L E C
EARLY LEARNING CENTER
DESIGN
AUGUST 25, 2014
OWNER
ARCHITECT
LANDSCAPE
ARCHITECT
CIVIL ENGINEER
ADDRESS: 2123 S. Arlington Hts Rd Arlington Hts, IL 60005
ADDRESS: 2015 Spring Road Oak Brook, IL 60523
ADDRESS: 221 W Jefferson Ave, Naperville, IL 60540
ADDRESS: 715 Ridgeview Drive McHenry, Illinois 60050
Director of Buildings and Grounds Tony Rossi
President Patrick Brosnan AIA, LEED AP BD+C, REFP
Project Principal Dave Frigo
Project Principal Scot DiGilio
Senior Landscape Designer Andy Howard
Project Engineer Tim Shoemaker
Director of K-12 Robin Randall AIA, LEED AP BD + C Project Manager Paul Pessetti AIA, LEED AP Project Architect Stephanie Marcan Project Designer Katie LaCourt Assoc. AIA, LEED AP BD + C Project Associate Bryan Archibald
2
Sustainable Design Specialist Vuk Vujovic Assoc. AIA, LEED AP BD+C
STRUCTURAL
ENGINEER
ADDRESS: 837 Oakton St, Elk Grove Village, IL 60007
ADDRESS: 1216 Tower Rd Schaumburg, IL 60173
Project Engineers Bob Siil Steve Schafer Todd Cooper Pete Nomellini
Project Engineer Jim Barrett
L E C
CONSTRUCTION
MANAGER
ADDRESS: 1001 Feehanville Dr Mt Prospect, IL 60056 Construction Manager Joe Papanicholas
PROJECT DIRECTORY
MEPFP ENGINEER
3
4
L E C
INITIAL CONCEPTS DESIGN STRATEGY SCHEMATIC DESIGN SITE INFORMATION MEETING MINUTES
TABLE OF CONTENTS
1 2 3 4 5
5
1
EARLY LEARNING CENTER
I N IT I A L C O N C E PT S L E C
8
Program NSF 900 sf
18,000 sf
Rooms Rooms Rooms Spaces Rooms Rooms
@ @ @ @ @ @
120 sf 175 sf 120 sf 150 sf 420 sf 100 sf
1,200 sf 1,750 sf 1,200 sf 600 sf 1,680 sf 200 sf 24,630 sf
1 1 1 1 1
Room Room Room Room Room
@ @ @ @ @
300 sf 750 sf 1,000 sf 400 sf 300 sf
300 sf 750 sf 1,000 sf 400 sf 300 sf 2,750 sf
C. Student Services Reception Director's Office Secretary (Clerical) Secretary Social Worker Psychologist Speech Therapy Pull-Out Room Nurse (Cot Area) Nurse (Toilet) Nursing Room General Office Storage Conference Room (w/ Play Area for Parent Meetings) Work Room (Faculty) Staff Center (with kitchenette) Sub-Total:
1 1 1 1 1 2 1 1 1 1 1 1 50 50
Room Room Space Space Room Rooms Room Room Room Room Room Rooms Staff Staff
@ @ @ @ @ @ @ @ @ @ @ @ @ @
D. Large Motor Skills Indoor Play Room Multi-Purpose Activity Room (Play and Snack) Warming Kitchen OT/PT Motor Room with in Storage Special Equipment Device Storage Equipment Storage Sub-Total:
1 1 1 1 1 1
Room Room Room Room Room Room
@ @ @ @ @ @
1,800 sf 1,800 sf 300 sf 900 sf 700 sf 450 sf
1,800 sf 1,800 sf 300 sf 900 sf 700 sf 450 sf 5,950 sf
1 1 4 2 2 1 1
Room Room Toilet Rms Toilet Rms Toilet Rms
@ @ @ @ @ @ @
800 sf 300 sf 50 sf 200 sf 200 sf 1,200 sf 1,500 sf
800 sf 300 sf 200 sf 400 sf 400 sf 1,200 sf 1,500 sf 4,800 sf
*plus up to 4 adults (teacher, aides)
Shared Therapy / Break Out Rooms Shared Integrated Therapy Rooms Shared Toilet Room (in the room) Dispersed Learning Stations OT/ PT/ SLP Team Collaboration Room Laundry Rooms with Dishwasher Sub-Total: B. Parent Support Center Secure Parent Waiting Parent Training Room Parent Support Center / Media Center Diagnostic Room Media Storage Sub-Total:
E. Operations and Maintenance General Storage Outdoor Storage (mower, snow blower - outdoor play equip.) Staff Toilets Public Toilets (2 @ Welcome) Student Toilets (2 @ Indoor Play) Mechanical Room Mechanical Mezzanines Sub-Total:
20 Classrooms @ 10 10 10 4 4 2
100 sf 150 sf 180 sf 180 sf 150 sf 150 sf 175 sf 200 sf 80 sf 80 sf 300 sf 400 sf 15 sf per staff 15 sf per staff
Subtotal Program (NSF) Circulation, Walls, Chases, etc. - % of Total Program Total Program Square Footage (GSF) - Excluding Enclosed Outdoor Courtyard and Sensory Gardens:
L E C
100 sf 150 sf 180 sf 180 sf 150 sf 300 sf 175 sf 200 sf 80 sf 80 sf 300 sf 400 sf 750 sf 750 sf 3,795 sf
PROGRAM
I. Program Spaces A. Classroom Spaces Classrooms (up to 15 students*)
41,925 sf 27.5%
15,932 sf 57,857 sf
9 CCSD59_ELC_Program_07 07 2014.xlsx PAGE 1 OF 1
ET
ET
EG INT HER T
EG INT HER T
.
IL TO
ET
.
.
EG INT HER T
EG INT HER T
/PT OT OTOR M M OO R
.
EG INT HER T
EG INT HER T
EG INT HER T
SSR
CLA
SSR
CLA
LL PU UT O
SSR
CLA SSR
CLA
M
SSR
CLA
M
OO
SSR
CLA
M OO
SSR
CLA
REC
C. SO ORK W
.
C PSY
RSE
SSR
CLA
.
O SL T/ P PT RO TEA / O M M
SEC .
O SL T/ P PT RO TEA / O M M
O SL T/ P PT RO TEA / O M M
SEC
DIA E ME ORAG ST
ENT G PAR AININ M TR ROO
ENT RT PAR PPO ER/ TER SU ENT CEN C IA D ME
OM
M
SSR
CLA
M
SSR
CLA SSR
CLA
M
OO
OM
SRO
S CLA
OO
OO
NF. CO OOM R
O
SE
RPO
I-PU
LT MU
NS
O ATI PER
LS
KIL
R OO IND PLAY
E RG
LA
RS TO O M
M
OO
ES PAC S M
M
OO
OO SSR
CLA
Y ULT K FAC WOR OM RO
ES
FF STA NTER ette) CE chen (kit
GDIA OSTIC M N OO R E UR T SEC AREN ING P AIT W
SSR
SSR
SSR
M OO
SRO
CLA CLA
M
OO
CLA S CLA
M
. GEN FICE GE OF ORA ST
NU
C. PSY
OM
OO
. RM . WA ITCH K
M OO
SRO
O SL T/ P PT RO TEA / O M M
ITO ET L
SSR
CLA SSR
S CLA
O SL T/ P PT RO TEA / O M M
.
R. NU RM.
. DIR FICE OF
M
M
CLA
OM
. UIP E EQ ORAG ST
OO
OO
M OO
SRO
S CLA
M
OO
OO
D. STUOILET T
FF STA ILETS TO O C T BLI IL. PU OILET TO L T C ICA S IL. BLI LET AN NE TO U P OI CH NI T ME EZZA M IL. TO C. AL E R E SPE QUIP. GE G E ORA GEN TORA S ST
EG INT HER T
.
EG INT HER T
EG INT HER T
.
TO
TO
. . IN IN TH TEG TH TEG ER . ER . . IN IN T TH TEG E TH G . ER ER . . IN IN T T E TH G TH EG ER ER . . IN IN T TH EG TH TEG ER ER . . IN TH TEG ER .
ET
IL TO
ET
ET
IL TO
IL TO
ET
IL TO
IL TO
T ILE
ET
IL TO
LAU DRY N
D. STUOILET T IL.
T ILE
IN TH TEG ER .
T. DIS ARN LE
T. DIS ARN LE
T. DIS ARN LE
T. DIS ARN LE
IL TO
LAU DRY N
NT
DE
STU
VIC SER
T
R PO UP ER S T T REN CEN PA
1 1
10
PROGRAM
1/32” = 1’-0”
MOTOR SKILL ADJACENCIES NT ME E UIP AG EQ STOR
E VIC E DE ORAG ST
D. STUOILET T
FF STA OILET T
SSR
CLA
M
OO
M
O SRO
S
CLA EG. NT R. I- I THE TO
ED LOS OOR E ENC UTD SPAC O LAY P
CLA
PU TO BL IL IC ET
. GN R DIA ENTE C
Y ULT K FAC WOR OM RO
L E C
NF. CO OOM R
FF STA NTER ette) CE chen (kit R. NU RM.
. DIR FICE OF
R. NU OIL. T C. SO ORK. W
. SEC
ENT RT PAR PPO ER/ TER SU ENT CEN C IA D ME
.
SEC
C. PSY
C. PSY
L ERA E GEN OFFIC RAGE STO .
