Fair Park Update 11/15/18 What’s Happening on Site 11/15/18 North Fields - All asphalt trails/road completed - Water fountain and bicycle rack installation complete - Post & chain installation ~95% completed South Fields -
Pervious concrete parking areas completed Asphalt paving completed Rain Garden Plantings completed Post & chain installation ~70% complete Parking Striping Tree planting completed
Restroom Building - Punch items - Bicycle rack and repair station installation complete Site Work - Site furnishing installation underway - Perimeter fence installation completed - Site Landscape planting 95% complete Dog Park -
Synthetic turf installation completed Bench, Waste station, and water fountain installation complete Dog agility equipment installation 90% complete Fence Installation ~90% completed Decomposed granite installation ~80% completed
Fair Park Update 11/15/18 Three Week Look Ahead North Fields -
Hydroseeding of Fescue Areas Completion of parking striping Re-seeding of native meadows Completion of Rain Garden plantings Begin Vehicle Gate Installation
South Fields - Re-seeding of native meadows - Completion of remaining post & chain - Begin Vehicle Gate Installation Restroom Building - Restroom building final punch completion Site Work -
Installation of remaining site furnishings Complete remaining plantings in beds Installation of site signage Removal of invasive foliage along Brown’s Creek
Dog Park -
Completion of remaining decomposed granite areas Complete remaining plantings in beds Complete installation of agility equipment Complete installation of remaining fencing Complete installation of gates Begin installation of seat wall cladding
Fair Park Update 11/15/18 Site Activity Photos Perimeter Fence and Planting
Trailhead Structure and Benches
Fair Park Update 11/15/18 South Field Parking and Post & Chain
Rain Garden Planting
Fair Park Update 11/15/18 Dog Park Fencing and Planting
Fair Park Update 11/15/18 Dog Agility Equipment
Fair Park Update 11/15/18 Site Furnishings
Fair Park Update 11/15/18
Fair Park Update 11/15/18 Site Progression Photos October 2018 Aerial Photos