LIVESTRONG Sporting Park Construction Update 4/27/11

Page 1

From:

Nick Roberts

Office: Kansas City Date:

4.27.11

Re:

Sporting Kansas City Project Update – Week of 4.27.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner

Current Activities this Week: Site/Playing field/Bowl: Seating installation is ongoing. Concrete retaining walls installation is ongoing. Concrete stair pouring and forming is ongoing. Grading of north side is nearly complete. Concrete Flatwork: East side walk pours are complete. Plaza flatwork is ongoing. VIP Entrance slab was poured. Supporter’s Club concrete staining is ongoing. Masonry: Plaza wall block is ongoing. Stone: Stone on field face of Victory Suite is complete. Cast stone installation is ongoing.

Plaza flatwork at North Breezeway.

Steel: Bowl handrail is ongoing. Concourse handrail is ongoing. Gate frame installation at Portal’s is ongoing. Terrace bar steel installation is nearly complete. Roofing and Sheet metal: Victory Suite metal panels are ongoing. Metal panels on East elevation at louver is ongoing. Metal panels on north mezz interior soffit are ongoing. Concession metal panel installation is ongoing. Installation of perforated panels are ongoing. Installation of Concourse handrails. Building the Future


Polycarbonate: Area 2- Polycarbonate installation is nearly complete. Area 3- Polycarbonate installation is ongoing. Metal Stud Framing/Drywall/Ceilings: Area 3-Drywall installation and finishing is complete. DAFS installation is nearly complete. Ceiling grid installation is ongoing in Area 3. Ceiling tile is ongoing in concessions. Glass/Doors/Hardware: Installation of Press level Solar innovation sliders is ongoing. Interview room glass will begin.

Test display on South Scoreboard.

MEP: Tie -in of canopy gutters to downspouts is nearly complete. Installation of speakers/lights in ceiling tiles is nearly complete on all levels in Area 1. MEP connections of concession equipment will be complete. Site electrical branch conduits are nearly complete. North and South scoreboards are displaying test video. Water is live on the building. Preliminary fire alarm device testing is ongoing. Elevators:. P1 installation is ongoing. Finishes in P2-P5 are ongoing.

Terrace Bar steel installation.

Painting: Area 3 – Field level paint is nearly complete. Painting of field walls is complete. Dryfall painting of cable tray in Supporter’s Club is ongoing. Painting of bowl is nearly complete. Wall coverings on Suite and Press are ongoing. Tile/Carpet/Finishes: Tile installation in Main Club is ongoing. Tile in Victory Suite is ongoing. Stone top installation for Press Buffett is complete. Victory Suite and Suite Club casework is complete.

Building the Future

Main Club backbar installation.


Main Club buffet casework installation is ongoing. Food Service: Installation of beer equipment is ongoing. Equipment install is ongoing in all areas. Installation of soda lines from Pepsi is ongoing. Caulking and completion of Commissary is complete. Induction warmers installation in suites is complete. Counter top equipment is ongoing. Nearly all coolers are operational. Projected Activities occurring next Week:

Removable seating installation.

Concrete Flatwork: Plaza flatwork will be ongoing. North side flatwork will be ongoing. North turn lane installation to begin. Stone/masonry: Stone in Plaza will be ongoing. Block in Plaza will be ongoing. Steel: Concourse handrail will be ongoing. Roofing and Sheet metal: Installation of metal panels at Victory Suite will be complete. Installation of South Fins will be copmlete.

Ceiling grid installation in Victory Suite.

Metal Stud Framing/drywall soffits: Ceiling grid installation to be complete in Area 1. Drywall will be complete in First Aid area. Drywall will be complete in Area 3. Glass: Installation of Interview Room glass will be ongoing. Ticket window glass will begin. MEP: Energizing mechanical equipment for commissioning/start up will be ongoing. Completed stone at Victory Suite. Building the Future


Installation of building network will be ongoing. Plaza electrical underground will be complete. Scoreboard/AV rack terminations will be ongoing. Coolers will be running. Test patterns will be shown on scoreboards. Health Inspections will continue. Ansul System inspections will be complete. Paint: Sealing of concrete floors to be ongoing. Wall covering in all areas will be ongoing.

Completion of South Fins.

Tile/Carpet/Finishes: Carpet in Main Club will begin. Site/Playing Field/Plaza: Plaza electrical underground will be complete. Concrete stairs and retaining wall installation will be ongoing. Tree planting will be ongoing. Concrete flatwork will be ongoing. Plaza electrical/AV panels and gear will be set. Plaza wire/cable pulls will begin.

Wall covering installation in Suites.

Completed soffits behind Press Suites. Building the Future


Additional Photos

Countertop Food Service equipment.

Top soil installation on Plaza.

VIP Entrance canopy.

Cameras will be recording next week.

Block fence post installation.

Perforated metal panels at Stair #1.