REC
FF STA OILET T
RA GE
OM
O SSR
R. NU OT. C
ST O
LL LET PU UT O
PU TO BL IL IC ET
S
CLA
D. STUOILET T
PARENT SUPPORT CENTER ADJACENCIES
EG. INT HER. T
OILL T ET PU UT L O
M
O SRO
Y
SE PA CU W RE RE AI N TI T NG
LL PU UT O / /PT . OT LP RM S
LAU DRY N
VIT
TI I-AC ULT
M R OO IND PLAY
CLASSROOM ADJACENCIES
ING RM EN WA KITCH
FF STA OILET T
11
CLASSROOM ZONES
DRAMATIC PLAY MUSIC BLOCKS LEGO WALL
COMPUTER LIBRARY LISTENING CENTER TOYS&GAMES
LOUD
QUIET
SCIENCE SENSORY TABLE ART NATURE
MESSY
L E C
SENSORY AREA SAND WATER PATH AROUND EDGE GARDEN
ZEN AREA PICNIC AREA WATER WALLS FISH POND UNDER BRIDGE BRIDGE/RAMP ENTRANCE
ACTIVE AREA TUNNEL TIRE SWING INTERACTIVE FAKE TREES CLIMBING AREA ROCK CLIMBING WALL RAMP&STAIRS
L E C
DIAGRAMMING
OUTDOOR ZONES
THREE RIBONS
ZIG ZAG
PROS PROS • Circular corridor around the courtyard space, for • Connection of Multi-activity to Holmes trike play. • Large corridor space adjacent to smaller • Groupings of 4 classrooms in each house courtyards for Learning Centers • One large centralized courtyard space • Preservation of play field space • Potential for north entry by Multi-activity CONS CONS • No equity between classrooms spaces and • No connection between Multi-activity and courtyard access Indoor Play/Courtyard space • No connection to the north • Open side of smaller courtyards to remainder of • Support and Teaching spaces too remote from site each other • Overtakes site space allocated for future expansion to Holmes (north edge)
14
ATRIUM VILLAGE
OPEN PLAYFIELDS
PROS PROS • Opportunity for themed activity courtyards (2) • Large corridor space adjacent to smaller in center courtyards for Learning Centers • Transition to ELC from Holmes through Staff • Transition to ELC from Holmes through Staff Services areas only Services and Parent Support Center areas only • Potential for north entry by Multi-activity • Preservation of play fields to the north • Equal division of classroom “Neighborhoods” on CONS either side of courtyards • One, long, wide central corridor CONS • No connection from Large Motor Skills to • No connection between Multi-activity and enclosed outdoor play Indoor Play/Courtyard space • Open side of smaller courtyards to remainder of • Open side of smaller courtyards to remainder of site site • Immediately adjacent to property line
L E C
15
DESIGN EXPLORATION 16
DESCRIPTION During our early Design Workshops with the Early Learning faculty and staff, everyone brought ideas derived from facility tours, pictures from existing learning spaces as well as a vast collection of inspirational images. Images ranged from full classroom spaces, playground structures, learning corners, materials and interactive play centers. As a method of organizing thoughts in a single location, the District set up a Pinterest account for all Early Learning staff members to post to and pull inspiration from. This resulted in an impressive library of sharable inspiration. This aided the Design Team to assess the intentions behind particular program spaces, as well as apply a playful lens to all decisions made. Staff members kept referencing particular images “Pin” when discussing a particular place within the addition. To aid in the dreaming of the Early Learning Center, the Design Team brought buttons of all “pins” posted to the School District 59 Early Learning Center Pinterest board and asked that staff place the inspirational buttons in their designated locations within the addition. This exercise allowed the Design Team to fully understand the staff’s hopes and intentions for particular program spaces as well as the overall design aesthetic of the center. The courtyard spaces were now explained with colorful images of stacked garden beds, rainwater study walls and children exploring playground structures. The Parent Support Center drew inspiration from airy, comfortable and expansive spaces for parents to get to know the center and staff while their children acclimate to the new environment. The Large Motor Skill areas should have all manner of climbing devices and structures that can service children of all needs.
bus dropoff LEGEND MOTOR SKILLS PARENT SUPPORT CENTER OUTDOOR PLAY STUDENT SERVICES CLASSROOM OPERATIONS
PARENT SUPPORT CENTER
parent dropoff
bus dropoff
isitor parking/ parent dropoff
staff parking
staff parking
RAH LN.
17
COTT PL.
L E C
W. LONNQUIST BOULEVARD
2
EARLY LEARNING CENTER
D E S I G N ST R AT E GY L E C
S. CRESTWOOD LANE
S. CRESTWOOD LANE
S. MEIER ROAD
bus dropoff
parent dropoff
bus dropoff visitor parking/ parent dropoff
staff parking
1 | ADJACENCIES • SS/Parent Support Center connect to Holmes • Motor Skills connects to the large outdoor play area • Classroom Spaces adjacent to outdoor play LEGEND MOTOR SKILLS PARENT SUPPORT CENTER OUTDOOR PLAY STUDENT SERVICES CLASSROOM OPERATIONS
20
KENNICOTT PL.
DEBORAH LN.
W. LONNQUIST BOULEVARD CAROL LN.
DEBORAH LN.
CAROL LN.
W. LONNQUIST BOULEVARD
KENNICOTT PL.
staff parking
2 | SENSORY GARDENS • E/W Orientation for energy efficiency • Sensory Gardens between classroom blocks for daylighting • “10 pack” of classrooms for constructibility
bus dropoff
S. CRESTWOOD LANE
S. CRESTWOOD LANE
S. MEIER ROAD
bus dropoff
parent dropoff
bus dropoff visitor parking/ parent dropoff
visitor parking/ parent dropoff
staff parking
staff parking
staff parking
3 | ALIGNMENT • Rotate alternating blocks slightly (5 degrees) to create horizontal “houses” while maintaining coupled classroom equity • The slight variance between each “house” creates a village-like feel • Creates splayed hallways with requested breakout spaces
L E C
KENNICOTT PL.
DEBORAH LN.
CAROL LN.
W. LONNQUIST BOULEVARD KENNICOTT PL.
DEBORAH LN.
W. LONNQUIST BOULEVARD CAROL LN.
parent dropoff
bus dropoff
staff parking
4 | STAGGER • Staggering the plan components creates a more playful corridor filled with break out space “rooms” • It eliminates the long, daunting corridor and produces a series of spaces
21
1 | Extrude • Each classroom “house” roof exceeds that of the corridor in between in order to provide high quality northern clerestory light into each classroom. • Each “house” registers on the exterior, breaking up the mass in individual components and relating to the scale of the adjacent residential area.
22
2 | Slope • Each classroom “house” roof slopes south, allowing the south wall to more closely relate to the scale of the users, while providing the northern clerestory light. • The shed roof relates to the massing of the residents across the street as well as Forest View.
10 3.0 0°
3 | Cant 4 | Expression Each southern “house” wall cants: • The shed roof metal panel wraps down the • CONTEXT: It relates to the slanted wall canted wall, relating to the Mansard roof language already present at Holmes. expression already present at Holmes. • ENVIRONMENT: Slanting the wall creates • The Eastern wall of each “house” takes on shading for glass on the south, resulting in a a different material, perhaps wood or brick more energy efficient building veneer. • AESTHETICS: It makes each “house” have a unique and sculptural form.
L E C
23
3
EARLY LEARNING CENTER
S C H E M AT I C D E S I G N L E C
SITE PLAN
DESCRIPTION 6
The addition would be located along the east edge of Holmes Junior High School, spanning North to South. There would be a new car dropoff as well as staff and visitor parking lot along Lonnquist Boulevard for the new Early Learning Center. Parents will drop their kids off along the new sidewalk and be escorted into the facility by staff members. Bus traffic for the Early Learning Center would drop off kids along the north turnaround accessed through Forest View’s existing parking lot, north of the Early Learning Center. Holmes would also be outfitted with a designated (and separated) bus and car drop-offs as well as staff and visitor parking. During afterhours events at Holmes, the ELC parking lot could be utilized as overflow parking. The area east of the ELC would be allocated for on-site stormwater storage.
90
NO PARKING
690
90 6
688
689
bu 688
visitor p
st N
688
688
688
0
20
60
140
687
688 688
26
W. LO 687
681
bus dropoff 683
684
685
686 680
679
7 68
CLASSROOM
OPS
TOILET
TEAM
TOILET
68 8
CLASSROOM
INTEGRATED THERAPY
68 9
680
MECHANICAL/ OPERATIONS
TOILET
CLASSROOM
TOILET
INTEGRATED THERAPY
STORAGE
CLASSROOM
CLASSROOM
INTEGRATED THERAPY
OT/PT MOTOR ROOM
TOILET
TOILET
TOILET
KITCHEN
67 9
68 0
STORAGE
CLASSROOM CLASSROOM
INTEGRATED THERAPY
MULTI-ACTIVITY
8 67
CLASSROOM
680
TOILET
678
TOILET
TOILET
9 67
8 67
INDOOR PLAY
INTEGRATED THERAPY
679
CUSTODIAL TEAM CLASSROOM
CLASSROOM
688
TOILET
CLASSROOM
679
INTEGRATED THERAPY
68 7
687
TOILET
689
CLASSROOM TEAMCUSTODIAL
67 8
TOILET
TOILET
67 7
TOILET
CLASSROOM
CLASSROOM
67 8
TOILET
RECEPTION/ WAITING
TEAM ROOM
OPS
CLASSROOM
?
CLASSROOM
678
678
DIAGNOSTIC
NURSE
677
689
TOILET
INTEGRATED THERAPY
TOILET
9 68
CLASSROOM
TOILET
689
PARENT SUPPORT CENTER TOILET
FACULTY WORK ROOM
STORAGE
PARENT TRAINING ROOM
OFFICE
STAFF CENTER
OFFICE
OFFICE
INTEGRATED THERAPY
679
TOILET
CLASSROOM
CLASSROOM
678
TOILET
INTEGRATED THERAPY CLASSROOM
us dropoff
parent dropoff
parking/ parent dropoff
staff parking
staff parking 7 67
683
682
67 8
67 9
680
68 4
677
681
679
680
0 68
8 67 9 67
27 77
68 5
7 67
L E C
ONNQUIST BOULEVARD 68 6
FLOOR PLAN
DESCRIPTION The link between Holmes Junior High and the Early Learning Center would be east of the existing Main Office, with individuals transitioning through the new Staff Services area. The new Outdoor Play courtyard would abut the existing east classrooms within Holmes, maintaining the current natural lighting within those rooms. The central corridor would act as a transportation spine and play space between the Support and Activity spaces with the Learning spaces. The classroom bars would be organized around smaller Sensory Gardens, creating “houses” of 10 classrooms.
GTT LAB
ORCHESTRA MUSIC
CLASSROOM
HEALTH & FITNESS CLASSROOM
CLASSROOM
CLASSROOM
CLASSROOM
CLASSROOM
READ
CLASSROOM
STORAGE
STORAGE
MECH.
LOCKER
LOCKER
LOCKER
LOCKER
OFFICE
MUSIC
OFFICE
MECH.
SP. ED.
