LIVESTRONG Sporting Park Construction Update - May 4th, 2011

Page 1

From:

Nick Roberts

Office: Kansas City Date:

5.4.11

Re:

Sporting Kansas City Project Update – Week of 5.4.2011

To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner Nick Durand - Turner

Current Activities this Week: Site/Playing field/Bowl: Seating installation is nearly complete. Figureas seat installation is ongoing. Concrete stair pouring and forming is ongoing. Grading of north side is complete. Concrete Flatwork: Plaza flatwork is ongoing. Supporter’s Club concrete staining is ongoing. North drop off lane will be poured. Masonry: Plaza wall block is ongoing. Plaza fence installation is ongoing. Stone: Cast stone installation is ongoing. Stone at VIP entrance is nearly complete.

Tree installation at Plaza.

Steel: Concourse handrail is nearly complete. Concourse handrail is ongoing. Gate frame installation at Portal’s is ongoing. Terrace bar steel installation is complete. Plaza portal steel to begin this week. Roofing and Sheet metal: Victory Suite metal panels are complete. Metal panels on north mezz soffit are nearly complete. Concession metal panel installation is nearly complete. Installation of perforated panels is ongoing.

Building the Future

Café rail at Plaza.


Polycarbonate: North polycarbonate is ongoing. Metal Stud Framing/Drywall/Ceilings: DAFS installation will be complete. Ceiling grid installation is ongoing in Area 3. Framing at accelerator gate is ongoing. Terrace bar waterproofing is ongoing. Glass/Doors/Hardware: Installation of Press level Solar Innovation sliders is nearly complete Interview room glass has been installed. Glass handrail is ongoing. Guest Services glass is complete.

Cloud installation at Main Club.

MEP: Installation of speakers/lights in ceiling tiles on East Field Level is ongoing. Site electrical branch conduits are nearly complete. North and South scoreboards are displaying test video. Preliminary fire alarm device testing is ongoing. Ansul Testing with Fire Marshall is complete. TV installation is ongoing. Elevators: P1 installation is ongoing. Finishes in P2-P5 are ongoing.

Terrace Bar waterproofing.

Painting: Area 3 – Field level paint is nearly complete. Dryfall painting of cable tray in Supporter’s Club is complete. Wall coverings on Suite and Press are nearly complete. VIP Canopy steel has been painted. Tile/Carpet/Finishes: Tile installation in Main Club is complete. Tile in Victory Suite is nearly complete. Victory Suite bar tops are ongoing. Main Club bar casework installation is ongoing. Main Club casework installation.

Building the Future


Food Service: Installation of beer equipment is ongoing. Equipment install is nearly complete in all areas. Installation of soda lines from Pepsi is complete. Counter top equipment is ongoing. Nearly all coolers are operational. Final Health Inspection to be complete. Equipment startup will begin. Signage: Concourse restroom signage is complete.

Glass rail at West Balcony.

Projected Activities occurring next Week: Concrete Flatwork: Plaza flatwork will be ongoing. North side flatwork will be ongoing. North drop off lane to be complete. Stone/masonry: Stone in Plaza will be ongoing. Block in Plaza will be ongoing. Steel: Concourse handrail will be ongoing. Plaza portal steel will be ongoing.

Concourse bathroom signage.

Roofing and Sheet metal: Installation of perforated panels will be ongoing. North mezz metal panels will be complete. Concession metal panels will be complete. Metal Stud Framing/drywall soffits: Waterproofing will be complete at Terrace Bar. Accelerator gate framing to be complete. Glass: Installation of Interview Room glass will be ongoing. Ticket window glass will begin. Glass handrail will be ongoing. Figureas seat installation. Building the Future


MEP: Energizing mechanical equipment for commissioning/start up will be ongoing. Installation of building network will be ongoing. Scoreboard/AV rack terminations will be complete. TV installation will be ongoing. Paint: Wall covering in all areas will be ongoing. East Field Level paint will be ongoing.

Suite sink installation.

Tile/Carpet/Finishes: Carpet in Main Club will begin. Site/Playing Field/Plaza: Plaza electrical underground will be complete. Concrete stairs and retaining wall installation will be ongoing. Tree planting will be ongoing. Concrete flatwork will be ongoing. Plaza electrical/AV panels and gear will be set. Plaza wire/cable pulls will begin. Light poles will begin to be set. Video Production camera equipment.

D6 fixtures in Executive Suites.

Building the Future


Additional Photos

Black ceiling tile in Field Club.

Suite Club bar equipment installation.

Athletic flooring and carpet installation.

Plaza electrical gear installation.

North drop off lane installation.