Third Year Construction Portfolio

Page 1

CONSTRUCTION PORTFOLIO

2192396 2021


TABLE OF CONTENTS Project 2 - Sustainability Project 3 - Precedent Study Tutorial 1 - Brief Analysis Project 4 - Core Concept Project 5 - Core Detail Project 6 - Structural Model Project 7 - Original Working Drawings Project 7 - Final Rework Working Drawings Tutorial 2 - Amazing Race Schedule


PROJECT 2 - Sustainability


Applied Strategies:

Materiality and Climatic response: Responding to local context and using local materials for building construction.

Breeze blocks / clere story openings

Warm air escape

1:00 PM

Cool air

7:26 PM

W

N

General Notes: 6:42 AM

S

E

Prevailing Wind

Sun Path (Summer Solstice)

Using tree to protect from harsh eastern/western sun (reduce heat gain)

1:00 PM

W

Average Temperatures in Baghere (2020)

N

Offices

6:38 PM

Baghere has a hot and humid climate. Due to its location near the equator the sun is more concentrated throughout the year. The graph above shows the average temperature in 2020. - All materials are sourced locally.

S

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

21 June

E

7:23 AM

21 December

Sun Path (Winter Solstice)

Sun Path throughout whole year

Overhangs according to sun angles

Covered Roof Construction: - Rope - 80mm rafters - 228mm x 114mm SAP beam - 4x 80mm bamboo columns

High thermal mass to store heat in winter. Ventilation will help remove heat in the summer

Gather Space

Cross Ventilation

Power Generation: Solar Panels/wind turbines

Bamboo screen Reducing heat gain

Joinery:

Gather Space roof construction: - 200mm Thatch - 30mm purlins - 80mm rafters - Gutter - 80mm bamboo downpipe - Rope

Bamboo Joinery:

Drainage Notes:

Eave Detail Bamboo screen Joinery: construction(Gather space): - 30mm screen members - 80mm supporting members - 2x 80mm bamboo columns Built up earth(adobe) : 1. sifted sand 2. clay 3. cow manure 4. sifted straw

Bamboo column construction: - 4x 80mm bamboo members

Sandbag Wall construction: - 200mm x 400mm sandbags - Excavated sand placed into bags. - Sandbag is made of burlap or woven polypropylene. - The wall will also provide a high thermal mass. - Sandbag walls will be plastered with mud (Adobe) on theoutside and inside for longer durability. - Earthen floor, built up earth floor serves as the foundation of the building. The raised height also allows for better ventilation.

Building Life Cycle: - Extraction of raw materials > Manufacturing > Contruction > Operation and maintenance > Demolition. Life cycle assessment of the building: - Is 50 years as it can be classified as a small commercial building. This is also depending on the type of materials used and climatic conditions.

Structural Axonemetric Recycle Building material: SANDBAGS: - Sand within bag can be put back into the earth. - Woven sandbag material can be recycled. - Life span of 25 years

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Bamboo screen (office spaces): Screen components: 1. 200mm Thatch 2. ⌀30mm Bamboo screen 3. 400mm x 200mm Sandbag walls 4. ⌀80 mm Bamboo rafter 5. Earth floor

1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Client Information:

University of the Witwatersrand Project Information: ARPL 3031A 2021 - Project 2 Revision Details: REV:NO

DESCRIPTION

Drawing Details: DRAWN BY:

DRAWING SCALE:

2192396

1:300

DRAWING NUMBER:

THATCH - Thatch, if properly maintained can be used for other building projects. - Thatch can be converted into compost. - 20 to 40 years lifespan

BAMBOO: - Bamboo, if in a good condition can be used for other building projects. - Bamboo can also be converted into compost. - 15 to 70 years lifespan

DATE ISSUED

DATE:

PR02-AB

2021/03/20

DRAWING NAME:

REVISION NUMBER:

Sustainability 3 Project - 2 SHEET 1 OF 4


Power supply and Usage: How much Electricity is needed ? Electricity will be needed in light fixtures if people want to work at night. Electricity can be sent back into the grid and power nearby buildings.

Using the sun and wind to produce electricity and implementing sustainable ways of energy reduction.

Average wind speed in Bahgere (2020)

Average sun days in Bahgere (2020)

Strategies applied to design: 1. Monocrystalline solar panel placed on the covered walkway to generate electricity. 2. Building entirely off the grid. 3. Generating power to feed back into the grid. 4. Using energy efficinent fixtures to reduce the amount of energy used within the building. How much Electricity will be produced ? 1. 550wh per week per solar panel times 20 = 11000wh per month, also depending on the amount of sun exerienced daily. 2. 44000wh for 20 solar panels - 44 kilowatt hours per month. 3. At 33% capacity a standard wind turbine will produce 1.67 mw = for 12 wind turbines it is 20.04 mw.

Electrical efficient components/fixtures: Light Bulbs: Warm White E27 5W Opal Golfball LED is a energy efficient light bulb from Eurolux. DC to AC inverter and Electrical Storage: The solar edge inverter is able to convert DC to AC power and in partnership with Tesla, the device is able to store electricity.

Primus Air 30 400W Wind turbine: The wind turbine, which is built into the screen of the gathering space will help the solar panels to produce electricity. For self sustaining use and to supply power to the main power grid.

General Notes:

Electrical power diagram:

Light switch

Solar Power components: 1. Solar racking 2. Monocrystalline solar panel for maximum power generation efficiency. 3. Conduit (DC Current) 4. Solar inverter and electrical storage. 5. DB board (Distribution) 6. Light fitting

Solar power generation according to sun angles indicates the solar power generation in the winter will be the most efficient.

S

As the diagram indicates, the solar panel will not be as efficient in summer. An alternative to this is an adjustable solar panel that can ensure it is efficient througout the entire year.

Light fixture Wiring

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Drainage Notes: 1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Client Information: DB board

7. Electrical meter

Inverter/battery

Electrical layout in reception and office space

Solar panels placed according to sun angles

8. Municipal meter and billing, sending power back into the grid

Solar Power Supply Axonemetric

University of the Witwatersrand Project Information: ARPL 3031A 2021 - Project 2 Revision Details:

Wind Power components: 1. Wind turbine 2. Conduit placed within bamboo members 3. DC Current will go to Inverter

REV:NO

DESCRIPTION

DATE ISSUED

Light fittings

Drawing Details: Wire

DRAWN BY:

DRAWING SCALE:

2192396

1:125 / 1:250

DRAWING NUMBER:

Power Supply Axonemetric

Wind Power Supply Axonemetric

Wind power operation diagram

DATE:

PR02-AB

2021/03/20

DRAWING NAME:

REVISION NUMBER:

Sustainability 3 Project - 2 SHEET 2 OF 4


Water supply and Usage: Using the gather space roof to capture rainwater to use for irrigation and filtered for potable water.

Average rainfall in Baghere (2020) How much water will be needed ? The amount of water needed depends on the users needs. Water will be supplied to the community with a water tank in the middle of the gather space. Water will then flow into the surface reserviour for drip irrigation use. A second water tank will be placed at the office spaces, this will supply the toilets and basins with water.

Water efficient fixtures: Strategies applied to design: 1. Using roof of gather space roof to collect rainwater. 2. Additionally using a portion of a roof to collect water for fixtures in the bathroom. 3. Water storage tanks to store water throughout the year. 4. Using water saving fixtures to reduce water usage.

How much water will be havested and stored ? - If 1mm of water falls one square meter of roof it is equal to 1 litre of water. - Total roof area is 60m2 = a total of 60 litres can be collected by the roof. - In August 2020 it rained 900mm this will equal 900 litres harvested water for that month. - Rain water collected by the gather space will be mainly used for irrigation purposes. - Rainwater collected on the office spaces will be used for fixtures. Water will be filtered before entering basin fixture.

1. Toilet: Natures Head Dry Composting Toilet: -This toilet seperates the solids from the liquids. And it can be easily removed and used as fertilization (composting) for plantations. -Does not need a water supply connection.

4. 1.

General Notes:

2. Basin Tap: -Hansgrohe Ecosmart basin tap, reduces water usage by 5 litres per minutre and will be fixed to every basin.

3. Storage Tank: -1500 liter JoJo storage tank to capture rain water. Before water can be collected it will move through a filtration system to make it potable.

3.

2.

5.

4. Drip Irrigation: -Drip irrigation is more efficient than traditional sprinkler systems and will use less water

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

5. Sub surface drip emmiters: -Rain bird tubing Sub surface emmiters will distribute the grey water into soil.

Natures head Dry composting toilet

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

Rain

Thatch roof at 45°

Drainage Notes: 1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Gutter

Thatch roof at 45°

Bamboo Downpipe

Basin Gutter Water tank, water will be filtered before entering basin (1500 litre) JoJo water tank ⌀50 mm PVC supply water pipe ⌀50mm PVC waste water pipe Sub Surface Emmiter

Sub-surface reservoir

Sub surface channel

Client Information: Water harvest diagram

Pipe connecting water tank and sub-surface reservoir

University of the Witwatersrand

Water Tank

Drip irrigation supply pipe

Project Information: ARPL 3031A 2021 - Project 2 Revision Details:

Thatch roof at 45 degree pitch

Water supply system in bathrooms

REV:NO

DESCRIPTION

DATE ISSUED

Bamboo Gutter ⌀30mm Bamboo Downpipe Channel

1500 litre water tank

Surface reservoir

Water Supply Axonemetric

Detailed Water Supply Axonemetric

Drawing Details: DRAWN BY:

DRAWING SCALE:

2192396

1:150

DRAWING NUMBER:

PR02-AB Drip irrigation pipe lines, running over plantDRAWING NAME: roots

DATE:

2021/03/20 REVISION NUMBER:

Sustainability 3 Project - 2 SHEET 3 OF 4


Economical and Social impact: Using the extents of the site to attract people of the Baghere village to ensure people engage with social ineractions and produce a socialy and economic sustainable future. Strategies applied to the design: 1. Creating an inclusive community where people can engage in social interaction. In the form of formal and informal trading. 2. Locals will be able to produce crops and manufacture produce and sell them and to make a profit. 3. The gather space will be used as a social hub where women can speak publically. 4. Office spaces in the inside of the building is a mulituse area, for education and more private meetings. 5. The open coutyard adjacent to the office space can be used for dancing or social gatherings.

The contextual map on the right shows the surrounding context. The Womans House aims to be a central trading hub for the community. As can be seen in the drawing many roadnetworks intersect the site, making it easy for people to travel to the Womans House.

Dancing space: The open courtyard in the office spaces serves as a large area where people can dance.

General Notes: N Sustainable cycle

Contextual Map of the Baghere village Plantations: - Peanuts for food - Cotton for clothing - Corn for food - Rice for food

Quiet resting area: - Intended space for people to rest. - Using tree canopy as shade. - Oppertunity to socialize with others. - Space of engagement. - Away from the busy street.

Processing: - Cleaning and manufacturing of produce. - Can use this as an oppertunity to learn others. - Engagement in processing of goods. - Learning of new skills - Processing can lead to profit

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Drainage Notes: Gather space: - Public meetings - Educational classes and public meetings.

1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Client Information:

University of the Witwatersrand

Offices: - Woman held private political meetings. - Educational rooms for teaching purposes.

Project Information: ARPL 3031A 2021 - Project 2 Revision Details: REV:NO

Main road

Construction: - Learning of new skills on how to build. - How to work with materials

Distribution of economic and social activities

DESCRIPTION

DATE ISSUED

Trading: - Formal and informal Selling of products in marketplace. - Marketplace opens up to the street. Making it easier for traders to sell products.

Drawing Details: DRAWN BY:

DRAWING SCALE:

2192396

1:300

DRAWING NUMBER:

DATE:

PR02-AB

2021/03/20

DRAWING NAME:

REVISION NUMBER:

Sustainability 3 Project - 2 SHEET 4 OF 4


A R C H I T E C T U R A L

D E S I G N

A N D

T H E O R Y

( A R P L 3 0 0 5 A )

P R O J E C T

1

-

W O M E N ' S

G R O U P

H O U S E

1 A

PAGE 1

KENDALL GOW - 1844024

STEFAN VAN HEERDEN - 2192396

ANA DAMJANOVIC - 2070688

JASON VAN STADEN - 1883906


GROUND FLOOR PLAN ON SITE MATERIAL PALLETTE

ADOBE CLADDING

EARTHBAGS

BAMBOO

TYPHA THATCH

SCALE 1:500

PROPERTIES OF CHOSEN MATERIALS

-

HIGH THERMAL MASS SOURCED LOCALLY READILY AVAILABLE NATURALLY OCCURRING AFFORDABLE SIMPLE CONSTRUCTION TECHNIQUES LOCALLY PRACTICED CONSTRUCTION TECHNIQUES

SECTION AA

SCALE 1:200

PAGE 4


AXONOMETRIC VIEW SHOWING STRUCTURE OF BUILDING SCALE 1:500

EXTERNAL CIRCULATION SPACE

3D OF BUILDING WITH CALL OUT BUBBLES TO EXPLAIN NB ELEMENTS AMPHITHEATRE

SECTION BB

SCALE 1:200

PAGE 5


VIEW FROM QUIET SPACE

INTERIOR MEETING SPACE

WEST ELEVATION

SCALE 1:200

EXTERIOR VIEW FROM PLANTATION

PAGE 6


CONCEPT CHRONOLOGY THE MARKET SPACE

EAST ELEVATION

SCALE 1:200

PAGE 1

PAGE 3


PROJECT 3 - Precedent Study


Structure and Structural Grid:

Drawing Details

References: ArchDaily.com, (2021) 78 Corlett Drive Building / Daffonchio and Associates. [online] Available at: https://www.archdaily. com/919164/78-corlett-drive-building-daffonchio-and-associates [Accessed 13 April 2021]

Zoning Information: Erf:

143

Township:

Melrose North

Property Owner

Legaro Properties Fund PTY LTD

Drawn By:

Drawing scale:

Group 2

NTS

Drawing Number:

Date:

PR03 - AC

13/04/2021

Drawing Name:

Revision:

Project 3 Building analysis

0 Sheet:

1 of 5


Building Core:

Drawing Details Drawn By:

Drawing scale:

Group 2

NTS

Drawing Number:

Date:

PR03 - AC

13/04/2021

Drawing Name:

Revision:

Project 3 Building analysis

0 Sheet:

2 of 5



Arrival and Circulation:

Drawing Details

References: ArchDaily.com, (2021) 78 Corlett Drive Building / Daffonchio and Associates. [online] Available at: https://www.archdaily. com/919164/78-corlett-drive-building-daffonchio-and-associates [Accessed 13 April 2021]

Drawn By:

Drawing scale:

Group 2

NTS

Drawing Number:

Date:

PR03 - AC

13/04/2021

Drawing Name:

Revision:

Project 3 Building analysis

0 Sheet:

4 of 5


Approach to Sustainability:

References: ArchDaily.com, (2021) 78 Corlett Drive Building / Daffonchio and Associates. [online] Available at: https://www.archdaily. com/919164/78-corlett-drive-building-daffonchio-and-associates [Accessed 13 April 2021]

The 78 Corlett Drive building is the only office development in Africa to achieve a 6 star energy efficiency rating and net zero carbon emmision accreditation.

Green star criteria:

Chiller tank Water pipes

6 - Star Rating Weigted score between 75 and 100

Remaining water flows into service core.

inception to closeout.

2. Indoor Environment Quality (IEQ):

Chiller system:

summer spring solstice equinox

winter solstice

Sun Angles Solar panels Atrium

N

Callout detail

1. Management: - Sustainable design intent from the

Photo Voltaic Array:

Atrium

Third Floor Roof Second Floor

Building setback

Site Plan:

First Floor

- Considerations in heating, cooling, lighting and indoor air pollutants.

Ground Floor

3. Energy: - Using pv array to power the building.

Fixed North facing Aluminium Louvers: summer solstice

4. Transport: - Accomodating alternative modes of transport.

spring equinox winter solstice

5. Water: - Using water efficient fixtures, leak detection system. (Low flow fittings)

6. Materials: - Reduction in the amount of natural materials used.

7. Land Use & Ecology:

S

E

- Reducing the impact of the building on the natrual ecology.

8. Emissions: - No substances or pollution are emitted from the site.

N

Callout detail

Moveable Horizontal Screens on west and east facade:

Sustainability Axo

N

Manufacture process

Louver assembly

Air cavity

9. Innovation:

Moveable aluminium screen

- Innovative shading system(passive) and airconditioning system(mechanical) installed.

Drawing Details

Tinted Single Glazing

10. Socio Economic: - Improving the socio economic aspects of the context by making the part of the building leasable for outside tenants.

W

East elevation

Callout detail

Moveable screen assembly

Drawn By:

Drawing scale:

Group 2

NTS

Drawing Number:

Date:

PR03 - AC

13/04/2021

Drawing Name:

Revision:

Project 3 Building analysis

0 Sheet:

5 of 5


Disabled

Public / Private

Access/ Circulation Requirements

Structural Requirements

Volumetric Requirements

Ventilation Requirements

Lighting Requirements

Other Services Required

Sustainability Required

1

Public

None (Ground Floor)

Long Span

Cathedral

Natural and Mechanical

Artifical and Natural

Circulation, Electrical, Storm Water, Fire Protection, HVAC, Lightening Protection, Alternate Modes of Transport

Shading Devices, Double Glazing , Thermal Insulation,Green Wall, Solar Panels

2

Public

None(Ground Floor)

Long Span

General Height

Natural and Mechanical

Artifical and Natural

Circulation, Electrical, Water, Fire Protection, HVAC, Storage

Shading Devices, Double Glazing , Thermal Insulation,Adjustable Screen, Natural Ventilation

7

7

Public

Stairs and Ramps

Long Span

Cathedral

Mechanical

Artifical

Circulation, Electrical, Fire Protection, Storage , HVAC

Thermal Insulation

6

4

5

Public

Stairs, Ramps, Elevator

Short Span

Cathedral

Natural and Mechanical

Artifical or Natural

Circulation, Electrical, Fire Protection, Storage , HVAC

Shading Devices, Double Glazing, Thermal Insulation , Natural Ventilation

3

2

3

Public

None(Ground Floor)

Short Span

Cathedral or General Height

Natural and Mechanical

Artifical and Natural

Circulation, Electrical, Fire Protection, HVAC,Water,Drainage,Gas,Refuse

Shading Devices, Double Glazing, Thermal Insulation , Natural Ventilation,Green Wall

7

10 15

8

10

Public

Stairs, Ramps, Elevator

Long Span

Cathedral

Natural and Mechanical

Artifical and Natural

Circulation,Electrical,Fire Protection,HVAC,Storage, Water

Shading Devices, Double Glazing, Thermal Insulation , Natural Ventilation,Adjustable Screen

1

1

2

2

1

2

Public

Stairs, Ramps, Elevator

Long Span

Cathedral

Natural and Mechanical

Artifical and Natural Circulation, Electrical,Fire Protection,Storage

Shading Devices, Double Glazing, Thermal Insulation , Natural Ventilation,Adjustable Screen

1

1

1

2

2

1

2

Public

None(Ground Floor)

Long Span

General Height

Natural and Mechanical

Artifical and Natural

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing, Thermal Insulation , Natural Ventilation

15

1

1

1

2

2

1

2

Semi Private

Stairs, Ramps, Elevator

Short Span

General Height

Mechanical

Artificial

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing , Artificial Ventililation,Thermal Insulation

40

40

2

3

3

3

4

3

4

Semi Private

Stairs, Ramps, Elevator

Short Span

General Height

Mechanical

Artificial

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing , Artificial Ventililation,Thermal Insulation

A3

100 50

50

2

3

3

3

4

3

4

Semi Private

Stairs, Ramps, Elevator

Short Span

General Height

Natural and Mechanical

Artifical and Natural

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing ,Thermal Insulation

100

A3

60

30

1

2

2

3

3

2

3

Semi Private

Stairs, Ramps, Elevator

Short Span

General Height

Natural and Mechanical

Artifical and Natural

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing ,Thermal Insulation

2x Large Dance Studios

200

A2

200 100 100 4

8

6

6 12

6

6

Semi Private

Stairs, Ramps, Elevator

Short Span

Cathedral

Natural and Mechanical

Artificial

Circulation, Electrical,Fire Protection, HVAC, Storage,Water

Shading Devices, Double Glazing ,Thermal Insulation

2x Dance Studios

100

A2

100 50

2

3

3

3

4

3

4

Semi Private

Stairs, Ramps, Elevator

Short Span

Cathedral

Natural and Mechanical

Artificial

Circulation, Electrical,Fire Protection, HVAC, Storage,Water

Shading Devices, Double Glazing ,Thermal Insulation

2x Large Theatre Practice 200 Rooms

A2

200 100 100 4

8

6

6 12

6

6

Semi Private

Stairs, Ramps, Elevator

Short Span

Cathedral

Mechanical

Artificial

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing ,Thermal Insulation

100 50

Ablution Requirements

A1

300 150 150 5 10

7

10 15

8

10

Public Reading Area/ Lounge Area

100

A3

20

1

1

1

2

2

1

Auditorium

300

A1

250 125 125 5

9

6

7 14

Lobby Space

120

A1

120 60

60

3

4

4

5

Resturant/ Coffee Shop

200

B3

60

30

1

2

2

3

Multi-purpose Gathering Space

300

A1

300 150 150 5 10

Exhibition Space

300

C1

30

15

15

1

Public Desk

24

A1

24

12

12

Large Computer Lab

150

A3

30

15

4x Computer Labs

400

A3

80

2x Large Seminar Rooms

150

4x Seminar Rooms

Male

300

10

30

30

Female

Public Forecourt / Reception / Enterance Foyer

Population

Classification

Female

Floor Area (sqm)

Male

Space

Floor

Design Population

10

50

W SH W WH SH W UR HB R C B R C

50

2

3

3

3

4

3

4

Semi Private

Stairs, Ramps, Elevator

Short Span

Cathedral

Mechanical

Artificial

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing ,Thermal Insulation

1

1

1

1

1

1

1

1

1

Private

Stairs, Ramps, Elevator

Short Span

General Height

Natural and Mechanical

Artifical and Natural

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing , Thermal Insulation, Natural Ventilation

1

1

1

1

1

1

1

1

1

1

Private

Stairs, Ramps, Elevator

Short Span

General Height

Natural and Mechanical

Artifical and Natural

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing , Thermal Insulation, Natural Ventilation

G1

4

2

2

1

1

1

1

1

1

1

Private

Stairs, Ramps, Elevator

Short Span

General Height

Natural and Mechanical

Artifical and Natural

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing , Thermal Insulation, Natural Ventilation

250

G1

10

5

5

1

1

1

1

1

1

1

Private

Stairs, Ramps, Elevator

Short Span

General Height

Natural and Mechanical

Artifical and Natural

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing , Thermal Insulation, Natural Ventilation

Reception Desk and Waiting Area

24

A1

24

12

12

1

1

1

2

2

1

2

Public

Stairs, Ramps, Elevator

Short Span

Cathedral/General Height

Natural and Mechanical

Artifical and Natural

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing , Thermal Insulation, Natural Ventilation

Kitchenette/ Staff Room

20

A1

20

10

10

1

1

1

2

2

1

2

Private

Stairs, Ramps, Elevator

Short Span

General Height

Natural and/or Mechanical Artifical and Natural

Circulation, Electrical,Fire Protection, HVAC, Storage,Water, Drainage,Gas

Double Glazing, Thermal Insulation, Thermal Insulation, Natural Ventilation

Boardroom

40

G1

3

2

2

1

1

1

1

1

1

1

Private

Stairs, Ramps, Elevator

Short Span

General Height

Natural and/or Mechanical

Artifical or Natural

Circulation, Electrical,Fire Protection, HVAC, Storage

Shading Devices, Double Glazing , Thermal Insulation, Natural Ventilation

Retail

200

B3

13

7

7

1

1

1

1

1

1

1

Public

Stairs, Ramps, Elevator

Short Span

Cathedral

Natural and/or Mechanical

Artifical or Natural

Circulation, Electrical,Fire Protection, HVAC, Storage,Water,Drainage,Gas,Refuse

Shading Devices, Double Glazing , Thermal Insulation, Natural/Mechanical Ventilation

Lettable Offices

500

G1

33

17

17

1

1

1

2

2

1

2

Private

Stairs, Ramps, Elevator

Short Span

General Height

Natural and Mechanical

Artifical and Natural

Shading Devices, Double Glazing , Thermal Insulation, Natural Ventilation

Air Conditioning Plant

50

D4

0

0

0

0

0

0

0

0

0

0

Private

Stairs

Short Span

Dungeon

Mechanical

Artificial

Circulation, Electrical,Fire Protection, HVAC, Storage Circulation,Electrical,Fire Protection,HVAC, Storage

Server Room

15

D4

0

0

0

0

0

0

0

0

0

0

Private

Stairs

Short Span

Dungeon

Mechanical

Artificial

Circulation,Electrical,Fire Protection,HVAC, Storage

IT Maintenance

40

D4

0

0

0

0

0

0

0

0

0

0

Private

Stairs

Short Span

Dungeon

Mechanical

Artificial

Circulation,Electrical,Fire Protection,HVAC, Storage

2x Store Rooms

80

J3

2

1

1

1

1

1

1

1

1

1

Private

Stairs

Short Span

General Height

Mechanical

Artificial

Circulation,Electrical,Fire Protection,HVAC, Storage

Security Control

25

G1

2

1

1

1

1

1

1

1

1

1

Private

Stairs

Short Span

General Height

Natural and/or Mechanical

Artificial

Circulation,Electrical,Fire Protection,HVAC, Storage

Recycling

40

D3

3

2

2

1

1

1

1

1

1

1

Semi Private

Stairs

Short Span

Mechanical

Artificial

Semi Public

Stairs, Ramps, Elevator

Long Span

Dungeon

Mechanical

Artificial

Circulation,Electrical,Fire Protection,HVAC, Storage,Storm Water

Public

Stairs, Ramps, Elevator

Short Span

General Height

Natural and/or Mechanical

Artifical and/or Natural

Circulation,Electrical,Fire Protection,HVAC, Storage,Water,Drainage

2x Theatre Rooms

100

A2

Head of Department

24

G1

2

Finance Manager

20

G1

4x Admin Staff Offices

60

10x Lecture Offices

Basement Parking Ablutions

J4

CLIENT INFORMATION: University of Witwaterstrand PROJECT INFORMATION ARPL 3031A 2021-Tutorial 1

Shading Devices, Double Glazing , Thermal Insulation, Natural Ventilation

Thermal Insulation, Natural/Artificial Ventilation

DRAWING DETAILS DRAWN BY: GROUP 2 DRAWING NUMBER: TUT 01-AA DRAWING NAME Tutorial 1 DRAWING SCALE N.T.S. DATE 2021/05/05


PROJECT 4 - Core Concept


Entrance Lobby and main circulation Service Staircase Core core

Project 4 - Core Concept Arrival and Circulation

Ablutions General Notes: 1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

S ta t

io n S

tree

Ve

hic

ul a

c rA

ce

ss

d Pe

es

n t r ia

A

e cc

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

ss

Drainage Notes:

Staircase core from basement level -3 up to fifth floor

t

Building mass Jo

se rri

nS

e tre

t

1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Client Information:

University of the Witwatersrand Project Information: ARPL 3031A 2021 - Project 2

Structural Axo (Above ground)

Basement structural Axo

Revision Details: REV:NO

7.5m

DESCRIPTION

DATE ISSUED

7.5m A 7.5m

5m

5m

7.5m

5m

7.5m

7.5m

Vehicle Access 3m

Drawing Details:

7.5m

3m

7.5m

3m B

Pedestrian Access

Vehicular basement access from station street (B-B)

DRAWING SCALE:

2192396

NTS

DRAWING NUMBER:

A

Arrival on ground floor (A-A)

B

DRAWN BY:

Circulation corridor

Typical Floor Plan

DATE:

PR04-AB

11/05/2021

DRAWING NAME:

REVISION NUMBER:

Core Concept Rev 2-AB Project 4 Sheet 1 of 5


Vertical Circulation of services through core

Primary Services of core Lift Core

Movement Corridor

Cable tray

Data duct adjacent to electrical duct

Passage

General Notes: 1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

Data duct Server room is on second floor

Fire Escape

Ablutions adjacent to core

Vertical Circulation (Movement)

Typical floor plan

Brown - Sewage Red - Fire escape Blue - Water supply Green - HVAC Cyan - Data Yellow - Electrical Circulation - Grey

HVAC room/ condensor

Data Water storage above lift core

Water supply pipe

Rainwater harvest

Ablutions

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Drainage Notes:

Waste water pipes Sewage Pipe HVAC duct Water supply pipe Sewage pipe

1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Client Information: Municipal connection Greywater tank

Water Supply

HVAC duct

University of the Witwatersrand

rainwater tank

Project Information: ARPL 3031A 2021 - Project 2

Ablutions duct

Roof scape

Revision Details:

Solar panels on roof

Electrical duct

REV:NO

air extraction from basement

Cable tray

Auditorium Refuse area

Drawing Details:

Bins

Electrical duct + cable tray

HT/LT room Generator room

Recycle sorting area

S

ic erv

e

e lan

DRAWN BY:

DRAWING SCALE:

2192396

NTS

DRAWING NUMBER:

Municipal connection Meter

Refuse area

Refuse

DATE ISSUED

DB Board on every floor

HVAC

Direct access to service lane

DESCRIPTION

HT/LT room

Electrical

Battery bank room (inverter)

Generator room

DATE:

PR04-AB

11/05/2021

DRAWING NAME:

REVISION NUMBER:

Core Concept Rev 2-AB Project 4 Sheet 2 of 5


Relationship between served and service spaces As seen in the previous slides, all the main services will circulate through the service core, this diagram below aims to show how these services will relate to the space that need to be served.