LIFE SKILLS
ART
STORAGE GYMNASIUM
SCIENCE
SCIENCE
BAND PREP
SERVING SCIENCE
CAFETERIA
N 0
28
15
45
105
SCIENCE
CLASSROOM
MECHANICAL/ OPERATIONS
TOILET TOILET
CLASSROOM
OPS
TEAM
INTEGRATED THERAPY
TOILET
INTEGRATED THERAPY
STORAGE
CLASSROOM
CLASSROOM
CLASSROOM TOILETTOILET
OT/PT MOTOR ROOM
TOILET INTEGRATED THERAPY TOILET
SENSORY GARDEN
KITCHEN
STORAGE
CLASSROOM TOILETTOILET
TOILET
CLASSROOM
2
CLASSROOM CUSTODIAL
INTEGRATED THERAPY
MULTI-ACTIVITY
TOILET LEARNING CENTER
IDF TEAM
INDOOR PLAY
INTEGRATED THERAPY CUSTODIAL CLASSROOM
TOILET TOILET
CLASSROOM
TOILET
STORAGE
GIRLS
OFFICE
BOYS
TOILET
CLASSROOM
STORAGE
SENSORY GARDEN
CLASSROOM
CONTROL ROOM
TEAM
CLASSROOM
CUSTODIAL
CLASSROOM
TOILETTOILET
CLASSROOM
INTEGRATED THERAPY TOILET
CCLASSROOM CLASSROOM
STORAGE
CLASSROOM
INTEGRATED THERAPY OFFICE
RES.
BOYS SP. PATH
SP. ED.
SP. ED.
SP. ED.
S.W.
PSYCH
CLASSROOM
STORAGE CLASSROOM
TOILETTOILET
CLASSROOM
CLASSROOM
4
CLASSROOM
GIRLS TOILET INTEGRATED THERAPY TOILET
CLASSROOM SENSORY GARDEN
NURSE MAIN OFFICE
TOILET
TOILET
CLASSROOM
CLASSROOM STORAGE
STORAGE
OFFICE
OFFICE
OFFICE
PARENT SUPPORT CENTER
STAFF CENTER
TOILETTOILET
CLASSROOM
CLASSROOM
CLASSROOM INTEGRATED THERAPY
PRINC.
CONF.
OFFICE
STUDY
OFFICE
TOILET
CLASSROOM STAFF WORKROOM
STAFF LOUNGE
FACULTY WORK ROOM
CLASSROOM
NURSE TOILET
PARENT TRAINING ROOM
RECEPTION/ WAITING STORAGE
L E C
TOILET
TOILET
OFFICE
DIAGNOSTIC
TEAM ROOM
INTEGRATED THERAPY
OPS
CLASSROOM
5
TOILETTOILET
3
CLASSROOM
1
29
PROGRAM
DESCRIPTION The main Staff Services and Parent Support Spaces would be located along the south edge, to serve parents immediately upon entry. The Large Motor Skills area to the north would house both the Indoor Play as well as a Multi-Activity Space. These spaces would both be adjacent to the Outdoor Play courtyard. Each pair of classrooms along the east would share an Integrated Therapy room, have a toilet room for student use and allow for the opportunity to open up a wall between classrooms for multiroom interaction. Each group of 5 classrooms would share a Team Teachers room, as well as staff and public restrooms. The central corridor would feature spontaneous learning and play “rooms”, between the Outdoor Play and Sensory Gardens as well as between the MultiActivity and Sensory Garden. These areas allow for specialized learning areas outside the designated classroom spaces.
N 0
30
15
45
105
GTT LAB
ORCHESTRA MUSIC
CLASSROOM
HEALTH & FITNESS CLASSROOM
CLASSROOM
CLASSROOM
CLASSROOM
CLASSROOM
READ
CLASSROOM
STORAGE
STORAGE
MECH.
LOCKER
LOCKER
LOCKER
LOCKER
OFFICE
MUSIC
OFFICE
MECH.
SP. ED.
LIFE SKILLS
ART
STORAGE GYMNASIUM
SCIENCE
SCIENCE
BAND PREP
SERVING SCIENCE
CAFETERIA
SCIENCE
CLASSROOM
LEGEND MOTOR SKILLS
CLASSROOM
OPS
TEAM MECHANICAL/ OPERATIONS
TOILET TOILET
INTEGRATED THERAPY
PARENT SUPPORT CENTER
TOILET
INTEGRATED THERAPY
STORAGE
CLASSROOM
OUTDOOR PLAY
CLASSROOM
CLASSROOM TOILETTOILET
OT/PT MOTOR ROOM
STUDENT SERVICES
TOILET INTEGRATED THERAPY TOILET
SENSORY GARDEN
KITCHEN
CLASSROOM
STORAGE
CLASSROOM TOILETTOILET
TOILET
OPERATIONS
CLASSROOM
CLASSROOM CUSTODIAL
INTEGRATED THERAPY
MULTI-ACTIVITY
TOILET LEARNING CENTER
IDF TEAM
INDOOR PLAY
INTEGRATED THERAPY CUSTODIAL CLASSROOM
TOILET TOILET
CLASSROOM
TOILET
STORAGE
GIRLS
OFFICE
BOYS
TOILET
CLASSROOM
STORAGE
SENSORY GARDEN
CLASSROOM
CONTROL ROOM
TEAM
CLASSROOM
CUSTODIAL
CLASSROOM
TOILETTOILET
CLASSROOM
INTEGRATED THERAPY TOILET
CCLASSROOM CLASSROOM
STORAGE
CLASSROOM
INTEGRATED THERAPY OFFICE
RES.
BOYS SP. PATH
SP. ED.
SP. ED.
SP. ED.
S.W.
PSYCH
CLASSROOM
STORAGE CLASSROOM
TOILETTOILET
CLASSROOM
CLASSROOM
CLASSROOM
GIRLS TOILET INTEGRATED THERAPY TOILET
CLASSROOM SENSORY GARDEN
NURSE MAIN OFFICE
TOILET
TOILET
CLASSROOM
CLASSROOM STORAGE
STORAGE
OFFICE
OFFICE
OFFICE
PARENT SUPPORT CENTER
STAFF CENTER
TOILETTOILET
CLASSROOM
CLASSROOM
CLASSROOM INTEGRATED THERAPY
PRINC.
CONF.
OFFICE
STUDY
OFFICE
TOILET
CLASSROOM STAFF WORKROOM
STAFF LOUNGE
FACULTY WORK ROOM
CLASSROOM
NURSE TOILET
PARENT TRAINING ROOM
RECEPTION/ WAITING STORAGE
L E C
TOILET
TOILET
OFFICE
DIAGNOSTIC
TEAM ROOM
INTEGRATED THERAPY
OPS
CLASSROOM
TOILETTOILET
CLASSROOM
31
CLASSROOM LAYOUT
TOILET B116 OPS B117 495 SF TEAM ROOM B115 398 SF
N 0
32
2
6
14
CLASSROOM B122 874 SF
INTEGRATED THERAPY B123 175 SF
CLASSROOM B124 874 SF
L E C
TOILET
TOILET
B122A
B124A
33
ROOF PLAN
DESCRIPTION In an effort to relate the new addition to the adjacent neighborhood scale and aesthetic, the roofs of each classroom bar would be sloped towards the south end of the site. This design will begin to break up the addition in to smaller pieces, bringing the overall scale down while creating a “neighborhood-like” repetition along the east façade. The sloped roofs will allow for easier (and obvious) rainwater collection, which would be used as a teaching tool within the Sensory Gardens. Roofs could also begin to push in to the Outdoor Play Courtyard and create shaded areas for play and protection.
N 0
34
15
45
105
2
4
L E C
5
3
1
35
BUILDING SECTIONS
DESCRIPTION Using the existing Holmes Junior High mansard roof edge shape and material as inspiration, the Early Learning Center would feature a bent plate of metal panel for the roof and south wall material. The south wall of each classroom bar would be canted to the south, resulting in south glazing shading, while creating a sculptural form for the addition. The sloped roofs would accommodate various ceiling heights throughout the addition while also incorporating clerestory lighting along the north edge. Beyond, the Staff Services area would serve as a beacon for visitors, directing their eye to a transparent, glowing mass at the south entrance.
