Building for the Future of Education: Propositions S & N

Page 1

SAN DIEGO COMMUNITY COLLEGE DISTRICT

Building for the Future of Education: Propositions S and N Presented to the Elite Service Disabled Veteran‐owned Business Network San Diego Chapter

November 6, 2012


San Diego Community College District

About the District • • • •

City College Mesa College Miramar College Continuing Education   

  

Centre City Campus Cesar Chavez Campus Educational Cultural Complex Linda Vista Campus Mid‐City Campus West City Campus


San Diego Community College District

Propositions S and N Overview $1.555 billion construction bond program provides for 80+ projects at City, Mesa and Miramar Colleges, and six Continuing Education campuses: • State of the art teaching and learning facilities • Major renovations and modernizations • Campus‐wide infrastructure projects

3


San Diego Community College District

City College Overview  Six new teaching and learning facilities  Eight major renovations  Campus expansion will provide facilities and programs to accommodate eventual enrollment of 25,000 students  Eight projects completed to date; two more under construction


San Diego Community College District

City College – Completed Projects

Learning Resource Center

Academic Success Center

“P” Building Renovation

Career Technology Center (CTC)

Central Plant

Mathematics & Social Science


San Diego Community College District

City College – Future Projects C Building Renovation

A Building Renovation

Builder: Sundt Construction Bid and Award Timeframe: Oct 2013 – Nov 2013 Construction Timeframe: Nov 2013 – Sept 2015

Design/Build RFP: Due Nov 16, 2012 Bid and Award Timeframe: Dec 2014 – March 2015 Construction Timeframe: April 2015 – March 2018

M Building Renovation

Engineering Technology (T Bldg.)

Builder: CW Driver Bid and Award Timeframe: Sept 2013 – Dec 2013 Construction Timeframe: Dec 2013 – March 2015

Design/Build RFP: Due Nov 16, 2012 Bid and Award Timeframe: Dec 2014 – March 2015 Construction Timeframe: April 2015 – March 2018

D Building Roof

Child Development Center (CDC)

Builder: TBD Design/Build RFP: Due Nov 16, 2012 Bid and Award Timeframe: Dec 2014 – March 2015 Bid and Award Timeframe: Dec 2015 – March 2016 Construction Timeframe: April 2015 – March 2018 Construction Timeframe: March 2018 – March 2019


San Diego Community College District

Mesa College Overview  Seven new teaching and learning facilities  Four major renovations  Nine infrastructure projects  Expansion will provide facilities to accommodate eventual enrollment of 25,000 students  Eleven projects completed to date; one more under construction


San Diego Community College District

Mesa College Completed Projects

Allied Health Education & Training Facility

Mesa College Design Center

Parking Structure

Student Services Center

College Police Station


Mesa College Projects in Design

Social & Behavioral Sciences Building Project Budget: $40.5 million Targeted DSA Approval: Dec 2012 Targeted Bid Period: Jan 2013 – Feb 2013 Targeted Construction Start: April 2013 Targeted Completion: March 2014 The Social and Behavioral Sciences building will consist of approximately 66,000 GSF of new labs and classrooms for Behavioral Sciences and Social Sciences programs. The building will include Psychology Labs, Speech Labs and ‘smart’ classrooms. Design/Build Team: Builder: Swinerton Builders Architect: Joseph Wong Design Associates


Mesa College Projects in Design

Cafeteria/Bookstore/Stockroom Project Budget: $45.7 million Targeted DSA Approval: Nov 2013 Targeted Bid Period: Nov 2013 – Dec 2013 Targeted Construction Start: Feb 2014 Targeted Completion: May 2015 The 65,000 SF building will house the Food Services, bookstore and stockroom components for the Campus. Design/Build Team: Builder: Legacy Building Services Architect: Mosher Drew Watson Ferguson and Miller Hull Architects


Mesa College Projects in Design

Fitness Center Project Budget: $10.4 million Targeted DSA Approval: Feb 2014 Targeted Bid Period: March ‐ Apr 2014 Targeted Construction Start: June 2014 Targeted Completion: June 2015 The Fitness Center will be approximately 25,000 gross square feet facility to house Mesa College's Health Service program and Physical Conditioning program. Design/Build Team: Builder: Balfour Beatty Construction Architect: gkkworks


