Shawnee County Willard Bridge Presentation August 27, 2015

Page 1

August 27, 2015


Weekly Inspection Update

Design Update

Permitting Update

R-O-W Update

Utility Relocation Update

Funding Update

Schedule Review

Other Items


Bridge Condition Unchanged • Pin & Hangar Inspection scheduled for Sunday, September 13, 2015


 99%

Complete

◦ Design completion by end of this month

◦ F&T finishing up detail drawings


Permitting Acquisition Remains on Schedule 

UPRR

◦ UPRR continuing review process. Not anticipating major issues

Environmental –

Others

◦ Project Considered for “Categorical Exclusion”  Not considered to have a significant effect on “human environment” ◦ Corps of Engineers: Submit for review by mid-September ◦ KDWR: Submit for review by mid-September


 Shawnee

County (NE, NW, SE

◦ All R-O-W has been acquired

 Wabaunsee

Quadrants)

County (SW Quadrant)

◦ Wabaunsee County has contacted property owners, staked R-O-W limits and is in process of acquiring ◦ Anticipate being completed by mid-September


 No

Change

◦ Will send final plans to utilities once design complete ◦ Not a critical path item at this point


TIGER Grant ◦ Comm. Buhler met with Senator Moran and USDOT Sect. Foxx ◦ Anticipate TIGER Grant award announcements in October

KDOT Request ◦Developed draft request letter and funding strategy outline to be sent to KDOT

City of Topeka (Sales Tax Extension) ◦ Interlocal Agreement Negotiations Upcoming


PROJECT PROGRESS SCHEDULE NW Carlson Road (Willard) Bridge over the Kansas River SNCO Bridge Number: BSN 130 SNCO Project No. S-121015.00 KDOT Project No. 89C 0066-01

TASK

2015 Jan

Feb Mar

Apr May Jun

Jul

2016 Aug Sep

Oct Nov Dec Jan Feb Mar Apr May Jun

Jul

2017 Aug Sep

Oct Nov Dec Jan Feb Mar Apr May Jun

Jul Aug Sep Oct Nov Dec

Design Right-of-Way Utility Adjustment SNCO / WabCo Agreement Permitting UPRR Agreement SNCO BID Bridge Const.

SNCO Award Contract Construction

NOTE: Progress Schedule assumes NO Federal Funding

Road Tie-In, Final Grading, Seeding




REMAINING PROJECT COSTS 2015

2016

2017

Total

Design

$115,625*

$115,625*

R-O-W

$124,000*

$124,000*

$35,000*

$35,000*

UPRR Permit Utility Relocation Construction Const. Engineering

$100,000*

$100,000*

$8,014,000

$12,021,000

$20,035,000

$641,120

$961,680

$1,602,800

Contingencies

$100,000*

$641,190

$961,785

$1,702,975

TOTAL

$374,625*

$9,296,310

$14,044,465

$23,715,400

*Funding is Currently Available