1 N-S Section Perspective
3 N-S Section Perspective
5 N-S Section Perspective
36
2 E-W Section Perspective
4 E-W Section Perspective
L E C
37
38
BUILDING ISOMETRIC
L E C
39
40
SOUTHEAST VIEW
L E C
41
42
SOUTHWEST VIEW
L E C
43
44
EAST VIEW
L E C
45
4
EARLY LEARNING CENTER
S I T E L E C
D E S I G N
SITE DESIGN
PREPARED FOR
Community Consolidated School District 59
NORTH SCALE: 1”=100’
IN ASSOCIATION WITH:
0’
48
25’
50’
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. © 2014 Hitchcock Design Group
150’
L E C
49
OUTDOOR PLAY
Sensory/tactile path Sensory plantings Poured-in-place rubber surfacing berm +/- 3’ HT Wee-saw
Leaf imprint Nature inspired play structure Poured-in-place rubber surfacing Log crawl
Trike track Rumble strip Picnic plaza with movable tables and chairs Raccoon tracks imprint
Leaf imprint Embankment slide Stone steps
Wood cookie steppers Log wall/ music circle Pretend stage with overhead arbor
Nature play tables Art wall
Flagstone path
PREPARED FOR
Community Consolidated School District 59
NORTH SCALE: 1”=10’
IN ASSOCIATION WITH:
0’
2.5’
5’
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. © 2014 Hitchcock Design Group
50
15’
Outdoor Play Area Concep Early Learning Center Mount Prospect, Illinois
pt
Sensory/tactile path Sensory plantings Poured-in-place rubber surfacing berm +/- 3’ HT Wee-saw
Nature inspired play structure Poured-in-place rubber surfacing Log crawl
Leaf imprint Embankment slide Stone steps
Nature play tables Art wall
L E C
PREPARED FOR
Community Consolidated School District 59
NORTH SCALE: 1”=10’
IN ASSOCIATION WITH:
0’
2.5’
5’
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. © 2014 Hitchcock Design Group
15’
51
OUTDOOR PLAY
Trike track
Pretend stage
Outdoor Play Area - Characte
52
Early Learning Center Mount Prospect, Illinois
L E C
er Images 1
Wood cookie steppers
Log wall / music circle
Stage with overhead arbor
Poured-in-place rubber surfacing berm PREPARED FOR
Community Consolidated School District 59 IN ASSOCIATION WITH:
53
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. Š 2014 Hitchcock Design Group
OUTDOOR PLAY
Wee-saw
Embankment slide
Outdoor Play Area - Characte
54
Early Learning Center Mount Prospect, Illinois
Nature inspired play structure
Nature inspired play structure
Art walls
Log crawl
L E C
er Images 2
PREPARED FOR
Community Consolidated School District 59 IN ASSOCIATION WITH:
55
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. Š 2014 Hitchcock Design Group
OUTDOOR PLAY
Picnic plaza with movable tables and chairs
Nature play tables
Outdoor Play Area - Characte
56
Early Learning Center Mount Prospect, Illinois
L E C
er Images 3
Stone steppers
Raccoon track imprint
Sensory path
Leaf imprint PREPARED FOR
Community Consolidated School District 59 IN ASSOCIATION WITH:
57
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. Š 2014 Hitchcock Design Group
SENSORY GARDEN
Sensory/tactile path Sensory plantings Poured-in-place rubber surfacing berm +/- 3’ HT Wee-saw
Elevated water runnels Sand play
Nature inspired play structure Poured-in-place rubber surfacing Log crawl
Sand diggers Texture path pebble paving Arched boardwalk Flagstone paving Stone play / pattern games
Leaf imprint Embankment slide Stone steps
Nature play tables Art wall
PREPARED FOR
Community Consolidated School District 59
NORTH SCALE: 1”=10’
Arched boardwalk
IN ASSOCIATION WITH:
0’
2.5’
5’
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. © 2014 Hitchcock Design Group
58
15’
Sensory Garden Concep Early Learning Center Mount Prospect, Illinois
pt
Sensory wall Kid-powered water pump
Elevated water runnels
Sensory wall Fiddlehead fern walk
Sensory plantings -Herbs -Perennials
Kid-powered water pump
Sand diggers
L E C
Stone play / pattern games
Sensory wall PREPARED FOR
Community Consolidated School District 59
NORTH SCALE: 1”=10’
59
IN ASSOCIATION WITH:
0’
2.5’
5’
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. © 2014 Hitchcock Design Group
15’
SENSORY GARDEN
Sandy play
Fiddlehead fern walk
60
Sensory Garden - Character Im Early Learning Center Mount Prospect, Illinois
L E C
mages
Sensory wall
Texture path / pebble path
Sensory plantings
Kid-powered water pump PREPARED FOR
Community Consolidated School District 59 IN ASSOCIATION WITH:
61
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. Š 2014 Hitchcock Design Group
FINE ARTS GARDEN
Sensory/tactile path Sensory plantings Poured-in-place rubber surfacing berm +/- 3’ HT Wee-saw
Art stations -paintings -water on slate Plantings
Nature inspired play structure Poured-in-place rubber surfacing Log crawl
Music fence Xylophone bench Harmony circle -tongue drums -slap drums Dance plaza -motor skills
Leaf imprint Embankment slide Stone steps
Nature play tables Art wall
PREPARED FOR
Community Consolidated School District 59
NORTH SCALE: 1”=10’
Xylophone bench
IN ASSOCIATION WITH:
0’
2.5’
5’
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. © 2014 Hitchcock Design Group
62
15’
Fine Art Garden Concep Early Learning Center Mount Prospect, Illinois
pt
Weaving wall Storage bench Theater space with wood arbor Weaving wall
Weaving wall
Log seats / benches Color chalk canvas Log wall
Theater space with wood arbor
Music fence
L E C
Colored concrete music notes
Harmony circle PREPARED FOR
Community Consolidated School District 59
NORTH SCALE: 1”=10’
63
IN ASSOCIATION WITH:
0’
2.5’
5’
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. © 2014 Hitchcock Design Group
15’
FINE ARTS GARDEN
Music play
Weaving wall
Fine Art Garden - Character Im
64
Early Learning Center Mount Prospect, Illinois
L E C
mages
Music play
Theater space
Art wall
Art wall PREPARED FOR
Community Consolidated School District 59 IN ASSOCIATION WITH:
65
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. Š 2014 Hitchcock Design Group
NATURE GARDEN
Sensory/tactile path Sensory plantings Poured-in-place rubber surfacing berm +/- 3’ HT Wee-saw
Animal imprints in concrete Rubber tile surfacing
Nature inspired play structure Poured-in-place rubber surfacing Log crawl
Boulder accents Balance log Loose parts play -barrels, nuts, seeds, leaves, corn Lean to fort Willow tunnel
Leaf imprint Embankment slide Stone steps
Nature play tables Art wall
PREPARED FOR
Community Consolidated School District 59
NORTH SCALE: 1”=10’
Willow tunnel
IN ASSOCIATION WITH:
0’
2.5’
5’
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. © 2014 Hitchcock Design Group
66
15’
Nature Garden Concept Early Learning Center Mount Prospect, Illinois
Raised garden Wood cookie hopscotch Nature observation table
Nature observation table
Leaf imprints Storytelling chair Elevated wood deck with log arbor Seasonal garden beds
Wood cookie hopscotch
Loose parts play
L E C
Storytelling chair
Balance log PREPARED FOR
Community Consolidated School District 59
NORTH SCALE: 1”=10’
67
IN ASSOCIATION WITH:
0’
2.5’
5’
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. © 2014 Hitchcock Design Group
15’
NATURE GARDEN
Lean to fort
animal imprints
Nature Garden - Character Im
68
Early Learning Center Mount Prospect, Illinois
L E C
mages
Nature observation table
Elevated wood deck
Leaf imprints
Raised garden PREPARED FOR
Community Consolidated School District 59 IN ASSOCIATION WITH:
69
ISSUE DATE: JULY 17, 2014 All drawings are preliminary and subject to change. Š 2014 Hitchcock Design Group
5
EARLY LEARNING CENTER
M E ET I N G M I N UT E S L E C
ENTRY/OFFICE
SENSORY ROOMS/GYM
OUTDOOR PLAY
CLASSROOMS
BUILDING-WIDE
THERAPY
WALL TOYS FOR KIDS
PADDED WALLS
DIRECT ACCESS FROM ALL CLASSROOMS
DIAPER-CHANGING AREA
CLEAN AND UNCLUTTERED
DIAGNOSTIC ROOM
KID-SIZED FURNITURE
FOAM WEDGES
GROSS MOTOR AREA
LOTS OF STORAGE - CUBBIES IN THE CLASSROOMS
APPROPRIATE ADULT AND KID FURNITURE
SEPARATE OT, PT, AND S
KID-LEVEL WINDOWS
BIG AREAS
BIKE PATHS
STANDARDIZED, INTERCHANGABLE ROOMS THAT ARE ADAPTABLE FOR CHANGES IN CURRICULUM COLLABORATIVE AREA TO STORE EVERYTHING
GOOD FLOW
MULTIPLE SMALL AREAS/ BREAK OUT ROOMS
OUTDOOR ART/MUSIC
OPEN STORAGE FOR KIDS TO ACCESS
LOTS OF WINDOWS AND NATURAL LIGHT
COLLABORATION ROOMS
COLOR-CODED PATHWAYS
INDOOR PLAYGROUND
WATER/SAND PLAY
HIGH, CLOSED STORAGE FOR TEACHERS
WINDOWS AT KID HEIGHT
OBSERVATION ROOM WI SPEAKER SYSTEM
COLLABORATION ROOMS
INDOOR COURTYARD WITH WATER FEATURE
MULTIPLE GROSS MOTOR AREAS
GARDEN WITH KID-SIZED STEPPING STONES
APPROPRIATE RATIO OF HARD TO SOFT FLOORING
SKYLIGHTS
PROXIMITY TO CLASSRO
HAVE THE WALLS TELL A STORY
AREAS FOR CLIMBING
RUBBERIZED FLOOR
SOFT AREA FOR READING
NO FLUORESCENT LIGHTING
SEPARATE TEACHING SP
OPEN LARGE OFFICE WITH WAITING ROOM EASY BUS AND DROP OFF
STAIRS FOR PT CALM DOWN ROOMS TOO
ACCESSIBLE FOR WHEELCHAIRS EXPLORATION SPACE
HARD AREA FOR MESSY ACTIVITIES OPEN-ENDED ENVIRONMENTS
CHILD-CENTERED LRC AREA INDOOR COURTYARD
ROOMS FOR PULLOUT TH PSYCH AND SOCIAL WOR
LENDING LIBRARY/ RESOURCE CENTER FOR PARENTS
OPPORTUNITIES FOR INSIDE PHYSICAL MOVEMENT
MULTIPLE ZONES FOR AGE GROUPS/ABILITIES
DRYING RACKS
INTERACTIVE BOARDS IN THE HALLWAYS
OFFICE AREAS LARGE EN FURNITURE AND DRAMA
COZY, HOME-LIKE TO MAKE IT SEEM FAMILIAR BRIGHT WITH LOTS OF WINDOWS
STAGE AREA SCIENCE AREAS
COLLABORATIVE AREAS SHADED AREAS
PROJECT DISPLAY AREAS ORGANIZED AND STRUCTURED ROOMS
COLORFUL TILES WIDE HALLWAYS
ACTIVITIES/WORK CENTERS FOR IMMEDIATE ENGAGEMENT TUNNELS FOR ENTRY
LARGE CIRCLE TIME SPACE FOAM PIT/ BALL PIT
FAMILY SPACES LARGE, OPEN, INVITING
OPEN, HIGH STORAGE FOR TEACHERS SINK
WARM, INVITING, AND COLORFUL - BUT NOT OVERSTIMULATING QUIET FLOORING FOR HALLWAYS
ACCESS TO BATHROOM FOR FAMILIES INVITING AND COLORFUL OFFICE
SLIDES AND TUNNELS SOFT YET SANITARY
NOT VISIBLE FROM DROP-OFF TO AVOID DISTRACTIONS PAVED AND GRASSY AREAS
SENSORY TABLE AREA TALL CEILINGS
INTERACTIVE AREAS IN THE HALLWAYS FOR GROUPS TO COME TOGETHER AIRY SPACES
COUCHES IN OFFICE AREA INVITING FOR KIDS
SPACE TO RUN SPACE FOR BALLS
OBSTACLE COURSES PLAY STRUCTURE
TILE FLOORS WARM FEELING
INVITING EXTERIOR WITH COLORS, BRIGHTNESS, AND WINDOWS PLACES FOR IMAGINATIVE PLAY
HELPFUL FOR VISITORS
DIVIDED YET OPEN FOR SUPERVISION
RUBBERIZED FLOOR - NO WOOD OR RUBBER CHIPS
MANY CENTERS AND SPACE FOR EACH
SPECIFIC THINGS AT KID EYE LEVEL - DISPLAYS, ART, FIXTURES
COLORFUL FOOTPRINTS IN THE SIDEWALK LEADING TO THE BUILDING
KID-SIZED BASKETBALL HOOPS
WHEELCHAIR BRIDGE
SAFETY
COURTYARD WITH LOW PLANTERS TEACHER LUNCHROOM
CONFERENCE ROOM WITH ROOM FOR LARGE GROUPS
ACCESS FOR ALL STUDENTS
BIG SWING
SPACE FOR KIDS TO HAVE INDIVIDUAL LEARNING, SMALL GROUP, AND WHOLE GROUP
TEACHER WORKROOM
MOTOR ROOM FOR THERAPY LARGE ENOUGH FOR GROUP MOTOR ACTIVITIES
INTERACTIVE EQUIPMENT/ MULTI-MODAL
THOUGHTFUL ATTENTION TO TECHNOLOGY SMARTBOARDS, PROJECTORS, SCREENS, ETC.
