LIVESTRONG Sporting Park Construction Update - 4/20/11

Page 1

From:

Nick Roberts

Office: Kansas City Date:

4.13.11

Re:

Sporting Kansas City Project Update – Week of 4.13.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner

Current Activities this Week: Site/Playing field/Bowl: Grading at Plaza is complete. Seating installation is ongoing. Concrete retaining walls installation is ongoing. Concrete stair pouring and forming is ongoing. Grading of north side is ongoing. South mow strip installation is complete Concrete Flatwork: East side walk pours are complete. Plaza flatwork is ongoing. VIP Entrance slab will be poured. Masonry: Finishing concourse exterior walls is complete. Plaza wall block is ongoing. Stone: NW elevation stone is complete. Stone on field face of Victory Suite will be complete. Cast stone installation is ongoing.

Pouring of Plaza flatwork.

Steel: Bowl handrail is ongoing. Gate frame installation at Portal’s is ongoing. Overhead door at south breezeway is complete. Terrace bar steel installation is ongoing. Roofing and Sheet metal: Canopy deck flashing installation is ongoing. Metal panels on East elevation at louver is ongoing. Metal panels on north mezz interior soffit are ongoing. Overhead rolling grilles at south breezeway. Building the Future


Concession metal panel installation is ongoing.

Polycarbonate: Area 2- Polycarbonate installation is ongoing. Area 3- Polycarbonate installation is ongoing. Metal Stud Framing/Drywall/Ceilings: Area 3-Drywall installation and finishing will be complete. DAFS installation is nearly complete. Ceiling grid installation is ongoing on all levels. Ceiling tile is ongoing in concessions.

Induction burners in suites.

Glass/Doors/Hardware: Installation of Press level Solar innovation sliders is ongoing. Installation of Supporter’s Club curtain wall is complete. Installation of OH doors at Supporter’s Club is complete. Installation of wood doors is complete on Press. Storefront at NE concourse Retail is complete. MEP: Ductwork installation is ongoing on the East side field level. Plumbing rough in is compelte on the East side field level. Tie -in of canopy gutters to downspouts is ongoing. South ad panel installation is ongoing. Installation of speakers/lights in ceiling tiles is nearly complete on all levels in Area 1. MEP connections of concession equipment is ongoing. Site electrical branch conduits are ongoing. Large underground Plaza conduit installation is complete. North and South scoreboards are displaying test video. Water is live on the building. Preliminary fire alarm device testing is ongoing.

Test display on South Scoreboard.

Elevators:. P1 installation is ongoing. Finishes in P2-P5 are ongoing. Painting: Area 3 – Field level paint is ongoing. Sealing of exposed concrete floors is ongoing. Terrace Bar steel installation. Building the Future


Painting of field walls is nearly complete. Painting of hollow metal doors is complete. Dryfall painting of cable tray in Supporter’s Club is ongoing. Painting of bowl is nearly complete. Tile/Carpet/Finishes: Tile installation in Main Club is ongoing. Tile in Victory Suite is ongoing. Tile in VIP Entrance is complete. Carpet on Press Level is complete. Stone top installation for Press Buffett is nearly complete. Suite countertop installation is complete. Victory Suite and Suite Club backbar installation is ongoing. Main Club buffet casework installation is ongoing.

Victory Suite backbar at Press Level.

Food Service: Installation of beer equipment is ongoing. Equipment install is ongoing in all areas. Installation of soda lines from Pepsi is ongoing. Caulking and completion of Commissary will be complete. Induction warmers installation in suites is complete. Counter top equipment (nachos, Projected Activities occurring next Week: Concrete Flatwork: Plaza flatwork will be ongoing. North side flatwork will be ongoing.

Tile at Supporter’s Club bathroom.

Stone/masonry: Stone in Plaza will be ongoing. Block in Plaza will be ongoing. Steel: Terrace Bar steel will be ongoing. Roofing and Sheet metal: Installation of metal panels at north mezz soffit will be complete. Installation of South Fins will be copmlete. Dryfall painting of Supporter’s cable tray. Building the Future


Metal Stud Framing/drywall soffits: Ceiling grid installation to be complete in Area 1. Drywall will be complete in First Aid area. Drywall will be complete in Area 3. Glass: Installation of Solar innovation sliders at back of suites on Press level will be complete. MEP: Energizing mechanical equipment for commissioning/start up will be ongoing. Installation of building network will be ongoing. Plaza electrical underground will be complete. Scoreboard/AV rack terminations will be ongoing. Coolers will be running. Test patterns will be shown on scoreboards.

Metal Panel enclosure at South Scoreboard.

Paint: Painting at Field level to be ongoing. Sealing of concrete floors to be ongoing. Painting of Supporter’s Club cable tray will be complete. Tile/Carpet/Finishes: Carpet in Press Suites will be ongoing. Carpet in Press Club will be ongoing.

South Fins and mowstrip.

Site/Playing Field/Plaza: Plaza electrical underground will be complete. Concrete stairs and retaining wall installation will be ongoing. Concrete flatwork will be ongoing.

Main Club buffet casework installation. Building the Future


Additional Photos

Painted South Mezzlocker bases.

Upper Suite Lounge buffet top installation.

Video Production equipment.

Beer system tap equipment.

Field Club buffet light fixtures.

Field Club bench seats.