LIVESTRONG Sporting Park Construction Update - May 18, 2011

Page 1

From:

Nick Roberts

Office: Kansas City Date:

5.18.11

Re:

Sporting Kansas City Project Update – Week of 5.18.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner

Current Activities this Week: Site/Playing field/Bowl: Figureas seat installation is ongoing. Drop off lane has been paved. Goal post installation is ongoing. Plaza landscaping is ongoing. Concrete Flatwork: Plaza flatwork is ongoing. Plaza colored concrete is complete. Masonry: Plaza wall block is ongoing. Plaza fence installation is ongoing. Stone: Cast stone installation is ongoing.

Colored concrete in Plaza.

Steel: Stair handrail is ongoing. Plaza portal steel is complete. Roofing and Sheet metal: Metal panels on north mezz soffit are nearly complete. Installation of perforated panels is nearly complete. VIP Canopy panels will be complete. Plaza Portal panels will begin. Accelerator gate panels are ongoing.

Polycarbonate: North polycarbonate is ongoing. Ceiling covering in Victory Suite. Building the Future


Metal Stud Framing/Drywall/Ceilings: DAFS installation will be complete. Ceiling grid installation is nearly complete. Framing at North Portal will be complete. Terrace bar waterproofing is complete. Glass/Doors/Hardware: Installation of Press level Solar Innovation sliders is nearly complete. Glass handrail is ongoing.

Nearly completed Shield Club.

MEP: Site North and South scoreboard testing is ongoing. Fire Alarm testing is nearly complete. TV installation is ongoing. Buffet/bar MEP is nearly complete. Prozone camera installation will begin. DAS installation is ongoing. BPU will energize Plaza transformer. Plaza light pole installation will be complete. Hydroworx pools are filled. Elevators: P1 finishes are ongoing. Finishes in P2-P5 are complete. Painting: Wall coverings are nearly complete in Owner’s Suite. Field Club wall coverings are complete. Painting of Concourse columns will be ongoing. Painting of Stair #6 is ongoing.

Finished landscape in the Plaza.

Tile/Carpet/Finishes: Victory Suite bar tops are complete. Main Club bar installation is complete. Food Service: Installation of beer equipment is nearly complete. Equipment install will be complete. Counter top equipment is ongoing. Pepsi cooler installation is ongoing. Soda gun installation is ongoing. Metallic wall covering in Victory Suite. Building the Future


Equipment startup will begin. Signage: Concession signage installation will be complete. Northeast gate exit signs are complete. Directory signage throughout is ongoing. Ad panels are ongoing. Projected Activities occurring next Week:

Fire burning in Victory Suite Pizza Oven.

Concrete Flatwork: Plaza flatwork will be nearly complete. North side flatwork will be complete. Stone/masonry: Stone in Plaza will be complete. Block in Plaza will be ongoing. Steel: Concourse handrail will be complete. Roofing and Sheet metal: Installation of perforated panels will be complete. Plaza Portal metal panels will be ongoing. Metal Stud Framing/drywall soffits: Plaza Portal framing will be complete. DAFS at Supporter’s Club entry to be complete.

Large wine cooler in Victory Suite.

Glass: Press Level sliders will be complete. Glass handrail will be ongoing. MEP: Energizing mechanical equipment for commissioning/start up will be ongoing. Owner training will be ongoing. TV installation will be ongoing.

Paint: Painting of Concourse Columns will be ongoing. Wall covering in Supporter’s Club. Building the Future


Tile/Carpet/Finishes: Nearly all finishes will be complete. Site/Playing Field/Plaza: Tree planting will be complete. Concrete flatwork will be ongoing. Plaza wire/cable terminations will be complete. Light poles will be energized. Speaker/device installation will be ongoing.

Panel installation at VIP Entrance.

Furniture install at Party Suite.

TV/Speaker installation at Supporter’s Club. Building the Future


Additional Photos

Field ready for evening practice.

Bar light fixtures at Victory Suite.

Team Bench seat installation.

Filled Hydrotherapy pools.

Completed Therapy Room.

Hard work paying off.

Building the Future