SNACKLUNCH ROOM FOR KIDS NEAR GYM
ACCESS CONTROL FOR VISITING PARENTS
INDOOR SPACE THAT RESEMBLES OUTDOOR SPACE
FENCED IN
THERAPY CLOSE OR WITHIN CLASSROOM
LIBRARY AND READING ROOM
TOUCHABLE STATUE/SCULPTURES IN THE FRONT
TRAMPOLINES
OUTDOOR SENSORY TABLES
SPACE TO NAVIGATE STROLLERS/WALKERS
KITCHEN WITH KID-LEVEL COUNTERS COMMUNITY SAFETY PATROL AREAS FOR PRETEND COMMUNITY HOOKS/CUBBIES IN THE HALLWAYS
FOUNTAIN SEASONAL DECORATIONS
TREES STORAGE FOR RIDING TOYS
WALK-IN CLOSET STORAGE BLANK WALL FOR NO DISTRACTION ACTIVITIES
DISPLAYS FOR ROTATING KID'S ARTWORK IN THE OFFICE
NO BABY SWINGS
VISIBILITY OF THE DOOR FROM EVERYWHERE
DIMMABLE LIGHTS
OPEN OFFICE AREA FOR RESOURCE STAFF PRIVATE ROOMS FOR CONVERSATIONS OVERHANG FOR BUS DROP-OFF TOY LENDING LIBRARY
ENCLOSED AREA FOR PROJECTS AND LEARNING ONE LEVEL SAFETY TOWN POOL
SENSOR ON DOOR TO ALERT TEACHER DOORS BETWEEN CLASSROOMS STORAGE SPACE FOR EXTRA CLOTHES AREAS FOR QUIET AND CALM ACTIVITIES
SHORTER WALKING DISTANCES IN THE BUILDING/CENTRALLY-LOCATED OFFICE KID HEIGHT BULLETIN BOARDS SEPARATION BETWEEN BUS AND CAR DROPOFF BRING NATURE INSIDE
WINDOWS TO SEE INTO LEARNING
PICNIC TABLES
WINDOWS ASSOCIATED WITH THE SCIENCE CENTER
ENVIRONMENTALLY CONSCIOUS
COMFY PLACES FOR FAMILIES TO WAIT
SANDBOX
AREA FOR SPEECH GROUPS WITHIN THE CLASSROOM FRUIT-BEARING TREES
HILLS
LITTLE NOOKS FOR READING
ABILITY TO SEE ALL SECRETARIES WHEN THEY ARE SEATED WELCOMING FOR PARENTS OF DIFFERENT CULTURAL BACKGROUNDS - SIGNAGE PARENTS FEEL SAFE AT DROPOFF HAPPY FACE ENTRY SIGN WELCOME DESK RATHER THAN AN OFFICE
L E C
TUNNELS AND SLIDES QUIET AREA FOR SHY KIDS TREE HOUSE
SLANTED ROOF - NOT FLAT ROUNDED ENTRANCE AREA SKY MURALS ON THE CEILINGS GLASS AND LIGHT STONE ON THE EXTERIOR MUSIC PLAYING
SEPARATE AREA FOR KID MEETINGS
BUILDING-WIDE
ASSROOMS
FLOORING
NO AUTOMATIC FLUSHERS FOR KIDS
APPROPRIATE ADULT AND KID FURNITURE
SEPARATE OT, PT, AND SPEECH
NO AUTOMATIC LIGHTS FOR KDS
COLLABORATION ROOMS FOR THERAPY
NO AUTOMATIC FAUCETS FOR KIDS
LOTS OF WINDOWS AND NATURAL LIGHT
COLLABORATION ROOMS FOR TEAM CONFERENCES
BATHROOM IN EACH CLASSROOM WITH SHELVES
WINDOWS AT KID HEIGHT
OBSERVATION ROOM WITH ONE-WAY MIRROR AND SPEAKER SYSTEM
DISHWASHER FOR TOYS
SKYLIGHTS
PROXIMITY TO CLASSROOMS
LAUNDRY AREA
NO FLUORESCENT LIGHTING
SEPARATE TEACHING SPACE FOR PT
COOKING AREA WITH SECURE AREA FOR MULTIPLE OVENS
CHILD-CENTERED LRC AREA INDOOR COURTYARD
ROOMS FOR PULLOUT THERAPY PSYCH AND SOCIAL WORKER NOT IN THE OFFICE
APPROPRIATE RATIO OF STAFF/PARENTS TOILET ROOMS FAMILY TOILET ROOM
INTERACTIVE BOARDS IN THE HALLWAYS
OFFICE AREAS LARGE ENOUGH FOR COMFY FURNITURE AND DRAMATIC PLAY
COLORFUL TILES WIDE HALLWAYS
SEPARATE AREA FOR KIDS TO PLAY DURING IEP MEETINGS
WARM, INVITING, AND COLORFUL - BUT NOT OVERSTIMULATING QUIET FLOORING FOR HALLWAYS INTERACTIVE AREAS IN THE HALLWAYS FOR GROUPS TO COME TOGETHER AIRY SPACES INVITING EXTERIOR WITH COLORS, BRIGHTNESS, AND WINDOWS PLACES FOR IMAGINATIVE PLAY SPECIFIC THINGS AT KID EYE LEVEL - DISPLAYS, ART, FIXTURES COURTYARD WITH LOW PLANTERS
EARNING,
TEACHER LUNCHROOM
OGY S, ETC.
SNACKLUNCH ROOM FOR KIDS NEAR GYM
M
LIBRARY AND READING ROOM
ERS
KITCHEN WITH KID-LEVEL COUNTERS
VITIES
COMMUNITY SAFETY PATROL AREAS FOR PRETEND COMMUNITY HOOKS/CUBBIES IN THE HALLWAYS
HERE
DIMMABLE LIGHTS SHORTER WALKING DISTANCES IN THE BUILDING/CENTRALLY-LOCATED OFFICE KID HEIGHT BULLETIN BOARDS SEPARATION BETWEEN BUS AND CAR DROPOFF BRING NATURE INSIDE
S
CE CENTER
SERVICE/SUPPORT AREAS
DIAGNOSTIC ROOM
MS THAT ARE UM COLLABORATIVE AREA TO STORE EVERYTHING
S
THERAPY
CLEAN AND UNCLUTTERED
ENVIRONMENTALLY CONSCIOUS
CLASSROOM FRUIT-BEARING TREES SLANTED ROOF - NOT FLAT ROUNDED ENTRANCE AREA SKY MURALS ON THE CEILINGS GLASS AND LIGHT STONE ON THE EXTERIOR MUSIC PLAYING
L E C
LOUNGE FOR MOTHERS WIDE BATHROOMS LARGE NURSE/HEALTH ROOM
Summary of a Traffic Study Meeting held at 1:30 p.m., Thursday, June 12, 2014 at Holmes Elementary School. These notes record our understanding of items discussed and decisions made at this meeting. Please notify us within seven (7) calendar days of any necessary additions or corrections. PERSONS IN ATTENDANCE
Matthew Lawrie, Project Engineer, Village of Mount Prospect Tony Rossi, Executive Director of Facilities & Operations, CCSD59 Joe Papanicholas, Project Manager, Nicholas & Associates Scott DiGilio, Principal, Applied/RTM Associates Robin Randall, Vice President, Legat Architects Stephanie Marcan, Project Architect, Legat Architects Katherine LaCourt, Project Designer, Legat Architects
ITEMS DISCUSSED
1. It was stated that the Early Learning Center would have car traffic along Lonnquist and buses to the North, while Holmes Elementary School would service both cars and buses from off Lonnquist. 2. Matthew Lawrie (ML) asked if there was a sidewalk present between the north bus drive and the south parking in front of Holmes. It was stated yes. There will also be a sidewalk running along the entire south end of the property, south of the parking and bus drive. ML asked if the sidewalk would jog to accommodate the new southern parking for Holmes. Katherine LaCourt (KL) noted that the sidewalk already jogs at the far west end of the site. Scott Degilio (SD) stated there will also be a sidewalk between the exit from the ELC dropoff and the entrance to the Holmes dropoff for children walking to school to safely traverse. Robin Randall (RR) and SD stated there would also be sidewalks along the outskirts of all the dropoff locations so as to accommodate pedestrians across the site. 3. ML inquired about student/pedestrian crosswalks. It was stated that we will maintain the two current crosswalks (adjacent to Carol and Deborah Lanes). The A/E will also investigate a third crosswalk at the far southeast corner of the site, adjacent to Kenneth Place.