San Diego Community College District

Mesa College Future Projects LRC Language Center

I‐300 Building Demolition

Builder: TBD Bid & Award Timeframe: April – May 2013 Construction Timeframe: May – Dec 2013

Builder: TBD Bid & Award Timeframe: Feb – May 2014 Demolition Timeframe: May – August 2014

Instructional Technology Building

Fine Arts and Dramatic Arts

Design/Build RFP Timeframe: April ‐ May 2013 Bid & Award Timeframe: April ‐ May 2015 Demolition Timeframe: June – July 2015 Construction Timeframe: Aug 2015 – Oct 2016

Design/Build RFP Timeframe: June ‐ July 2014 Bid & Award Timeframe: Sept – Dec 2016 Construction Timeframe: Jan – April 2017

Facilities Support Area (L‐200 Remodel) Builder: TBD Bid & Award Timeframe: June ‐ August 2015 Construction Timeframe: Aug 2015 – June 2016

Mesa Quad Project Builder: TBD Bid & Award Timeframe: August – Nov 2015 Demolition Timeline: Jan – Feb 2017 Construction Timeframe: Feb – Aug 2017


San Diego Community College District

Miramar College Overview  15 new facilities  Seven major renovations  Three infrastructure projects  Expansion will provide facilities to accommodate eventual enrollment of 25,000 students  19 projects completed to date; two more under construction


San Diego Community College District

Miramar College Completed Projects

Mathematics & Business

Hourglass Park Field House

Humanities & Arts

Police Station & Parking Structure


San Diego Community College District

Miramar College Completed Projects

Library/Learning Resource Center (LLRC)

College Services Center

Aviation Technology Center


Miramar College Projects in Design

Student Services Project Budget: $7.3 million Targeted DSA Approval: Nov 2012 Targeted Bid Period: Jan – Feb 2013 Estimated Construction Start: April 2013 Targeted Completion: April 2014 The Student Services project will repair, renovate and convert the interim library space to support Assessment Services, Health Services, and Outreach. Design/Bid/Build Team: Builder: To be determined Architect: Mosher Drew Watson Ferguson


Miramar College Projects in Design

Fire Science/EMT Training Facility Budget: $16.5 million Targeted DSA Approval: Nov 2012 Targeted Bid Period: Dec 2012 – Jan 2013 Estimated Construction Start: March 2013 Targeted Completion: July 2014 The Fire and EMT Training Facility will consist of approximately 22,900 SF to serve as a classroom and active training center for the Fire Science and Emergency Medical Training (EMT) programs. The facility will have labs, support space, equipment staging, classrooms, offices and an outdoor training area. Design/Build Team: Builder: Swinerton Builders Architect: gkkworks


Miramar College Projects in Design

Science Building Expansion Budget: $34.9 million Targeted DSA Approval: March 2013 Targeted Bid Period: March 2013 – June 2013 Estimated Construction Start: June 2013 Targeted Completion: August 2014 The project will be a new 50,000 SF structure with classrooms, and labs for chemistry, astronomy, geology, anatomy, marine biology, microbiology, physics and biology. The roof level includes a greenhouse and observatory. Design/Build Team: Builder: DPR Construction Architect: Marlene Imirzian and Associates


Miramar College Projects in Design

Administration Building Budget: $10.4 million Targeted DSA Approval: Nov 2012 Targeted Bid Period: Jan – Feb 2013 Estimated Construction Start: Feb 2013 Targeted Completion: Oct 2013 The Administration Building project will provide for 17,000 SF of new construction at the north end of campus, and allow for the existing administration wing to be converted to a classroom facility for Continuing Education programs offered at Miramar. Design/Build Team: Builder: Charles Pankow Builders Architect: IBI


