Shawnee County Willard Bridge Presentation September 24, 2015

Page 1

September 24, 2015


Weekly Bridge Inspection – No change

Design – 100% Complete

Permits ◦ UPRR has approved pp plans; p ; now developing p g agreement g ◦ USCOE and KDWR permit application submitted/under review ◦ Environmental: NEPA “Categorical Exclusion”

R-O-W ◦ Terms for all ROW purchases have been negotiated/agreed upon

Utility Relocation ◦ All utility companies have been contacted/provided plans and preparations being made for relocations (2017)


Funding ◦ USDOT TIGER Grant –  Anticipate award i i d announcements in i October b ◦ KDOT –  In receipt of LOR from BCC; In process of developing No Interest Loan Agreement g ◦ Inter-local Agreement –  COT reviewed/discussed; Anticipate return in next few weeks with comments/requested revisions ◦ Wabaunsee County Agreement: Develop after TIGER Grant determination

Schedule ◦ Still hoping for a December 2015 bid letting/December 2017 completion ◦ Dependent upon funding availability and type

SCDPW currently tl in i “Waiting” “W iti ” Mode M d