Circulation

Circulation

ADMINISTRATION OFFICES Services required: - Electrical - Internet (secured access)

OFFICE SPACES Services required: - Electrical - Internet (secured access) - Naturally ventilated

MULTI-PURPOSE GATHER SPACE (double volume)

Electrical wiring

HVAC duct

Electrical wiring

Data Wiring Green - HVAC Yellow - Electrical Cyan - Data cables

General Notes:

THEATRE PRACTICE ROOMS Services required: - HVAC - Electrical

Data Wiring

Server room Security control room Building Core Providing all services

Second Floor

Green - HVAC Yellow - Electrical Cyan - Data cables Building core: Providing all services

Fifth Floor

Circulation

Electrical wiring

HVAC duct

OFFICE SPACES Services required: - Electrical - Internet (secured access) - Naturally ventilated

Dance Studios Services required: - Electrical

ADMINISTRATION OFFICES Services required: - Electrical - Internet (secured access)

Green - HVAC Yellow - Electrical Cyan - Data cables

Data Wiring IT MAINTENANCE ROOM: Services required: - Electrical - Internet

First Floor

Storage Room Board room

Fourth Floor

Building core: Providing all services

RESTAURANT SEATING Services Required: - Electrical - Natural ventilation

Retail Services Required: - Electrical - Naturally ventilated Electrical wiring

Green - HVAC Yellow - Electrical Cyan - Data cables

HVAC duct

Ground Floor

Building Core Providing all services

Project Information: ARPL 3031A 2021 - Project 2

REV:NO

DESCRIPTION

DATE ISSUED

LARGE CAD LAB Services required: - Electrical - Internet (secured access)

Cad Labs Services required: - Electrical - Internet (secured access)

PUBLIC SPACE Services Required: - Electrical

RESTAURANT KITCHEN Services Required: - Electrical - Water supply - Sewage / waist - Gas supply Reading room

University of the Witwatersrand

Revision Details: Circulation

Circulation

Drainage Notes: 1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Client Information:

Electrical Data Wiring wiring

Building Core Providing all services

AUDITORIUM Services Required: - HVAC - Electrical

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Circulation

MULTI-PURPOSE GATHER SPACE Services required: - HVAC - Electrical

Green - HVAC Yellow - Electrical Cyan - Data cables

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

Drawing Details: Green - HVAC Yellow - Electrical Cyan - Data cables

Electrical wiring

Third Floor

Data Wiring

DRAWN BY:

DRAWING SCALE:

2192396

NTS

DRAWING NUMBER:

Building core: Providing all services

SEMINAR ROOMS Services required: - Electrical - Internet (secured access)

DATE:

PR04-AB

11/05/2021

DRAWING NAME:

REVISION NUMBER:

Core Concept Rev 2-AB Project 4 Sheet 3 of 5


Legend:

Massing and Zoning Diagram:

Public -

PLA transport logistics

Core

Private -

Malawi: embassy

Circulation 56 Jorrisen He nri s

J

n is e orr

ee str

tre et

Senate House

t

Wits theatre

Building Mass within its urban context Wits arts museum

Admin offices(G1): - Long Span - Dungeon - Natural - Natural Board room(G1): - Short Span - Dungeon - Natural - Natural Admin offices(G1): - Long Span - Dungeon - Natural - Natural

Fifth Floor

Core

Fourth Floor

Large Cad Lab(A3): - Short span - Dungeon - Natural/artificial - Natural

Third Floor

Educational Cad Labs(A3)

Fifth Floor Fourth Floor

Second Floor

Multi-purpose gather space(A1)

First Floor

Auditorium(A1)

Third Floor

Private Public

Dance studios(G1)

Public

Ground Floor Basement -1 Basement -2 Basement -3

Section through building

Basement Parking

Letable Office Spaces(G1): - Long Span - Dungeon - Natural - Natural

Letable Office Spaces (G1): - Long Span - Dungeon - Natural - Natural

Cad Labs(A3): - Short span - Dungeon - Natural/Artificial - Natural

Core Multi-purpose gather space (DOUBLE VOLUME)

Core

First Floor

Multi-purpose gather space (A1): - Long span - Cathedral - Special - Mechanical

Core: Ablutions HVAC duct Electrical duct Water duct Data duct

Ground Floor

General Notes: 1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Drainage Notes: 1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Client Information:

University of the Witwatersrand

Second Floor

Reading room(A3): - Long Span - Dungeon - Natural - Natural Restaurant (B3): - Long Span - Cathedral - Natural/Artificial - Natural Space: - Structural requirements - Volumetric requirements - Lighting Requirements - Ventilation Requirements

Dance Studio(A2): - Short span - Dungeon - Natural/Artificial - Natural

Core

Seminar room(A1): - Short span - Dungeon - Natural - Natural

Entry to East campus

Theatre practice(A2): - Short span - Dungeon - Natural/Artificial - Natural

Auditorium (A1): - Long Span - Cathedral - Special - Mechanical

Project Information: ARPL 3031A 2021 - Project 2 Revision Details: REV:NO

DESCRIPTION

DATE ISSUED

Drawing Details: DRAWN BY:

DRAWING SCALE:

2192396

NTS

DRAWING NUMBER:

DATE:

PR04-AB

11/05/2021

DRAWING NAME:

REVISION NUMBER:

Core Concept Rev 2-AB Project 4 Sheet 5 of 5


PROJECT 5 - Core Detail


Occupants will escape into a fire rated lobby/foyer, all doors within foyer to be 120min fire rated ,as per NBR

C

Self closing class B door fire rated door at 120 min, as per NBR

D 7500

Type FR wall 220mm brickwork, plastered inside and outside fire rated at 120min

3881

240

3239

Fire extinguishers, 1/200sqm as per NBR

General Notes:

New Reception Lobby

2225

1816

300mm cast concrete lift core to eng. detail Lift door to be 120min fire rated and sealed for smoke ingress of 30min as per NBR

UP 1800

14 13 12

3822

315

1540

3.7m x 1.5 m Stretcher lift

1681

B 5013

C 7500

D 7498

E 7493

F 5000

5000

G 7500

H 5000

I

J

8400

1 2

D50

ie

whb

whb

616

Service duct 10 m² 1- Ground Floor Steel Grate

ie

ie

ie

whb

whb

whb

50mm waste pipe

130

1215

1314

new lintels over

New Male Bathroom

counter top

D42

D42

D42

D42

D42

353

355

356

357

545

wc

110mm uPVC soil pipe

Closet

1900

wc

wc

wc

ie

ie

ie

ie

ie

wc

wc

2 m² 1- Ground Floor Tiles

130

Disabled bathroom (1.8 x 1.8)

ie

ie

Vent stack

ie

D42 358

new lintels over

Disabled bathroom (1.8m x 1.8m)

7500

4

400mm x 600mm concrete column, according to eng detail

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Drainage Notes: 1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Client Information:

Core

Reference Plan - Ground Floor Scale 1:500

130

Single stack piping system

ie

960

new lintels over

ie

4

3

1800

1800

ie

960

whb

new lintels over

1800

4

615

130

22 m² 1- Ground Floor Tiles

D41

new lintels over

⌀300mm HVAC duct to auditorium according to eng. detail

ie

785

584

D41

1826

2664

1826

Acoustic timber sound panels

900mm x 2600mm HVAC duct according to eng detail

911

HVAC DUCT

7500

DB board

17818

300

Electrical Duct

130 1314 130 785 130 911 300

Data Duct

7500

1775

241

A

3 3710

400mm x 600mm concrete column, according to eng detail

1241

300

9 10 11

3

1217

3710

1 2 3 4 5 6 7 8

24 23 22 21 20 19 18 17 16 15

Roof ventilator to be installed above emergency route, as per NBR

2710

26 m² 1- Ground Floor Slip Resistant floor

7500

Emergency route

1000mm high balustrade as per NBR

300

2

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

240

Staircase note: Concrete cast in situ staircase 24 risers 280mm min treads , 170mm max risers 1000mm balustrade

168 m² 1- Ground Floor Polished screed

D44

3710

+1500mm from staircase midpoint to escape door as per NBR

University of the Witwatersrand Project Information: ARPL 3031A 2021 - Project 2

D42

1223

D42

D42

D42

D42

346

348

349

350

New Female Bathroom

whb 465

whb 466

whb

whb 468

467

469

526

ie

ie

ie

ie

single stack system

Perforated alumium screen

ie

Soil Pipe

DESCRIPTION

DATE ISSUED

whb

D41

⌀50mm waste pipe

Electrical

REV:NO

ie

550

whb

Revision Details: Data

Motion sensor

31 m² 1- Ground Floor Tiles

535 240

counter top

1878

1878

Service duct for ablutions

1340 130

ie

Legend:

240

9 m² 1- Ground Floor Tiles

351

3348

HT/LT room

wc

1900

whb

HTLT room

new lintels over

wc

Waste Pipe

Municipal shutoff valve

vent stack (discharge pipe)

Property Boundary

Property Boundary

⌀50mm municipal water supply pipe

⌀50mm Municipal W ater Supply Municipal electrical supply

⌀110mm municipal sewage pipe

N

⌀110mm Municipal Sewage connection

Municipal Water supply

Electrical wires

Service Lane

Service core (Ground Floor) Scale 1:100

DRAWN BY:

DRAWING SCALE:

2192396

1:100

DRAWING NUMBER:

SMH

C

Drawing Details:

D

HVAC

DATE:

PR05-AB

06/06/2021

DRAWING NAME:

REVISION NUMBER:

Project 5 core detail

01 SHEET 1 OF 3


C

D 7500 3881

Self closing class B doors Fire rated door at, 120 min as per NBR

398

1220

420

1220

221

General Notes:

Type FR wall 240mm brickwork, plastered inside and outside fire rated at 120min as per NBR

Fire extinguishers, 1/200sqm as per NBR

Slip resistant floor to be installed

240

Staircase note: Concrete cast in situ staircase 24 risers 280mm min treads, 170mm risers max 1000mm balustrade

D44

24 23 22 21 20 19 18 17 16 15 14 13 12

1 2 3 4 5 6 7 8 9 10 11

3

300mm cast concrete lift core to eng. detail

UP

241

3838

Lift door to be 120min fire rated and sealed for smoke ingress of 30min as per NBR

1220

A

3 3221 1311

B 5013

C 7500

D 7500

F

E 7491

5000

5000

G 7500

1345

whb

ie

whb

whb

1826

D42

D42 390

D42

D42

D42

D42

392

393

394

546

ie

⌀100mm uPVC soil pipe Automatic motion lights to be installed according to eng detail (occupancy activated)

ie

wc

ie

Vent stack

ie

ie

wc

wc

ie

ie

ie

ie

2 m² 2 - First Floor plan ?

D42 395

7500 1314

4

Core

Client Information:

University of the Witwatersrand Project Information: ARPL 3031A 2021 - Project 2

Reference Plan - First Floor Scale 1:500

Revision Details: REV:NO

DESCRIPTION

DATE ISSUED

D42

1900

wc

wc

wc

388

D42

D42

D42

D42

383

385

386

387

1878 130

382

3348

D42

wc

TYPE F walls, minimum of 60min fire resistance for interior partition walls depending on use, as per NBR.

whb 1878

wc

Disabled bathroom 1.9m x 1.9m

New Female Bathroom

whb

whb

whb 461

462

whb

whb 463

whb

Perforated aluminium screen

ie

ie

ie

ie

ie

550

ie

Data

Electrical

464

240

460

1340

25 m² 2 - First Floor plan Tiles

counter top

Legend:

Drawing Details:

240

⌀50mm uPVC waste pipe

Soil Pipe

7500

Waste Pipe

N

1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

120

130

ie

wc

400mm x 600mm concrete column, according to eng detail

130

1900

Closet

970

wc

Single stack piping system

4

1800

whb

HW

1800

389

606

130

4

D41

130

22 m² 2 - First Floor plan Tiles

130

New Male Bathrooms

3

1800

counter top

1314

whb

whb

960

Disabled bathroom 1.8m x 1.9m

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Drainage Notes:

7500

whb

ie

130

ie

TYPE F walls, minimum of 60min fire resistance for interior partition walls depending on use, as per NBR.

17818

785

ie

TYPE fire rated doors dependent on occupational use, as per NBR

1826

605

10 m² 2 - First Floor plan Single stack piping system Steel grate

585

ie

8400

D41

130

HVAC DUCT

D50

ie

J

2

7500 911

900mm x 2600mm HVAC duct according to eng detail

2664

Service Duct

⌀50mm uPVC waste pipe

5000

I

300

DB board 300mm HVAC duct to auditorium, according to eng. detail

H

1 3.7m x 1.5 m Stretcher lift

1775

Electrical duct/ data duct

1220

7500

26 m² 2 - First Floor plan Slip resistant floor

3710

400mm x 600mm concrete column, according eng. detail

Emergency route

3710

2525

14

7020

1000mm high balustrade as per NBR

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

C

D Electrical light wires

Service core (First Floor) Scale 1:100

HVAC

DRAWN BY:

DRAWING SCALE:

2192396

1:100

DRAWING NUMBER:

DATE:

PR05-AB

06/06/2021

DRAWING NAME:

REVISION NUMBER:

Project 5 core detail

01 SHEET 2 OF 3


A

B

C

D

F

E

H

G

J

I

General Notes: 1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

63532 600

62332 5013

7500

7500

7491

600 5000

5000

7511

5000

8397

A

B 600

600

2.4 x 5m parking bay 2.4 x 5m parking bay

New Storage room 1

4891

130

4891

599

240

600

2.4 x 5m parking bay

2.4 x 5m parking bay

2.4 x 5m parking bay

2.4 x 5m parking bay

2.4 x 5m parking bay

5000

240

D42

303

1102

600mm secant rataining wall 2.4 x 5m parking bay

24 m² -1 Basement Level 1 Polished screed

D42

240

New concrete 1:12 ramp, landing at every 500mm rise, according to NBR (ramp up to first floor)

54376

New Storage room 2

7597

38 m² -1 Basement Level 1 Polished screed

2.4 x 5m parking bay

1

Drainage pipe leading to sump

5m x 3.5m disabled parking bay

D44

UP 2339

598

3554

7826

4891

600

400mm x 600mm structural column spaced at 7.5m x 5m, according to eng. detail

7500

600

600

Property Boundary

2.4 x 5m parking bay

Drainage pipe leading to sump

5998

604

20 19 18 17 16

10 11 12

15 14 13

2.4 x 5m parking bay

2.4 x 5m parking bay

Drainage pipe leading to sump

300

whb

whb

whb

whb

619

Sewage and waste pump, up to invert level

D42

D42

D42

D42

484

486

487

488

wc

Vent stack (discgarge pipe)

i.e

i.e i.e

i.e

i.e

i.e

i.e

wc

wc

wc

wc

130 130

D42

i.e

549

D41

D42

D42

D42

D42

477

479

480

481

whb

whb

whb

whb

i.e

i.e

i.e

whb

whb

587

To municipal connection

Project Information:

ARPL 3031A 2021 - Project 5

Basement level 1 bottom of ramp

new 1:8 concrete driveway ramp

7489

130

i.e

1878

Stage

960

i.e

Street level Top of ramp + 3000mm

wc

10008

586

wc

Parking Circulation

D41

University of the Witwatersrand

4

1800

whb

24 m² -1 Basement Level 1 Tiles

Drainage pipe leading to sump

Parking Circulation

D41

New Male Bathroom

counter top

600

400

whb

7500

Client Information:

i.e

i.e

1314

whb

1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

To grey water storage tank i.e

Disabled seating area on floor level

Revision Details:

UP

7502

i.e

130

i.e

785

618

i.e

7500

1826

1891

D50

Wet wall system for water proofing

1305 m² -1 Basement Level 1 Concrete floor(non combustable)

Automatic sprinkler system to be installed in basement >500sqm as per NBR

900mm x 2600mm HVAC duct according to eng detail

Hvac Duct UP

280

3

DRAIN

3650

1681

30060

1540

400mm x 800mm structural beam overhead according to eng. detail spaced at 7.5m x 5m

1743

288

400mm x 600mm structural column according to eng. detail spaced at 7.5m x 5m

New Parking basement

REV:NO

DESCRIPTION

DATE ISSUED

Cirulation down into basement level 2

D42

130

280

7500

300 6799

3851

3710

Data duct

3.7m x 1.5 m Stretcher lift

DB board

280

Drainage Notes:

Lift door to be 120min fire rated and sealed for smoke ingress of 30min as per NBR

1200

30088

1220

UP

31288

2.4 x 5m parking bay

1678 1 2 3 4 5 6 7 8 9

Electrical duct

Soundproofing timber panels

1772

2.4 x 5m parking bay

2.4 x 5m parking bay

2.4 x 5m parking bay

26 m² -1 Basement Level 1 Slip Resistant floor

1800

22148 19569

Emergency route

300

2026

3881

31288

2.4 x 5m parking bay

Staircase note: Concrete cast in situ staircase 24 risers 280mm min treads, 170mm risers max 1000mm balustrade

2.4 x 5m parking bay

13

400mm x 600mm concrete column, according eng. detail

22148

400mm x 600mm structural column spaced at 7.5m x 5m, according to eng. detail

2.4 x 5m parking bay

Slip resistant floor to be installed

Type FR wall 220mm brickwork, plastered inside and outside fire rated at 120min

242 m² -1 Basement Level 1 Carpet

2.4 x 5m parking bay

2.4 x 5m parking bay

Self closing class B door, rated at 120 min as per NBR

D44

Auditorium

Parking Circulation

D45

7500

AUDITORIUM RAKES UPWARDS

2.4 x 5m parking bay

Parking Circulation

240

2 10 000 litre rainwater harvest tank

Perforated screen

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

536

New Female Bathroom

whb

i.e

i.e

50mm waste pipe

discharge stack

600mm secant rataining wall Top of concrete to top of concrete dimension = 3000mm

607

600

i.e

600

600

600

Single stack system

whb

262

To grey water collection tank

937

2528

counter top

2528

2528

36 m² -1 Basement Level 1 Tiles

1340

25 m² -1 Basement Level 1 Tiles

Auditorium Back Stage

Municipal electrical connection

D

C

Municipal sewage line

63532

N

Drawing Details:

Legend: Data

Electrical

DRAWN BY:

DRAWING SCALE:

2192396

1:100

DRAWING NUMBER:

DATE:

Soil Pipe

Basement level 1 Scale 1:100

Waste Pipe

Municipal Water supply

Electrical wires

HVAC

PR05 - AB DRAWING NAME:

Project 05 Core Detail

30/05/2021 REVISION NUMBER:

01 SHEET 3 OF 3


PROJECT 6 - Structural Model


2192396_Structural Model_P6 1.

Round concrete columns

Cast in situ concrete floor plate

General Notes:

Concrete transfer beam

Jorrisen Street

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Drainage Notes: 1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

2.

Client Information:

University of the Witwatersrand Project Information: ARPL 3031A 2021 - Project 6 Revision Details: REV:NO

DESCRIPTION

DATE ISSUED

Drawing Details: DRAWN BY:

2192396 DRAWING NUMBER:

Floor plan showing tribituary areas of structural elements (LOAD PATHS)

DRAWING SCALE:

NTS DATE:

PR06-AB

2021/08/03

DRAWING NAME:

REVISION NUMBER:

Project 6 Structural M

02 Page 1 of 2


3.

General Notes: 1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

North elevation showing the flow of structural forces.

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Drainage Notes: 4.

1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Client Information:

University of the Witwatersrand Project Information: ARPL 3031A 2021 - Project 6 Revision Details: REV:NO

DESCRIPTION

DATE ISSUED

Load Paths

Drawing Details: DRAWN BY:

2192396 DRAWING NUMBER:

DRAWING SCALE:

NTS DATE:

PR06-AB

2021/08/03

DRAWING NAME:

REVISION NUMBER:

Project 6 Structural M

02 Page 2 of 2


PERFORMING ARTS SCHOOL GROUND FLOOR PLAN

SECTION A-A 5m

0m A

B

10m

15m

Scale Bar 1:250

JORRISEN STREET

Dance studio 4

UP

UP

UP

UP

Auditorium

Timber deck (street level)

UP

UP

Service duct

Restaurant kitchen (Ground Level)

Passage

Rake downwards

ORIGINAL DESIGN

IT maintenance

UP

Third Floor

UP

Second Floor STATION STREET

Exibition space

Lifts

Publi c Seati ng

Restaurant seating

Reception

Balcony Side walk

Ramps

Fourth Floor

Exib ition spac e/pu blic plaza

UP

Public Seating

Public Seating

UP

Service Lane

HT/LT room

Basement Level 1 Backstage area

Basement Level 2 Basement parking

Basement Level 3

Property boundary Service Lane

PROJECT 2

Page 9

N

NORTH ELEVATION The Performing Arts School Concept Note:

0m

5m

10m

15m

Scale bar 1:200

The perfoming art school is a building that intends to uplift the social interaction of the surrounding Braamfontein context. The shape of the building is dictated by the facade that represents motion and movement, a crucial element in the performing arts. The building is expressed as flowing and moving. Additionally using the prevailing seasonal winds to aid in the design of the footprint of the building. The performing art school is fitted with sustainable materials such as a planted screen on the exterior. The school also provides people with education spaces and dancing practice spaces, an auditorium and exibition spaces. The building makes it easy to enjoy the views of Braamfontein with dedicated balcony spaces looking out onto the city.

Scale 1:200

Generator room Auditorium

Ground Floor

Fire escape

Generator room

Cad lab 3

Multi purpose gather space

Public Bathrooms A

15m

Dance studio 3

Retail

UP Refuse/Recycle Area

10m

First Floor

Ramp access to basement parking B

Cad lab 4

5m

Scale bar 1:200

Theatre practice 3

Fifth Floor

Side walk

Public relations

0m

Theatre practice 4

Security office

Retail

Scale 1:200

Atrium

Scale 1:250

Fire escape staircase

N

Page 18

View from Jorrisen street sidewalk 1.

2.

Page 14


PROJECT 7.1 - Working Drawings (Original Submission)


WITS EAST CAMPUS SOUTH ENTRANCE

WITS THEATRE

Site dimensions AB 63m BC 31m CD 63m DA 31m

sidewalk

bus stop

Statutory Requirements Description Total 1985m2 Site Area Allowable 5000sqm 2.1 50%

Total Floor Area Total F.A.R Total Coverage

JORRISEN STREET

Actual 4450sqm 2.1 45%

Area Schedule -1 Basement Level 1739

K

A

B

C

D

E

F

H

G

I

J

17 38

A

63532

40

5037

7476

7491

7500

5000

5000

7500

8400

5000

sidewalk

Covered balcony F.B.O (⌀90mm)

455mm concrete flat slab, according to eng detail Finish: 50mm Concrete pavers

7500

F.B.O (⌀100mm)

F.B.O (⌀124mm)

4310

3700 21 57

FFL_-3000 Covered balcony

455mm concrete suspended floor 20MPA @ 28 days, to engineer specification Finish: Ceramic Tiles

FFL_ 25160

50mm paving placed above waterproofing layer

62 35

FFL_-2050

F.B.O (⌀90mm)

F.B.O (⌀160mm)

Kerb

3

22427

1924

SW SUMP

7

6

5

4

3

2

1

1091

UP

1611

STAIRCASE NOTE: Concrete cast in situ staircase 24 risers 250mm min treads , 170mm max risers 1000mm balustrade

FFL_-3900

5

UP

1:8 concrete ramp to basement parking

Property Boundary

-4350

Municipal Water Supply

-2899

Sewer Manhole Invert Level 1200m

Municipal Sewage

LEVELS/DATUM

A

ERF 2929

8

13 14 15 16 17 18 19 20 21 22 23 24

63m

1016

D

5079

12 11 10 9

6606 1542

3110

F.B.O (⌀196mm)

SW manhole cover -3042 is 0.0

ERF 2930

C

Service Lane

Stormwater Note: All stormwater on roof will move of the roof through a series of full bore outlets, connected to downpipes within structural columns, water flows into sump on lowest baseent floor for re-use. Overflow to be connected to municpal stormwater sump.

ERF 2931

173

ERF 2932

ERF 2934

7

4

prefabricated high density polystyrene prefabricated panels

240

F.B.O (⌀140mm)

3 17

ERF 2951

5003

4984

280

Auditrium Back Stage Area

35sqm

Storage Room 2

24sqm

Male Bathroom

24sqm

Female Bathroom

24sqm

Retail

53sqm

Restaurant kitchen

46sqm

Refuse Area

11sqm

Generator Room

17sqm

HTLT Room

8sqm

Male Bathroom

24sqm

Female Bathroom

24sqm

IT maintenance room

32sqm

Security Office

9sqm

Public Relations office

8sqm

Closet

2sqm

Reception Lobby

127sqm

Letable Offices

153sqm

Reading Room

43sqm

Male Bathroom

24sqm

Female Bathroom

24sqm

Male Bathroom

24sqm

Multi-purpose gather space

394sqm

Second Floor Level

HVAC UNIT (Plant room), according to mechanical engineer detail

220mm brick parapet wall

38sqm

First Floor Level

10600

14640

Property Boundary

4696

Covered balcony

ERF 2952

31m

1000mm glass panel railing

UP

5000 litre Water storage tank

2

UP

240

Ceramic tile finish on roof slab, installed above torch-on waterprooding, ontop of 50mm XPS insulation, above screed to fall layer.

