LIVESTRONG Sporting Park Construction Update - 3/30/11

Page 1

From:

Nick Roberts

Office: Kansas City Date:

3.30.11

Re:

Sporting Kansas City Project Update – Week of 3.30.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner

Current Activities this Week: Site/Playing field/Bowl: Grading on plaza is onging. Installation of field sod will be complete. Forming of east side and plaza concrete stairs is ongoing. Seating installation is ongoing. Concrete retaining wall installation is ongoing. Concrete Flatwork: East side walks will begin. Area 1- SOG work at SW toilet entry to be completed. SE vomitory road was poured to completion. Masonry: Block installation at NW transformer area to be ongoing. Block at Terrace bar is being washed. Sealing and final wash of block on the East side to be ongoing. Finishing concourse exterior walls will be ongoing.

Sod installation and irrigation.

Stone: NW elevation stone is complete. Stone outside Owner’s Suite is ongoing. Cast stone installation is ongoing. Steel: Wind columns are complete. NE entry gate steel installation is complete. SW breezeway gate steel is complete.

Building the Future

Stone installation outside owner’s suite.


Roofing and Sheet metal: Installation of fins on East elevation are ongoing. Gutter shrouds at canopy gutter are nearly complete. Canopy deck flashing installation is ongoing. Coping cap installation at concourse buildings is ongoing. Metal panels on East elevation are ongoing. Concession metal panel installation is ongoing. Polycarbonate: Area 1- Polycarbonate installation is complete. Area 2- Polycarbonate installation is ongoing. Area 3- Polycarbonate installation is ongoing.

Fin installation on East elevation.

Metal Stud Framing/Drywall/Ceilings: Area 3-Drywall installation and finishing will be complete. DAFS installation is nearly complete. Ceiling grid installation is ongoing on all levels. Ceiling tile is ongoing in all levels of Area 1. Stud framing in NW First Aid area is complete. Supporter’s Club interior soffits are complete.

Glass/Doors/Hardware: Installation of storefronts at Main Concourse retail buildings are ongoing. Installation of Press level Solar innovation sliders is ongoing. Installation of Supporter’s Club curtain wall is ongoing. Area 1 – installation of aluminum curtain wall doors to Main Concourse club are complete. Installation of hollow metal doors and hardware is ongoing. Installation of wood doors is ongoing.

Aluminum doors at Interview Room.

MEP: Ductwork installation is ongoing on the East side field level. Plumbing rough in is ongoing on the East side field level. All racks and cabinets are set and terminated. Fixtures and devices installation in Area 1 is nearly complete. Kitchen equipment MEP connections. Building the Future


Area 1-installation of toilet fixtures is nearly complete Tie -in of canopy gutters to downspouts is ongoing. North scoreboard module installation is complete. South ad panel installation is ongoing. Installation of speakers/lights in ceiling tiles are ongoing on all levels. Installation of light fixtures in concourse bathrooms is ongoing. Installation of beer lines is ongoing. MEP connections of concession equipment is ongoing. Installation of unit heaters in concourse RR’s is ongoing. All rooftop units will be operating. Site electrical branch conduits are ongoing.

Toilet accessory installation.

Elevators: F1 elevator is complete. P1 installation is ongoing. Painting: Area 1-Painting at Field level is complete. Area 3 – Field level paint is ongoing. Painting in all Main Concourse buildings is complete. Area 1-Painting on Press and Suite nearly complete. Area 1-Painting of the Main Concourse West tower is ongoing. Sealing of exposed concrete floors is ongoing. Painting of field walls is ongoing. Painting of hollow metal doors is ongoing.

Installation of seats.

Tile/Carpet/Finishes: Tile installation at Press level Suites is complete. Tile installation in club areas at Suite and Press levels is ongoing. Tile in Owner’s Suites is ongoing. Carpet installation in Suite corridor is ongoing. Quartz counter installation is nearly complete. Tile in Field Club is complete. Wood base installation is nearly complete in Suite and Press. Food Service: Installation of all counters and kitchen equipment at

Building the Future

Floor tile in corridor behind Owner’s Suite.


Concessions is complete. Equipment install is ongoing in all areas. Caulking and completion of Commissary will begin. Projected Activities occurring next Week: Concrete Flatwork: Plaza stairs will be ongoing. Stone/masonry: Final cleaning of masonry will be complete.

Overhead doors at Supporter’s Club.

Steel: Installation of stone support steel at Stadium Suite to be complete. Installation of gate framing will begin. Roofing and Sheet metal: Canopy gutter shroud installation will be complete. Installation of metal panels at concessions to be ongoing. Installation of coping cap at concourse roof to be ongoing. Metal Stud Framing/drywall soffits: DAFS installation to be ongoing at exterior soffits. Ceiling grid installation to be ongoing on all levels. Ceiling tile to be complete in Field Club.

Carpet installation in Suite Level corridor.

Glass: Area 1-Aluminum door frame installation to be ongoing. Installation of storefronts at Main Concourse buildings to be complete. Installation of Solar innovation sliders at back of suites on Press level to be ongoing. MEP: Water will be live on the building. Energizing mechanical equipment for commissioning/start up will be ongoing. Installation of traffic and network fiber will be ongoing. Installation of building network will be ongoing. Plaza electrical underground will be ongoing.

Building the Future

Partition installation in Concourse RR’s.


Scoreboard/AV racks terminations will be ongoing.

Paint: Area 1-Painting of the Suite and Press level areas to be complete. Painting at Field level to be ongoing. Sealing of concrete floors to be ongoing. Painting of bowl and hallow metal doors will be ongoing. Tile/Carpet: Tile in Field Level will be ongoing. Tile in Suite and Press Club will be ongoing. Carpet in press suites will be ongoing.

Installed cast stone in SE corner.

Site/Playing Field: Installation of field sod will begin. Plaza electrical installation will begin. Plaza layout will be ongoing. Concrete stairs and retaining wall installation will be ongoing.

Suite Club bar installation.

Additional Photos:

Installation of NE entry gate steel.

Building the Future

Inside of F1 elevator, ready for use.


Field Club bar counter top installation.

Forming of Retaining Wall #5 in Plaza.

Carpet installation inside suites.

Forming of stairs on East side.

Preparation for south walk installation.

Finished stair risers in Area E.

Building the Future


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.