From:
Nick Roberts
Office: Kansas City Date:
3.23.11
Re:
Sporting Kansas City Project Update – Week of 3.23.2011
To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner
Current Activities this Week: Site/Playing field/Bowl: Grading on plaza is onging. Installation of underground drainage at plaza is ongoing. Installation of fence around field is ongoing. Final field preparation for sod is nearly complete. Seating support install is ongoing. Concrete Flatwork: Area 3-Topping slab at cauldron club is complete and protected. Area 1- SOG work at SW toilet entry to be completed. SE vomitory road was poured. Masonry: Block installation at NW transformer area to be ongoing. Block installation at Terrace Bar is nearly topped out. Sealing and final wash of block on the East side to be ongoing. Washing and sealing F-line will be complete this week. Finishing concourse exterior walls will be ongoing.
Irrigation of field and protective fence.
Stone: Area 1-Stone installation in area H is nearly complete. Steel: Installation of dock overhead doors is complete. Wind columns will be complete. Installation of tube header at NE retail will be complete. RFI 971 stone support is complete. NE entry gate steel installation is ongoing. Conduit for NW Main Entry sign in stone.
Building the Future
Roofing and Sheet metal: Gutter shrouds at canopy gutter are ongoing. Canopy deck flashing installation is ongoing. Coping cap installation at concourse buildings is ongoing. Metal panels on east elevation are ongoing. Concession metal panel installation is ongoing. Polycarbonate: Area 1- Polycarbonate installation is complete. Area 2- Polycarbonate installation is ongoing. Area 3- Polycarbonate installation begins this week.
Metal panels outside Stadium Suite.
Metal Stud Framing/Drywall/Ceilings: Area 3-Drywall installation and finishing is near complete. DAFS installation is nearly complete. Stud framing for north screenwall/ metal panels is complete. Ceiling grid installation is ongoing on all levels. Ceiling tile is ongoing in all levels of Area 1. Stud framing in NW First Aid area is ongoing. Glass/Doors/Hardware: Area 1-installation of aluminum doors is complete. Installation of storefronts at Main Concourse retail buildings are ongoing. Installation of Press level Solar innovation sliders is ongoing. Installation of Supporter’s Club curtain wall is ongoing. Area 1 – installation of aluminum curtain wall doors to Main Concourse club are complete. Installation of hollow metal doors and hardware is ongoing. MEP: Ductwork installation is ongoing on the East side field level. Plumbing rough in is ongoing on the East side field level. All racks and cabinets are set and terminated. Fixtures and devices installation in Area 1 is ongoing. Sub air equipment complete and ready for owner training. Area 1-installation of toilet fixtures is nearly complete Tie -in of canopy gutters to downspouts is ongoing.
Building the Future
Interior framing at NW First Aid area.
Soccer cloud features over Main Club.
North scoreboard module installation is complete. South ad panel installation is ongoing. Signage light conduit for North Main Entry Sign in stone has been installed. Installation of speakers/lights in ceiling tiles are ongoing on all levels. Installation of light fixtures in concourse bathrooms is ongoing. Installation of beer lines is ongoing. MEP connections of concession equipment is ongoing. Installation of unit heaters in concourse RR’s is ongoing. Irrigation and conduits to field in SE vomitory installed.
Modified MEP for VIP Canopy adjustment.
Elevators: F1 elevator is complete. P1 installation is ongoing. Painting: Area 1-Painting at Field level to be complete. Painting in all Main Concourse buildings to be complete. Area 1-Painting on Press and Suite is ongoing. Area 1-Painting of the Main Concourse west tower is ongoing. Sealing of exposed concrete floors is ongoing. Area 1- Resinous flooring at field level is complete. Painting of bowl is ongoing. Painting of hallow metal doors is ongoing.
Subair soffit louver installation.
Tile/Carpet/Finishes: Tile installation at Press level Suites is ongoing. Tile installation in club areas at Suite and Press levels is ongoing. Tile in restrooms at all levels is near complete in Area 1. Carpet installation and base is ongoing in Area 1. Quartz counter installation is ongoing. Tile in Field Club is ongoing. Wood base installation is ongoing on Suite and Press. Food Service: Installation of all counters and kitchen equipment at Concessions will be complete. Equipment install is ongoing in all areas. Tile installation in Field Club. Building the Future
Press Level. Projected Activities occurring next Week: Concrete Flatwork: Rest of SE vomitory truck drive will be poured. Stone/masonry: Stone installation will be complete on north elevation.
Curtain wall installation at Supporter’s.
Steel: Installation of stone support steel at Stadium Suite to be complete. Installation of gate framing will begin. Roofing and Sheet metal: Canopy gutter shroud installation will be complete. Installation of metal panels at concessions to be ongoing. Installation of coping cap at concourse roof to be ongoing. Metal Stud Framing/drywall soffits: DAFS installation to be ongoing at exterior soffits. FRP installation in Concessions to be complete. Ceiling grid installation to be ongoing on all levels. Ceiling tile to be complete in Field Club. Completed drainage structure in Plaza. Glass: Area 1-Aluminum door frame installation to be ongoing. Installation of storefronts at Main Concourse buildings to be ongoing. Installation of interior glazing on Field/Mezz is complete. Installation of Solar innovation sliders at back of suites on Press level to be ongoing. MEP: Installation of North Scoreboard to be ongoing. Preliminary hydrostatic testing of the fire sprinkler lines to be ongoing. Energizing mechanical equipment for commissioning/start up will be ongoing. Installation of traffic and network fiber will be ongoing. Installation of building network will be ongoing.
Building the Future
Seating support installation.
Plaza electrical underground will be ongoing. Scoreboard/AV racks will begin installation. Paint: Area 1-Painting of the Suite and Press level areas to be complete. Painting at Field level to be ongoing. Sealing of concrete floors to be ongoing. Painting of bowl and hallow metal doors will be ongoing. Tile/Carpet: Tile in Field Club will be ongoing. Tile in Suite and Press Club will be ongoing. Carpet in press suites will be ongoing.
Installation of light fixtures at Supporter’s.
Site/Playing Field: Installation of field sod will begin. Plaza electrical installation will begin. Plaza layout will be ongoing.
Bar top installation in Loft Suites.
Additional Photos:
Installation of NE entry gate steel. Building the Future
Painting of seating bowl.
First pour of SE truck entry vomitory.
Survey layout of Plaza.
Unloaded and boxed seats ready for install.
Near completion of ceiling tile @ Stair 8.
Tile installation in Upper Suite Lounge.
Scoreboard racks delivered.
Building the Future