UP

5

3 17

6

STATION STREET

FFL_-1550

50mm paving placed above waterproofing layer

31344

15735

37 57

375 1

7500

FFL_-2050

1000mm glass panel railing 1:12 concrete ramp

3695

Covered balcony

220mm curved plastered brickwork wall, supported by concrete sub structure

27486

13125

220mm brick wall

ERF 2940

31m

31344

FFL_-1550

F.B.O (⌀124mm)

7500

Creeper planted screen suspended by a timber structure

F.B.O

ERF 2937

12499 F.B.O (⌀110mm)

1738

7500

ref er to

1

Kerb

ramp,

sidewalk

455mm concrete flat slab, according to eng detail Finish: 50mm Concrete pavers

1:12 concrete ramp

ncrete 1:12 co

0m Building Line Fever trees, according to landscape architect details Concrete Seating Blocks

UP

r detail enginee

0m Building Line Property Boundary

5445

14770

7502

1000mm glass panel balustrade, according to sans requirement

23194

TOC_-1559

F.B.O (⌀100MM)

Property Boundary

1610

748

63m

Exterior Balcony

-2700

B

Sidewalk bollard

7500

1000mm glass panel balustrade, according to sans requirement

A

Kerb

8233

-14695

Street Parking

3110

Street Parking

Kerb

243sqm

Storage Room 1

Ground Floor Level

2441

17

1730

Auditorium

Offices

168sqm

Security control room

33sqm

Server Room

10sqm

Male Bathroom

24sqm

Female Bathroom

24sqm

General Notes: 1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Drainage Notes: 1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Client Information:

Third Floor Level Computer Labs

372sqm

Seminar rooms

79sqm

Male Bathroom

24sqm

Female Bathroom

24sqm

University of the Witwatersrand Project Information:

Fourth Floor Level Dance Studios

241sqm

Board Room

29sqm

Offices

114sqm

Storage Room

13sqm

Computer Labs

372sqm

ARPL 3031A 2021 - Project 7.1 Revision Details: REV:NO

DESCRIPTION

DATE ISSUED

Fifth Floor Level 0m

4m

8m

12m

16m

20m

Refuse Calculations f(g) × FA / 100 = volume (m³)/week f(g) = Offices 0.2258 f(g) = Shops 0.92353

VISUAL SCALE 1:200 @ A1

N

Theatre Practice rooms

266sqm

Offices

138sqm

Male Bathrooms

24sqm

Female Bathrooms

24sqm

Stormwater Calculations Offices 0.2258 x 1030sqm/100 = 2.32 (m3)/week

SITE

Site Plan N

Scale 1:200

Shops 0.92353 x 53sqm/100 = 0.48 (m3)/week

Roof Slab Area

4. 5m x 10m = 50m²

Locality Map

= 3.142(4.5)² = ⌀64sqmm pipe = ⌀90mm pipe

Drawing Details: DRAWN BY:

DRAWING SCALE:

2192396

1:200

DRAWING NUMBER:

DATE:

πr² 1. 13m x 7.5m = 98m² = 3.142(5.5)² = ⌀96sqmm pipe = ⌀110mm pipe

PR07.1

17/08/2021

DRAWING NAME:

REVISION NUMBER:

3. 15m x 8m = 120m² = 3.142(6.2)² = 121sqmm = ⌀124mm pipe

PROJECT 7.1 Site Plan

02

Public Space Storage Area size: 2.8m3 perweek x 4 bins/m3 = 11 bins That would require 11sqm size for refuse room

1m² = 1cm²

πr² 1. 18.5m x 7.2m = 133m² = 3.142(7)² = ⌀155sqmm pipe = ⌀140mm pipe 2. 15m x 20m = 300m² = 3.142(9.8)² = ⌀301sqmm pipe = ⌀196mm pipe 3. 15m x 13m = 195m² = 3.142(8)² = ⌀201sqmm pipe = ⌀160mm pipe

1m² = 1cm²

2. 15m x 4.5m = 68m² = 3.142(5)² = ⌀79sqmm pipe = ⌀100mm pipe 4. 12.5m x 7.5m = 120m² = 3.142(6.2)² = 121sqmm = ⌀124mm pipe 5. 7.5m x 7.5m = 56m² = 3.142(4.5)² = 64sqmm = ⌀90mm pipe

Page 1 of 3


1739

1740

JORRISEN STREET

K

A

A

B

AUDITORIUM NOTE: Auditorium can be accessed from ground floor level, through the direct connecting door, lower levels of auditorium can be accessed through the multilevel ramp or through basement level 1.

C

D

F

E

H

G

STORMWATER NOTE: Stormwater reticulation within public space will be dealt dealt with screed to fall, leading into seperate full bore outlets, From the full bore outlets the piping reticulates to the sumps at the lowest basement floor. Stormwater will be reused within the building.

WATER RETICULATION NOTE: Water to all fixtures will be supplied from the indicated municipal connection, water will be stored in water tank on above the lift core. On the roof level.

J

I

63532

General Notes:

58404 5037

1728

280

7500

7476

10720

240

3600

191

1925

130

1875

5000

7491

240410

10284

7500

5000

280

9855

7500

237

2441

8400

5000 4696

307

3801

4336

2463

1738

-1195

Sidewalk

-997

240

240

531

895

130

wc

901

130

wc

1012

240

ie

ie

ie

ie

wc

wc

533

D42 358

130

875

130

875

130

881

130

D42

D42

D42

D42

346

348

349

350

3293

whb

1823

wc

730

240

4800

280

280

280

RESTAURANT KITCHEN

ø6 00

Tiles TOC Ground Floor level 48 m²

counter top D42 579

Dry St

D42

521 Tiles TOC Ground Floor level

285

DGS

5 m² 2230 D42

368

475

Cold St

S

Tiles TOC Ground Floor level

130

ie

S

ie

6 m²

2828

130

1937

280

counter top

466

whb

94

ie

467

468

94

ie

94

ie

29 m²

ie

469 94

ie

7568

7500

240665 6018

7500

31344

27503 7500

3410

1436

Property Boundary

2311

1915

University of the Witwatersrand

1166

69

FFL_-3000 50mm paving as finish

seating

4

counter top

Boomed access control

STAIRCASE NOTE: Concrete cast in situ staircase, 24 risers 250mm min treads , 170mm max risers 1000mm balustrade Finish: Off shutter

Project Information:

ARPL 3031A 2021 - Project 7.1 Revision Details:

90mm uPVC downpipe

Gas Bottles 12 11 10 9 8 7 6 5 4 3 2 1

REV:NO

DESCRIPTION

DATE ISSUED

1736

5 1:8 concrete ramp to basement parking

13 14 15 16 17 18 19 20 21 22 23 24

UP

20mm Perforated alumium screen

UP 3110

whb

550 240

465

Tiles TOC Ground Floor level whb whb whb

633

50mm paving as finish

1465

24 23 22 21 20 19 18 17 16 15 14 13 12

1 2 3 4 5 6 7 8 9 10 11

2394

FFL_-2050 1453

4845

0m Building Line

7499 100

counter top

FEMALE BATHROOM

⌀50mm waste pipe

D42

ie

2271

Closet

850

ie

179

5003

130

D43

178

3110

895

240 850 240

130

D43

1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Client Information:

240

545

UP

32 m²

3 1737

7990

D42

357

Tiles TOC Ground Floor level

7597

D42

356

IT MAINTENANCE RM

1745

D42

355

wc

1820

94

470

Fuel storage D45

D42

1745

whb

DGS

455mm concrete solid flat slab, according to eng. detail Finish: 50mm concrete pavers

4999

72

615

353

280mm brickwork cavity wall plastered and painted

4743

DGS

351

ie

5671

10523

4488

2505

whb

D42

6100 240

130

130

counter top

6185whb

D42

wc

whb

2724

15 m²

4620

2255

Drainage Notes:

13187

38

3738 ⌀50mm waste pipe

ie

new lintels over

ie

Tiles TOC Ground Floor level

11 m²

-4350

C

Municipal Shuttoff valve

Property Boundary Municipal Water supply

-14695

SW SUMP

N

A

ERF 2930

Sewer Manhole Invert Level = 1200m

LEVELS/DATUM SW manhole cover -3042 is 0.0

ERF 2931

Ground Floor Plan Scale 1:100

Municipal Sewage Connection

0m

STAIRCASE NOTE: Concrete cast in situ staircase, 24 risers 250mm min treads , 170mm max risers 1000mm balustrade Finish: Slip resistant coating

ERF 2932 2m

4m

VISUAL SCALE 1:100 @ A1

6m

8m

SERVICE LANE ERF 2934

10m 35 17

STATION STREET

D

whb

ie ⌀110mm sewage pipeie

620

GENERATOR RM

Tiles TOC Ground Floor level

240

D1

new lintels over

4958

REFUSE AREA

260

2108

whb

ie

MALE BATHROOM

1820

18 m²

1000mm high glass panel balustrade

280

whb

ie

wc

Acoustic timber sound panels

⌀124 mm F.B.O

D5

4845

6780

1041 230 1649

900

400mm x 1500mm concrete beams overhead, according to eng detail

240

D45

T1

DGS

22 m²

Tiles TOC Ground Floor level

⌀100mm F.B.O

300

Tiles TOC Ground Floor level

ie

77

3221

HVAC EXTRACTION 1000mm x 800mm (stainless steel) ie

ie

new lintels over

386

300

HVAC SUPPLY 1000mm x 800mm(stainless steel)

240 1215 130

HTLT ROOM

Stormwater channel to sump

D2

3838

2141

UP

DGS

WT

Stage

150

27 m²

241

DB board

400mm x 900mm concrete column, according to eng detail

2163

5997

top

Disabled Seating area

130

⌀600mm concrete columns , according to eng detail

ter

400

7530

307

400mm x 900mm concrete column, according to eng detail

300mm cast concrete lift core to eng. detail 3.7m x 1.5 m Kone MonoSpace DX Stretcher lift according to mech eng detail

1348

3524

2

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

FFL_-1500

Concrete FLAT SLAB no beams overhead

un co

Auditorium entry 2 on basement level 1 (Refer to section A-A)

Lift door to be 120min fire rated and sealed for smoke ingress of 30min as per NBR

Polished screed TOC Ground Floor level

Electrical Duct 700mm x 600mm

785

233 m²

Data Duct 600mm x 400mm

Fire Escape

280mm brickwork cavity wall plastered and painted, insulated with 30mm XPS insulation within 50 mm cavity

10694

UP

seating

UP 240

T1

300

Carpet TOC Ground Floor level

12

1280

232 1180

⌀90mm F.B.O

Not Enclosed

Conways Crealco Curtain Wall System, Façade 60 Pressure Glazed Curtain Wall

126 m²

1826

14520

AUDITORIUM

11

Foam Fire Extinguisher 1/200sqm as per NBR

130 1314 130

2252

STAIRCASE NOTE: Concrete cast in situ staircase, 24 risers 280mm min treads , 170mm max risers 240 1000mm balustrade Finish: Slip resitant coating

24 23 22 21 20 19 18 17 16 15 14 13

10

Polished Screed TOC Ground Floor level

7319

Timber Deck TOC Ground Floor level

8 9

300

7225 320

22724

Property Boundary

31197

400mm x 900mm concrete column, according to eng detail

1 2 3 4 5 6 7 8 9 10

7

RECEPTION LOBBY

240

UP

400mm x 600mm concrete column, according to eng detail

400mm x 1500mm concrete beams overhead, according to eng detail

1875

2700

Roof ventilator to be installed above emergency route, as per NBR

130

3710

1876

455mm concrete solid flat slab, according to eng detail Finish: 50mm concrete pavers

RESTAURANT SEATING AREA

6

FHR According to NBR

3461

240

5

1738

UP

seating

240

628

3

30mm SAP timber deck, according to eng detail

50mm paving as finish

4881

DGS

627

2

4

3383

DGS

3710

14840

1

Self closing class B door fire rated door at 120 min, as per NBR

Type FR wall 220mm brickwork, plastered inside and outside fire rated at 120min

240

1000mm high glass panel balustrade

16

Occupants will escape into a fire rated lobby/foyer, all doors within foyer to be 120min fire rated ,as per NBR

D3

Staircase note: Concrete cast in situ staircase 10 risers 250mm min treads , 170mm max risers 1000mm glass panel balustrade Finish: Off Shutter

5222

D45

3832

2291

230mm brickwork plastered and painted

ERF 2940

1:12 concrete ramp, according to eng detail

Drainage Channel Stainless steel grate

FFL_-2050

240

400mm x 900mm concrete column, according to eng detail To be plastered on exterior

603

Stormwater channel to sump

1:12 concrete ramp, according to eng detail (Slip resistant coaring)

d T1

DGS

14560

⌀124 mm FLUSH F.B.O

FFL_-1559 50mm paving as finish, placed above torch-on waterproofing

1000mm high glass panel balustrade

Glass exit and entrance doors

1:12 concrete ramp, according to eng detail (Slip resistant coating)

⌀110 mm FLUSH F.B.O flush with paving finish

Sc

UP

2214

ing to ccord

240

2242 190

400mm x 1500mm concrete beams overhead, according to eng detail

22724

1:1

p, a

re e

263

263

240

8 m²

ram

te ncre 2 co

280

Fridge

Stormwater drainage channel to sump

1427

7500

2110

455mm concrete solid flat slab, according to eng detail Finish: 50mm concrete pavers

1796

240

600

Tiles TOC Ground Floor level

104 949

455mm concrete solid flat slab, according to eng. detail Finish: 50mm concrete pavers

UP

il deta eng

7500

50mm paving as finish

600

DGS

13125

8233

FFL_-3000

601

2978

3600

238

Concrete seating

DGS

1905

BIC

PUBLIC REL

7500

3110

746 9 m²

ll

240

Counter top

1:12 concrete ramp Finish: Slip resistant floor

1625

879

4999

fa

10720

Shelving

BIC

240

52 m²

280

Tiles TOC Ground Floor level

5540

5540

Polished Screed TOC Ground Floor level

1

Stormwater channel to sump

1000mm high glass panel balustrade

SECURITY OF

Shelving

RETAIL SPACE

0m Building Line

to

Shelving

3600

3190

400mm x 1500mm concrete beams overhead, according to eng detail

Fever Trees, refer to landscape arch detail

Property Boundary

20mm perforated alumium screen

-2700

B

T1

473

T1

280

T1

280

T2

1485

A

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

Drawing Details: DRAWN BY:

DRAWING SCALE:

2192396

1:100

DRAWING NUMBER:

DATE:

PR07.1

17/08/2021

DRAWING NAME:

REVISION NUMBER:

PROJECT 7.1 Ground Floor

02 Page 2 of 3


2

3

4

5 ROOF NOTE: Ceramic tile finish on roof slab, installed above torch-on waterprooding(Supplied by apex waterproofing), ontop of 50mm XPS insulation, above screed to fall layer. Supported by 455mm solid concrete flat slab.

31317 747

27487 7500

3083

7500

7500

4987

1567

1502 Seasonally adjustable monocrystalline solar panel for electricity production optimum angle 25 to 35 degrees Eurolux O403 Silicon module

Prefabricated concrete supporting wall Steel bracing according to eng, detail

455

1330

286

4641

3545

Polished Screed TOC Third floor level

280

5035

300

13638 455

455

vertical HVAC duct

7545

4000

400mm x 1500mm RC beams overhead, according to eng detail 600

220

Screed to fall, to overflow pipe

Polished Screed TOC Ground Floor level

Concrete retaining wall beam

-3000

D42 533

15.67°

4395

4090

20mm carpet

Wheelchair zone

1180

400

604

1595

D45

599

7500

4987

-13390

wet wall system for basement waterproofing

Basement Level 3

wet wall system sump

N

Section A-A Scale 1:100

⌀110mm drainage pipe to sump

-10400

455

50mm concrete pavers

60 Compacted Drainage stones

Compacted Drainage stones

DRAWN BY:

Basement Level 3

Compacted Drainage stones Compacted Drainage stones

Drawing Details:

-13390

wet wall sump

Engineer to determine the use of ground beams between pile caps

⌀110mm agricultural drain

600mm secant concrete retaining walls depth to be determined by geotech engineer ⌀110mm agricultural drain

⌀110mm agricultural drain

⌀110mm agricultural drain

⌀110mm agricultural drain

⌀400mm concrete pile foundation

LOWEST BASEMENT FLOOR NOTE: Lowest basement floor made of 50mm pavers, sitting on compacted drainage stones to effectively keep ground water away from the lowest basement level.

-7400

20mm sand blinding layer

Compacted Drainage stones

1000 x 2000mm concrete pilecap

240

220mm brick wall, to be waterproofed on inside skin

Off shutter finish on U/s of slab

FFL

2000 x 2000mm concrete pilecap refer to eng. detail

PILE FOUNDATION NOTE: pile foundation 28MPA concrete @28 days , 2m x 2m concrete pile cap, 4x ⌀400mm pile foundation to bedrock, Depth of pile foundations to be determined by civil engineer.

DATE ISSUED

TOC Ground Floor level

TOC Basement Level 2

2535

2990

455 2535

2990

230mm brickwork wall, plastered and painted, supported by 900mm x 200mm concrete strip foundation

1564

455mm concrete suspended floor 20MPA @ 28 days, to engineer specification Finish: 50mm polished screed

FFL

TOC Basement Level 2

DESCRIPTION

TOC Basement Level 1 7500

2545

7500 2545

3000

-10400

HVAC system to be used to extract and supply fresh air for all basement levels 600mm secant concrete retaining wall 110mm pipe to sump

3000

455

455

FFL

TOC Basement Level 1

REV:NO

220mm brick wall, to be waterproofed on inside skin with vapour membrane 455mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 20mm carpet

Stage D42

Revision Details:

-3000

NGL SW manhole invert level 1200mm

24 m²

Project Information:

ARPL 3031A 2021 - Project 7.1

Street Level

SW manhole cover

20mm perforated aluminium screen

1310

University of the Witwatersrand

LEVELS/DATUM POINT SW manhole cover -3042 is 0.0

-3042

3871

Polished screed TOC Basement Level 1

Client Information:

-1559

233 m²

STORAGE ROOM 2

RETAINING WALL NOTE: 600mm secant concrete retaining wall, wet wall system to be implemented to effectively waterproof basement. Sump water will be pumped back into the building for re-use.

Tiles TOC Ground Floor level

plastered and painted

Carpet TOC Ground Floor level

5695 TOC First Floor level

GENERATOR RM 15 m²

AUDITORIUM

D3

5740

681240

For lighting detail, refer to electrical engineer specifications

763

310

FFL

23.53 °

4599

50mm polished screed finish

Side walk

11045

52 m²

Drainage Notes: 1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

AUDITORIUM NOTE: Auditrium acoustic quality to be determined by sound engineer, pre fabricated timber panels placed on perimiter of space, roof scape also finished with suspended ceiling

228 mm SAP acoustic timber panels refer to sound engineer detail

28MPA cast in situ concrete, refer to eng detail.

TOC Second Floor Level

455mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: Polished Screed

plastered and painted

RETAIL SPACE

9695

400mm x 900mm concrete column, according to eng detail

4987

566

310 1340

1441

280mm, brickwork cavity cladding wall, insulated with 30mm XPS insulation within 50 mm cavity

455

455

455

3642

Diffuser

D45

4400

50mm curved plywood achieved through steam bending

D42

6590

1:12 cast in situ concrete ramp

-1559

-7400

400mm x 1500mm RC beams overhead, according to eng detail

plastered and painted

Conways Crealco Curtain Wall System, Façade 60 Pressure Glazed Curtain Wall

Street lamp

Jorrisen Street

100mm steel CHS attached to base plate

Suspended HVAC (stainless steel) ducting from concrete floor slab according to mech, eng detail Supplied by DUCT HVAC

To Basement levels

50mm polished screed finish

400mm x 1500mm RC beams overhead, according to eng detail

7254

7500

597

287

4000

7500 DGS

FFL

TOC Ground Floor level

455mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: Polished Screed

plastered and painted

397 m²

7500

4000

TOC Third floor level

Polished Screed TOC First Floor level

455mm concrete suspended floor 20MPA @ 28 days, to engineer specification

38550

8000

7545

7545

MULTI PURPOSE GATHER SPACE

Conways Crealco Curtain Wall System, Façade 60 Pressure Glazed Curtain Wall

FLOOR SLAB NOTE: Structure consists of 455mm solid flat slab floors, consisting of a 7.5 by 5 meter grid. Reinforcement within slab to be referred by the civil engineer.

13695

Service Lane

4000

TOC Second Floor Level

17695 TOC Fourth floor plan

Glazing Note: Glazing to be single clear glass, refer to window and door schedule for further details

100mm steel CHS attached to base plate

50mm curved plywood achieved through steam bending

NGL

280

FFL

20mm perforated aluminium screen

Street Level

3465

1564

89 m²

Suspended HVAC (stainless steel) ducting from concrete floor slab according to mech, eng detail

9695

Off shutter finish on U/s of slab

76

FFL

455

110mm FBO inlet 45° flat F.B.O gratings out of ductile iron

608

455mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: Polished Screed

4000

455

COMPUTER LAB 2

Polsihed Screed TOC Third floor level 34 m²

280

cable tray

lintel over

COMPUTER LAB 4

3

vertical HVAC duct

FFL

400mm x 900mm concrete column, according to eng detail

13677

89 m²

1000mm glas panel balustrade, according to sans specifications

cable tray

D46

Polished Screed TOC Fourth floor plan

4000

76

38550

231 361

FFL

1000mm high glass panel balustrade

TOC Fifth Floor Level 280mm brickwork Cladding wall, 10mm plastered inside and outside, 50mm cavity to be insulated with 30mm XPS insulation.

8695

5015

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

21695

455 280 2350

2019

4588

455mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: Polished Screed

To plant unit on roof

Screed to fall, connected to overflow pipe

25160 TOC Roof Level

455mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: Ceramic Tiles

644

1564

Off shutter finish on U/s of slab

89 m²

DANCE STUDIO 1 3545

3545

20 m²

810

cable tray

lintel over

Polished Screed TOC Fourth floor plan

581

1000mm high glass panel balustrade

FFL

DANCE STU 4

D46

Polished Screed TOC Fifth Floor Level

3010

3010

2350

510

455

455 lintel over

30mm screed to fall

4000

plastered and painted

D45

FFL

WISPECO, Crealco 41mm casement window

13695

TOC First Floor level

67 m²

53

lintel over

5695

Polished Screed TOC Fifth Floor Level

577

747

TOC Third floor level

455

455 3010

lintel over

4605

Triple volume

2370

TOC Fourth floor plan

747

THEATRE PRACTICE 4

cable tray

lintel over

THEATRE PRAC 2

455

17695

50mm XPS insulation

5015

2019

94

3545

4000

TOC Fifth Floor Level

lintel over 584

3539

Property Boundary

21695

110mm FBO inlet

1224

3465

AUDITORIUM NOTE: Auditorium can be accessed from ground floor level, through the direct connecting door, lower levels of auditorium can be accessed through the multilevel ramp or through basement level 1.

torch on waterproofing applied to roof slab, applied by apex waterproofing

glass skylight FFL

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

Concrete coping 230mm brickwork parapet wall ceramic tile finish

HVAC plant unit refer to mech eng. detail

Torch on waterproofing applied by apex waterproofing

0m Building Line

TOC Roof Level

2562

General Notes:

1000mm high glass panel balustrade, mounted on baseplate

4400

5686

50mm XPS insulation

AUDITORIUM NOTE: Auditrium seating to be made of 28MPA @ 28 days, cast in situ concrete, refer to eng. detail.

25160

5000 litre JoJo Water tank 300mm concrete cast in situ lift core

230mm brickwork wall

Property Boundary

GENERAL NOTE : Building to consist of off shutter finish on the U/s of the slab, all services to be exposed, in a neat manner.

2990

747

WATER RETICULATION NOTE: Water to all fixtures will be supplied from the indicated municipal connection, water will be stored in water tank on above the lift core. On the roof level.

3000

1

PILE FOUNDATION NOTE: pile foundation 28MPA concrete @28 days, 2m x 2m concrete pile cap, 4x ⌀400mm pile foundation to bedrock, Depth of pile foundations to be determined by civil engineer.

⌀400mm concrete pile foundation refer to eng. detail

0m

2m

4m

VISUAL SCALE 1:100 @ A1

6m

8m

10m

DRAWING SCALE:

2192396

1:100

DRAWING NUMBER:

DATE:

PR07.1

17/08/2021

DRAWING NAME:

REVISION NUMBER:

PROJECT 7.1 Section A-A

02 Page 3 of 3


PROJECT 7.2 - Working Drawings (Original Submission)


J

I

H

G

F

E

D

C

B

A

K

60129 8400

5000

7500

FLOOR SLAB NOTE: Structure consists of 435mm solid flat slab floors, consisting of a 7.5 by 5 meter grid. Reinforcement within slab to be determined by civil engineer.

5000

5000

7488

7500

7476

230mm curved brickwork wall, supported by prefabricated concrete panels, supported by steel bracing.

230mm curved brickwork wall, supported by prefabricated high density polystyrene panels, supported by steel bracing.

DATUM NOTE: SW manhole cover -3042m is 0.0m Wispeco, crealco, 80mm top hung 3000mm x 1000mm window aluminium frame with single Low-E glass.

Primed and Painted

25160

1725

A

GENERAL NOTE : Building to consist of off shutter finish on the U/s of the slab, all services to be exposed, in a neat manner.

ROOF NOTE: 5mm Ceramic tile finish on roof slab, installed above torch-on waterproofing (Supplied by apex waterproofing), ontop of 80mm XPS insulation, above screed (1:80) to fall layer. Supported by 345mm solid concrete flat slab.

5040

Pre-fabricated mild steel frame/shading device

5mm Barista white ceramic tile 330mm x 330mm First grade ceramic tile 5mm white tile grout

3.7m x 1.5 m Kone MonoSpace DX Stretcher lift according to mech eng detail

Creeper planted screen, supported by timber framework

General Notes:

TOC Roof Level 503

2708

55 506

92

3953

4222

55

3023

531

528

529

67

67

67

504

345

344

76

76

343

2975

3465

55

55

76

T1

1000mm high glass panel railing

DGS

Wispeco, crealco, 80mm top hung 3000mm x 6700mm aluminium window frame with double, tinted Low-E glass.

48

D42

21695

55

530

445

67

TOC Fifth Floor Level

114mm x 228mm SAP timber strut 152mm x 228mm SAP timber bracing

523 521

67

55

67

522

67

DGS

1000mm high glass panel railing

T1

55

Creeper plants installed onto balcony railing

D45

Wispeco, crealco, 80mm top hung 1300mm x 2400mm aluminium window frame with double, tinted Low-E glass.

T1

T1

1128

502

47

D46

D46

581

582

490

499

499

Galvanized mild steel shading device

67

Lift door to be 120min fire rated and sealed for smoke ingress of 30min as per NBR

525 497

67

532

D47

67

578

501

498

508

55

55

55

3510

55

T1

T1

DGS

T1

D46

D46

D7

D6

46

Wispeco, crealco, 80mm top hung 1600mm x 3800mm aluminium window frame with double, tinted Low-E glass.

Fixed 490 55

932

518

TOC Third floor level

509

67

90

Woodoc 50 sealer applied to protect timber from sun and rain

513 64

514 55

9695

14900

DGS

T1

1000mm high glass panel railing

510

103

2400

526

3404

4000

67

45

500

2400

2400

2400

2400

90

2400

20mm perforated aluminium screen 1943

Concrete Upstand

67

175

520

491

67

55

67

T1

1000mm high glass panel railing

492 55

14

505

67

Prefabricated wall panel seam

600mm x 420mm RC column, to eng specification

450

230mm brickwork wet wall, plastered on both sides, primed and painted

600mm x 420mm RC column, to eng specification

8400

-1364

Concrete and brickwork seating area

629

628

69

69

8340

Wispeco, crealco, 80mm skyline double door 2700mm x 4000mm, single Low-E glass

1000mm high glass panel 75mm concrete pavers railing 1:80 screed to fall, to f.b.o outlets

University of the Witwatersrand

T1 D46 D10

D2

D2

C1

C2

Wispeco, crealco, 80mm skyline double door 2000mm x 4000mm, single Low-E glass

NGL

NGL

Project Information:

600mm x 420mm RC column, to eng specification

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification.

