Shawnee County Willard Bridge Presentation June 25, 2015

Page 1

June 24, 2015


Weekly Inspection Update

Design Update

Permitting Update

R-O-W Update

Utility Relocation Update

Funding Update

Schedule Review

Other Items


◦ No Change in Condition Since Last Status Update  Recent hot weather causing expansion of structural members  Actually may hear more noise during hot weather  No cause for concern


Bridge Design Divided Into Three Units: ◦ Unit 1: South end of bridge over UPRR ◦ Unit 2: Portion spanning Kansas River ◦ Unit 3: North end of bridge

Unit 1 (98% Complete)

Unit 2 (90% Complete)

Unit 3 (75% Complete)

Estimated Completion date: Late July – August


UPRR ◦

Environmental

◦ NEPA (National Environmental Pollution Act) Document  KDOT has led the NEPA process since the project field check was completed in 2010  Project considered for a “Categorical Exclusion”  KDOT will be re-confirming clearances due to time that has passed since original consideration ◦

Proposed plans (Unit 1) sent to UPRR  UPRR continuing review process

Previously obtained 7 environmental clearances

Others ◦ ◦ ◦ ◦

Corps of Engineers 404 Permit – Will be submitted by mid-July KDWR – Action Plan will be submitted by mid-July KDHE Notice of Intent KDOT Environmental Services Action Permit


NE Quadrant ◦

R-O-W documents have been finalized; Negotiations with property owners to begin in next two weeks

NW Quadrant

R-O-W documents have been finalized; Negotiations with property owners to begin in next two weeks

SE Quadrant ◦ ◦

Agreement reached with major property owner and executed by BCC R-O-W documents have been finalized; Negotiations with property owners to begin in next two weeks

SW Quadrant – NO CHANGE ◦ ◦

R-O-W documents have been finalized and submitted to Wabaunsee County on June 1, 2015 Wabaunsee County in process of acquiring


No Change

◦ Previously met with Westar ◦ Other utility involved is Rural Water ◦ Not a critical path item at this point


TIGER Grant

◦ Final Application Submitted on June 5, 2015  Requested $16.7M in federal funds  Benefit-Cost Analysis over 30-year Period:  @7% Discount: NPV = $92.1M; B/C Ratio = 7.35  @3% Discount: NPV = $173.9M; B/C Ratio = 15.55  Anticipate TIGER Grant award announcements by end of September


Letters of Support (LOS)

◦ Rep. Jenkins, Sen. Roberts and Sen. Moran issued joint federal delegation LOS ◦ Union Pacific Railroad ◦ KDOT ◦ Wabaunsee County Commission ◦ Pottawatomie County Commission ◦ City of Rossville ◦ USD 321 (Kaw Valley) ◦ Westar


KDOT Request

◦ KDOT confirmed ability to advance SNCO $7-$10M in no interest loan  Provided:  No drastic economic downturn in the upcoming year  SNCO develops funding package for balance of project  Funding likely not available until July 1, 2016  Funding would be provided based upon actual reimbursable expenses

City of Topeka (Sales Tax Extension) – NO CHANGE ◦ Interlocal Agreement Negotiations Upcoming  Becoming a high priority to complete – Likely need by end of September


YEAR

AMOUNT (est)

FUNDING SOURCE

2016/2017

$7-$10M

KDOT Advance

STE* (2017-2026)?

2016

$2-$3M

2016 Gen Fund

N/A

2016

$5-$10M??

TIGER Grant??

N/A

2017

$6-$7M

CST** Excess

N/A

2017

$1M

Wabaunsee Co.

N/A

2017

$2-$3M

2017 Gen Fund

N/A

2017

$1-$2M

STE*/Exch. Funds/PW 391

N/A

2018 (if nec.)

$2-$3M

2018 Gen Fund

N/A

*Sales Tax Extension **Current Sales Tax

REPAYMENT SOURCE


KDOT Financial Advance

◦ Provides Construction Funding for 2016 (July 1)

 May need temporary financing for first few months of project

◦ Prior to Current Sales Tax Excess Funds Availability ◦ Significantly reduces bonding costs 

Sales Tax Extension County Bridge Allotment ◦ $32.5M (includes $10M allotted for Willard Bridge) ◦ Provides reimbursement funds for KDOT Advance

Assistance in Expediting UPRR Agreement


PROJECT PROGRESS SCHEDULE NW Carlson Road (Willard) Bridge over the Kansas River SNCO Bridge Number: BSN 130 SNCO Project No. S-121015.00 KDOT Project No. 89C 0066-01

TASK

2016

2015 Jan

Feb Mar

Apr May Jun

Jul

Aug Sep

Oct Nov Dec Jan Feb Mar Apr May Jun

Jul

2017 Aug Sep

Oct Nov Dec Jan Feb Mar Apr May Jun

Jul Aug Sep Oct Nov Dec

Design Right-of-Way Utility Adjustment SNCO / WabCo Agreement Permitting UPRR Agreement SNCO BID SNCO Award Contract Construction

NOTE: Progress Schedule assumes NO Federal Funding

Bridge Const.

Road Tie-In, Final Grading, Seeding




PROJECT PROGRESS SCHEDULE NW Carlson Road (Willard) Bridge over the Kansas River SNCO Bridge Number: BSN 130 SNCO Project No. S-121015.00 KDOT Project No. 89C 0066-01 TASK Jan

Feb Mar

2015 Apr May Jun Jul

Aug Sep

2016 Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Aug Sep

2017 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb

2018 Mar Apr May

Design Right-of-Way Utility Adjustment SNCO / WabCo Agreement Permitting UPRR Agreement SNCO BID SNCO Award Contract Construction

NOTE: Progress Schedule assumes NO Federal Funding

Bridge

Road Tie-In, Final Grading, Seeding


REMAINING PROJECT COSTS 2015

2016

2017

Total

Design

$115,625*

$115,625*

R-O-W

$124,000*

$124,000*

$35,000*

$35,000*

UPRR Permit Utility Relocation

$100,000*

$100,000*

$8,014,000

$12,021,000

$20,035,000

$641,120

$961,680

$1,602,800

$100,000*

$641,190

$961,785

$1,702,975

$374,625*

$9,296,310

$14,044,465

$23,715,400

Construction Const. Engineering Contingencies TOTAL *Funding is Currently Available