74
2. ML asked if there would be any parent drop-off traffic intended at the north entrance. It was stated no. The north entrance drive would solely be for bus dropoff and staff marking for Forest View Elementary School. 3. ML asked what the hours of operation would be for the new ELC. TR stated there would be two sessions; one in the morning and one in the afternoon. The hours for dropoff for the ELC will stagger those for Holmes. 4. TR stated that the ELC would need to accommodate 70% bus dropoff and 30% parent dropoff. The parent drivers would be limited to approximately 50 cars per day (25 in the morning and 25 cars in the afternoon). TR stated the importance of separating car and bus traffic. 5. SD stated that the parking stalls depicted in front of the ELC would be staff parking spaces. TR noted that we will need to accommodate visitor parking spaces between dropoff times. ML stated that we need to accommodate all parked cars on site so as to avoid parked cars on Lonnquist or other neighborhood arterial streets. 6. ML stated he was concerned about the exit from Holmes dropoff being immediately adjacent to the exit/entrance to the Holmes staff parking lot. ML asked if the two separated drives be joined somehow. SD stated this would be difficult as the goal would be to separate the car and bus traffic. There was also the potential to lose current vital parking spaces within the staff parking lot. 7. ML stated that signage would need to be critically considered for all parking areas, entrances and exits. Signage should be utilized to safely control the exit of buses and cars from both the Holmes dropoff and staff parking lot. Visitor parking spots should be identified with signage.
L E C
MEETING MINUTES
1. ML inquired about the current median just south of what will be the new entrance drive for the ELC. SD stated the median would most likely be removed and a left turn lane would be installed. If the median were removed, 4 trees would need to be removed as well. The median could not be moved west as the road narrows. ML asked if there was a large demand for left-turners along Lonnquist (or if there was expected to be). Joe Papanicholas (JP) and Tony Rossi (TR) stated no; perhaps 50-60 cars a day.
75
1. SD stated that along the median at the Holmes dropoff, there would be parallel parking spots that would be utilized as visitor parking between dropoff times. 2. ML stated there are no Red Flags that he can identify with the current plan. TR asked if ML could foresee any problems down the road. ML stated that the exit from the ELC dropoff should more closely align with Deborah Lane or should be completely offset to the east. SD stated this could be adjusted slightly, but the current design strives to maintain the most parking spaces possible. 3. TR asked if the Village would like to see any other material used at the aprons to the street other than asphalt. ML stated this was not necessary. 4. ML asked if the design team had considered reversing the flow of traffic from west to east. SD stated this would not be feasible due to the current loading/unloading of buses along the right side. If the flow was reversed, children would need to walk in front of vehicles to get within either building. 5. TR asked if parallel parking was currently allowed along Lonnquist Blvd. ML stated yes. 6. ML stated that if he were sent some options, he would cautiously review with individuals in his office for review and comment. TR stated he would email the PDFs that were brought to the meeting. RR stated she would like to make a few of the changes noted prior to emailing them to ML. 7. ML asked the schedule for the ELC work. TR stated that we are awaiting Board approval in June, ground breaking would be in October and the new building would be occupied by August 2015. 8. ML stated that parent parking should be considered and accommodated within the design. He stated that at Westbrook, they did not intend to have any parents that would like to park, but have since encountered a problem as there are not enough spaces to accommodate both staff parking and visitor dropoff spots. TR stated there is no reason to assume ample parent dropoff as the school demographics do not support this theory. 9. ML asked about lighting in the parking lots. TR stated all lights would be LED.
76
PERSONS IN ATTENDANCE
Tony Rossi, Executive Director of Facilities & Operations, CCSD59 Joe Papanicholas, Project Manager, Nicholas & Associates Patrick Brosnan, President, Legat Architects Robin Randall, Vice President, Legat Architects Paul Pessetti, Project Manager, Legat Architects Stephanie Marcan, Project Architect, Legat Architects Katherine LaCourt, Project Designer, Legat Architects
ITEMS DISCUSSED
1. It was stated that consultants would be contacted in the coming days to submit proposals for structural and MEPFP work. CS2, 2010 Engineering (for their Geothermal expertise), WMA (for their sustainability expertise), KJWW and Chuck Anderson would all be contacted for proposals. 2. Patrick Brosnan (PB) asked if we would be pursuing LEED certification for this project. Tony Rossi (TR) stated that if we received a grant, we should strive to achieve LEED Certification; either way we should be designing to LEED standards to achieve the most sustainable building we can. PB asked if the Board would support a $500,000 grant for LEED Gold efforts if the money were allocated for application and monitoring efforts. TR stated yes. 3. Robin Randall (RR) stated that we should consider designing for the installation of future solar opportunities as the possibility for a Net Zero building could be achievable in the future. DESIGN PROGRESS
1. The massing studies were presented. Each study aims to break down the scale of the overall building mass for a more “neighborhood-like” feel and incorporate shed roofs for clerestory and natural lighting in the corridors and classrooms. TR asked that the team further investigate the central hallway with the goal of breaking down the vista of the 300’ corridor.
L E C
MEETING MINUTES
Summary of a Progress Meeting held at 11:00 a.m., Tuesday, June 23, 2014 at Legat Architects. These notes record our understanding of items discussed and decisions made at this meeting. Please notify us within seven (7) calendar days of any necessary additions or corrections.
77
Option 1: The two end classroom neighborhoods begin to step down in elevation to combat the site slope. The roofs would be comprised of separate sloped planes. This scheme does have the disadvantage of creating to classroom neighborhoods that are somewhat separated from the rest of the school. Option 2: The two end classroom neighborhoods are more closely connected to the rest of the classrooms. All the classrooms are able to accommodate some northern light exposure with the implementation of shared sloped roofs
Option 3: This scheme maintains the same floor plan from Option 2, but the roof slopes are slightly different. Rather than limiting the sloped roof areas to the classroom pairs, the slopes extend beyond and over the corridors. This scheme advantageously creates covered patio areas along the west face. This scheme does have the disadvantage of limiting the natural clerestory light to the corridors and it also creates very tall corridors which could be overwhelming for the ELC students.
78
The roofs could extend over the corridors, clerestory windows would light the tall masses. The corridor at the East end could push out and become glazing walls to the East for Inside/Outside interaction and observation.
3.
Physical models were reviewed for their program-specific studies. The master site model will likely be at 1:20 scale, while smaller study models will be at 1/8” scale. The boundaries of the site model were set at the centerline of Lonnquist up to Forest View (model a portion of this building and from the existing parking lot of the west to the homes on the east. RR stated that the model(s) will serve as working studies for the design team to try out ideas and work through various design concepts.
L E C
MEETING MINUTES
2. Preliminary glazing studies were presented to illustrate the ideal lighting and building/roof configuration. Low, horizontal glazing along the South façade could turn the corner and become clerestory glazing along the North façade. This could allow the East and West walls to remain blank and could become teaching walls.
79
A centralized shared teaching room would implement pivot/movable/hinged walls to blur the lines of classroom and breakout space. If a pivot wall is utilized, the “open� position could become a presentation wall for the classroom
Mobile cubbies (middle) could define loud areas for themed play and study.
A low window seat (top left corner) could create a quiet zone. A low ceiling element could be implemented to break down the scale of the classroom and further define zones within the room.
80
5. RR noted that the east-to-west corridors could incorporate ramps (partial width of the corridor) that could terminate with a “lookout” space higher than the lower level. These “lookout” spaces could overlook the east side of the site or the covered patios. 6. Joe Papanicholas (JP) stated that the construction process will involve a fair amount of site regarding and the multiple level changes may not be required. He stated that if the level changes are desired, this could be accommodated in the budget. RR stated that the design team would develop a few sectional options and send to Nicholas & Associates for constructibility review. 7. Building materials were briefly discussed with the team. TR stated that he would like the exterior of the ELC to be sympathetic to Holmes, but not necessarily identical. RR stated the tan/light brown slit face CMU on the current exterior of Holmes could be a good jumping-off point for color and materiality for the exterior of the ELC. 8. PB suggested that cold formed metal framing should be considered for the exterior walls, rather than the traditional CMU walls. He explained that given the compact construction schedule, the cold formed framing could be constructed throughout the winter and masonry veneer could follow in the spring. JP agreed that this method should be considered. TR asked if the R-value suffers from not utilizing CMU exterior walls. Paul Pessetti (PP) stated that the same (if not better) R-value could be achieved as the full cavity of the wall would be filled with insulation. 9. PP suggested that all drywall walls should incorporate 4’-6’ of impact resistant drywall from the finished floor up. This will help with the durability of finished spaces. 10. It was stated that the flexibility of the interior walls should be considered in the design. 11. RR asked if the design should include exterior doors from all the classrooms. While this is considered Best Practice for a facility of this type, it is not a code requirement. TR stated that exterior doors from the classrooms should not be incorporated.
L E C
MEETING MINUTES
4. The sectional quality of the building was discussed. As the site steps off 10’ on the east as well as 10’ on the north, the design team would like to explore incorporating ramps and stairs throughout the building. There would most likely be a combination of 1:12 sloped ramps (with handrails) and 1:20 sloped ramps (no handrails required).
81
12. It was stated that the space(s) for potential future expansion at Holmes should be maintained (north of classrooms 128 & 134). 13. TR confirmed that the ELC should be a minimum of 130’ from the east property line. 14. TR confirmed that the design should not depict a connection to Forest View. 15. The budget was confirmed at $14.3 million ($250/sf for 57,200sf). 16. It was agreed that the design team would refine the floor plans and develop some building sections for Nicholas & Associates to begin pricing efforts. JP stated that floor elevations (and some rough site elevations) would be ideal for the site grading pricing. JP asked that a building elevation be included for pricing efforts. JP asked that the documents be placed on a Cloud drive so that he could begin to view them. The design team stated that a Dropbox folder would be created and shared with the team. 17. It was discussed that the following items would be expected for the Board Meeting on July 21st:
a. b. c. d. e. f.
Thank you.
82
Physical model(s) 3D Massing Model (Revit and/or sketchup) Renderings Floor Plans Site Plan Schematic Design Budget from Nicholas & Associates
PERSONS IN ATTENDENCE
Tony Rossi, Executive Director of Facilities & Operations, CCSD59 Joe Papanicholas, Project Manager, Nicholas & Associates Robin Randall, Vice President, Legat Architects Paul Pessetti, Project Manager, Legat Architects Stephanie Marcan, Project Architect, Legat Architects Katherine LaCourt, Project Designer, Legat Architects ITEMS DISCUSSED
1. The partial site survey is expected today. This will include only the area east of Holmes, where the addition is expected. 2. Tony Rossi (TR) stated that the contract will be a requirement of the Board Resolution on July 21st. Paul Pessetti (PP) stated that he will coordinate with TR and Patrick Brosnan to lock in the Architectural fees. 3.
