LIVESTRONG Sporting Park Construction Update - May 11, 2011

Page 1

From:

Nick Roberts

Office: Kansas City Date:

5.11.11

Re:

Sporting Kansas City Project Update – Week of 5.11.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner

Current Activities this Week: Site/Playing field/Bowl: Figureas seat installation is ongoing. France Family Drive has been paved. Drop off lane will be paved. Concrete Flatwork: Plaza flatwork is ongoing. Supporter’s Club concrete staining is complete. Plaza colored concrete will begin. Masonry: Plaza wall block is ongoing. Plaza fence installation is ongoing. Stone: Cast stone installation is ongoing. Stone at VIP entrance is complete.

Plaza transformer has been set.

Steel: Stair handrail is ongoing. North Portal steel frame is complete. Terrace bar steel installation is complete. Plaza portal steel to begin this week. Roofing and Sheet metal: Metal panels on north mezz soffit are nearly complete. Concession metal panel installation is nearly complete. Installation of perforated panels is ongoing. VIP Canopy panels will begin. Plaza Portal panels will begin. Accelerator gate panels are ongoing.

Building the Future

Stained concrete in Supporter’s Club.


Polycarbonate: North polycarbonate is ongoing. Metal Stud Framing/Drywall/Ceilings: DAFS installation will be complete. Ceiling grid installation is nearly complete. Framing at North Portal will be complete. Terrace bar waterproofing is complete.

Pepsi equipment installation.

Glass/Doors/Hardware: Installation of Press level Solar Innovation sliders is nearly complete. Glass handrail is ongoing. MEP: Site electrical branch conduits are complete. North and South scoreboard testing is ongoing. Preliminary fire alarm device testing is ongoing. TV installation is ongoing. Buffet/bar MEP is ongoing. Concession menu board installation will be complete. Elevators: P1 installation is ongoing. Finishes in P2-P5 are ongoing.

Nearly completed Field Club.

Painting: Wall coverings on Suite and Press are complete. Field Club wall coverings are complete Painting of Concourse columns will begin Tile/Carpet/Finishes: Tile in Victory Suite is complete. Victory Suite bar tops are ongoing. Main Club bar casework installation is ongoing. Food Service: Installation of beer equipment is nearly complete. Equipment install is nearly complete in all areas. Installation of soda lines from Pepsi is complete. Counter top equipment is ongoing.

Building the Future

Plants in the Plaza.


Nearly all coolers are operational. Final Health Inspection to be complete. Pepsi cooler installation is ongoing. Equipment startup will begin. Signage: Concession signage installation will begin. VIP Entrance “Sporting Club� sign is complete. Directory signage throughout is ongoing. Directory signage installation. Projected Activities occurring next Week: Concrete Flatwork: Plaza flatwork will be nearly complete. North side flatwork will be complete. Stone/masonry: Stone in Plaza will be ongoing. Block in Plaza will be ongoing. Steel: Concourse handrail will be ongoing. South Plaza portal steel will be ongoing. Roofing and Sheet metal: Installation of perforated panels will be ongoing. Plaza Portal metal panels will be ongoing. Accelerator gate panels will be complete.

Laundry equipment installation.

Metal Stud Framing/drywall soffits: Accelerator gate framing to be complete. Plaza Portal framing will be complete. Glass: Press Level sliders will be complete. Glass handrail will be ongoing. MEP: Energizing mechanical equipment for commissioning/start up will be ongoing. Owner training will be ongoing. TV installation will be ongoing.

Building the Future

Completed Executive Suite.


Paint: Wall covering in West side will be complete. Painting of Concourse Columns will be ongoing. Tile/Carpet/Finishes: Supporter’s Club tile and bar tops will be complete. Site/Playing Field/Plaza: Plaza electrical underground will be complete. Concrete stairs and retaining wall installation will be complete. Tree planting will be ongoing. Concrete flatwork will be ongoing. Plaza wire/cable terminations will begin. Light poles will be ongoing.

Supporter’s Club tile installation.

Accelerator gate panel installation.

Completed Press Level Suite. Building the Future


Additional Photos

Light pole installation on the Plaza.

Completed concession area.

Sneezeguard installation in Press Buffet.

Shield Club buffet and carpet installation.

TV network is online.

Exec Chef enjoying the completed kitchen.