-2986

ARPL 3031A 2021 - Project 7.2

4995

5005

Revision Details:

1:12 concrete ramp ⌀110mm Drainage piep from channel to sump (Suspended from floor slab)

1000mm high glass panel railing

7500

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification

FFL

75mm concrete pavers

⌀110mm FBO drainage pipe to sump(Suspended from floor slab)

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification.

1:8 RC vehicle ramp, refer to engineer detail

5000

FFL

Client Information: 1540

7013

69

⌀600mm RC column, to eng specification

7491

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification

First floor basement level

7500

600mm x 420mm RC column, to eng specification

DGS

7476

624

REV:NO

600mm x 420mm RC column, to eng specification

5037

DESCRIPTION

DATE ISSUED

1728

345

345

345

345

1030

-7400 TOC Basement Level 1

630

69

3925

300

600 1037 250

2700

4400

1055

⌀124mm FBO drainage pipe to sump(Suspended from floor slab)

631

T1

345

345

NGL

6383

69

496

705

-1924

-2600

445

TOC Ground Floor level

Tree Box

FFL

FFL

632

208

1000mm high glass panel railing

-3000

250

1712

Conways Crealco Curtain Wall System, Façade 60 Pressure Glazed Shop front

4055

8695

1558

⌀600mm RC column, to eng specification

20mm perforated aluminium screen

6859

T1

⌀600mm RC column, to eng specification

2400

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification

20mm perforated aluminium screen

2400

TOC First Floor level

230

Drainage Notes:

Conways Crealco , Façade 60 Pressure Glazed Shop front

DGS

515

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

T1

2400

5695

67 516

2400

Curved facade to be constructed out of steel frame, prefabricated panels will be lifted onto the steel frame during the construction process.

519 D47

55

3505

4000

114mm x 228mm timber strut 495

511

4000

32560

490

TOC Second Floor Level

Property Boundary

Concrete upstand 596

13695

5000

0m Building Line

4000

TOC Fourth floor plan

8400

570

3555

4000

2458

Property Boundary

17695

T1

Galvanized mild steel gusset plate connection

55

550

Concrete Upstand

T1

290

505

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

355mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification

⌀110mm drainage pipe to sump

A

600mm secant concrete retaining walls depth to be determined by geotech engineer

Section Cut Section Cut N

Drawing Details:

123 456 789 10

NORTH ELEVATION Scale 1:100

0m

2m

4m

VISUAL SCALE 1:100 @ A1

6m

8m

10m

DRAWN BY:

24 1 23 22 2 21 3 20 4 5 19 18 6 17 7 16 8 15 9 14 10 11 13 12

24 1 23 22 2 21 3 20 4 5 19 18 6 17 7 16 8 15 9 14 10 13 11 12 12 11 10 987654321 13 14 15 16 17 18 19 20 21 22 23 24

BUILDING AXO Context of section cut through public space

N

DRAWING SCALE:

2192396

1:100

DRAWING NUMBER:

DATE:

PR07 PR07.2

17/08/2021

DRAWING NAME:

REVISION NUMBER:

PROJECT 7.2 02 North Elevation Page 1 of 3


Water control Roof note: This portion of roof is not membrane accessible Timber fillet 0.8mm Dove grey chromadek IBR counter flashing

0.8mm Dove grey chromadek IBR flashing 5mm Barista white ceramic tile 330mm x 330mm First grade ceramic tile 5mm white tile grout

Section Cut

2

FFL

25386

10mm Ceramic tile finish Torch-on waterproofing 85mm EPS insulation

230mm Concrete Upstand

25160

345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 5mm ceramic tile

TOC Roof Level

100mm max, 30mm min screed to fall (1:80) , to FBO outlet

Thermo-sun GP Laminated double low-e tinted glazing,supplied by glass partners. Section Cut

Wispeco, crealco, 80mm top hung 3000mm x 6700mm aluminium window frame with double, tinted Low-E glass.

Context elevation of perimiter cut

Context section of perimiter cut (Section A-A)

CR - Value required for occupation type = 80HR

Polished Screed

15mm Galvanized Mild steel rib

T1

TOC Fifth Floor Level 67 m²

15mm Galvanized Mild steel sheet metal

345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 30mm Polished screed

DATUM NOTE: SW manhole cover -3042m is 0.0m

CR VALUES FOR EXTERNAL WALLING

THEATRE PRACTICE 2

1000 micron DPC

400mm x 900mm RC column, refer to eng. detail

280mm concrete upstand

30mm polished screed FFL 21695

1471 TOC Fifth Floor Level

R - value

1,44m2K/W

C - Values

337 KJm2k

CR - Values

135 hours

Balcony Composition Note: 100mm max - 30mm min screed to fall (1:80) laid to full bore outlet drainage, 85mm rigid board layed above screed to fall, Torch on waterproofing to be applied to balcony, balcony to be finishd by 5mm white ceramic floor tiles. 5mm dovegrey grout to be applied

30mm expanded polystyrene insulation

805

Mineral board control joint 280mm cavity wall, plastered inside and outside. 76 x 210mm pre stressed concrete lintel

75mm brickforce every 4 courses above lintel 1000 micron DPC

weepholes at 900 centres & above all openings

1000mm high glass panel railing

DANCE STUDIO 4

T2

Polished Screed

5mm Barista white ceramic tile 330mm x 330mm First grade ceramic tile 5mm white tile grout

TOC Fourth floor plan

Water control membrane

20 m²

0.8mm Dove grey chromadek IBR flashing 0.8mm Dove grey chromadek IBR counter flashing

75mm/100mm PVC pipe for overflow Marley streamline galvanised steel 160mm x 200mm gutter to fall downpipes

45° F.B.O gratings out 1000 Micron of ductile iron DPC f.b.o

50mm polished screed

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 50mm Polished screed

300

556

Summer Solstice: 12 AM

FFL

Wispeco, crealco, 80mm skyline sliding 2700mm x 1500mm sliding door, single Low-E glass 351

Values (Actual)

395

External walling Material 10mm Plaster on interior / Sand Cement mixture 110mm stock clay brickwork 30mm EPS insulation within 50mm core cavity 110mm stock clay brickwork 10mm Plaster on exterior / Sand Cement mixture

86 .4 2°

40.6 3°

Winter Solstice: 12 AM

1

1000mm glass(Toughened) panel railing

D46 D7

COMPUTER LAB 4

1000mm glass(Toughened) panel railing

34 m²

400mm x 900mm RC column, refer to eng. detail

Upstand fill (screed) Water control membrane

13695

FFL

TOC Third floor level

395

1000 micron DPC

570

400mm x 1500mm RC beams overhead, according to eng detail

300

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 50mm Polished screed

Bolted galvanized baseplate

2Galvanized C channel fixing c Channel.

40mm steel CHS attached to galvanized steel base plate

300

20mm perforated aluminium screen Alumium perforated screen fixed to wall with bolted connection, glavanized c Channel.

50mm Polished screed

TOC 13425

200

300mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 15mm ceramic tile

5mm ceramic tile finish 5mm torch on waterproofing 0.8mm Dove grey chromadek 85mm rigid board insulation Screed to fall 1:80 IBR counter flashing

300

250mm Concrete upstand

N

Polished Screed

TOC Third floor level

Marley streamline galvanised steel 110mm downpipe

0.8mm Dove grey chrimadek IBR flashing

3599

3605

Wispeco, crealco, 80mm skyline sliding 2700mm x 1500mm sliding door, single Low-E glass

Balcony Composition Note: 100mm max - 30mm min screed to fall (1:80) laid to full bore outlet drainage, 85mm rigid board layed above screed to fall, Torch on waterproofing to be applied to balcony, balcony to be finishd by 5mm white ceramic floor tiles. 5mm dovegrey grout to be applied

Stepped slab to tie into concrete columns, refer to engineer detail.

300mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 15mm ceramic tiles 15mm Mild steel rib 15mm Mild steel plate

1000 micron DPC

300mm steel CHS attached to galvanized steel base plate

502

MULTI PURPOSE GATHER SPACE 40

Stepped slab to tie into concrete columns, refer to engineer detail.

Polished Screed

400mm x 1500mm RC beams overhead, according to eng detail

TOC First Floor level

Suspended HVAC (stainless steel) ducting from concrete floor slab according to mech, eng detail

1000 micron DPC

500

396 m²

400mm x 900mm RC column, refer to eng. detail

Conways Crealco , Façade 60 Pressure Glazed Shop front 1000 micron DPC

30mm polished screed

5695

FFL

TOC First Floor level

Property Boundary 0m Building Line

Jorrisen Street

345

Galvanized C channel fixing

500

345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 30mm Polished screed

400mm x 1500mm RC beams overhead, according to eng detail Drip

230mm brickwork wall, plastered inside and outside (Stock clay brick)

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 30mm Polished screed

500

1000mm high glass panel railing

400mm x 1500mm RC beams overhead, according to eng detail

RETAIL SPACE Polished Screed

TOC Ground Floor level

20mm suspended plywood ceiling

52 m²

Sidewalk

RECEPTION LOBBY

200mm concrete upstand

Polished Screed

1000mm high glass panel railing 75mm concrete pavers

75mm concrete pavers

110mm brickwork wall, primed and painted, plastered on exterior

600mm concrete secant retaining wall beam

116 m² T1

1000mm high glass panel railing

weepholes at 900 centres & above all openings 75mm concrete pavers

Wispeco, crealco, 80mm skyline double door 2700mm x 4000mm, single Low-E glass

FFL

50mm Polished screed

75mm concrete pavers Screed to fall, 1:80 249

345

600mm concrete secant retaining wall, refer to eng, detail 230mm Wet Wall, plastered on both sides, primed and painted

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204

Drainage Notes: 1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

0.5m

1m

1.5m

PERIMITER SECTION DETAIL

0m

Scale 1:25

VISUAL SCALE 1:25 @ A1

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

-3000

1000 micron DPC

-3065

Polymer Drainage Channel 1m H55 ACO

General Notes:

Street Level

TOC Ground Floor level

1:12 concrete ramp

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification.

-1559

2m

2.5m

TOC Ground Floor level

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 30mm Polished screed 250mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 30mm Polished screed

Revision Details: REV:NO

DESCRIPTION

Drawing Details:

DATE ISSUED

DRAWN BY:

Client Information:

University of the Witwatersrand Project Information:

ARPL 3031A 2021 - Project 7.2

DRAWING SCALE:

2192396

1:25

DRAWING NUMBER:

DATE:

PRS_7.2

01/10/2021

DRAWING NAME:

REVISION NUMBER:

Project 7.2 02 Perimiter Detail Sheet 2 of 3


345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 30mm Polished screed

3 1000 Micron DPC

FFL

M20 galvanized mild steel washer, M20 galvanized mild steel Nut weepholes at 900 centres & above all openings Fire stop to be applied at each level

21695

345

Capliniary Break

M20x300mm galvanized mild steel threaded rod, cast into place 20mm galvanized mild steel baseplate

TOC Fifth Floor Level

FINISH NOTE : Building to consist of off shutter finish on the U/s of the slab, all services to be exposed.

⌀120mm CHS steel frame member

30mm EPS insulation

General Notes:

⌀440 concrete column, according to eng detail

Galvanized mild Steel Spacer Prefabricated bricwork cavity wall, to be assembled on site. Brickwork plastered on interior and exterior

4000

BUILDING AXO

3649

4000

15mm galvanized steel backing

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

FINANCE MANAGER OFFICE Carpet

Galvanized mild Steel Spacer

TOC Fourth floor plan 23 m²

345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 10mm carpet

FFL

weepholes at 900 centres & above all openings Fire stop to be applied at each level

M20x300mm galvanized steel mild threaded rod, cast into place

17695

Concrete upstand

Capliniary Break weepholes at 900 centres & above all openings 15mm galcanized mild steel sheet metal Galvanized Mild steel rib

357

10mm carpet

FACADE ASSEMBLY

1000 Micron DPC 20mm galvanized mild steel baseplate

TOC Fourth floor plan

Envelope wall/cladding

Covered Balcony

Tubular steel frame, bolted to concrete floor slab

1000 Micron DPC 15mm galvanized steel backing

Prefabricated mild steel Window frame

1000 micron DPC

Envelope wall/cladding steel backing

20mm perforated alumium screen

Fixed

Window frame

3649

4000 12000

Wispeco, crealco, 80mm top hung 3000mm x 1000mm window aluminium frame with single Low-E glass.

4000

12000

⌀440 concrete column, according to eng detail

LARGE COMPUTER LAB

Concrete floor slab

Drainage Notes:

ENVELOPE ASSEMBLY

1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

Summer Solstice 12:00 PM - 86°

Polished Screed

TOC Third floor level 102 m²

M20x300mm galvanized mildvsteel threaded rod, cast into place

Prefab mild steel frame to house window frame.

345

TOC Third floor level

SUN ANGLES

Fire stop to be applied at each level 345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 30mm polished screed U/S finish: Off shutter

⌀440 concrete column, according to eng detail

University of the Witwatersrand

13695

120mm CHS steel frame member Capliniary Break 20mm galvanized mild steel baseplate

Winter Solstice 12:00 PM - 40°

Client Information:

weepholes at 900 centres & above all openings

FFL

3° 40.6

30mm polished screed

0° .0 85

1000 micron DPC

weepholes at 900 centres & above all openings

Project Information:

FENESTRATION CALCULATIONS/GLAZING

ARPL 3031A 2021 - Project 7.2

15mm galvanized mild steel sheet metal

1000 Micron DPC 1000 micron DPC

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Galvanized Mild steel rib

Revision Details:

3655

4000

Wispeco, crealco, 80mm casement 1600mm x 1000mm window aluminium frame with single Low-E glass.

OFFICE 4

Polished Screed

1000 micron DPC

TOC Second Floor level 51 m²

TOC Second Floor level

FFL 345

9695

345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 30mm polished screed

M20x250mm galvanized steel threaded rod, cast into place

PERIMITER SECTION DETAIL Scale 1:25

0m

0.5m

1m

VISUAL SCALE 1:25 @ A1

1.5m

Prefab steel frame to house window frame. 15mm galvanized mild steel sheet metal 15mm Galvanized Mild steel rib

10mm sand, cement plaster on exterior and interior 1000 micron DPC Concrete upstand Torch-on waterproofing 1:80 screed to fall, FBO, FBO pipe connection to drainage pipe within column

M20 galvanized steel Nut 20mm galvanized mild steel baseplate

30mm polished screed

DATE ISSUED

30mm expanded polystyrene insulation

15mm galvanized steel backing

30mm polished screed

DESCRIPTION

4000

REV:NO

2m

2.5m

Drawing Details:

9695

DRAWN BY: TOC Second Floor level

DRAWING SCALE:

2192396

1:25

CR VALUES FOR EXTERNAL WALLING

DRAWING NUMBER:

DATE:

CR - Value required for occupation type = 80HR

PR07.2

17/08/2021

DRAWING NAME:

REVISION NUMBER:

PROJECT 7.2 Perimiter Section 2

02

External walling Material

Values

10mm Plaster on interior / Sand Cement mixture 110mm stock clay brickwork 30mm EPS insulation within 50mm core cavity 110mm stock clay brickwork 10mm Plaster on exterior / Sand Cement mixture

R - value

1,44m2K/W

C - Values

337 KJm2k

CR - Values

135 hours

Page 3 of 3


C

1 48

A

D

C

D

F 843

-

32 m²

lintel over

830

4

5915

3m

5m

VISUAL SCALE 1:50 @ A1

Electrical Duct 700mm x 600mm DB board (3-Phase Large Side Isolator Distribution Board)

Tiles TOC Ground Floor level

3184

---

1600

968

1025

1207

556

lintel over

whb

5mm Barista white ceramic tile 330mm x 330mm First grade ceramic tile 5mm dovegrey tile grout On 5 mm tile adhesive

245 165

Movement sensor (Radiant GPE039-W (RFS48) Disc-4LED Pir Sensor Light)

330

400

DB board (3-Phase Large Side Isolator Distribution Board) lintel over

MALE AND FEMALE ABLUTION DETAIL_TILE LAYOUT Scale 1:50

whb

32 m²

Geberit Sigma concealed cistern Geberit Icon Pan Rimfree Wall-Hung White

-3000

i.e

SECTION G-G Toilets Tile Layout

45 ⌀50mm single stack system ⌀50mm uPVC waste pipe

i.e

463

whb

whb

whb

843

988

991

882

968

1025

1007

⌀22mm insulated copper water supply pipe

WT

FEMALE BATHROOM Suspended ceiling

29 m²

University of the Witwatersrand

whb

whb 990

990

Geberit Sigma concealed cistern

⌀50mm uPVC waster pipe, connected to ⌀110mm uPVC sewage pipe. (1:40)

Geberit Sigma concealed cistern

Mentis Grating to be installed within wet service duct at every floor level

i.e

i.e

wc

i.e

wc

i.e

Cold Water outlet only (Fixture)/WC Cold and warm Water outlet (Fixture, Cold Only))/WHB

cw

i.e i.e cw

cw

wc 1871

1880

whb

WT

Water supply from water tank

cw

Cold Water supply pipe (⌀22mm)

hw

Warm water supply pipe (⌀22mm)

cw

wc

507

i.e

i.e i.e WT Single stack reticulation system ⌀110mm uPVC sewage pipe at 1:40 fall wc 1011

wc 1649

1019

FEMALE BATHROOM Tiles TOC Ground Floor level

1865

1025

29 m²

1018

998

whb

1047

whb

1047

whb

1047

whb

cw

WHB

1350

Wash hand basin (Grohe cube counter top basin 50)

whb

Grohe cube counter top basin 50 Cobra P-trap, ⌀50mm

460

whb

1047

928

5 1047

20mm Perforated screen

Water closet (Geberit Sigma concealed cistern)

WC

5

i.e

i.e

i.e

i.e

D

i.e

i.e

i.e

⌀50mm uPVC waste pipe ⌀50mm single stack system

WATER RETICULATION LAYOUT Scale 1:50

0m

1m

2m

VISUAL SCALE 1:50 @ A1

3m

5m

VISUAL SCALE 1:50 @ A1

DESCRIPTION

01

Mechanical ventilation

DATE ISSUED 06/10/2021

01

Louver door spec

06/10/2021

01

Suspended ceiling tiles

06/10/2021

01

Tiling set out point

06/10/2021

01

Vanity Elevation

06/10/2021

4 Single stack sewage reticulation system

⌀110mm uPVC sewage pipe

1010

4m

3m

REV:NO

4990

⌀50mm uPVC waste pipe

892

0m

5

22mm water supply pipe, chased within wall cw

cw

4m

FEMALE BATHROOM

cw

29 m²

whb

Single stack waste reticulation system Suspended from floor slab above

WT

cw

i.e i.e cw

411

Project Information:

ARPL 3031A 2021 - Project 7.2

TOC Ground Floor level

Geberit Sigma concealed cistern Geberit Icon Pan Rimfree Wall-Hung White

wc

i.e

cw

cw

cw

cw

2m

1m

cw

cw

5 ⌀110pmm uPVC sewage pipe at 1:40 fall

-3000

Geberit Icon Pan Rimfree Wall-Hung White

wc

MALE BATHROOM 32 m²

cw

E

cw

lintel over

⌀110mm uPvc sewage pipe (1:40 fall)

wc

cw

wc

cw

555

1015

1018

wc

SECTION E-E Vertical Reticulation Layout Scale 1:50

Water reticulation Legend

32 m²

2130

1853

1865

1865

Tiles TOC Ground Floor level

200

MALE BATHROOM

wc

i.e i.e

i.e

⌀110mm uPVC sewage pipe at 1:40 fall

4

949

2545

1061

2330

1020

cw

1020

whb 505

45

wc

1447

cw

E

Client Information:

lintel over

⌀50mm uPvc waste pipe

i.e

⌀63mm uPVC water supply pipe, to water tank located on the roof

Drainage Notes: 1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

⌀110mm single stack PVC sewage pipe

Tiles TOC Ground Floor level

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Revision Details: 1865

⌀50mm uPVC waste pipe

20mm supawood bulkhead LED Strip Lights 12Volts Cool White Colour SMD5050

D

lintel over

4

631

ELECTRICAL LAYOUT_ REFLECTED CEILING PLAN Scale 1:50

Scale 1:50

⌀22mm insulated copper water supply pipe, chased in wall WATER RETICULATION NOTE: Watter supply from municipality to flow into water tank on the roof level, from roof water tank, will supply fixtures within building.

i.e

lintel over

508

1600

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

D

i.e

i.e

1620

C

TOC Ground Floor level

4

5

20mm perforated screen

330mm X 120mm white barista tile skirting

-3000

D

400mm x 900mm concrete column, according to eng detail

5mm Barista white ceramic tile 330mm x 330mm First grade ceramic tile 5mm white grout

MALE BATHROOM

TOC Ground Floor level

C

22mm insulated copper water supply pipe, supplied from water tank, located on roof.

330

Floating vanity 330mm X 120mm white barista tile skirting

SECTION F-F Vanity Tile Layout Scale 1:50

892

Geberit Sigma concealed cistern

Geberit Icon Pan Rimfree WallHung White

i.e

whb

⌀50mm uPvc waste pipe

whb

Partition Wall

1730

whb

LED Strip Lights 12Volts Cool White Colour SMD5050 (Hidden behind Bulkhead, above vanity)

29 m²

400mm x 500mm fibre glass suspended ceiling tiles

330

330 whb

715

whb

Double Plug Point (Veti 2VW224 Double RSA V-Slim 4x4 Socket White) Eurolux Round 8 Inch Extractor Ceiling Fan (300mm) White F46W Number of extractor fans deternined by mechanical engineer

Tiles TOC Ground Floor level

558

Cristallo Silver Frameless Mirror - 2200 x 700mm 20mm supawood bulkhead 5mm Barista white ceramic tile 330mm x 330mm First grade ceramic tile 5mm white grout

2200

2

1207

881

5

1025

1499

871

902

5mm Barista white ceramic tile 330mm x 330mm First grade ceramic tile 5mm dovegrey tile grout on 5 mm tile adhesive

968

FEMALE BATHROOM

⌀220mm HVAC ducting overhead HT/LT Room

Tiles TOC Ground Floor level

7158

1600

1499

3283

3283

5

FEMALE BATHROOM 29 m²

2200

Single switch panel (Veti Switch 1-Lever 2way - White)

857

220mm brickwork wall,10mm plaster inside and putside, 2 coat painted finish

857

165 245

Stainless steel Dividing strip

5

286

LED Recessed Downlight (Bright Star Lighting DL035 Integrated Downlight - Cool White (30W))

4

730

6505Wet service duct

400mm x 500mm fibre glass suspended ceiling tiles

32 m²

854

854

4

330

MALE BATHROOM

Electrical Legend

32 m²

500

850

Tiles TOC Ground Floor level

lintel over

lintel over

lintel over

MALE BATHROOM

1473

330

G

400mm x 900mm concrete column, according to eng detail

1473

330

7

330

General Notes:

2

Closet

45

Setting out point (Start Point) Setting out point (Start point)

LED Strip Lights 12Volts Cool White Colour SMD5050 2100mm x 900mm door, louvers to be installed

2330 2545

4

MALE BATHROOM

2m

1m

0m 330mm X 120mm white barista tile skirting Stainless steel Dividing strip

lintel over

4m

i.e

⌀22mm insulated copper water supply pipe 20mm suspended fibreglass ceiling tile

Grohe cube counter top basin 50

-3000

DRAWING SCALE:

2192396

1:50

DRAWING NUMBER:

DATE:

PRAB7.2

14/09/2021

DRAWING NAME:

REVISION NUMBER:

wc

TOC Ground Floor level

5m

SECTION D-D Scale 1:50

Drawing Details: DRAWN BY:

Suspended mentis grate floor installed at every level in duct

PROJECT 7.2 02 Ablution Details Page 1 of 2


Components: 1. Brickwork Wall 2. Amalfi Jade plus mixer tap (x5) 3. Grohe cube counter top basin 50 (x5) 4. Snowstorm Quartz countertop (20mm) (460mm x 5000mm) (x1) 5. Snowstorm Quartz countertop (20mm) (390mm x 5000mm) (x1) 6. Prefabricated mild steel frame (steel segments(35mm SHS) to be welded together. (x6) 7. M20 mild steel nut, M20 mild steel 1. washer, M20 threaded bolt (x24)

5000 988

991

35

955

990

35

955

35

990 933

35

891

35

126

875

460

20 mm supawood bulkhead 20 mm Snowstorm Quartz countertop

whb

whb

25mm mild steel SHS 110

whb

whb

Amalfi Jade Plus Chrome Basin Mixer Tap

35mm mild steel SHS

893

whb

990

991

Grohe cube counter top basin 50

968

General Notes:

2.

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

3.

4. 5.

927

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

6. 7.

VANITY DETAIL_Callout A

0m

Scale 1:10

VISUAL SCALE 1:10 @ A1

0.2m

0.4m

0.6m

0.8m

H

1m

H

3 48

3

Vanity assembly diagram

48

20mm suspended fibre glass ceiling tile

MALE BATHROOM

Tiled

Tiles

TOC Ground Floor level 32 m²

Drainage Notes:

LED Strip Lights 12Volts Warm White Colour SMD5050

20mm supawood bulkhead

Cristallo Silver Frameless Mirror - 2200 x 700mm

Cristallo Silver Frameless Mirror - 2200 x 700mm Cristallo Silver Frameless Mirror - 2200 x 700mm

988

whb

991

whb

990

990

969

533

whb

908

91 35

143

857

35

955

35

20mm Snowstorm Quartz facing

-3000 TOC Ground Floor level

954 5001

35

934

35

873

University of the Witwatersrand Project Information:

Revision Details:

20 mm Snowstorm Quartz facing glued onto steel frame 25mm mild steel SHS 35mm mild steel SHS

DESCRIPTION

01

Dimensions

06/10/2021

01

Detailed Specifications

06/10/2021

01

Hidden elements

06/10/2021

I.E 440

35 125

5mm Tile adhesive 5mm dovegrey grout 30mm screed

35mm square hollow section, frame welded and assembled off site

GIO Chrome Bottle Trap (80 x 120mm)

-3000

Drawing Details:

TOC Ground Floor level

VANITY DETAIL

0m

Scale 1:10

VISUAL SCALE 1:10 @ A1

0.2m

0.4m

0.6m

0.8m

1m

DATE ISSUED

REV:NO

420

723

720

989

whb

720

990

whb

Grohe cube counter top basin 50 20mm Snowstorm Quartz countertop Glued onto steel frame 7° 24 42.7

892

20mm Snowstorm Quartz countertop

25

Grohe cube counter top basin 50

Client Information:

ARPL 3031A 2021 - Project 7.2

460

317

400

Amalfi Jade Plus Chrome Basin Mixer Tap

101 25

99

Amalfi Jade Plus Chrome Basin Mixer Tap

50mm PVC waste pipe

20mm supawood bulkhead

1. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

DRAWN BY:

SECTION H-H Scale 1:10

DRAWING SCALE:

2192396

1:10

DRAWING NUMBER:

DATE:

PRVT7.2

14/09/2021

DRAWING NAME:

REVISION NUMBER:

PROJECT 7.2 Vanity Detail

02 Page 2 of 2


J

I

H

G

F

E

D

C

B

A

K

60129 5000

7500

FLOOR SLAB NOTE: Structure consists of 435mm solid flat slab floors, consisting of a 7.5 by 5 meter grid. Reinforcement within slab to be determined by civil engineer.

