 1
5a Sciences 5b Engineering Technology P
Parking SAN DIEGO COLLEGE
City College Facilities Master Plan Facilities Master Plan 2008 Update
campus gateway
B Street B Street
pedestrian pathways
Broadway
16th Street
C Street
SAN DIEGO COLLEGE
City College Facilities Master Plan Facilities Master Plan 2008 Update “A U Unified ifi d Campus” C ” Great Collegial Environments Linked Campus Areas
B Street
Academic Neighborhoods
B Street
g Parking g Integrated Consideration for Topography & Landscape
C Street
Consideration C id ti ffor Safety and Accessibility
Broadway
16th Street
Phased Growth Plan
SAN DIEGO COLLEGE
SAN DIEGO COLLEGE
Propositions S and N Projects In Progress
Propositions S and N Projects in Progress
Career Technology Center (CTC) Project Budget: $72.5 million Construction Start: May 2008 Construction Start: May 2008 Targeted Completion: May 2010 New five New five‐story story, 88,000 sq. ft. facility to 88 000 sq ft facility to house the Nursing, Cosmetology and Photography and Digital Arts programs. Includes state‐of‐the‐art classrooms, l d f h l computer labs and medical simulation labs, and a gallery for student work. The CTC will provide new headquarters for City College Police and also includes a new parking structure with 694 stalls a new parking structure with 694 stalls.
Propositions S and N Projects in Progress
Humanities and Business Technology Buildings Project Budget: $85 million Expected Construction Start: May 2010 Targeted Completion: January 2012 Arts & Humanities will consist of approximately 70,000 sq. ft. to include new classrooms, a lecture hall, computer labs, studio space and a 100‐seat “black box theatre.” Business Technology will consist of approximately 40,000 sq. ft. to include classrooms, computer labs and areas for start‐up businesses for students. The project includes sublevel parking designated for ADA and faculty.
Propositions S and N Projects in Progress
General Purpose Classroom Building Project Budget: $83.5 million (incl. land acquisition) Expected Construction Start: Sept. 2010 Targeted Completion: May 2012 Project involves land acquisition and construction of new 72 000 72,000 sq. ft. general purpose classroom building . The f l l b ildi Th facility will have floor floors of academic classrooms and laboratories, and will also house the Chancellor’s Corporate Education Center, Military Education and a Family Health Center. The project will include a The project will include a six‐story parking structure with 400+ stalls.
Propositions S and N Projects in Progress
General Purpose Classroom Building
Propositions S and N Projects in Progress
Science Building Project Budget: $54.8 million Expected Construction Start: Sept. 2010 Expected Construction Start: Sept. 2010 Targeted Completion: Sept. 2012 Four-story, L-shaped building providing 73,000 square feet of new construction for classrooms, labs and a planetarium.
SAN DIEGO COLLEGE
Propositions S and N Facilities and Master Plan Update Facilities and Master Plan Update Quest o s Questions? Dave Umstot,, Vice Chancellor Facilities Management dumstot@sdccd.edu @ (619) 388-6546