Stephanie Marcan (SM) asked what the agenda would include for the Community Forum on Tues day, July 15th at 6:00 pm. TR stated that the Community Forum will include a 20 minute Lead ership Team presentation of the intention of the addition followed by small breakout groups lead by Tony and Ruth. These breakout groups will discuss the financial aspects of the addition as well as the construction plans thus far. Timeline, design floor plans and construction impact will be detailed for the group. TR stated that a mounted floor plan (with a few massing models on top) would be helpful in explaining the plans. Legat will provide both. TR stated that following the Community Forum, the District website would be updated regularly to include plans and information as a follow-up.
MEETING MINUTES
Summary of a Progress Meeting held at 1:00 p.m., Wednesday, July 2, 2014 at Legat Architects. These notes record our understanding of items discussed and decisions made at this meeting. Please notify us within seven (7) calendar days of any necessary additions or corrections.
4. The SD62 building tour will be on Monday, July 14th at 2:00pm
L E C
83
5.
The Design Workshop should be coordinated through Melissa Ward. Robing Randall (RR) suggested Wednesday, July 9th as a potential date. RR stated that we will likely discuss the Classroom spaces (including the Integrated Therapy rooms), the enclosed courtyard spaces as well as the corridor learning areas. RR stated that Legat will also discuss the floor plan and basic massing with group and explain the process followed thus far
DESIGN PROGRESS
1.
The three (3) floor plans were reviewed in detail. Pros and cons of each were discussed. A short video walkthrough was shown to express the Central Corridor experience. The massing studies were presented. Each study aims to break down the scale of the overall building mass for a more “neighborhood-like” feel and incorporate shed roofs for clerestory and natural lighting in the corridors and classrooms. TR asked that the team further investigate the central hallway with the goal of breaking down the vista of the 300’ corridor. . Option 1: Straight This scheme has the longest of the central hallways. It features a 30’ separation between the Motor Skills rooms and the potential Holmes addition area. This (and all subsequent schemes) depicts a 10’ corridor north-south between Holmes and the Outdoor Play Courtyard. If, in the event that a reconfiguration of interior Holmes classrooms occurs (and the hallway become unnecessary) the ELC plan could be shifted 10’ to the west or the extra space could be reallocated within the Courtyard.
84
Option 3: Stepped This scheme achieves the desired Central Corridor experience. There is very little, to no north vista observed when standing at the south entrance and ample breakout spaces are created in the corridors, of varying size and shape. There is more opportunity for spontaneous play, which was a deeply desired attribute discussed in the two previous workshops. The south entry is a bit wider, making the entrance sequence clearer for visitors.
L E C
MEETING MINUTES
Option 2: Staggered This scheme brings the ELC closer to the north Bus Dropoff drive and beings to alter the experience within the Central Corridor. A short walkthrough was shown, depicting the new, deeper and spacious corridor learning zones that are created by the angled corridor.
85
2. Option 3: Stepped, was chosen as the favored scheme. The design team will proceed with refining this scheme to potentially achieve a 30’ separation between the Motor Skills rooms and the potential Holmes addition to the north. 3. Katherine LaCourt (KL) stated that in the event that alterations were made within Holmes and the new 10’ corridor were no longer required, it would be preferred that the space be reallocated within the Courtyard, rather than shifting the ELC design to the west. TR agreed. 4.
TR asked if there will be further development within the Outdoor Play Courtyard prior to the July 21st Board Meeting. RR stated yes. Hitchcock Design Group will likely be involved as they have ample experience with outdoor educational spaces. Hitchcock will also be involved with the design of the smaller sensory gardens. These areas will also be on the agenda to discuss at the next Workshop.
5. Various massing studies were reviewed, inclusive of wall orientation, roof slopes, glazing studies and covered patio areas. Progression #1: As a progression from our previous meeting, the exterior of Holmes was studied for materiality and form precedent. The canting of the south wall of each “house” builds upon the angled mansard roof and the angled walls of Holmes. The canted walls provide shading for the glazing elements along the south wall while creating a unique and sculptural form of each house.
86
Massing Option #2: This particular option explores the possibility of mirroring the classroom houses such that the Faculty Team Rooms would be along the outside east face, rather than off of the main corridor. This provides the opportunity to create a small patio of outdoors room for the faculty to utilize. 6. TR noted his hesitance to explore Massing Option #2 as it would create another point of egress from the addition as well as a potential security issue. PP noted that given the function of the Faculty Team Rooms, they would best be served if located along the central corridor. 7. The sectional potential of the east-to-west classroom corridors was discussed. These areas are prime for transitioning the addition from one elevation to another if the site constraints require this. A 48� drop in elevation could be achieved through a 1:12 sloping ramp. This design could result in a central ramp with flanking stairs to transition from one level to the next. Handrails would be required along the hallways as the drop is more than 30�.
L E C
MEETING MINUTES
Massing Option #1: Building upon the house shape of the massing progression #1, material is illustrated. The south canted wall and the shed roof become one continuous metal material, relating to the mansard roofs surrounding Holmes. The eastern wall of each house could then be articulated with a different material, perhaps wood or masonry veneer.
87
A 48” drop in elevation could be achieved through a 1:12 sloping ramp. This design could result in a central ramp with flanking stairs to transition from one level to the next. Handrails would be required along the hallways as the drop is more than 30”.
8.
The sectional quality of the building was discussed. As the site steps off 10’ on the east as well as 10’ on the north, the design team would like to explore incorporating ramps and stairs through out the building. There would most likely be a combination of 1:12 sloped ramps (with handrails) and 1:20 sloped ramps (no handrails required).
9. TR noted his concern that the ramps and stairs could potentially change the use of, or limit the use of the hallways. 10. TR noted that if this element were incorporated, he would not want to see handrails within the corridors. 11. TR asked if the addition could be at grade, or if a level change was necessary. PP stated that we would need to discuss further with the Civil engineer, but he did not see why a single level could be maintained. 12. Joe Papanicholas (JP) asked that a copy of the final Option 3 floor plan and a building section be sent to him so that he can begin the pricing exercise prior to the Holiday weekend. He asked that the basic building materials and structural components be noted within the building section. 13. TR stated that the design team should be investigating Sustainable Design elements to incorporate. Geothermal and solar design should both be considered. There should be a potential for Holmes to monitor and learn from these design elements (eg. solar power monitors for the Science classes).
88
Thank you.
JULY 9, 2014 at 10:00am
Breakout Group #1: Sensory Garden Theme Assignment & Brainstorming CLASS
CLASS
OPS
TEAM
bus dropoff
CLASS
CLASS
CLASS
CLASS
CLASS
MOTOR SKILLS
RNING CENTER 118
CONTROL ROOM -
CLASSROOM 126
TEAM
CLASSROOM 130
CCLASSROOM LRC1
CLASS
OUTDOOR PLAY
CLASSROOM 132
• • • •
Near Equipment Storage Tactile Pebble Walk Herb Growing Area
• • • •
Theater Stage Ivy Wall Music: Xylophone Art: Vertical Slate
Sensory panel
CLASS
FINE ARTS
SENSORY GARDEN
CLASSROOM 134
CLASS
CLASS
OPS
CLASSROOM 128
Music station / Xylophone
OPS
TEAM
Modular play structure with climbing boulder
STORAGE 116 BOYS 108
SENSORY
SENSORY GARDEN
LEARNING CENTER
OFFICE -
CLASS
Specialty paving
Art stations
Raised planter beds
Play Environment - Concept 3 - Character Images
PREPARED FOR
Moody Nolan
Malcolm X College Chicago, Illinois
SP. ED. 145A SP. ED. 145B
SP. ED. 146
PSYCH 147
S.W. 142
GIRLS 106
CLASS Log wall / Loose parts play area CLASSROOM 127
CLASSROOM 133
CLASS
Log wall / Loose parts play area
CLASSROOM 129 CLASSROOM 125
CLASSROOM 131
OFFICE STUDY OFFICE 308 309 310
STAFF LOUNGE 307
CLASSROOM 121
Flexible concrete paving
CLASSROOM 123
STOR. STAFF CENTER
PARENT TRAINING
FACULTY WORK
T
T NURSE
T
PARENT SUPPORT CENTER
CLASS
CLASS
NATURE
Raised stage with overhead arbor
• •
CLASS
DIAG./ CONF Art station
Leaf shape imprints
CLASS Play Environment - Concept 2 - Character Images CLASS Malcolm X College Play Environment - Concept 2 - Character Images
RECEP./ SW PSY PSY DIR WAITING
OPS
OOM
TOILET 314 TOILET 316
Raised stage with overhead arbor
CLASS
SENSORY GARDEN
TEAM
NURSE 313 STORAGE 312
Flexible concrete paving
ISSUE DATE: JUNE 11, 2013 PROJECT NUMBER: 06-1033-001-01-05 All drawings are preliminary and subject to change. © 2013 Hitchcock Design Group
Art station
Raised garden beds PREPARED FOR
MoodyRaised Nolangarden beds
Leaf shape imprints
PREPARED FOR
Moody Nolan
Chicago, Illinois
Malcolm X College
Raised Planting Beds Planting Seeds
S. CRESTWOOD LANE
OPERATIONS
MEETING MINUTES
DESIGN WORKSHOP
ISSUE DATE: JUNE 11, 2013 PROJECT NUMBER: 06-1033-001-01-05 All drawings are preliminary and subject to change. © 2013 Hitchcock Design Group
Chicago, Illinois ISSUE DATE: JUNE 11, 2013 PROJECT NUMBER: 06-1033-001-01-05 All drawings are preliminary and subject to change. © 2013 Hitchcock Design Group
parent dropoff
L E C
staff parking
89 T PL.
LN.