5000

5000

7488

7476

5040

GENERAL NOTE : Building to consist of off shutter finish on the U/s of the slab, all services to be exposed, in a neat manner.

ROOF NOTE: 5mm Ceramic tile finish on roof slab, installed above torch-on waterproofing (Supplied by apex waterproofing), ontop of 80mm XPS insulation, above screed (1:80) to fall layer. Supported by 345mm solid concrete flat slab.

Wispeco, crealco, 80mm top hung 3000mm x 1000mm window aluminium frame with single Low-E glass.

10mm plaster Primed and Painted 2 coat white paint

Pre-fabricated mild steel frame/shading device

General Notes:

1725

230mm curved brickwork wall, supported by prefabricated concrete panels, supported by steel bracing.

230mm curved brickwork wall, supported by prefabricated RC concrete panels, supported by steel bracing, tied into structural column grid.

DATUM NOTE: SW manhole cover -3042m is 0.0m

25160

7500

5mm Barista white ceramic tile 330mm x 330mm First grade ceramic tile 5mm white tile grout, fixed with metal tie between every course

3.7m x 1.5 m Kone MonoSpace DX Stretcher lift according to mech eng detail

Creeper planted screen, supported by timber framework, refer to detail drawing 3

Wispeco, crealco, 80mm top hung 3000mm x 6700mm aluminium window frame with double, tinted Low-E glass.

1213

8400

TOC Roof Level 503

2733

55 506

92

3953

4222

55

3023

67

55

528

529

67

67

345

344

76

76

343 76

T1

1000mm high glass panel railing

DGS 48

2997

531 504

2975

3501

3465

55

D42

Galvanized mild steel gusset plate connection

55

550

Concrete Upstand

T1

290

505

55

530

TOC Fifth Floor Level

T1

523 521

67

570

502

55

67

522

67

DGS

T1

55

Creeper plants installed onto balcony railing

3235

T1

1128

3555

5000

D45

1000mm high glass panel railing

47

D46

D46

581

582

499

Wispeco, crealco, 80mm top hung 1600mm x 3800mm aluminium window frame with double, tinted Low-E glass.

490

600 67

Lift door to be 120min fire rated and sealed for smoke ingress of 30min as per NBR

525 497

67

D47 578

67 501

498

508

55

55

55

3510

532

3450

55

T1 D46 DGS

T1

4010

499

Galvanized mild steel shading device

T1 D46

D7

D6

46

Fixed 490

Woodoc 50 sealer applied to protect timber from sun and rain

509 90

67 513 64

514 55

9695

T1

510

14900

DGS

1000mm high glass panel railing

103

2400

526

3404

4000

67

45

500

2400

2400

2400

1977

518

596

TOC Third floor level

550

55

Concrete upstand Finish: 10mm plaster finish

932

0m Building Line

13695

8400

3732

2458

4000 4000

TOC Fourth floor plan

Wispeco, crealco, 80mm top hung 1300mm x 2400mm aluminium window frame with double, tinted Low-E glass.

114mm x 228mm SAP timber strut 152mm x 228mm SAP timber bracing

Property Boundary

17695

T1

445

67

2400

90

2400

8020

490

TOC Second Floor Level

10mm perforated aluminium screen Alumium perforated screen fixed to wall with bolted connection, glavanized c Channel.

Concrete Upstand

491

67

55

T1

1000mm high glass panel railing

55

DGS

515

14

3396

450

1712

69

Concrete and brickwork seating area

FFL

-1364

629

628

69

69

Project Information:

8340

T1

1540

Wispeco, crealco, 80mm skyline double door 2700mm x 4000mm, single Low-E glass

1000mm high glass panel 75mm concrete pavers railing 1:80 screed to fall, to f.b.o outlets

345

ARPL 3031A 2021 - Project 7.2

T1 D46 D10

Wispeco, crealco, 80mm skyline double door 2000mm x 4000mm, single Low-E glass 147

NGL

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification.

NGL

Conways Crealco Curtain Wall System, Façade 60 Pressure Glazed Shop front

University of the Witwatersrand

15045

7013

630

69

208

631

69

T1

⌀600mm RC column, to eng specification

1450

-872

Tree Box

1000mm high glass panel railing

632

496

FFL

-1548

6383

705

TOC Ground Floor level

FFL

250

⌀600mm RC column, to eng specification

3484

8695

⌀600mm RC column, to eng specification

2400

6859

600mm x 420mm RC column, to eng specification 2400

Prefabricated wall panel, 10mm plastered finish, fixed to steel circular hollow section.

1558

Elevation Notes: 1. All surface to comply with NBR. 2. Public access ramps to be 1:12 gradient 3. Car access ramps to be 1:8 within basement. 4. Fenestration to comply with SANS 10400 XA, SANS 204 5. All structural columns to be plastered, primed and 2 coat paint to be applied. 6. FBO to be ⌀90mm at minimum 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum. 9. All railings to be 1000mm high at minimum. 10. All levels to be checked by Contractor.

Client Information:

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification

10mm perforated aluminium screen Alumium perforated screen fixed to floorslab with bolted connection.

230

T1

Conways Crealco , Façade 60 Pressure Glazed Shop front

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

505

67

TOC First Floor level

-3000

4000

520

492

15435

67

175

2400

5695

519 D47

55

67 67

2400

495

511 516

3505

4000

114mm x 228mm timber strut

Curved facade to be constructed out of steel frame, prefabricated panels will be lifted onto the steel frame during the construction process.

Property Boundary

21695

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

Revision Details:

NGL REV:NO

DESCRIPTION

01

Show basement sec. 15/10/2021

DATE ISSUED

01

Legibility

15/10/2021

01

Public space steps

15/10/2021

01

Exterior finish

15/10/2021

02

Tile fixing

25/10/2021

02

Side hung door height 25/10/2021

Drawing Details: DRAWN BY:

NORTH ELEVATION Scale 1:100

0m

2m

4m

6m

8m

10m

DRAWING SCALE:

2192396

1:100

DRAWING NUMBER:

DATE:

PR07 PR07.2

17/08/2021

DRAWING NAME:

REVISION NUMBER:

VISUAL SCALE 1:100 @ A1

PROJECT 7.2 03 North Elevation Page 4 of 8


PROJECT 7 (7.1/7.2) Working Drawings (Final Rework)


WITS EAST CAMPUS SOUTH ENTRANCE

WITS THEATRE

Site dimensions AB 63m BC 31m CD 63m DA 31m

sidewalk

bus stop

1739

B

L

C

7494 5400

Kerb

E

H

I 1

63532 5000

7491

G

F 5000

5000

7500

Street Parking

8400

Street Parking Kerb

F.B.O (⌀120mm)

F.B.O (⌀110mm)

50mm paving placed above torch-on waterproofing layer

FFL_18800

31m

Covered balcony

7500

Covered balcony

FFL_10850 F.B.O (⌀120mm)

Property Boundary

F.B.O (⌀160mm)

4330

23546

5000 litre Water storage tank

FFL_-1900 Covered balcony

FFL_26291

FFL_22830

22450

250

DGS

4406 1612

D

8

7

6

5

4

3

2

1

3804

13 14 15 16 17 18 19 20 21 22 23 24

63m

50mm paving placed above torch-on waterproofing layer

STAIRCASE NOTE: Concrete cast in situ staircase 24 risers 250mm min treads , 170mm max risers 1000mm balustrade

Pre-fabricated mild steel frame/shading device

Kerb

Boomed access control Concrete Landing

ERF 2952

31m

3

1

SW SUMP

Municipal Water Supply Sewer Manhole Invert Level 1200m

Municipal Sewage

LEVELS/DATUM

Parking Exit

5

A

ERF 2929

Contour 1740 = 0.0

ERF 2930

ERF 2931

Service Lane

173

ERF 2932

ERF 2934

m

ERF 2951

1

C

Stormwater Note: All stormwater on roof will move of the roof through a series of full bore outlets, connected to downpipes within structural columns, water flows into sump on lowest baseent floor for re-use. Overflow to be connected to municpal stormwater sump.

38sqm

Auditrium Back Stage Area

35sqm

Storage Room 2

24sqm

Male Bathroom

24sqm

Female Bathroom

24sqm

Retail

53sqm

Restaurant kitchen

46sqm

Refuse Area

11sqm

Generator Room

17sqm

HTLT Room

8sqm

Male Bathroom

24sqm

Female Bathroom

24sqm

IT maintenance room

32sqm

Security Office

9sqm

Public Relations office

8sqm

Closet

2sqm

Reception Lobby

127sqm

Letable Offices

153sqm

Reading Room

43sqm

Male Bathroom

24sqm

Female Bathroom

24sqm

Male Bathroom

24sqm

Multi-purpose gather space

394sqm

Second Floor Level

-3298 -1948

7 73

4

UP 1:8 concrete ramp to Parking Entrance basement parking

Property Boundary

243sqm

Storage Room 1

First Floor Level

FFL_-3300

UP 1151

F.B.O (⌀196mm)

5054

12 11 10 9

FFL_-970

F.B.O (⌀90mm)

220mm brick parapet wall

368

3110

Covered balcony Finish, stone(gravel), laid on F.B.O (⌀120mm) torch on waterproofing, laid on 1:80 screed to fall. downpipe connected to colum downpipe.

F.B.O (⌀160mm)

F.B.O (⌀140mm)

UP

Covered balcony

F.B.O (⌀160mm)

345mm concrete suspended floor 20MPA @ 28 days, to engineer specification Finish: Ceramic Tiles laid on torch-on waterproofing, above 1:80 screed to fall, laid on 85mm XPS insulation.

290

345mm concrete flat slab, according to eng detail, Finish: 50mm Concrete pavers, laid on torch on waterproofing 1000mm glass panel railing

FFL_14730 3821

HVAC UNIT (Plant room), according to mechanical engineer detail, fixed onto concrete slab.

4986

ERF 2937

7499

31344

Glass Skylight F.B.O (⌀160mm)

2

UP

37 51

375 1

F.B.O (⌀120mm)

UP

5m

6 73

m

sidewalk

FFL_-980

ERF 2940

STATION STREET

FFL_-420

1738m

7500

Creeper planted screen suspended by a timber structure, refer to callout detail B

345mm concrete flat slab, according to eng detail Finish: 50mm Concrete pavers, laid on torch on waterproofing

7500

Brickwork seating

UP

r detail enginee

7500

ref er to

1

5003

ramp,

0m Building Line Property Boundary

220mm curved plastered concrete panel wall, supported by steel bracing, refer to eng. detail. Finish: 10mm plaster, primed and 2 coat pain to be applied

ncrete 1:12 co

1:12 concrete ramp

7500

14765

sidewalk

31344

Fever trees, according to landscape architect details, planter to be waterproofed with mariseal. Drainage to flow into sump.

1:12 concrete ramp

746 Creeper planted screen suspended by a timber structure

Exterior Balcony

B

Property Boundary 0m Building Line

Timber Backrest

F.B.O (⌀100MM)

8233

63m

FFL_-704

1:12 concrete ramp

A1 set out point

-1648

730

Sidewalk bollard

3110

A

m

Auditorium

Ground Floor Level

sidewalk

-432

8 73

2441

Kerb

17

D

7500 2450

4994

40m

1753

Actual 4450sqm 2.1 45%

-1 Basement Level

A A

Allowable 5000sqm 2.1 50%

Total Floor Area Total F.A.R Total Coverage Area Schedule

JORRISEN STREET

J

Statutory Requirements Description Total 1985m2 Site Area

Offices

168sqm

Security control room

33sqm

Server Room

10sqm

Male Bathroom

24sqm

Female Bathroom

24sqm

4m

8m

12m

16m

20m

Refuse Calculations f(g) × FA / 100 = volume (m³)/week f(g) = Offices 0.2258 f(g) = Shops 0.92353

VISUAL SCALE 1:200 @ A1

N

Offices 0.2258 x 1030sqm/100 = 2.32 (m3)/week

SITE

Site Plan N

Scale 1:200

Locality Map - 48 Jorissen ST

Shops 0.92353 x 53sqm/100 = 0.48 (m3)/week Storage Area size: 2.8m3 perweek x 4 bins/m3 = 11 bins That would require 11sqm size for refuse room

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Site Plan Notes: 1. Site pegs to be confirmed by contractor. 2. All levels to be checked by contractor. 3. Screed to fall in public space and roof to be 1:80 max. 4. Distance between site pegs to be checked by contractor. 5. Grid A1 to be used as set out point for structural grid. 6. Drawing to comply with SANS 10400 XA, SANS 204.

Third Floor Level

Alleyway

Computer Labs

372sqm

Seminar rooms

79sqm

Male Bathroom

24sqm

Female Bathroom

24sqm

Client Information:

University of the Witwatersrand Project Information:

Fourth Floor Level Dance Studios

241sqm

Board Room

29sqm

Offices

114sqm

Storage Room

13sqm

Computer Labs

372sqm

Fifth Floor Level 0m

General Notes: 1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

ARPL 3031A 2021 - Project 7.2 Revision Details: REV:NO

DESCRIPTION

01

Legibility

DATE ISSUED

01

Public space waterpr 18/08/2021

18/08/2021

Theatre Practice rooms

266sqm

Offices

138sqm

01

External context

18/08/2021

Male Bathrooms

24sqm

01

Street contours

18/08/2021

Female Bathrooms

24sqm

02

Site set out point

25/10/2021

02

Levels

25/10/2021

02

Waterproofing pspac. 25/10/2021

02

Screed to fall on roof

02

Screed to fall balcony 02/11/2021

03

Legibility

Stormwater Calculations Roof Slab Area

1m² = 1cm²

πr² 1. 18.5m x 7.2m = 133m² = 3.142(7)² = ⌀155sqmm pipe = ⌀140mm pipe 2. 15m x 20m = 300m² = 3.142(9.8)² = ⌀301sqmm pipe = ⌀196mm pipe 3. 15m x 13m = 195m² = 3.142(8)² = ⌀201sqmm pipe = ⌀160mm pipe 4. 5m x 10m = 50m²

Public Space

= 3.142(4.5)² = ⌀64sqmm pipe = ⌀90mm pipe

1m² = 1cm²

πr² 1. 13m x 7.5m = 98m² = 3.142(5.5)² = ⌀96sqmm pipe = ⌀110mm pipe 2. 15m x 4.5m = 68m² = 3.142(5)² = ⌀79sqmm pipe = ⌀100mm pipe 3. 15m x 8m = 120m² = 3.142(6.2)² = 121sqmm = ⌀124mm pipe

4. 12.5m x 7.5m = 120m² = 3.142(6.2)² = 121sqmm = ⌀124mm pipe 5. 7.5m x 7.5m = 56m² = 3.142(4.5)² = 64sqmm = ⌀90mm pipe

01/11/2021 03/11/2021

Drawing Details: DRAWN BY:

DRAWING SCALE:

2192396

1:200

DRAWING NUMBER:

DATE:

PR07.1

17/08/2021

DRAWING NAME:

REVISION NUMBER:

PROJECT 7.1 Site Plan

04 Page 1 of 8


1739m

1740m

AUDITORIUM NOTE: Auditorium can be accessed from ground floor level, through the direct connecting door, lower levels of auditorium can be accessed through the multilevel ramp or through basement level 1.

JORRISEN STREET

J

A

A

L

B

C

E

D

WATER RETICULATION NOTE: Water to all fixtures will be supplied from the indicated municipal connection, water will be stored in water tank on above the lift core. On the roof level.

G

F

STORMWATER NOTE: Stormwater reticulation within public space will be dealt dealt with screed to fall, leading into seperate full bore outlets, From the full bore outlets the piping reticulates to the sumps at the lowest basement floor. Stormwater will be reused within the building.

I

H

63532

General Notes: 1753

4994

290

7494

10710

7500

250

3595

5000

7491

201

14794

7500

5000

400

9795

7500

127

2441

8400

5000 4806

317

3600

4528

2463

1738m

Sidewalk_50mm concrete paving finish

Tiles

250

ie

ie

ie

wc

wc

D42 358

25

1000

25

993

25

973

4735

D42

D42

D42

D12

D13

D14

ie

ie

Tiles 28 m²

whb

whb

ie

ie

ie

S

250

2631

19 231

1949

ie

290

301

6365

D42

533

C3

250

730

1000mm high glass panel balustrade

Gas Bottles

7568

7500

1:12 concrete ramp, according to eng detail (Slip resistant coating)

8233

250665 6008 2154 250

4

5 1:8 concrete ramp to basement parking

D36

1550

Property Boundary

UP Parking Entrance

C

LEVELS/DATUM Contour 1740 = 0.0

Municipal Sewage Connection

ERF 2931

STAIRCASE NOTE: 28 meter high Concrete cast in situ staircase, 24 risers 250mm min treads , 170mm max risers 1000mm balustrade Finish: Slip resistant coating

ERF 2932

Ground Floor Plan

0m

Scale 1:100

VISUAL SCALE 1:100 @ A1

2m

4m

6m

8m

SERVICE LANE ERF 2934

10m

m 35 17

STATION STREET

ERF 2930

Sewer Manhole Invert Level = 1200m

Municipal Stormwater Pipe

A

Municipal Sewage Pipe

L

N

REV:NO

DESCRIPTION

01

Bathroom stalls

29/09/2021

01

Dimensions

29/09/2021

01

Public space waterpr. 29/09/2021

DATE ISSUED

01

Public space waterpr. 29/09/2021

02

Grid Line K

02

Grid B2

13/10/2021

02

Fire escape lobby

13/10/2021

Kitchen store walls

03/11/2021

Municipal Water supply 03

SW SUMP

J

Project Information:

ARPL 3031A 2021 - Project 7.2 Revision Details:

1736m

DGS

12 11 10 9 8 7 6 5 4 3 2 1

Client Information:

University of the Witwatersrand

Boomed access control

3895

⌀50mm waste pipe

Parking Exit

50mm paving as finish

475

UP

1. All finish items to be completed as stated in drawing. 2. Screed to be at 1:80 fall, 30mm min, 100mm max. 3. Torch on waterproofing to be applied to balconies, underneath floor finish. 4. All ramps to comply with SANS 10400, 1:12 gradient. 5. Weather step is to be maintained at thresholds. 6. Basement parking ramps to comple to SANS, 1:8 gradient. 7. All Levels to be checked by contractor. 8. Stormwater to be redirected to stormwater sump. 9. All fire escape stairs to comple with SANS 10400. 10. All waste pipes to be connected to municpal connection 11. Stormwater overflow pipe to be connected with SW sump.

1166

2142

FFL_-3300

834

380 D42

ie

7499 ° .05

90mm uPVC downpipe

DGS

13 14 15 16 17 18 19 20 21 22 23 24

250

1915

250

613

5978 S

Tiles 7 m²

250

whb

2515

25

FEMALE BATHROOM FFL + 0 7409 whb

521

2397

368

4142 D42 D15

whb

DGS

3208

1740

1853

351

250

D42

5 m²

50mm paving as finish

brickwork seating area

Tiles

Tiles

50mm paving as finish, laid ontop of torch on waterproofing T1

11479

Dry St

Tiles

28 m²

D42

wc

579

Cold St

FFL + 0

FFL_-1900

3110 3110

1091

FFL_-970

7990

ie

ie

25

wc

1915

345mm concrete solid flat slab, according to eng. detail Finish: 50mm concrete pavers

3110

ie

1036

6860

7597

25

wc

623317650

4999

995

4193

Tiles 62 m²

DGS

290

25

9.9 5°

FFL + 0

400

290

995

11

14309 KITCHEN RESTAURANT

IT MAINTENANCE RM

250 895 250

25

4785 6048

100

290

T1

FFL_-2000

T1

D29

3454

3 1737m

60

357

wc

whb

ie

ie

5701

250

179

400

D42

356

wc

whb

Fuel storage

D43

178

D30

new lintels over

2466

2466

250

531

D43

2555

D42

355

1688

whb

D42

353

ie ⌀110mm sewage pipeie

6090

500 250

D45

D2

3112

1716

DGS

T1

DGS

whb

895

4741

4737

3050

623

⌀124 mm FLUSH F.B.O

1000mm high glass panel balustrade

468

whb

D42

250

4610

10523

3023

ie

⌀100mm F.B.O

290

whb

GENERATOR ROOM

Tiles 11 m²

250

285

whb

wc

620

Tiles Not Enclosed

2165

Ground Floor Notes: 31344

320 ie

Tiles

DGS

FFL + 0

350

1012

1421

⌀600mm concrete columns ,according to eng detail. Finish: 10mm plaster finish

D5

300 ie

MALE BATHROOM 8529 FFL + 0

Tiles 19 m²

FFL + 0

300mm cast concrete lift core to eng. detail. 10mm Plaster on exterior 3.7m x 1.5 m Kone MonoSpace DX Stretcher lift according to mech eng detail

2141

Stormwater channel to sump

1

300

HTLT ROOM

REFUSE AREA

2

DGS

FFL + 0

250

3221

30 m²

Acoustic timber sound panels

3

250 whb

250 1090 250

1853

Stage

D

3461

300

ie

ie

500mm x 1500mm concrete beams overhead, according to eng detail

77

14753

Timber Deck Not Enclosed

D45

Electrical Duct 700mm x 600mm DB board

400mm x 900mm concrete column, according to eng detail

4

400mm x 900mm concrete column, according to eng detail Finish: 10mm plaster, primed and 2 coat paint to be applied.

2113

Slip Resistant Coating 23 m²

ie

386

1348 3710

1280

FFL + 0

HVAC SUPPLY 1000mm x 800mm(stainless steel) HVAC EXTRACTION 1000mm x 800mm (stainless steel)

FFL - 420

5

UP

1495

11

RESTAURANT SEATING AREA

6 10

5987

SAP timber back rest

8

9

317

UP

FFL_-420

9

4220

1649

906

1036

12

UP 7

Fire Escape

900

400

1 2 3 4 5 6 7 8 9 10

3119

Carpet 227 m²

24 23 22 21 20 19 18 17 16 15 14 13

900

TOC - 6350

1

8

250

Data Duct 600mm x 400mm 878 277

22429

AUDITORIUM

2 6 7

3710

250 6200

6679 2247

2010

Property Boundary

31202 22429

14515

STAIRCASE NOTE: Concrete cast in situ staircase, 24 risers 280mm min treads , 170mm max risers 1000mm balustrade Finish: Slip resitant coating

10624

all

UP 500mm x 1500mm concrete beams overhead, according to eng detail

250

3524

3110

1875

5

1645

130

4

of

1716

3 3

dt

413

Self closing class B door fire rated door at 120 min.

ree

D60

Sc

14500

D45

D61

352 1180

⌀90mm FLUSH F.B.O

27503

4

1 2

D45

7199

STAIRCASE NOTE: Concrete cast in situ staircase, (monolithic) 10 risers, 280mm min treads , 170mm max risers 1000mm balustrade Finish: Slip resitant coating

UP

2311

10

1436

8

2711

7 9

250

1796

3721

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

7500

6

6

2

5003

5

7

Tiles 174 m²

Property Boundary

4

brickwork seating area

UP

0m Building Line

3

UP

brickwork seating area

12478

2 8

290

400

50mm paving as finish 6951

1738m

7500

Staircase note: Concrete cast in situ staircase 10 risers 250mm min treads , 170mm max risers 1000mm glass panel balustrade Finish: Off Shutter concrete

1 9

30mm SAP timber deck, according to eng detail 345mm concrete solid flat slab, according to eng detail Finish: 50mm concrete pavers, laid ontop of torch on waterproofing.

4282

14845

325

ERF 2940

4881

FFL + 0

Foam Fire Extinguisher 1/200sqm as per NBR

1000mm high glass panel balustrade

FFL_-980

12967

10

UP

5

400mm x 900mm concrete column, according to eng detail

Stormwater channel to sump

50mm paving as finish, placed above torch-on waterproofing

1:12 concrete ramp, according to eng detail

T2

RECEPTION LOBBY

D50

332

FFL_-420

⌀124 mm FLUSH F.B.O

250

Drainage Channel Stainless steel grate to SW sump

290

D3

⌀124 mm FLUSH F.B.O

250 665

2242

1000mm glass(Toughened) panel railing, fixed onto galvanized steel baseplate. ⌀60mm stainless steel handrail

1022

1

1427

7500

Occupants will escape into a fire rated lobby/foyer, all doors within foyer to be 120min fire rated ,as per NBR

D45

D35

4556

⌀110 mm FLUSH F.B.O flush with paving finish

590

300mm x 500mm cast in situ concrete beam

603

to rding ac c o

500

2234 500

DGS

500mm x 1500mm concrete beams overhead, according to eng detail

2000

1:12

D2

p, ram

D56

Conways Crealco Curtain Wall System, Façade 60 Pressure Glazed Shop front

1100

rete conc

13376

243

500 1100 42 1100 243

250

243 2242

13367 500

8 m²

UP

D2 D57

345mm concrete solid flat slab, according to eng detail Finish: 15mm ceramic floor tile

Tiles

T1

1102

Ceramic Floor Tile

400

600

104 949

345mm concrete solid flat slab, according to eng. detail Finish: 50mm concrete pavers, laid ontop of torch on waterproofing

UP

tail

fa ll

TOC + 50

FFL_0 DGS

3595

13235

to

BIC

7627

Brickwork seating area

de eng

re ed

250

PUBLIC REL.

1:12 concrete ramp Finish: Slip resistant floor

601

250

4601

10710

T1

Stormwater drainage channel to SW sump. 300mm x 500mm cast in situ concrete beam

DGS

BIC

2105

290

4999

T1

Tiles Not Enclosed

5540

5540

1000mm high glass panel 19786 balustrade

TOC + 50

TOC - 250 Polished Screed 52 m²

8423

565

SECURITY OFF. RETAIL SPACE

SAP timber backrest

1:12 concrete ramp, according to eng detail (Slip resistant coating)

3595

0m Building Line

3185

T1

50mm paving as finish

730

746

290

400mm x 1500mm concrete beams overhead, according to eng detail

T2

B

FFL_-660

Property Boundary

10mm perforated alumium screen

7500

T1

1607

Conways Crealco Curtain Wall System, Façade 60 Pressure Glazed Shop front

Sc

A

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

13/10/2021

Drawing Details: DRAWN BY:

DRAWING SCALE:

2192396

1:100

DRAWING NUMBER:

DATE:

PR07.1

17/08/2021

DRAWING NAME:

REVISION NUMBER:

PROJECT 7.1 Ground Floor

04 Page 2 of 8


35 m²

4922

290

TOC + 14740 Carpet 87 m²

410

345

Carpet

256

1862

1306 250693

345 2655 4987

2502

2648

2598

7500

185 Compacted Drainage stones

⌀110mm agricultural drain

SW manhole invert level 1200mm

⌀110mm agricultural drain

PILE FOUNDATION NOTE: pile foundation 28MPA concrete @28 days , 2m x 2m concrete pile cap, 4x ⌀400mm pile foundation to bedrock, Depth of pile foundations to be determined by civil engineer.

Compacted Drainage stones

⌀110mm agricultural drain

Revision Details: REV:NO

7254

TOC Basement Level 1

345mm concrete suspended floor 20MPA @ 28 days, to engineer specification Finish: 50mm polished screed

220mm brick wall, to be waterproofed on inside skin 175mm concrete surface bed, 20 MPA @ 28 days, to engineer spec. Finish: 30mm Polished screed 20mm sand blinding layer wet wall sump

-10400

Compacted Drainage stones

⌀110mm agricultural drain

PILE FOUNDATION NOTE: pile foundation 28MPA concrete @28 days, 2m x 2m concrete pile cap, 4x ⌀400mm pile foundation to bedrock, Depth of pile foundations to be determined by civil engineer.