Miramar College Projects in Design

A‐100 Building Remodel Budget: $6.6 million Targeted DSA Approval: March 2013 Targeted Bid Period: March – May 2013 Estimated Construction Start: October 2013 Targeted Completion: June 2014 This project will provide for the renovation of the existing A‐100 building to house the Continuing Education programs at Miramar. The project will include classrooms, assessment, counseling and parent education spaces in the existing 16,000 gross square feet facility. An outdoor play area for the parent education program will enhance the indoor learning spaces. This project is slated to achieve a Leadership in Energy and Environmental Design (LEED) Silver certification. Design/Build Team: Builder: Charles Pankow Builders Architect: IBI


San Diego Community College District

Miramar College Future Projects Remodel Existing Police Academy Targeted Construction Timeframe: Nov 2013 – June 2014

Maintenance Facilities Expansion Targeted Construction Timeframe: Sept 2014 – Oct 2015


San Diego Community College District

Continuing Education Overview  Seven projects completed  Two projects under construction  Two projects in design  Total of 11 projects to expand and modernize the six Continuing Education sites


San Diego Community College District

Continuing Education Completed Projects

Mid City Campus

West City Campus

North City Campus Parking Structure

Skills Center

Cont. Ed. Mesa College Campus


Continuing Education Future Projects

Cesar Chavez Campus Project Budget: $48.5 million DSA Approval: June 2012 Targeted Bid Period: Feb – March 2013 Targeted Construction Start: April 2013 Targeted Completion: Nov 2014 This project consists of land acquisition and construction of a new 70,000 GSF building to consolidate the current programs at the Cesar Chavez and Centre City campuses. It will also include underground parking with 154 spaces and an adjacent parking structure. CM Multiple Prime Builder: Rudolph & Sletten Architect: Martinez + Cutri


Continuing Education Future Projects

Cesar Chavez Center Parking Structure Project Budget: $6.5 million DSA Approval: August 2013 Targeted Bid Period: August – September 2013 Targeted Construction Start: September 2013 Targeted Completion: September 2014 As part of the Cesar Chavez Campus project, a multi‐level parking structure with 300+ parking spaces will be built. Design/Build Team: Builder: PCL Construction Architect: RJC Architects


San Diego Community College District

Getting Involved Fill out and submit the SDCCD’s Certification Verification Form Upon submittal and verification, you will be added to the District’s database of small and historically underutilized firms. The database is shared with Design/Build proposal teams looking for firms to include in Design/Build Subcontracting Participation Plans, and with GCs and Campus Project Managers for task order work.

Pursue all the small business certifications for which you are eligible By obtaining formal certifications from approved agencies, you are added to state and federal databases made available to the public and which make you ‘findable.”

Track SDCCD’s construction opportunities Track SDCCD on Facebook and Twitter for updates, and check the Bid & Plan Room on the Propositions S & N website: http://public.sdccdprops‐n.com/Pages/Home.aspx


San Diego Community College District

Resources SDCCD Certification Verification Form http://public.sdccdprops‐n.com/CR/Forms/SDCCDCertificationForm.pdf

SDCCD Database of Small/Underutilized Businesses http://public.sdccdprops‐n.com/CR/Forms/PFDSHUF.pdf

SDCCD Approved Certifying Agency Directive http://public.sdccdprops‐n.com/CR/Forms/ACAP_Directive.pdf

SDCCD Prequalified Contractors http://public.sdccdprops‐n.com/CR/Pages/Prequal.aspx

Propositions S & N on Facebook: http://www.facebook.com/PropsSN Propositions S & N on Twitter: https://twitter.com/SDCCDPropsSN


San Diego Community College District

Design/Build Contacts Balfour Beatty

C.W. Driver

Clark Construction davisReed Group Construction, Inc.

DPR Construction

Harper Construction Co.

Hensel Phelps Construction Co.

Legacy Building Services

PCL Construction Services, Inc.

Rudolph & Sletten, Inc.

McCarthy Building Pankow Builders Companies

Sundt Construction Swinerton Builders TB Penick & Sons

Turner Construction


SAN DIEGO COMMUNITY COLLEGE DISTRICT

Questions? Richard Burkhart Construction Manager rburkhar@sdccd.edu (619) 388‐6456

Ursula Kroemer Outreach Coordinator ukroemer@sdccd.edu (619) 819‐5484

29