OULEVARD
MOTOR Breakout Group #1: Outdoor Play Courtyard Programming SKILLS
OPS
TEAM
CLASS
Mosaic mural
SENSORY GARDEN
CLASSROOM 134
ROOM
Log steppers
CLASSROOM 130
Water play
Trike track
Malcolm X College
OUTDOOR PLAY
CLASSROOM 132
Malcolm X College
Raised stage and loose parts play
Loose parts table / exploration
OILET 314 TOILET 316
Moody Nolan
Flexible concrete paving
CLASSROOM 127
CLASSROOM 133
CLASSROOM 129 CLASSROOM 125
Butterfly Weed
Log wall / Loose parts play PREPARED FOR
Moody Nolan
SENSORY GARDEN CLASSROOM 131
Art station
Leaf shape imprints
Raised garden beds
Log wall / Loose parts play area
Flexible concrete paving Moody Nolan
Play Environment - Concept 2 STOR. - Character Images Malcolm X College
Chicago, Illinois
CLASSROOM 121
Prickley Pear
Raised stage with overhead arbor
CLASS
ISSUE DATE: JUNE 11, 2013 PROJECT NUMBER: 06-1033-001-01-05 All drawings are preliminary and subject to change. © 2013 Hitchcock Design Group
DY OFFICE 9 310
OUNGE 7
PREPARED FOR
Log wall / Loose parts play area
Chicago, Illinois
• Trucks w/Textured Pavement • Log Walls • Balance beams • Small & Large Components • Shade CLASS • Art Wall • See-Saw(safe) • Art Tables • Swing • Diggers • Crawling Log • CLASS Steps CLASS • Movable Surface ISSUE DATE: JUNE 14, 2013 PROJECT NUMBER: 06-1033-001-01-05 All drawings are preliminary and subject to change. © 2013 Hitchcock Design Group
CLASSROOM 123
STAFF CENTER
FACULTY T WORK T NURSE
PARENT SUPPORT CENTER
PARENT TRAINING
T
Raised stage with overhead arbor
PREPARED FOR
CLASS
CLASS
CLASS
ISSUE DATE: JUNE 11, 2013 PROJECT NUMBER: 06-1033-001-01-05 All drawings are preliminary and subject to change. © 2013 Hitchcock Design Group
DIAG./ CONF
Art station
OPS
CLASSROOM 126
Sensory plantings
GIRLS 106
Embankment slide
Chicago, Illinois
Play Environment - Concept 2 - Character Images
PSYCH 147
CLASS
Play Environment - Concept 1 - Character Images
TEAM
ROOM 1
Imagination / Storytelling stage
Ornamental grasses
Log crawl
OPS
CLASSROOM 128
CLASS
Sensory garden
TEAM
ORAGE 116 BOYS 108
CLASS
CLASS
CLASS
Leaf shape imprints
RECEP./ CLASS SW PSY PSY DIR WAITING Play Environment - Concept 2 - Character Images Malcolm X College
Raised garden beds
CLASS
Chicago, Illinois ISSUE DATE: JUNE 11, 2013 PROJECT NUMBER: 06-1033-001-01-05 All drawings are preliminary and subject to change. © 2013 Hitchcock Design Group
90
parent dropoff
PREPARED FOR
Moody Nolan
Breakout Group #2: Parent Support Center Configuration
4 HOLMES A
B 3 4 C
D 3
2 2
1 1
VISITORS • • •
L E C
STAFF
Varying paths for visitors, staff and Holmes community. Flip the Diagnostic/Conference Room with the Nurse’s Office. Nurse should be closer to the Main Corridor as well as the Outdoor play Courtyard Parent Training & Staff Center ideally located along Courtyard wall for children view.
The Team Room would ideally include: • IEP/OT Team • Speech Offices/Meeting place • Staff and Public toilets nearby • Printer/Copier • WiFi enabled • Place for (4) people
91
Breakout Group #3: Classroom and Support Spaces Configuration MUD ROOM P.O. T
INT. T.
T P.O.
P.O.
INT. T.
T
P.O.
T
ART SINK •
There should be a single toilet per classroom (inclusive of a changing table and storage for T diapers P.O. and clothes) P.O. T INT. T. • No occupancy sensor in toilet rooms • Divide up the Pullout Room to double as a ARTstorage room (for files, etc.) teacher • If all the support elements are moved to the corridor wall, the opposite wall can accommodate for windows; the wall between the two classrooms couldREADING begin to blur and students could SCIENCE utilize more program space.
92
•
• •
Relocate the Pullout Room to the corridor corner, creating a cubby nook. This area could create a “Mud Room” upon entry into the P.O.sequence INT. T. P.O. classroom (enter, put coats away, wash hands). Cubbies should be portable and adaptable. If the Toilet rooms move to the opposite corner, they can share a plumbing wall with eachother T sink. T and allow for an art The nook created between the Integrated Therapy room and the Toilet rooms could have a movable wall and allow students to utilize both classrooms
T
T
ART SINK
T P.O.
INT. T.
P.O. T
P.O. INT. T. P.O.
ART T SCIENCE •
• •
T
READING
By locating both the Toilet room and the Pullout room to the back corner, this area would allow for a supervised entry sequence as well as an Art Area, as plumbing would be in one location. The Science Area could form around the front corner, as the lighting would be ample for planting growth and study. The corner between the two classrooms could include a low bench, to create a quiet Reading Area.
L E C
•
• •
By moving the support spaces into the corners of the classrooms, there instantly become double the corners within the classroom. These corners make for ideal Learning Zones within the classroom. Small, medium and large spaces begin to form. If the center wall between classrooms were operable, students could not only move from one room to the next, but could observe activities within the opposite room.
93
PERSONS IN ATTENDANCE
Tony Rossi, Executive Director of Facilities & Operations, CCSD59 Patrick Brosnan, President, Legat Architects Robin Randall, Vice President, Legat Architects Paul Pessetti, Project Manager, Legat Architects Stephanie Marcan, Project Architect, Legat Architects Joyce Hanlon, Project Intern, Legat Architects ITEMS DISCUSSED
1. Tony Rossi (TR) stated that the Board Meeting on July 21st will consist of a statement of 2. Resolution,. The Design Team will not be required to fully present all elements developed during Schematic Design at this time. The Design Team should prepare a Floor Plan and Site Plan for presentation, along with a summary of progress thus far and steps taken since our last 3. presentation. If, in the event, that the Board approves Legat to proceed with full architectural services, they will proceed with a vote for bonds, followed by a secondary presentation of the full Schematic Design progress. 4. TR noted that the next meeting, following the Board Meeting, will be with Melissa, Veronica and himself to review the Schematic Design studies. The Design Team should come prepared with any specific questions regarding program organization and space configuration and the group will resolve the issues. Stephanie Marcan (SM) and Robin Randall (RR) reviewed the site plan, floor plan, building section and axons with the team. Legat should be prepared to present all the items noted above, along with a suggested axon of the learning spaces in particular (including furniture and “learning spaces� preliminarily defined.
94
MEETING MINUTES
Summary of a Progress Meeting held at 1:00 p.m., Wednesday, July 16, 2014 at Legat Architects. These notes record our understanding of items discussed and decisions made at this meeting. Please notify us within seven (7) calendar days of any necessary additions or corrections.
DESIGN PROGRESS
Site Plan: This plan will focus solely on the parking and drive improvements to the north and south. The site plan will better illustrate the demarcation between Holmes and the ELC. • The quantities of parking spaces should remain un-labeled until the Civil Engineer can confirm the required and final quantities. • The final parking space quantity will likely be between 60-70 new spaces • The east edge of the center Sensory Garden should show a clear wall between the courtyard and the field to the east. • Ideally, the site plan would show the Google neighborhood context. Floor Plan: This plan will focus in on the actual program spaces and the flow of activity, learning and staff spaces. • The program color and key should be included for clarity. • The corridor/circulation color should be something other than white for clarity (white reads as negative space rather than a portion of the building).
L E C
95
1. The floor plan was walked through in detail as there were comments and ideas incorporated from the Early Learning Design Workshop with staff. a. At the termination of each classroom corridor id currently shown an exterior monumental stair for gathering and presentation space. This would be accessed by doors to the exterior at the end of these corridors. These stairs allow for transition to the a lower grade, while creating a new learning/gathering space opportunity. Egress requirements will need to be explored fully prior to implementing this element completely. b. The classroom pairs now show an alternate Integrated Therapy, Toilet Room(s) and Breakout Space configuration as a result of the Design Workshop with staff. There was a desire to have two separate Toilet rooms, rather than a shared space. This will eliminate the potential for accidental locked doors on either side of the Toilet Room, after student use. It was noted that by code, we will be required to include doors into the Toilet Rooms, as food will be prepared and served within the Classrooms. The Design Team is also working through a way(s) to incorporate more corners within the Classroom to divide the space into designated learning spaces (resulting from relocating the Breakout Space into the front corner of the Classroom, rather than being located within the shared core space). This will result in 20 – 100sf rooms, rather than 10 – 120sf rooms. c. The Design Team will need to maintain the corridor along the east face of Holmes, as a decision has yet to be made regarding the potential renovation(s) within Holmes. d. The Multi-Activity and Indoor Play spaces are noted. TR asked if the exterior toilet room adjacent to the Outdoor Play space was necessary. This particular program element was a request from staff during the first Design Workshop. Currently, if a child needs to use the restroom, they will enter the building at the nearest Toilet Room. The same is true at the District 62 ELC. This should be reviewed with Melissa and Veronica. e. Both the Parent Support Center and the Motor Skills areas will need a closer look at the program configurations.
96
Building Section: This view begins to clarify the form intentions of the classroom bars. They will incorporate a canted south wall, sloped roof and high clerestory windows.
Building Isometric View: This view depicts the sloped roofs as well as the splay of the classroom forms. Some of the classroom roofs begin to extend and form shaded areas within the Outdoor Play and to the east of the Classroom bars.
NEXT STEPS
1. TR asked that the Design Team outline the plan for completing design and engineering for the early Site bid package in September. Patrick Brosnan (PB) noted that we will need to lock in our consultants in the next few days. The Design Team will then need to quickly lock in the floor plan. The design has not altered significantly in the last few weeks, as the floor plan is oriented and configured according to staff comments and program requirements.
L E C
97
2. A Kickoff Meeting with the Design Team and all consultants was scheduled on Wednesday, July 23rd at 11:00am at Nicholas & Associates office. Consultant arrivals should be staggered to be time-effective. 3. A Holmes Renovation Discussion Meeting was scheduled on Monday, July 21st at 10:30am at Holmes Junior High School. 4. LEED goals and possibilities were discussed. It was emphasized that the budget should be carefully monitored when considering LEED technologies and designs. If LEED design, registration and technologies can be achieved within the confines of the budget, the Design Team should explore this opportunity. PB to set up a meeting with Bob Romo from the Illinois Clean Energy Community Foundation to discuss grant-based opportunities. Robin Randall (RR) suggested a meeting prior with Vuk Vujovic with Legat to further research the grant opportunities. A meeting to review grant-bases sustainable design opportunities on Wednesday, July 30th at 1:00pm at the Oak Brook Legat office. Thank you.
98
L E C
99