Wet wall system

01/09/2021

01

Basement flooring

01/09/2021

01

Weather step at entr. 01/09/2021

01

Slanted conc. wall

02

Envelope

26/10/2021

02

Floor to wall junc.

26/10/2021

02

Weather step

26/10/2021

03

Lower NGL

03/11/2021

01/09/2021

Drawing Details: DRAWN BY:

Basement Level 3

600mm secant concrete retaining walls depth to be determined by geotech engineer 2000 x 2000mm concrete pilecap refer to eng. detail ⌀400mm concrete pile foundation refer to eng. detail

2m

DATE ISSUED

01

-13390

⌀110mm agricultural drain

0m

DESCRIPTION

TOC Basement Level 2

Compacted Drainage stones Compacted Drainage stones

Project Information:

-3000

⌀110mm drainage pipe to sump 250

University of the Witwatersrand ARPL 3031A 2021 - Project 7.2

TOC Ground Floor level

220mm brick wall, to be waterproofed on inside skin with vapour membrane

345

2655 345

2655 345

1559

Client Information:

-1559 Street Level

-7400

4987

1. All finish items to be completed as stated in drawing. 2. Screed to be at 1:80 fall, 30mm min, 100mm max. 3. Torch on waterproofing to be applied to balconies, underneath floor finish. 4. All balcony + roof spaces to be covered with 85mm XPS insulation, according to SANS 204. 5. Weather step is to be maintained at thresholds. 6. Structural details to comply with engineer. 7. Levels to be checked by contractor. 8. Wet wall system to comply with waterproofing requirements. 9. Fenestration to comply with SANS 10400.

LEVELS/DATUM POINT Contour 1740 is 0.0

1180

1340

345 7500

7493

2648

2648

2648

FFL

wet wall system sump

⌀400mm concrete pile foundation

345

545 345

2455

2655

Off shutter finish on U/s of slab

7500

2020

609

5695 TOC First Floor level AUDITORIUM NOTE: Auditrium acoustic quality to be determined by sound engineer, pre fabricated timber panels placed on perimiter of space, roof scape also finished with suspended ceiling

NGL

3138 7500

345

FFL

Section A-A

Off shutter finish on U/s of slab

7500

SW manhole cover

Stage

Wheelchair zone

526

20mm carpet 345

HVAC system to be used to extract and supply fresh air for all basement levels

250

545

604

1109

15.67°

3443

4400

5740

D45

599

4446

Screed to fall, to overflow pipe Torch on waterproofing Gravel stones laid ontop of waterproofing layer Concrete coping

-1990

404

957

10mm perforated aluminium screen

500mm x 1500mm RC beams overhead, according to eng detail. Finish: Off shutter finish

2466

227 m²

3866

D42

2609

plastered and painted

TOC - 6350

FFL

1000 x 2000mm concrete pilecap

4000

For lighting detail, refer to electrical engineer specifications

AUDITORIUM

D3

Polished Screed 24 m²

Section Notes:

4400

FFL

TOC Second Floor Level

1441

610

310

11972

12750

3999

310

28MPA cast in situ concrete, 5839 refer to eng detail.

1:12 cast in situ concrete ramp

75MM concrete paving Torch on waterproofing

50mm polished screed finish

2149

2932

2234

250

4055

4490

23.66°

600

plastered and painted

228 mm SAP acoustic timber panels refer to sound engineer detail

Service Lane

3752

lintel over 566

-7400

Engineer to determine the use of ground beams between pile caps

400mm x 900mm concrete column, according to eng detail

FFL

D42

T1

600

Polished Screed 52 m²

plastered and painted

230mm brickwork wall, plastered and painted, supported by 900mm x 200mm concrete strip foundation wet wall system for basement waterproofing

TOC Third floor level

38550

To Basement levels

4987

345

345

345

lintel over TOC - 250

T1

600mm secant concrete retaining wall

TOC Basement Level 2

13695

345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 50mm Polished Screed

D45

110mm pipe to sump

345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: Hardwood Oak Floor

500mm, brickwork cavity cladding wall, insulated with 30mm XPS insulation within 150 mm cavity. 220mm double leave wall, 110mm single leave wall. Finish: 10mm plaster applied on interior and exterior

plastered and painted

T1

Concrete retaining cap

-10400

TOC Fourth floor plan

Steel shelf angle

9695

vertical HVAC duct

7655

8000

30mm polished screed finish

RETAIL SPACE

Street lamp

Jorrisen Street

7655

7431

597

9.5mm Gyproc Rhinoboard fixed to floor slab above

Side walk

7500

DGS

6700

4000

7500

17695

Steel shelf angle

TOC + 6747

7500

4000

To plant unit on roof

13797

TOC - 7600

Basement Level 3

1554

Polished Screed 393 m²

T1

STORAGE ROOM 2

TOC Basement Level 1

410

T1

COMPUTER LAB 2

plastered and painted

MULTI PURPOSE GATHER SPACE

plastered and painted

3465

vertical HVAC duct

345 345

13518

500mm x 1500mm RC beams overhead, according to eng detail. Finish: 10mm plaster on exterior, primed and 2 coat paint to be applied

345mm concrete suspended floor 20MPA @ 28 days, to engineer specification

Conways Crealco Curtain Wall System, Façade 60 Pressure Glazed Curtain Wall

TOC Fifth Floor Level

280mm brickwork Cladding wall, 10mm plastered inside and outside, 50mm cavity to be insulated with 30mm XPS insulation.

410

cable tray

5030

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

21695

Fire stop at every level

T1

FFL

FFL

torch on waterproofing applied to roof slab, applied by apex waterproofing

3000

Carpet

lintel over 1309 290

TOC + 17695 Hardwood Oak 87 m²

13532

Property Boundary

TOC + 14740

2250

2950

3649

COMPUTER LAB 4

1460

25160

DANCE STUDIO 1

plastered and painted

3655

290

1554

lintel over

3655

2950

256

FFL

4696

1420

3120

2900

2914 351 3649

5005

357

FFL

290

345

4000 4000

345

568

345 3120 345 3649

0m Building Line

Property Boundary

2014

cable tray

TOC Ground Floor level

-13390

Scale 1:100

Hardwood Oak 21 m²

805

87 m²

General Notes: 1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

TOC Roof Level

345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: Hardwood Oak floor

Hardwood Oak

plastered and painted

cable tray

lintel over

lintel over

T1

TOC + 22750

510

FFL

410

THEATRE PRACTICE 4

TOC + 17695

814

T2

13532

cable tray

D45

DANCE STUDIO 4

581

lintel over

Conways Crealco Curtain Wall System, Façade 60 Pressure Glazed Curtain Wall

38550 7254

N

lintel over

Screed to fall, connected to overflow pipe

lintel over 290

Triple volume

10mm perforated aluminium screen

NGL

2990

LOWEST BASEMENT FLOOR NOTE: Lowest basement floor made of 50mm pavers, sitting on compacted drainage stones to effectively keep ground water away from the lowest basement level.

TOC + 22750

FFL

1000mm high glass panel balustrade

5005

THEATRE PRACTICE 2

D46

FFL

3000

RETAINING WALL NOTE: 600mm secant concrete retaining wall, wet wall system to be implemented to effectively waterproof basement. Sump water will be pumped back into the building for re-use.

2014

Hardwood Oak 32 m²

Galvanized steel shelf angle

600 775 250

FLOOR SLAB NOTE: Structure consists of 345mm solid flat slab floors, consisting of a 7.5 by 5 meter grid. Reinforcement within slab to be referred by the civil engineer.

2337

1250

3465 4000

280mm brickwork cavity wall, plastered on interior and exterior, 2 coat paint to be applied to the exterior

500mm x 1500mm RC beams overhead, according to eng detail

1441

-3000

410

50mm curved plywood achieved through steam bending (Kellerwood Products)

Street Level

HVAC plant unit refer to mech eng. detail Fixed to concrete slab 50mm XPS insulation

glass skylight FFL

Suspended HVAC (stainless steel) ducting from concrete floor slab according to mech, eng detail

-1559

Seasonally adjustable monocrystalline solar panel for electricity production optimum angle 25 to 35 degrees Eurolux O403 Silicon module 1000mm high glass panel balustrade, mounted on baseplate Concrete coping 230mm brickwork finish: 10mm plaster, primed and 2 coat paint to be applied 15mm ceramic tile finish, stacked bond, 5mm tile grout

4000

110mm FBO inlet

WATER RETICULATION NOTE: Water to all fixtures will be supplied from the indicated municipal connection, water will be stored in water tank on above the lift core. On the roof level.

1502

300mm concrete cast in situ lift core

85mm XPS insulation Torch on waterproofing applied by apex waterproofing

15mm ceramic tile finish, stackbond, 10mm tile grout

TOC Second Floor Level

TOC First Floor level

1497

5000 litre JoJo Water tank

747

9695

5695

4987

Prefabricated concrete supporting panel wall

1000mm high glass panel balustrade, ⌀60mm stainless steel handrail

TOC Third floor level

7500 Steel bracing according to eng, detail

747

TOC Fourth floor plan

3083

7500

5501

13695

ROOF NOTE: Ceramic tile finish on roof slab(stacked bond), installed above torch-on waterprooding(Supplied by apex waterproofing), ontop of 1:80 screed to fall, laid on 85mm XPS insulation. Supported by 345mm solid concrete flat slab.

4000

7500

1:80 screed to fall

17695

5

27487

747

TOC Roof Level

TOC Fifth Floor Level

4

31317

AUDITORIUM NOTE: Auditorium can be accessed from ground floor level, through the direct connecting door, lower levels of auditorium can be accessed through the multilevel ramp or through basement level 1.

21695

3

747

AUDITORIUM NOTE: Auditrium seating to be made of 28MPA @ 28 days, cast in situ concrete, refer to eng. detail.

25160

2

2990

1 GENERAL NOTE : Building to consist of off shutter finish on the U/s of the slab, all services to be exposed.

4m

VISUAL SCALE 1:100 @ A1

6m

8m

10m

DRAWING SCALE:

2192396

1:100

DRAWING NUMBER:

DATE:

PR07.1

17/08/2021

DRAWING NAME:

REVISION NUMBER:

PROJECT 7.1 Section A-A

04 Page 3 of 8


I

H

G

F

E

D

C

B

L

A

J

60129 8400

5000

7500

FLOOR SLAB NOTE: Structure consists of 345mm solid flat slab floors, consisting of a 7.5 by 5 meter grid. Reinforcement within slab to be determined by civil engineer.

5000

5000

7488

7500

230mm curved brickwork wall, supported by prefabricated RC concrete panels, supported by steel bracing, tied into structural column grid.

Wispeco, crealco, 80mm top hung 3000mm x 1000mm window aluminium frame with single Low-E glass.

Pre-fabricated mild steel frame/shading device 2733

92

3953

7300

690

92

676

55 531 504

67

55

345

528

529

67

67

76

344

343

76

76

4210

87

3501

3465

97 687

92

T1

506

97

662

87

55

680

679

87 678

97

503

21695

General Notes: 1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

Wispeco, crealco, 80mm top hung 3000mm x 6700mm aluminium window frame with double, tinted Low-E glass.

Creeper planted screen, supported by timber framework, refer to detail drawing 3 677

TOC Roof Level

Concrete Upstand Finish: 10mm plaster, primed and 2 coat paint white to be applied.

1753

230mm curved brickwork wall, supported by prefabricated concrete panels, supported by steel bracing.

DATUM NOTE: 1470 level = 0.0 10mm plaster Primed and Painted 2 coat white paint

4994

A

GENERAL NOTE : Building to consist of off shutter finish on the U/s of the slab, all services to be exposed, in a neat manner.

ROOF NOTE: 5mm Ceramic tile finish on roof slab, installed above torch-on waterproofing (Supplied by apex waterproofing), laid on 1:80 screed to fall, laid on 85mm XPS insulation. Supported by 345mm solid concrete flat slab.

25160

7494

DGS

Galvanized mild steel gusset plate connection

48

686

D42

663

92

92

290

505 55

550

661

55

530

92

445

67

10mm perforated aluminium sheets, supported by 20x300mm steel mullions fixed to structure with M20 threaded rod and M20 Nut 55

67

522

67

55

92

T1 DGS

1000mm high glass panel railing

668

47

672 92

683

673

97

87

578

67 498

508

55

55

55

3510

D47

3450

532

D46 D7

T1

681

92

97

D6

DGS 46

Fixed

526

509

67

90 513

D47

64

174

514 55

1000mm high glass panel railing

45

32560

490

90

495

519 D47

55

67

67

175

520

491

67

55

T1

492

15435

55

DGS

67

14

⌀600mm RC column, to eng specification

T1

1595

250

FFL

-872 445

1:8 RC vehicle ramp, refer to engineer detail

600mm x 420mm RC column, to eng specification

8400

1000mm high glass panel railing

D2

D2

D56

D57

Wispeco, crealco, 80mm skyline double door 2000mm x 4000mm, single Low-E glass

NGL 345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification

50mm concrete pavers, fitted with slip resistant strips

5000

600mm x 420mm RC column, to eng specification

First floor basement level

1000mm high glass panel railing

7500

4995

5005

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification

7491

600mm x 420mm RC column, to eng specification

600mm x 420mm RC column, to eng specification

DGS 624

21741

345

345

345

345

D2 D10

NGL

Project Information:

ARPL 3031A 2021 - Project 7.2 Revision Details:

1030

-7400

T1

1:12 concrete cast in situ ramp

3925

1055 300

230mm brickwork wet wall, plastered on both sides, primed and painted

2700

600 1037 250

University of the Witwatersrand

T1

Conways Crealco Curtain Wall System, Façade 60 Pressure Glazed Shop front

⌀110mm FBO drainage pipe to sump(Suspended from floor slab)

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification.

⌀124mm FBO drainage pipe to sump(Suspended from floor slab)

5496

345

NGL

T1

4055

FFL

-1548

Concrete and brickwork seating area. 230 brickwork wall, 200mm concrete slab 75mm concrete pavers 1:80 screed to fall, to f.b.o outlets

Client Information: T2

6383

Fever trees, according to landscape architect details, planter to be waterproofed with mariseal. Drainage to flow into sump.

Miracle grow garden soil.

⌀600mm RC column, to eng specification

3590

1000mm high glass panel railing

-3000

192

15256

4400

13400

Conways Crealco , Façade 60 Pressure Glazed Shop front

7299

8340

Finish: 10mm plaster, inside and outside, primed and 2 coat white paint applied.

1. All surface to comply with NBR. 2. Public access ramps to be 1:12 gradient 3. Car access ramps to be 1:8 within basement. 4. Fenestration to comply with SANS 10400 XA, SANS 204 5. All structural columns to be plastered, primed and 2 coat paint to be applied. 6. FBO to be ⌀90mm at minimum 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum. 9. All railings to be 1000mm high at minimum. 10. All levels to be checked by Contractor.

10mm perforated aluminium sheets, supported by 20x300mm steel mullions fixed to structure with M20 threaded rod and M20 Nut

10mm perforated aluminium screen Alumium perforated screen fixed to wall with bolted to underside of slab 600mm x 420mm RC column, to eng specification. Finish: 10mm plaster, primed and 2 coat paint to be applied.

Prefabricated wall panel, 10mm plastered finish, fixed to steel circular hollow section frame. Frame to be fixed to floor slab structure. Steel bracing to be be supplied by futurecon.

2458

505

515

16350

Fever trees, according to landscape architect details, planter to be waterproofed with mariseal. Drainage to flow into sump.

T1

1000mm high glass panel railing

5695 TOC First Floor level

Elevation Notes:

114mm x 228mm timber strut

3505

511

10mm perforated aluminium sheets, supported by 20x300mm steel mullions fixed to structure with M20 threaded rod and M20 Nut

Concrete Upstand Finish: 10mm plaster, primed 2 coat plaster to be applied.

T1

67

103

DGS

T1

510

516

15111

Property Boundary

Woodoc 50 sealer applied to protect timber from sun and rain

5198

4000

1874

596

67

6050

8400

518

10mm perforated aluminium sheets, supported by 20x300mm steel mullionsfixed to structure with M20 threaded rod and M20 Nut

8695

669

87

2400

2458

TOC Second Floor Level

4400

689

D46

55

9695

TOC Basement Level 1

87

490

Concrete upstand Finish: 10mm plaster finish, primed and 2 coat paint to be applied

TOC Ground Floor level

582

4010

67

55

501

D46

581

525 497

Galvanized mild steel shading device

D46

92

499 67

675

490

600

Concrete downstand Finish: 10mm plaster finish, primed and 2 coat paint to be applied

TOC Third floor level

4000

97 664

92

3235

521

502

3555

523

570

3404

13695

1128

1000mm glass(Toughened) panel railing, fixed onto galvanized steel baseplate. ⌀60mm stainless steel handrail

0m Building Line

4000

TOC Fourth floor plan

5000

684 97 666

67

Property Boundary

17695

8400

87 682

152mm x 228mm SAP timber bracing

550

4000

2458

674

114mm x 228mm SAP timber strut

3732

TOC Fifth Floor Level

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

355mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification

⌀110mm drainage pipe to sump

A

600mm secant concrete retaining walls depth to be determined by geotech engineer

REV:NO

DESCRIPTION

01

Show basement sec. 15/10/2021

DATE ISSUED

01

Legibility

15/10/2021

01

Public space steps

15/10/2021

01

Exterior finish

15/10/2021

02

Tile fixing

25/10/2021

02

Side hung door height 25/10/2021

03

Fenestration change

03/11/2021

Section Cut Section Cut N

Drawing Details:

123 456 789 10

SECTIONAL NORTH ELEVATION Scale 1:100

0m

2m

4m

6m

8m

24 1 23 22 2 21 3 20 4 5 19 18 6 17 7 16 8 15 9 14 10 11 13 12

DN

DRAWN BY:

10m

VISUAL SCALE 1:100 @ A1

BUILDING AXO Context of section cut through public space

N

DRAWING SCALE:

2192396

1:100

DRAWING NUMBER:

DATE:

PR07 PR07.2

17/08/2021

DRAWING NAME:

REVISION NUMBER:

PROJECT 7.2 04 North Elevation Page 4 of 8


0.8mm Dove grey chromadek IBR flashing

Upstand screed fill

230mm x 380mm Concrete Upstand 345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 15mm ceramic tile

25160 Section Cut

TOC Roof Level

2

Water control membrane Screed fillet 0.8mm Dove grey chromadek IBR counter flashing

30mm XPS insulation within 50mm cavity

Roof note: This portion of roof is not accessible 15mm Ceramic tile finish, , stacked bond, 5mm tile grout Torch-on waterproofing 85mm EPS insulation

240

25160 355

NFP Brickwork cladding to be fixed with galvanized steel angle, fixed to concrete slab. Finish: 10mm plaster applied to interior and exterior, primed and 2 coat paint to be applied.

TOC Roof Level

555

ROOF NOTE: 5mm Ceramic tile finish on roof slab, installed above torchon waterproofing (Supplied by apex waterproofing), laid on 1:80 screed to fall, laid on 85mm XPS insulation. Supported by 345mm solid concrete flat slab.

100mm max, 30mm min screed to fall (1:80) , to FBO outlet

Plastered, Primed and 2 coat white paint to be applied

THEATRE PRACTICE 2 TOC + 22750

DATUM NOTE: Contour 1740 is level 0.0

TOC Fifth Floor Level 32 m²

25mm x 120mm Rectangular hollow section skirting

Section Cut

1000 micron DPC

TOC Fifth Floor Level

345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 30mm Polished screed

Context elevation of perimiter cut

1476

TOC Fifth Floor Level

3.5mm oak hardwood for floor finish, laid ontop of progressive shock obsorbing foam.

805

30mm expanded polystyrene insulation

Galvanized mild steel shelf angle Balcony Composition Note: 85mm rigid board layed below screed to fall 100mm max - 30mm min screed to fall (1:80) laid to full bore outlet drainage, , Torch on waterproofing to be applied to balcony, balcony to be finishd by 15mm white ceramic floor tiles. 5mm dovegrey grout to be applied

21695

FFL 357

21695

weepholes at 900 centres & above all openings

1000mm glass(Toughened) panel railing, fixed onto galvanized steel baseplate. ⌀60mm stainless steel handrail

DANCE STUDIO 4 TOC + 17695

0.8mm Dove grey chromadek IBR flashing

TOC Fourth floor plan

1030

T2

21 m²

Water control membrane 245mm x 375mm concrete upstand

FFL

1000 Micron DPC

17695

556

TOC Fourth floor plan

1000 micron DPC

Wispeco, crealco, 80mm skyline sliding 2700mm x 1500mm sliding door, single Low-E glass

Balcony Composition Note: 85mm rigid board layed below screed to fall, 100mm max - 30mm min screed to fall (1:80) laid to full bore outlet drainage, Torch on waterproofing to be applied to balcony, balcony to be finishd by 15mm white ceramic floor tiles(stacked bond). 5mm dovegrey grout to be applied.

1000mm glass(Toughened) panel railing, fixed to galvanized steel base plate

3655

1000mm glass(Toughened) panel railing, fixed onto galvanized steel baseplate. ⌀60mm stainless steel handrail

3599

Plastered, Primed and 2 coat white paint to be applied

1

COMPUTER LAB 4

D7

TOC Third floor level

Interior walls to be plastered on both sides, primed and 2 coat paint to be applied.

5mm ceramic tile finish, stretcher bond, 5mm grout joint 5mm torch on waterproofing 85mm rigid board insulation Screed to fall 1:80

Water control membrane 0.8mm Dove grey chromadek IBR counter flashing

13695 TOC Third floor level

13695

FFL

1000 micron DPC

TOC Third floor level

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 50mm Polished screed Underside of slab: Off shutter finish

300

200

300

570

300mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 15mm ceramic tile

10mm Baltimore, Broadloom carpet 50mm Polished screed

345

1030

7500

Upstand fill (screed)

250mm x 550mm Concrete upstand

Bolted galvanized baseplate

500mm x 1500mm RC beams overhead, according to eng detail

40mm steel CHS attached to galvanized steel base plate

Galvanized steel C channel fixing

300mm steel CHS attached to galvanized steel base plate

922

10mm perforated aluminium screen Alumium perforated screen fixed to concrete beam with bolted connection, glavanized c Channel.

300

1000 micron DPC

Suspended HVAC (stainless steel) ducting from concrete floor slab according to mech, eng detail

MULTI PURPOSE GATHER SPACE

500

Stepped slab to tie into concrete columns, refer to engineer detail.

TOC + 6747

TOC First Floor level

40

40

393 m²

500mm x 1500mm RC beams overhead, according to eng detail Finish: Off shitter finish

300

400mm x 900mm RC column, refer to eng. detail Finish: Column to be 10mm flush plastered with wall.

230mm brickwork wall, plastered inside and outside (Stock clay brick)

Jorrisen Street

345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 30mm Polished screed 400mm x 1500mm RC beams overhead, according to eng detail

10mm perforated aluminium screen Alumium perforated screen fixed to concrete beam with bolted connection, glavanized c Channel. 9.5mm Gyproc Rhinoboard suspended ceiling board.Fixed to 40mm steel RHS Fixed to floor slab with 40mm horizontal RHS at 500mm centres. To be finished with 10mm rhinolite plaster.

30mm polished screed

5695

FFL

TOC First Floor level

345

TOC First Floor level

Conways Crealco , Façade 60 Pressure Glazed Shop front

Property Boundary 0m Building Line

5695

500

Plastered, Primed and 2 coat white paint to be applied 502

1000mm glass(Toughened) panel railing, fixed onto galvanized steel baseplate. ⌀60mm stainless steel handrail

RETAIL SPACE

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 30mm Polished screed

500

400mm x 1500mm RC beams overhead, according to eng detail

TOC - 250

TOC Ground Floor level 52 m²

20mm suspended plywood ceiling Drip

110mm outer leaf wall, 220mm inner leaf wall,no insulation, plastered inside and outside, primed and 2 coat paint to be applied.

8

1000mm glass(Toughened) panel railing, fixed onto galvanized steel baseplate. ⌀60mm stainless steel handrail

7

5

4

3

Polymer Drainage Channel 1m H55 ACO 50mm concrete pavers Screed to fall, 1:80

2

1

369

-3000

⌀600mm cast in situ concrete column Finish: Plastered, primed and 2 coat paint to be applied Wispeco, crealco, 80mm skyline double door 2700mm x 4000mm, single Low-E glass Ceramic floor tile finish 50mm Polished screed 5mm tile adhesive to be applied below tile

Staircase note: Concrete cast in situ staircase 10 risers 250mm min treads , 170mm max risers 1000mm glass panel balustrade Finish: Off Shutter concrete

6

⌀600mm cast in situ concrete column

50mm concrete pavers, laid ontop of riversand, supported by concrete cast in situ ramp

400mm x 900mm RC column, refer to eng. detail Finish: 10mm flush plastered with wall

TOC + 14740

D46

35 m²

0.8mm Dove grey chromadek IBR flashing

N

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 50mm Polished screed Stepped slab to tie into concrete columns, refer to engineer detail.

300mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 15mm ceramic tiles 15mm Mild steel rib(flange) 15mm Mild steel plate

Context section of perimiter cut

17695 TOC Fourth floor plan

300

0.8mm Dove grey chromadek IBR counter flashing

Wispeco, crealco, 80mm skyline sliding 2700mm x 1500mm sliding door, single Low-E glass. 3.5mm oak hardwood for floor finish, laid ontop of progressive shock obsorbing foam. Laid ontop of 50mm screed.

345

DN

24 23 1 2 22 21 3 20 4 19 5 18 6 7 17 16 8 15 9 14 10 13 11 12

345

123 456 789 10

230mm brickwork (NFP) wall, plastered inside and outside, primed and 2 coat paint to be applied. 76 x 210mm pre stressed concrete lintel

-3000

General Notes: 1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204

Perimiter Notes: 1. All finish items to be completed as stated in drawing. 2. Screed to be at 1:80 fall, 30mm min, 100mm max. 3. Torch on waterproofing to be applied to balconies, underneath floor finish. 4. All balcony + roof spaces to be covered with 85mm XPS insulation, according to SANS 204. 5. Weather step is to be maintained at thresholds.

487

600mm x 300mm 20mpa concrete cast in situ beam

370

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification. Finish: 75mm concrete pavers. Underside of slab: Off shutter concrete

0.5m

1m

1.5m

PERIMITER SECTION DETAIL

0m

Scale 1:25

VISUAL SCALE 1:25 @ A1

2m

TOC Ground Floor level

345mm concrete suspended flat slab 25MPA @ 28 days, to engineer specification Finish: 15mm ceramic floor tile Underside of slab: Off shutter finish

⌀110mm Marley uPVC drainage pipe to SW sump

305

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

345

TOC Ground Floor level

2.5m

Revision Details:

Client Information:

University of the Witwatersrand Project Information:

ARPL 3031A 2021 - Project 7.2

Drawing Details:

REV:NO

DESCRIPTION

DATE ISSUED

01

Weather Step

14/10/2021

01

Water proofing balc.

14/10/2021

DRAWN BY:

01

Entrance threshold

14/10/2021

2192396

1:25

02

Floor finishes

25/10/2021

DRAWING NUMBER:

DATE:

02

Fenestration Calc

25/10/2021

DRAWING SCALE:

PRS_7.2

01/10/2021

DRAWING NAME:

REVISION NUMBER:

Project 7.2 03 Perimiter Detail Sheet 5 of 8


345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 10 mm carpet

1000 Micron DPC M20 galvanized mild steel washer, M20 galvanized mild steel Nut weepholes at 900 centres & above all openings

3

FFL

TOC Fifth Floor Level

Capillary Break 120mm CHS steel frame member, welded to galvanized steel baseplate

Fire stop to be applied at each level M20x300mm galvanized mild steel threaded rod, cast into place

FINISH NOTE : Building to consist of off shutter finish on the U/s of the slab, all services to be exposed.

