Shawnee County Willard Bridge Presentation May 21, 2015

Page 1

May 21, 2015


Weekly Inspection Update

Design Update

Permitting Update

R-O-W Update

Utility Relocation Update

Funding Update

Schedule Review

Other Items


â—Ś No Change in Condition Since Last Status Update


Design Continuing “Full Speed Ahead”

Estimated Completion date: July – August


UPRR

Environmental – NO CHANGE

Others - NO CHANGE

◦ Proposed plans (Unit 1) sent to UPRR ◦ UPRR provided preliminary comments ◦ F&T currently making revisions as per UPRR request ◦ Obtained 7 environmental clearances

◦ ◦ ◦ ◦

Corps of Engineers KDWR KDHE Notice of Intent KDOT Environmental Services Action Permit


NE Quadrant – NO CHANGE ◦

NW Quadrant – NO CHANGE ◦

R-O-W documents still being finalized

SE Quadrant ◦ ◦

R-O-W documents still being finalized

Agreement reached with major property owner and approved by BCC R-O-W documents being finalized for minor property owners

SW Quadrant – NO CHANGE ◦ ◦

R-O-W documents still being finalized Wabaunsee County will acquire


No Change

◦ Met with Westar in March ◦ Other utility involved is Rural Water ◦ Not a critical path item at this point


KDOT Request – NO CHANGE ◦ Awaiting end of legislative session

City of Topeka (Sales Tax Extension) – NO CHANGE ◦ Interlocal Agreement Negotiations Upcoming

TIGER Grant

◦ Pre-application submitted by SCDPW on April 27, 2015 ◦ Final Application due June 5, 2015

 Contracted with Parsons-Brinckerhoff to assist in development  Multiple staff working on application


PROJECT PROGRESS SCHEDULE NW Carlson Road (Willard) Bridge over the Kansas River SNCO Bridge Number: BSN 130 SNCO Project No. S-121015.00 KDOT Project No. 89C 0066-01

2015

TASK Jan

Feb Mar

Apr May Jun

Jul

2016 Aug Sep

Oct Nov Dec Jan Feb Mar Apr May Jun

Jul

Aug Sep

Oct Nov Dec Jan Feb Mar Apr May

Design Right-of-Way Utility Adjustment SNCO / WabCo Agreement Permitting UPRR Agreement SNCO BID SNCO Award Contract Construction

NOTE: Progress Schedule assumes NO Federal Funding

Bridge Const.


Letters of Support (LOS) ◦ KDOT

◦ USD 321 (Kaw Valley) ◦ Rep. Jenkins staff coordinating efforts for joint federal delegation LOS ◦ Will be meeting with Wabaunsee and Pottawatomie County Commissions on June 1, 2015  Provide update  Request LOS ◦ Requesting LOS from:  State/Local delegates  UPRR  Westar  Motor Carriers Association


HB 2435 ◦ Removal of tax-exempt status for government building projects ◦ Could potentially have significant impact to project cost




PROJECT PROGRESS SCHEDULE NW Carlson Road (Willard) Bridge over the Kansas River SNCO Bridge Number: BSN 130 SNCO Project No. S-121015.00 KDOT Project No. 89C 0066-01 TASK Jan

Feb Mar

2015 Apr May Jun Jul

Aug Sep

2016 Oct Nov Dec Jan Feb Mar Apr May Jun Jul

Aug Sep

2017 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb

2018 Mar Apr May

Design Right-of-Way Utility Adjustment SNCO / WabCo Agreement Permitting UPRR Agreement SNCO BID SNCO Award Contract Construction

NOTE: Progress Schedule assumes NO Federal Funding

Bridge

Road Tie-In, Final Grading, Seeding


REMAINING PROJECT COSTS 2015

2016

2017

Total

Design

$115,625*

$115,625*

R-O-W

$124,000*

$124,000*

$35,000*

$35,000*

UPRR Permit Utility Relocation Construction Const. Engineering

$100,000*

$100,000*

$8,014,000

$12,021,000

$20,035,000

$641,120

$961,680

$1,602,800

Contingencies

$100,000*

$641,190

$961,785

$1,702,975

TOTAL

$374,625*

$9,296,310

$14,044,465

$23,715,400

*Funding is Currently Available


YEAR

AMOUNT (est)

FUNDING SOURCE

2016

$7-$10M

KDOT Advance

STE* (2017-2026)

2016

$2-$3M

2016 Gen Fund

N/A

2017

$6M

CST** Excess

N/A

2017

$1M

Wabaunsee Co.

N/A

2017

$2-$3M

2017 Gen Fund

N/A

2017

$1M

STE*/Exch. Funds/PW 391

N/A

2018 (if nec.)

$2-$3M

2018 Gen Fund

N/A

*Sales Tax Extension **Current Sales Tax

REPAYMENT SOURCE


KDOT Financial Advance

Sales Tax Extension County Bridge Allotment

Assistance in Expediting UPRR Agreement

Goal is a Dec 2015/Jan 2016 Bid

◦ Provides Construction Funding in 2016 ◦ Prior to Current Sales Tax Excess Funds Availability ◦ Significantly reduces bonding costs ◦ $32.5M (includes $10M allotted for Willard Bridge) ◦ Provides reimbursement funds for KDOT Advance ◦ KDOT/Sen. Moran

◦ Construction in Jan/Feb 2016

 Environmental Restrictions April 1st - August 31st

◦ Completion in Dec 2017