0° .0 85

3649

General Notes: 1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

Winter Solstice 12:00 PM - 40° 3° 40.6

Galvanized mild Steel Spacer Prefabricated bricwork cavity wall, to be assembled on site. Brickwork plastered on interior and exterior. Supplied by futurecon. Welded to CHS frame. CHS structural frame welded to fixing baseplate. Galvanized steel baseplate bolted to floor slab.

15mm galvanized steel bracing

4000

Summer Solstice 12:00 PM - 86°

30mm EPS insulation

20mm galvanized mild steel baseplate

⌀440 concrete column, according to eng detail

21695 TOC Fifth Floor Level

345

21695

BUILDING AXO

SUN ANGLES

FINANCE MANAGER OFFICE Carpet

345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 10mm carpet

weepholes at 900 centres & above all openings

1000 Micron DPC 20mm galvanized mild steel baseplate

23 m²

FFL

Fire stop to be applied at each level Capillary Break

weepholes at 900 centres & above all openings 15mm galvanized mild steel sheet metal Galvanized Mild steel rib/flange

357

17695

Galvanized mild Steel Spacer

TOC Fourth floor plan

TOC Fourth floor plan

M20x300mm galvanized steel mild threaded rod, cast into place 1000 micron DPC

15mm galvanized steel backing

Envelope wall/cladding 20mm perforated alumium screen

Fixed

Tubular steel frame, bolted to concrete floor slab

3649

4000

TOC Fourth floor plan

Wispeco, crealco, 80mm top hung 3000mm x 1000mm window aluminium frame with single Low-E glass.

Prefabricated mild steel Window frame

Envelope wall/cladding steel backing

Window frame

Perimiter Notes:

LARGE COMPUTER LAB Carpet

1. All finish items to be completed as stated in drawing. 2. Screed to be at 1:80 fall, 30mm min, 100mm max. 3. Torch on waterproofing to be applied to balconies, underneath floor finish. 4. Wall cavities to be insulated with 30mm XPS insulation, according to SANS 204. 5. Weather step is to be maintained at thresholds. 6. M20 bolts to be used for fixing, incase other specified. 7. All U/S to be off shutter concrete. 8. Services, ie, HVAC and electrical ducts to be exposed underneath slabs, in a neat manner. 9. Fenestration to comply with sans 10400 XA / SANS 204

Concrete floor slab

TOC Third floor level 102 m²

ENVELOPE ASSEMBLY 1000 micron DPC

13695

M20x300mm galvanized mild steel threaded rod, cast into place

10mm carpet

Prefab mild steel frame to house window frame.

Client Information:

weepholes at 900 centres & above all openings 120mm CHS steel frame member, welded to galvanized steel baseplate

FFL

University of the Witwatersrand

13695 TOC Third floor level

Capillary Break

345

TOC Third floor level

ENVELOPE ASSEMBLY

PLATE ASSEMBLY

Fire stop to be applied at each level 20mm galvanized mild steel baseplate 345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 30mm polished screed U/S finish: Off shutter

⌀440 concrete column, according to eng detail

Project Information:

weepholes at 900 centres & above all openings 15mm galvanized mild steel sheet metal 1000 micron DPC

ARPL 3031A 2021 - Project 7.2

Galvanized Mild steel rib

Revision Details: REV:NO Wispeco, crealco, 80mm casement 1600mm x 1000mm window aluminium frame with single Low-E glass.

3655

4000

OFFICE 4 Carpet

1000 micron DPC

TOC Second Floor level 51 m²

10mm carpet FFL 9695

PERIMITER SECTION DETAIL Scale 1:25

Galvanized mild steel flange, welded to CHS

9695

CHS frame welded to baseplate Galvanized bolt, cast in situ

TOC Second Floor level

0m

0.5m

1m

VISUAL SCALE 1:25 @ A1

1.5m

2m

2.5m

14/10/2021

01

Floor Thickness

14/10/2021

01

Water proofing balc.

14/10/2021

01

Fenestration calc.

14/10/2021

01

Window fixing

02

Floor finish (Dance st) 25/10/2021

Galvanized mild steel web

1:80 screed to fall, FBO, FBO pipe connection to drainage pipe within column

M20x250mm galvanized steel threaded rod, cast into place

Envelope

14/10/2021

Dove grey chromadeck flashing

Gravel stones Torch-on waterproofing

TOC Second Floor level

DATE ISSUED

01

Glavanized bolts fixed to brickwork

10mm sand, cement plaster on exterior and interior 1000 micron DPC Concrete upstand

M20 galvanized steel Nut 20mm galvanized mild steel baseplate

DESCRIPTION

280 cavity brickwork wall

Prefab steel frame to house window frame. 15mm galvanized mild steel sheet metal 15mm Galvanized Mild steel rib 30mm expanded polystyrene insulation

15mm galvanized steel backing

345

12000

Concrete upstand Finish: 10mm plaster, primed and 2 coat paint to be applied Covered Balcony

1000 Micron DPC

⌀440 concrete column, according to eng detail

FACADE ASSEMBLY 17695

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

345mm concrete suspended flat slab 20MPA @ 28 days, to engineer specification Finish: 10mm carpet

Galvanized mild steel baseplate

Concrete suspended floor

Drawing Details: DRAWN BY:

DRAWING SCALE:

2192396

1:25

DRAWING NUMBER:

DATE:

PR07.2

17/08/2021

DRAWING NAME:

REVISION NUMBER:

PROJECT 7.2 Perimiter Section 2

03 Page 6 of 8


B

1 48

A

C

B

F

MALE BATHROOM

lintel over

4

5915

5m

1600

968

1025

LED Strip Lights 12Volts Cool White Colour SMD5050 2100mm x 900mm door, louvers to be installed

1207

lintel over

whb

5mm Barista white ceramic tile 330mm x 330mm First grade ceramic tile 5mm dovegrey tile grout On 5 mm tile adhesive

300 110

Movement sensor (Radiant GPE039-W (RFS48) Disc-4LED Pir Sensor Light)

330

400

DB board (3-Phase Large Side Isolator Distribution Board) lintel over

30 m²

Geberit Sigma concealed cistern

TOC Ground Floor level

953

WT

whb

FEMALE BATHROOM FFL + 0

Suspended ceiling

28 m²

i.e

whb

whb 990

990

1447

⌀22mm insulated copper water supply pipe, chased in wall WATER RETICULATION NOTE: Watter supply from municipality to flow into water tank on the roof level, from roof water tank, will supply fixtures within building.

University of the Witwatersrand

Grohe Rapid SL Set for Disabled WC 39140 ⌀50mm uPVC waster pipe, connected to ⌀110mm uPVC sewage pipe. (1:40)

Mentis Grating to be installed within wet service duct at every floor level

i.e

i.e

wc

i.e

wc

i.e

Cold Water outlet only (Fixture)/WC

cw

cw

cw

WT

wc

wc 1011

wc

1740

Water supply from water tank

cw

Cold Water supply pipe (⌀22mm)

hw

Warm water supply pipe (⌀22mm)

1649

1019

FEMALE BATHROOM TOC Ground Floor level

1865

1025

28 m²

1018

998

1010

1047

whb

1047

whb

1047

whb

1047

Water closet (Geberit Sigma concealed cistern)

whb

5 WHB

1375

cw

i.e

cw

i.e

cw

i.e

cw

i.e

Wash hand basin (Grohe cube counter top basin 50)

Grohe cube counter top basin 50

whb

D

Cobra P-trap, ⌀50mm

cw

i.e

i.e

⌀50mm uPVC waste pipe ⌀110mm single stack system

WATER RETICULATION LAYOUT Scale 1:50

0m

1m

2m

VISUAL SCALE 1:50 @ A1

3m

2m

1m

0m

4m

3m

Project Information:

ARPL 3031A 2021 - Project 7.2

5m

VISUAL SCALE 1:50 @ A1

REV:NO

DESCRIPTION

01

Mechanical ventilation

DATE ISSUED 06/10/2021

01

Louver door spec

06/10/2021

01

Suspended ceiling tiles

06/10/2021

01

Tiling set out point

06/10/2021

01

Vanity Elevation

06/10/2021

4 Single stack sewage reticulation system

20mm Perforated screen

385

whb

1047

1058

411

-3000 TOC Ground Floor level

wc

4990

cw

4m

i.e

FEMALE BATHROOM

cw

28 m²

whb

Single stack waste reticulation system Suspended from floor slab above

WT

22mm water supply pipe, chased within wall cw cw

⌀110mm uPVC sewage pipe

WC

5

i.e

5

⌀50mm uPVC waste pipe

917

FFL + 0

whb

WT

⌀110mm uPVC sewage pipe at 1:40 fall

cw

1880

i.e

i.e

Single stack reticulation system

i.e

wc

i.e

⌀110mm uPvc sewage pipe (1:40 fall)

⌀110pmm uPVC sewage pipe at 1:40 fall

i.e i.e

900

i.e i.e

45

Cold and warm Water outlet (Fixture, Cold Only))/WHB

cw

i.e

cw

cw

cw

cw

5

Geberit Sigma concealed cistern Geberit Icon Pan Rimfree Wall-Hung White

wc

cw

E

2130

lintel over

200

567

wc

2545

wc

2330

1015

1018

SECTION E-E Vertical Reticulation Layout Scale 1:50

Water reticulation Legend

30 m²

wc

wc

Revision Details:

cw

1865

TOC Ground Floor level

wc

Geberit Sigma concealed cistern Geberit Icon Pan Rimfree Wall-Hung White

⌀110mm uPVC sewage pipe at 1:40 fall

4

949

cw

505

1061

FFL + 0

1688

⌀63mm uPVC water supply pipe, to water tank located E on the roof

1020

MALE BATHROOM 1700

⌀50mm uPVC waste pipe

1020

whb

Client Information:

lintel over

cw

i.e

1. Mentis grate to be fixed with L bracets within wet service duct. 2. All I.E/ R.E is to be installed at junctions. 3. Waste pipes to be ⌀50mm, min 4. Soil pipes to be ⌀110mm, min 5. Single stack system to be used for waste and soil drainage. 6. Electrical details to comply with engineer detail. 7. ⌀22mm copper pipes to supply cold/hot water. 8. All pumbing to comply with SANS 10400, PART P

⌀110mm single stack PVC sewage pipe

TOC Ground Floor level

⌀110mm uPvc waste pipe

1865

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

Ablution Notes:

C ⌀22mm insulated copper water supply pipe

lintel over

4

LED Strip Lights 12Volts Cool White Colour SMD5050

i.e

cw

cw

cw

i.e

991

20mm supawood bulkhead

cw

whb

631

MALE BATHROOM 30 m²

Geberit Sigma concealed cistern

Geberit Icon Pan Rimfree WallHung White

i.e

cw

⌀110mm single stack system ⌀50mm uPVC waste pipe

i.e

988

1007

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

C

45

453

whb

1025

ELECTRICAL LAYOUT_ REFLECTED CEILING PLAN Scale 1:50

SECTION G-G Scale 1:50 Toilets Tile Layout

lintel over

508

968

B

TOC Ground Floor level

i.e

1600

330mm X 120mm white barista tile skirting

-3000

i.e

1620

Geberit Icon Pan Rimfree Wall-Hung White

-3000

B

400mm x 900mm concrete column, according to eng detail

5mm Barista white ceramic tile 330mm x 330mm First grade ceramic tile 5mm white grout

MALE BATHROOM

4

862

806 330

330

SECTION F-F Vanity Tile Layout Scale 1:50 22mm insulated copper water supply pipe, supplied from water tank, located on roof.

558

Floating vanity 330mm X 120mm white barista tile skirting

D

20mm perforated screen

whb

⌀110mm uPvc waste pipe

whb

5

cw

whb

917

cw

whb

715

whb

LED Strip Lights 12Volts Cool White Colour SMD5050 (Hidden behind Bulkhead, above vanity)

cw

2200

FFL + 0

TOC Ground Floor level

Partition Wall

Cristallo Silver Frameless Mirror - 2200 x 700mm 20mm supawood bulkhead 5mm Barista white ceramic tile 330mm x 330mm First grade ceramic tile 5mm white grout

30 m²

Eurolux Round 8 Inch Extractor Ceiling Fan (300mm) White F46W Number of extractor fans deternined by mechanical engineer

400mm x 500mm fibre glass suspended ceiling tiles

1730

330

MALE AND FEMALE ABLUTION DETAIL_TILE LAYOUT Scale 1:50

Double Plug Point (Veti 2VW224 Double RSA V-Slim 4x4 Socket White)

28 m²

5

MALE BATHROOM

2

1207

1499

28 m²

1025

FEMALE BATHROOM

902

⌀220mm HVAC ducting overhead HT/LT Room

TOC Ground Floor level

968

1499

942

FFL + 0

7183

1600

3208

3208

5

FEMALE BATHROOM

5mm Barista white ceramic tile 330mm x 330mm First grade ceramic tile 5mm dovegrey tile grout on 5 mm tile adhesive

whb

Single switch panel (Veti Switch 1-Lever 2way - White)

802

220mm brickwork wall,10mm plaster inside and putside, 2 coat painted finish

802

165 245

Stainless steel Dividing strip

5

2200

LED Recessed Downlight (Bright Star Lighting DL035 Integrated Downlight - Cool White (30W))

4

730

6505Wet service duct

400mm x 500mm fibre glass suspended ceiling tiles

286

844

844

4

330

330

Electrical Legend

30 m²

500

850

FFL + 0

TOC Ground Floor level

lintel over

lintel over

lintel over

MALE BATHROOM

1473

330

G

400mm x 900mm concrete column, according to eng detail

1473

330

7 45

Setting out point (Start Point) Setting out point (Start point)

General Notes:

2

Closet

2330 2545

4

830

DB board (3-Phase Large Side Isolator Distribution Board)

30 m²

3129

---

TOC Ground Floor level

4m

3m

VISUAL SCALE 1:50 @ A1

Electrical Duct 700mm x 600mm

FFL + 0

953

-

2m

1m

0m

330mm X 120mm white barista tile skirting Stainless steel Dividing strip

lintel over

C

i.e

⌀22mm insulated copper water supply pipe 20mm suspended fibreglass ceiling tile

Grohe cube counter top basin 50 -3000

Drawing Details: DRAWN BY:

DRAWING SCALE:

2192396

1:50

DRAWING NUMBER:

DATE:

PRAB7.2

14/09/2021

DRAWING NAME:

REVISION NUMBER:

wc

TOC Ground Floor level

5m Suspended mentis grate floor installed at every level in duct

SECTION D-D Scale 1:50

PROJECT 7.2 02 Ablution Details Page 7 of 8


Components: 1. Brickwork Wall 2. Amalfi Jade plus mixer tap (x5) 3. Grohe cube counter top basin 50 (x5) 4. Snowstorm Quartz countertop (20mm) (460mm x 5000mm) (x1) 5. Snowstorm Quartz countertop (20mm) (390mm x 5000mm) (x1) 6. Prefabricated mild steel frame (steel segments(35mm SHS) to be welded together. (x6) 7. M20 mild steel nut, M20 mild steel 1. washer, M20 threaded bolt (x24)

5000 988

35

955

990

35

955

35

990

933

35

891

35

136

875

991

450

10mm galvanized steel bulkhead

whb

whb

25mm mild steel SHS 110

whb

whb

893

Grohe cube counter top basin 50 5.

Amalfi Jade Plus Chrome Basin Mixer Tap

35mm mild steel SHS 990

991

968

1. All windows areas to be 10% of floor area of which 50% is openable. 2. Read figured dimensions in preferance to scaling. 3. All levels dimensions, heights of plinths, depths of excavations and number of steps to be finally checked and determined by contractor on site. 4. Drawings prepared on basis of surface examination on site. Walls below ground level. 5. Recommended - AB's over all windows and doors without fanlights. 6. All handrails to be min 1,000mm high, ballister max 100 ccs 7. All drawings to comply with SANS 10400 and SANS 204 NOTES 5 AND 6 ARE RECOMMENDED

3.

20 mm Snowstorm Quartz countertop

whb

General Notes:

2.

4.

927

Quality of all materials and workmanship to comply with the relevant S.A.B.S, Specification and shall comply with the minimum standard specified in the Standard Preambles in the bills of Quantities or, in the absence of a bill of quanitities, available for perusal at the offices of the Architects. A project specification document will be issued by the Architects to elaborate on the pre-ambles. Where the contractor finds these two documents to be conflicting this must be brought to the architect's attention before doing the work. The contractor is responsible for correct setting out of the buildings, all external and all internal walls with particular reference to boundaries, building lines, etc. The contractor is to verify levels, heights and dimensions on site and to check same against the drawings before putting any work in hand. Any discrepencies from the theoretical to be brought to the architect's attention. The contractor and all Sub-contractors are to check the details shown on this drawing for compliance with standards of best building practice (which is what is expected to be delivered) with particular reference to special requirements necessitated by local and/or on site conditions and to report any comment to the Architect. The contractor is to locate and identify existing services on site and to protect these from damage throughout the duration of the works. Any errors, discrepancies or omissions on this drawing are to be reported to the Architect immediatly. The Contractor is to build in approved DPC's whether or not these are shown on drawings, to all external walls at each floor, beam or parapet level and to all windows, doors, grilled or other opening in external walls. Cavity walls to have stepped DPC's. Any quaries arising from the above must be reported to the Architect for clarification before any work is put in hand. This drawing is not to be scaled. Where figured dimensions are given, this must be confirmed by the Architect.

6. 7.

VANITY DETAIL_Callout A

0m

Scale 1:10

VISUAL SCALE 1:10 @ A1

0.2m

0.4m

0.6m

0.8m

H

1m

H

3 48

3

Vanity assembly diagram

48

20mm suspended fibre glass ceiling tile

MALE BATHROOM FFL + 0

TOC Ground Floor level

Tiled

30 m²

Vanity detail Notes:

10mm galvanized steel bulkhead

110mm PVC waste pipe

LED Strip Lights 12Volts Warm White Colour SMD5050

10mm galvanized steel bulkhead

Cristallo Silver Frameless Mirror - 2200 x 700mm

Cristallo Silver Frameless Mirror - 2200 x 700mm

Amalfi Jade Plus Chrome Basin Mixer Tap

20mm Snowstorm Quartz countertop, supplied by the granite warehouse

Cristallo Silver Frameless Mirror - 2200 x 700mm

Amalfi Jade Plus Chrome Basin Mixer Tap

99

400

101 25

Grohe cube counter top basin 50 988

whb

whb

990

whb

990

Grohe cube counter top basin 50 20mm Snowstorm Quartz countertop Glued onto steel frame

533

whb

857

-3000 TOC Ground Floor level

35

955

35

20mm Snowstorm Quartz facing

954 5001

35

934

35

873

Project Information:

REV:NO

DESCRIPTION

01

Dimensions

06/10/2021

01

Detailed Specifications

06/10/2021

01

Hidden elements

06/10/2021

420 440

35 125

5mm Tile adhesive 5mm dovegrey grout

35mm square hollow section, frame welded and assembled off site

GIO Chrome Bottle Trap (80 x 120mm)

30mm screed -3000

Drawing Details:

TOC Ground Floor level

VANITY DETAIL

0m

Scale 1:10

VISUAL SCALE 1:10 @ A1

0.2m

0.4m

0.6m

0.8m

1m

DATE ISSUED

I.E

25 723

25mm mild steel SHS 35mm mild steel SHS

317

91 35

143 720

908

720

969

7° 42.7

989

24

990

University of the Witwatersrand

Revision Details:

20 mm Snowstorm Quartz facing glued onto steel frame 892

Client Information:

ARPL 3031A 2021 - Project 7.2

460

991

whb

1. All finish items to be completed as stated in drawing. 2. No drainage bends or junctions below floors. 2. Bends and junctions in drains to be fitted with C.E's and I.E's with marked covers at ground level. 3. Drains under building to be adequetly protected against load. 4. Waste pipes to have reseal traps and to be fully accesible over full length. 5. Bathwast 50mm internal diameter basinwaste 50 mm internal diameter. 6. Gulleys at kitchens to have a cw tap over. 7. All surfaces to comply with NBR's. 8. Soil pipes to be 110mm at minimum.

DRAWN BY:

SECTION H-H Scale 1:10

DRAWING SCALE:

2192396

1:10

DRAWING NUMBER:

DATE:

PRVT7.2

14/09/2021

DRAWING NAME:

REVISION NUMBER:

PROJECT 7.2 Vanity Detail

02 Page 8 of 8


CLIENT: STAND NUMBER:

1711844 1833372 2193758

TOWNSHIP: PROJECT NUMBER:

01T2

20/10/2021

DRAWN BY:

Mickyle Berling

Dustbins

TOTAL NO. OF FITTINGS

MALE 3

DISABLED

FEMALE

SPECIFICATION

3

NEW FITTINGS

FITTING

WASH HAND BASINS

SUPPLIER: Vaal PRODUCT CODE: CCRBAJN1-2CO0423 Description: Vaal Cardinal Basin Underslung Vitreous china 470x360mm rectangular underslung basin, with integrated overflow. No provision for tapholes. 470x360 For Disabled Toilet

IMAGE

6

SUPPLIER: COBRA PRODUCT CODE: G-3947500H Description: Cobra Pause Basin Mixer Standard Pause basin mixer, - one hole single lever, chrome INSTALLATION: Surface mounted

2

2

INSTALLATION: Under-slung, installed 650 mm from ground

WC

7

2

IMAGE

4

SUPPLIER: Cobra PRODUCT CODE: CARSTWH1-2CO0372 Description: 90deg, Outlet back inlet, rimless bck to wall toilet pan, with quality thermostat soft close seat with wall brackets.

INSTALLATION: Wall hung SUPPLIER: COBRA PRODUCT CODE: CPSCCST1-6DT01 Description: Cobra Pause Close coupled toilet suite. Top, dual flush capability with 3L and 4.2L flush available.

IMAGE

2

2

4

Flushmaster / Cistern

2

7

3

3

SUPPLIER:Grohe Bau PRODUCT CODE:G-39438000 Description: Urinal concealed inlet flush volume

Urinal

SANITARY FITTINGS

IMAGE INSTALLATION: Concealed system

IMAGE

SANITARY FITTINGS

INSTALLATION: Floor mounted 480mm from floor with 740mm grab rail SUPPLIER: COBRA PRODUCT CODE:CENSHJNN-2CO Description: cistern DIY friendly concealed cistern, with compression resistant reinforced tank.

SUPPLIER: AIKEN Product code: TBD051370601B Description: 04 Stainless Steel Automatic SensorJet Hand Dryer High Speed Airflow for Home Hotel Airport Hands Drying Machine(Polished silver)

IMAGE

IMAGE

3

6 2

4

SUPPLIER:COBRA PRODUCT CODE: FELSODCC-0GT0071 Description: Cobratron touch-free, electronic-control, pillar-type soap dispenser, chrome. INSTALLATION : Table mounted

IMAGE

2

2

3

Toilet Roll Holders Soap Hand Dryers Dispensers

ACCESSORIES

SUPPLIER:Volkem PRODUCT CODE:WATR-1003 Description TOILET ROLL HOLDER – STAINLESS STEEL INSTALLATION : Wall Mounted

IMAGE

3

2

8

1

Taps

SUPPLIER:Cobra Pause Basin Mixer Standard PRODUCT CODE:FBL1D1Y6-0GT0383 Description: Pause basin mixer, - one hole single lever, chrome Disabled Toilet INSTALLATION : Table mounted

IMAGE

3

INSTALLATION: Wall hung

SUPPLIER: COBRA PRODUCT CODE:FBL1D1Y6-0GT0383 Description: Pause basin mixer, - one hole single lever, chrome INSTALLATION: Table mounted

1

1

3

SANITARY SCHEDULE STUDENT NUMBERS

7

2/2

PROJECT: 2192396 2179641

CLIENT: STAND NUMBER:

1711844 1833372 2193758

TOWNSHIP: PROJECT NUMBER:

SUPPLIER:Volkem PRODUCT CODE:SA426135 Description: REFLEX DISPOSER BIN – 35L STAINLESS STEEL INSTALLATION: Wall hung

Performance DRAWING NUMBER: Wits ISSUED FOR: 2940 REVISION NUMBER: JohannesburgDATE: JHGHCJ CHECKED BY:

01T2

20/10/2021

DRAWN BY:

IMAGE

1

2192396 2179641

Performance DRAWING NUMBER: Wits ISSUED FOR: 2940 REVISION NUMBER: JohannesburgDATE: JHGHCJ CHECKED BY:

GROUP NO. 2

PROJECT:

ACCESSORIES

GROUP NO. 2

SANITARY SCHEDULE STUDENT NUMBERS

1

Mickyle Berling

1

3


Floor Finish Type

SPECIFICATION Floor Finish No. 1 Product: Supplier Product Code: Contact Details of Supplier: Preferred Installer Notes:

Floor Finish Type

SPECIFICATION Floor Finish No. 2

Carpet finish for Auditorium Cast - Exposed Broadloom Carpet Belgotex Flooring

Carpet finish for Office

Product: Supplier Product Code: Contact Details of Supplier: Preferred Installer Notes:

+27 33 897 7500 Belgotex Flooring +27 11 066 2952 Top Carpets & Floors - Alberton Product to be laid in accordance with SANS10186 fitting code practice. Heavy Commercial, SDN, Tufted Broadloom

Stainproof Miracle Fibre (Polypropelene) Essex carpet Belgotex Flooring Belgotex Flooring [+ 27 (11) 380 9300] Arebone [+ 27833467187] ESSEX (Stainproof Miracle Fibre (Polypropelene)

01. Preperation

Sweep and Clean Floor Ensure room has no loose items, if so is should be removed

02. Installation

Lay underpad onto screed/install new tackless strips if applicable Install new carpet padding Lay new carpet Match carpet seams Stretch and attach carpet at walls and install skirting

02. Installation

Lay underpad onto screed / install new tackless strips if applicable Install new carpet padding Laying new carpet Match Carpet Seams Stretching and attaching the carpet / Tucking at the walls, install skirting trim

03. Finish & Colour

Finish: Industrial finish of solid concrete Colour : Flint Stainproof SDX

03. Finish & Colour

Stainproof Miracle Fibre (Polypropylene) Colour = GIN

04: Sealer

N/A

04: Sealer

N/a

05. Tiling Layout

N/A

05. Tiling Layout

N/a

06. Trim

Meranti skirting 70 x 18 mm

06. Trim

Meranti Skirting

IMAGE

FLOOR FINISHES SCHEDULE

FLOOR FINISHES SCHEDULE

2192396 PROJECT:

Performing Arts

DRAWING NUMBER: 02T2

2179641 CLIENT:

Wits

ISSUED FOR:

Construction

2940 REVISION NUMBER:

1711844 STAND NUMBER: 2193758 TOWNSHIP:

Johannesburg

1833372 PROJECT NUMBER:

F5568

DATE:

20/10/2021

CHECKED BY: DRAWN BY:

Mickyle Berling

1

Student No.'s

IMAGE

GROUP NO. 2

Student No.'s

Prepare for installation by vacuuming and mopping the floor clean Remove any Obstructions

GROUP NO. 2

01. Preperation

2192396

PROJECT:

Performing Arts

DRAWING NUMBER: 03T2

2179641

CLIENT:

Wits University

ISSUED FOR:

1711844

STAND NUMBER:

2193758

TOWNSHIP:

Johannesburg

1833372

PROJECT NUMBER:

PRT2L

Construction

2940 REVISION NUMBER: DATE:

20/10/2021

CHECKED BY: DRAWN BY:

S. van Heerden

1


Atrificial Grass

SPECIFICATION Floor Finish No. 3

Porcelin Floor Tile

SPECIFICATION Floor Finish no. 5

Artificial Grass for Roof

Office Balcony Floor Tile

Product: Supplier Product Code: Contact Details of Supplier: Preferred Installer Notes:

Leisure 30 mm + Infill Belgotex Grass N/A Italtile, Telephone: 010 271 2272, Email: sales@italtile.co.za Belgotex Grass Commercial, 10 Year UV Warranty , 5 Year Guarentee , 15kg/m^2 ARTIFICIAL GRASS FOR ROOF

Product: Supplier Product Code: Contact Details of Supplier: Preferred Installer Notes:

01. Preperation

Measure ground and set out boundries Make provisions for artificial grass base on the dry surface Ensure correct drainage provisions have been set out for underneath the artificial grass Pour a block of concrete around the perimeter of the area and Install waterproof barrier on the perimeter Install a geotextile fabric barrier Smooth and flatten surface using a roller Lay performance pad Ensure all is level Install underlay and artificial grass Join pieces together by applying an adhesive on the underside and pulling edges together Trim excess edges Secure Grass with Adhesive Place infill into artificial grass @ 15kg/m^2 Brush Grass 30mm Infill Leisure , Green

01. Preperation

Sweep & Clean Surface Level & Patch Screed Apply Tile Sealer a minimum of 6 hours before Grouting

02. Installation

Map out Tile layout and setting out point. Apply Adhesive ( Pro Grip XXL Tile Adhesive ) Lay Tiles from setting out point with 3mm Tile Spacers Apply 3mm Grout ( Pro Grip Taupe Water Repellent Tile Grout ) in Grounting Joints Check Tile Levels and Spacing

03. Finish & Colour

Matt, Brown

04: Sealer

No Sealer required

05. Tiling Layout

220 x 895mm Stretcher Bond Tiling Layout Pattern with 3mm Grouting

06. Trim

8mm Promax Aluminium Straight Edge Trim

IMAGE

IMAGE

FLOOR FINISHES SCHEDULE

FLOOR FINISHES SCHEDULE

2192396

PROJECT:

Performing Arts

DRAWING NUMBER: 04T3

2179641

CLIENT:

Wits University

ISSUED FOR:

1711844

STAND NUMBER:

2940

REVISION NUMBER: 1

2193758

TOWNSHIP:

Johannesburg

DATE:

1833372

PROJECT NUMBER:

PRT2L

CHECKED BY: DRAWN BY:

Construction 20/10/2021 C. Giannoccaro

Student No.'s

Student No.'s

GROUP NO. 2

03. Finish & Colour

GROUP NO. 2

02. Installation

Ampezzo Natural Matt Glazed Slip-Resistant EcoTec Porcelain Tile 8x220x895mm Italtile GR1IAMA30R31EA Italtile, Telephone: 010 271 2272, Email: sales@italtile.co.za Contractor Made in South Africa , Slip Resistant , Eco Friendly , Rectified Edges , Low Maintenence OFFICE BALCONY FLOOR TILE

2192396

PROJECT:

Performing Arts

DRAWING NUMBER: 06T2

2179641

CLIENT:

Wits University

ISSUED FOR:

1711844

STAND NUMBER:

2940

REVISION NUMBER: 1

2193758

TOWNSHIP:

Johannesburg

DATE:

1833372

PROJECT NUMBER:

PRT2L

CHECKED BY: DRAWN BY:

Construction 20/10/2021 C. Giannoccaro


Ceramic Wall Tile

SPECIFICATION Wall Finish no.1

Mosaic Wall Tile

SPECIFICATION Wall Finish no.2

Toilet Wall Tile

Vanity Wall Tile

Product: Supplier Product Code: Contact Details of Supplier: Preferred Installer Notes:

Shore Stone Ceramic Wall Tile 8x265 x800mm Italtile WS1ISS20U9LA Italtile, Telephone: 010 271 2272, Email: sales@italtile.co.za Contractor Made in South Africa , Eco Friendly , Low Maintenence TOILET WALL TILE

Product: Supplier Product Code: Contact Details of Supplier: Preferred Installer Notes:

Pegasus Double Glazed Recycled Glass Mosaic 6x258 x 300mm Italtile GSMO00147 Italtile, Telephone: 010 271 2272, Email: sales@italtile.co.za Contractor 100% Recycled Glass VANITY WALL TILE

01. Preperation

Repair any cracks/damages Level and sand surface Clean and Dry Surface Prime surface

01. Preperation

Repair any cracks/damages Level and sand surface Clean and Dry Surface Prime surface

02. Installation

Plaster Wall Map out Wall Tile layout and setting out point & Cut appropriate sizes for fittings (if applicable) Apply Adhesive ( Pro Grip XXL Tile Adhesive ) Lay Tiles from setting out point with 3mm Tile Spacers Apply 3mm Grout (Pro Grip White Waterproof Tile Grout) in Grounting Joints Check Tile Levels and Spacing

02. Installation

Plaster Wall Map out Mosaic Square Layouts & Cut appropriate sizes for fittings (if applicable) Apply Adhesive ( Pro Grip XXL Tile Adhesive ) Lay Mosaic according to layout details Apply Grout (Pro Grip White Waterproof Tile Grout) in Grounting Joints Check Tile Levels and Spacing Apply Top Sealer

03. Finish & Colour

Shiny, Grey

03. Finish & Colour

Semi-Gloss, Grey

04: Sealer

No Sealer required

04: Sealer

Top Seal TFC

2192396

PROJECT:

Performing Arts

DRAWING NUMBER: 07T2

2179641

CLIENT:

Wits University

ISSUED FOR:

1711844

STAND NUMBER:

2940

REVISION NUMBER: 1

2193758

TOWNSHIP:

Johannesburg

DATE:

1833372

PROJECT NUMBER:

PRT2L

CHECKED BY: DRAWN BY:

Construction 20/10/2021 C. Giannoccaro

Student No.'s

WALL FINISHES SCHEDULE GROUP NO. 2

Student No.'s

GROUP NO. 2

WALL FINISHES SCHEDULE 2192396

PROJECT:

Performing Arts

DRAWING NUMBER: 08T2

2179641

CLIENT:

Wits University

ISSUED FOR:

1711844

STAND NUMBER:

2940

REVISION NUMBER: 1

2193758

TOWNSHIP:

Johannesburg

DATE:

1833372

PROJECT NUMBER:

PRT2L

CHECKED BY: DRAWN BY:

Construction 20/10/2021 C. Giannoccaro


Limestone Vanity Countertop

SPECIFICATION Vanity Finish no.1

Vanity Countertop

Product: Supplier Product Code: Contact Details of Supplier: Preferred Installer Notes:

BIANCO CAPRI LIMESTONE SLAB Union Tiles N/A Union Tiles , Bedfordview , Telephone: 011 663 2000 , Email: info@uniontiles.co.za Contractor Limestone Slab VANITY COUNTERTOP

01. Preperation

Map out and cut slab including fitting holes into to correct dimensions Map out and install new cabinetry in correct accordance to slab size (including overhangs etc.) Ensure correct level over all cabinetry Place protective covers on floors/furniture (if applicable) Ensure enough space is allocated for transportation of slab into area

02. Installation

Ensure level is flat Map out correct positioning of slab Install slab in correct position in accordance to the fittings and layout Join seams of different slabs together using colour matched epoxy ensuring the slabs are flush against eachother Seal and attach slab on the underside to the cabinetry by using acrylic caulk Apply granite sealer onto clean countertop stone and leave to set

03. Finish & Colour

Natural Stone, White with natural stone elements

04: Sealer

TFC Natural Stone Sealer

Student No.'s

GROUP NO. 2

VANITY TOP SCHEDULE 2192396

PROJECT:

Performing Arts

DRAWING NUMBER: 09T2

2179641

CLIENT:

Wits University

ISSUED FOR:

1711844

STAND NUMBER:

2940

REVISION NUMBER: 1

2193758

TOWNSHIP:

Johannesburg

DATE:

1833372

PROJECT NUMBER:

PRT2L

CHECKED BY: DRAWN BY:

Construction 20/10/2021 C. Giannoccaro


Student No.'s

Product: Dulux Paint Supplier Dulux Expert Painting Services Product Code: Contact Details of Supplier: 0860 330 111 Preferred Installer Notes: DULUX WOODGARD MARINE TIMBAVARNISH

GROUP NO.

PAINT - DOOR FINISH TYPE

SPECIFICATION Wall finish no.:

2192396

PROJECT:

Performing Arts

2179641

CLIENT:

Wits University

1711844

STAND NUMBER:

DRAWING NUMBER: 10T2 ISSUED FOR:

Construction

2940 REVISION NUMBER:

2193758

TOWNSHIP:

Johannesburg

DATE:

1833372

PROJECT NUMBER:

PRT2L

CHECKED BY: DRAWN BY:

20/10/2021 Mfundo Mokotong

PAINT - DOOR FRAME FINISH TYPE

SPECIFICATION Wall finish no.:

01. Preparation

Timber door: sand down wood including the end grain to a smooth even surface using 100 - 150 grit sandpaper, sanding in the direction of wood grain, remove dust with a clean lint free cloth dampened with water Ensure that surface is now smooth, free from dust, dirt, grease, oil and mortar splatter, surfaces must be thoroughly dry, no more than 12% moisture content

Product: Dulux Paint Supplier Dulux Expert Painting Services Product Code: Contact Details of Supplier: 0860 330 111 Preferred Installer Notes: DULUX STEEL PRIMER

02. Installation

Timber door: Stir Dulux Woodgard Exterior Marine Timbavarnish until homogenous with a flat paddle, when brushing apply in an even thickness and finish in the direction of the grain, thin the first coat with mineral turpentine to aid penetration on raw wood, allow to dry overnight and sand lightly, apply second and third coat undiluted, sanding lightly, between coats

01. Preparation

Steel door frame: All rust, scale and dirt must be removed by scraping or with steel wire brushes and then thoroughly sand with medium grit sandpaper and with fine grit sandpaper - down to a metail finish, a solvent wash (dipped in lacquer) may be used

03. Finish & Colour

Timber door: Gloss finish and clear only

02. Installation

Steel door frame: Stir Dulux Steel Primer until homogenous, can be brushed, rolled or sprayed, brush application preferred to ensure wetting of the surface, apply 1 or 2 coats ,over coat primer with one coat of Dulux Universal Undercoat and finish with two coats of selected Dulux decorative topcoat

04: Sealer

Timber door: N/A

03. Finish & Colour

Steel door frame: Matt to low sheen finish and Light grey colour

04: Sealer

Steel door: N/A

DOOR FINISH SCHEDULE


2192396

PROJECT:

Performing Arts

DRAWING NUMBER: 10T2

2179641

CLIENT:

Wits University

ISSUED FOR:

1711844

STAND NUMBER:

2193758

TOWNSHIP:

Johannesburg

DATE:

1833372

PROJECT NUMBER:

PRT2L

CHECKED BY: DRAWN BY:

Mfundo Mokotong

Product: Dulux Paint Supplier Dulux Expert Painting Services Product Code: Contact Details of Supplier: 0860 330 111 Preferred Installer Notes: DULUX ACRYLIC PVA

03. Finish & Colour

04: Sealer

Wall in the foyer: Apply Dulux Universal Undercoat by brush, rolling or spraying, followed by Dulux Acrylic PVA

2192396

PROJECT:

Performing Arts

DRAWING NUMBER: 10T2

2179641

CLIENT:

Wits University

ISSUED FOR:

1711844

STAND NUMBER:

2193758

TOWNSHIP:

Johannesburg

DATE:

20/10/2021

1833372

PROJECT NUMBER:

PRT2L

CHECKED BY: DRAWN BY:

Mfundo Mokotong

Construction

2940 REVISION NUMBER:

PAINT - WALL IN THE BATHROOM

SPECIFICATION

Product: Dulux Paint Supplier Dulux Expert Painting Services Product Code: Contact Details of Supplier: 0860 330 111 Preferred Installer Notes: DULUX EGGSHELL ENAMEL 01. Preparation

Wall in the bathroom: Plaster mix must be applied to a min thickness of 10mm, curing to a hard sound finish

04: Sealer

Wall in the bathroom: N/A

02. Installation

Wall in the bathroom: Dulux Eggshell Enamel Ready for use after thorough stirring, apply 2 - 3 coats to wall for a firm and solid color

03. Finish & Colour

Wal in the bathroom: Mid-sheen and Natural Hessian from Dulux colour system

Wall in the foyer: Matt finish and Linesh lush from Dulux colour system

WALL FINISHES SCHEDULE

Wall in the foyer: N/A

Student No.'s

02. Installation

Wall in the foyer: Fresh cement plaster should be applied on the wall, prime with one coat of Dulux Plaster Primer

Student No.'s

20/10/2021

GROUP NO.

2940 REVISION NUMBER:

PAINT - WALL IN THE FOYER

SPECIFICATION

01. Preparation

WALL FINISHES SCHEDULE

Construction

GROUP NO.

Student No.'s

GROUP NO.

DOOR FRAME FINISH SCHEDULE

2192396

PROJECT:

Performing Arts

2179641

CLIENT:

Wits University

1711844

STAND NUMBER:

DRAWING NUMBER: 10T2 ISSUED FOR:

Construction

2940 REVISION NUMBER:

2193758

TOWNSHIP:

Johannesburg

DATE:

20/10/2021

1833372

PROJECT NUMBER:

PRT2L

CHECKED BY: DRAWN BY:

Mfundo Mokotong


GROUP NO. 2

LIGHTING SCHEDULE STUDENT NUMBERS:

2192396 2179641 1711844 1833372 2193758

PROJECT: CLIENT: STAND NUMBER: TOWNSHIP: PROJECT NUMBER:

Performance Arts Wits Univ. Johannesburg PRT2L

DRAWING NUMBER: ISSUED FOR: REVISION NUMBER: DATE: CHECKED BY: DRAWN BY:

11T2 Construction 20/10/2021 M.Bham

See Drawing No.:See Ablution layout,electrical reticulation,working P7.2

IMAGE

Type of globe.LED Osram Duris E5 Nominal wattage:10W Color temp:4000K Nominal flux:1428Im

See Drawing No.:See Ablution layout,electrical reticulation,working P7.2

IMAGE

Type of globe.LED Cove 14 - 15W/m 4000K Strip Length:1995mm Power (W):29.00W Nominal Flux:4650 Im

Type of globe. LED Samsung E2835 Voltage:220V Nominal Wattage: 15W Colour temp:4000K Nominal flux:2098 Im

See Drawing No.:See Ablution layout,electrical reticulation,working P7.2

Type of globe.LED Wattage as per lamp manufacturer. Base: GU10

See Drawing No.:See Ablution layout,electrical reticulation,working P7.2

Type of globe.

See Drawing No.:

Type of globe.

See Drawing No.:

Type of globe.

See Drawing No.:

2 Fittings per floor

Description:This square wall or celing mounted sconces with UV stabilised high impact opal acrylic diffuser. A range of die-cast aluminium and extruded bulkhead luminaries offered in two style variant - They are suitable for both interior and exterior.

Wall

1

SUPPLIER:REGENT LIGHTING SOLUTIONS PRODUCT CODE:GEO ADVANCED

SUPPLIER:REGENT LIGHTING SOLUTIONS PRODUCT CODE:LINEAR LED COVE

Wall

Description:This round wall or ceiling mounted sconces with UV stablised high impact opal acrylic diffuser. A range of die-cast aluminium and extruded bulkheads lumninaries offered in three style variants. Available as an emergency lighting variant-they are suitable for both interior and exterior applications.

IMAGE

Description:The Kalypso round is a small surface mounted cylindrical down lighter with an elegant design to decorate your interiors.

IMAGE 6 Per block

Ceiling

SUPPLIER:REGENT LIGHTING SOLUTIONS PRODUCT CODE:KALYPSO ROUND PRO

4

LIGHT FITTINGS

3

SUPPLIER:REGENT LIGHTING SOLUTIONS PRODUCT CODE:SOLO CROSS ARM

SUPPLIER: PRODUCT CODE: Description

IMAGE

SUPPLIER: PRODUCT CODE: Description

IMAGE

SUPPLIER: PRODUCT CODE: Description

12 / 13

2 Fittings per floor/duct

6 Fittings,2 around each mirror

2 wall

Description:This luminare provides a stylish solutions for creating a visual impact for interior of architectural buildings

TOTAL NO. OF FITTINGS

SPECIFICATION

Reference Drawings

Globe

Type

Fitting No.

NEW FITTINGS

IMAGE


Ironmongery Schedule

SPECIFICATION Door No.: D01

Door location & type: Shop-front / Entrance door (Aluminium Frame with Glass Panes)

Product: Supplier Product Code: Contact Details of Supplier: Preferred Installer Notes:

Ironmongery Schedule

SPECIFICATION Door No.: D10

Door location & type: Office door(First Floor, Aluminium Frame with single pane glass insert

Product: Supplier Product Code: Contact Details of Supplier: Preferred Installer Notes:

[011 624 3535] Mildo Projects [011 760 2407]

IRONMONGERY Pull Straight Fixing centers:150mm / Annodized Aluminium Contract Hardware CH1321 [011 624 3535] Mildo Projects [011 760 2407] 02. Lockset Electric Lock / 60 Backset / Stainless Steel Description: Contract Hardware Locking mechanism to CH1555 lock front door [011 624 3535] Mildo Projects [011 760 2407] 03. Cylinder / Mortice lock Cisa Cylinder lock / 42.5mm / Single Cylinder with adjustable cam Description: Contract Hardware Mechanism within lockset CH1703 used for key insertion [011 624 3535] 04. Hinges, type & No. Stainless steel, sinkless Hinge / 100mm x 75mm x 3mm / Stainless Steel Description: Contract Hardware Mechanism to allow door CH1903 to open and close(to allow [011 624 3535] door swing) No. 3 per door Mildo Projects [011 760 2407] 05. Door Stop (if applicable) Half Moon Door Stop / Aluminium Components then stops the Contract Hardware door from colliding with a CH2057 wall. [011 624 3535 Mildo Projects [011 760 2407] 06. Door Closer (if applicable) Cam-Action Slide Channel Door Closers Description: Contract Hardware Mechanism that closes CH1753 door when not properly [011 624 3535] manually closed Mildo Projects [011 760 2407] 07. Push Plate (if applicable) Description: 01. Door Handle Description: Pull handle to open/close heavy door

IMAGE

01. Door Handle Description: Handle mechanism to open door. 02. Lockset Description: Locking mechanism to lock door

IMAGE

IMAGE

IMAGE

03. Cylinder / Mortice lock Description:

[011 624 3535] Mildo Projects [011 760 2407] IRONMONGERY Door Handle (Vita Legno Handle) Satin / Walnut wood Contract Hardware CH3025 [011 624 3535] Mildo Projects[011-760-2407] Stainless Steel Rebate Conversion Set for 2 lever Upright Lock Contract Hardware CH1451 [011 624 3535] Mildo Projects[011-760-2407] N/a

IMAGE

IMAGE

IMAGE

04. Hinges, type & No. Description: Mechanisme to allow door to swing. No, 2 per door 05. Door Stop (if applicable) Description: Mechanism to stop door from colliding with wall

Howick Metal Products Brass Handle Contract Hardware CH1940 [011 624 3535] Mildo Projects[011-760-2407] Assa Alboy - Half Moon Doorstop / Aluminium Contract Hardware CH2057 [011 624 3535] Mildo Projects[011-760-2407] 06. Door Closer (if applicable) N/a Description:

IMAGE

IMAGE

IMAGE

IMAGE

07. Push Plate (if applicable) N/a Description: IMAGE

08. Kick Plate (if applicable) Description:

IMAGE

08. Kick Plate (if applicable) Description:

N/a

IMAGE

IMAGE

2192396 PROJECT:

Perfoming Arts School DRAWING NUMBER: 02T2

2179641 CLIENT:

Wits University

ISSUED FOR:

1711844 STAND NUMBER:

2940

REVISION NUMBER: 3

1833372 TOWNSHIP:

Johannesburg

DATE:

20/10/2021

2193758 PROJECT NUMBER:

PRT2L

CHECKED BY:

M. Bham

DRAWN BY:

S van Heerden

Construction

Student No.'s

IRONMONGERY SCHEDULE GROUP NO. 2

Student No.'s

GROUP NO. 2

IRONMONGERY SCHEDULE

2192396 PROJECT:

Performing arts School DRAWING NUMBER: 02T2

2193758 CLIENT:

Wits University

ISSUED FOR:

2179641 STAND NUMBER:

2940

REVISION NUMBER: 1

1711844 TOWNSHIP:

Johannesburg

DATE:

1833372 PROJECT NUMBER:

PRT2L

CHECKED BY:

M. Bham

DRAWN BY:

S van Heerden

Construction 20/10/2021


Ironmongery Schedule

SPECIFICATION Door No.:

Door location & type: Ground Floor Ablution (Entrance to Ablution), Louvered Aluminium Door

Product: Supplier Product Code: Contact Details of Supplier: Preferred Installer Notes: 01. Door Handle Description: Solid handle used to open and close door, backplate can be used to push open 02. Lockset Description:

[011 624 3535] Mildo Projects [011 760 2407] IRONMONGERY Aluminium Sable Pull Handle on 3mm Aluminium Backplate Contract Hardware CH1319 [011 624 3535] Mildo Projects [011 760 2407] N/a

IMAGE

IMAGE

03. Cylinder / Mortice lock Description:

N/a

04. Hinges, type & No. Description: Mechanism to allow door to swing No. 2 05. Door Stop (if applicable) Description: Mechanism stopping door from colliding with a wall

Stainless steel. Sinkless Hinge. 100mm x 75mm x 3mm. Contract Hardware CH1903 [011 624 3535] Mildo Projects [011 760 2407] Assa Abloy - Halfmoon doorstop / Aluminium Contract Hardware CH2057 [011 624 3535] Mildo Projects [011 760 2407] Dorma. Rack and Pinion Projecting Arm Closers. Contract Hardware CH1757 [011 624 3535] Mildo Projects [011 760 2407] N/a

IMAGE

06. Door Closer (if applicable) Description: Mechanism to allow door to close automatically when not properly closed 07. Push Plate (if applicable) Description:

Ironmongery Schedule

SPECIFICATION

IMAGE

IMAGE

Door No.: D04

Door location & type: Ground floor Ablution, Cubicle Door (15mm Melawood )

Product: Supplier Product Code: Contact Details of Supplier: [011 624 3535] Preferred Installer Mildo Projects [011 760 2407] Notes: IRONMONGERY 01. Door Handle Martinelli Ring Handle / Chrome Description: Contract Hardware Handle used to open and CH3018 close cubicle door [011 624 3535] Mildo Projects [011 760 2407] 02. Lockset Assa Abloy Rim Lock with Plastic Knob / Painted Black Description: Contract Hardware Mechanism used to lock CH1501 door from inside of cubicle [011 624 3535] Mildo Projects [011 760 2407] 03. Cylinder / Mortice lock N/a Description:

IMAGE

IMAGE

IMAGE

04. Hinges, type & No. Howick Metal Products Canopy Hinge Size: 80 x 75mm / Aluminium Description: Contract Hardware Mechanism that allows for d CH1944 No. 2 per door [011 624 3535] Mildo Projects [011 760 2407] 05. Door Stop (if applicable) Wall mounted door stop / Stainless Steel Description: Contract Hardware Mechanism stops door from CH2058 colliding with cubicle wall. [011 624 3535] Mildo Projects [011 760 2407] 06. Door Closer (if applicableN/a Description:

IMAGE

IMAGE

IMAGE

IMAGE

07. Push Plate (if applicable N/a Description: IMAGE

08. Kick Plate (if applicable) Description: Plate installed on door, can use feet to open door if using a handle is not desired

IMAGE

08. Kick Plate (if applicable) N/a Description:

Kick Plate 150x4m Stainless steel Finish L009 FIT Buco 1236391 [27117953733] (Honeydew) Mildo Projects [011 760 2407]

IMAGE

IMAGE

2192396 PROJECT:

Performing Arts School DRAWING NUMBER: 03T2

2179641 CLIENT:

Wits University

ISSUED FOR:

1711844 STAND NUMBER:

2940

REVISION NUMBER: 1

1833372 TOWNSHIP:

Johannesburg

DATE:

20/10/2021

2193758 PROJECT NUMBER:

PRT2L

CHECKED BY:

M. Bham

DRAWN BY:

S. van Heerden

Construction

Student No.'s

IRONMONGERY SCHEDULE GROUP NO. 2

Student No.'s

GROUP NO. 2

IRONMONGERY SCHEDULE

2192396 PROJECT:

Performing Arts School DRAWING NUMBER: 02T2

2179641 CLIENT:

Wits Uniersity

ISSUED FOR:

1711844 STAND NUMBER:

2940

REVISION NUMBER: 2

1833372 TOWNSHIP:

Johannesburg

DATE:

20/10/2021

2193758 PROJECT NUMBER:

PRT2L

CHECKED BY:

M. Bham

DRAWN BY:

S. van Heerden

Construction


Ironmongery Schedule

SPECIFICATION Door No.: D03

Door location & type: Ground Floor fire escape, Fire Escape Door (Class B Hardboard)

Product: Supplier Product Code: Contact Details of Supplier: Preferred Installer Notes:

[011 624 3535] Mildo Projects [011 760 2407] IRONMONGERY Assa Abloy. Panic Latch- single point, central latch. Door 900mm max. Contract Hardware CH1851 [011 624 3535] Mildo Projects [011 760 2407] N/a

01. Door Handle Description: Mecanism used to open emergency fire escape door 02. Lockset Description:

IMAGE

IMAGE

03. Cylinder / Mortice lock Description:

N/a IMAGE

04. Hinges, type & No. Description: Mechanism used to allow for door swing No. 3 per door 05. Door Stop (if applicable) Description:

Howick Metal Product 100mm x 44mm / Aluminium Contract Hardware CH1941 [011 624 3535] Mildo Projects [011 760 2407] Wall Mounted Door Stop. Contract Hardware CH2058 [011 624 3535] Mildo Projects [011 760 2407] 06. Door Closer (if applicable) Dorma. Rack and Pinion Projecting Arm Closers. Description: Contract Hardware Door stop used to stop CH1758 door from colliding with wall [011 624 3535] Mildo Projects [011 760 2407] 07. Push Plate (if applicable) PUSH PLATE 150X150 2MM / Aluminium Description: Handles Inc. Plate mounted to door, used H5001 to push open door with hands [+27877110470] Hanldes Inc Parkhurst Mildo Projects [011 760 2407] 08. Kick Plate (if applicable) Kick Plate 150 x 4mm stailess finish L009 FIT Description: Buco Plate mounted to doorm used to 1236391 push open door with feet. [27117953733] (Honeydew) Mildo Projects [011 760 2407]

IMAGE

IMAGE

IMAGE

IMAGE

IMAGE

Student No.'s

GROUP NO. 2

IRONMONGERY SCHEDULE 2192396 PROJECT:

Performing arts School DRAWING NUMBER: 02T2

2179641 CLIENT:

Wits University

ISSUED FOR:

1711844 STAND NUMBER:

2940

REVISION NUMBER: 2

1833372 TOWNSHIP:

Johannesburg

DATE:

20/10/2021

2193758 PROJECT NUMBER:

PRT2L

CHECKED BY:

M.Bham

DRAWN BY:

S van Heerden

Construction


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.