TADEH_HAKOPIAN_BIM_VDC_SAMPLE_11X17_20170418

Page 1

TADEH HAKOPIAN BIM & VDC SAMPLE WORK


This portfolio contains samples of work done in VDC and BIM support roles in the AEC industry.

Examples include: ● ● ● ● ●

Laser Scanning and 3D point clouds Site Logistic Plans for construction phasing Navisworks coordination and clash detection Revit modeling Facilities lifecycle model process with parametric settings


FACILITIES BIM MODEL USE - VGG - LIFECYCLE & MAINTENANCE

LACCD Valley College Valley Glen Gateway Building 70,000 SF Educational Building Post-construction As-builts for the owner meant for Facilities use and BIM model data

Client wanted building models submitted to match the built conditions including equipment data for their facilities managers to review


FACILITIES MODEL USE- VGG - NAVISWORKS COORDINATION

Combined model – section of building displaying all construction and systems. These elements will appear in the facility models as a reference model.


FACILITIES MODEL USE - VGG – DESIGN AND COORDINATION

As-builts for the VGG project showing MEPF, Framing, Structure, Civil and Architecture models. All edited per COBIE standards


COBIE REQUIREMENTS FROM CLIENT - VGG

Top: Required fields from LACCD COBIE standards. COBIE is a method of exchanging data in BIM models. Bottom: Fields listed in Revit models. (to be completed). Each piece of installed equipment will have this field filled in the model.


REQUIREMENTS - VGG - SPACES

Top: Space plans from model. Spaces will establish schedule boundaries for generating in-place equipment information. Bottom: Section showing height clearance for space in a room. Each space needs to be fully enclosed to function properly.


REQUIREMENTS - VGG - SCHEDULES

Schedules created in spreadsheet format from model to provide equipment data. Each space or room will be in a schedule per trade showing all the equipment available as a sort of index. The schedules will be used as a reference to quickly sort through the availability of equipment and warranties in the model instead of a hard copy.


APPLICATION -VGG - EQUIPMENT

Facilities technicians can navigate the equipment in their buildings based on the provided model and data using tablets and software like Bentley Projectwise


SITE LOGISTICS PLAN - FIFTH & OLIVE

Site logistic plans are used in the construction industry to demonstrate the intent of the builder’s use of the project area. Explanation of excavation plan - these plans are submitted to the client and city to show how we meet construction operation guidelines


SITE LOGISTICS PLAN - FIFTH & OLIVE

Explanation of foundation plan - Construction equipment and street closures are depicted for city planning review


SITE LOGISTICS PLAN - FIFTH & OLIVE

Explanation of structure plan - Final phase of building and typical site conditions including adjacency of crane to nearby buildings


EXISTING CONDITIONS MODELING - FORD THEATRE

FORD THEATRE PROJECT

LOWER LEVEL AND OS2 BELOW STAGE

MEZZANINE LEVEL, STAGE AND LOADING AREA

NORTH BUILDING

John Anson Ford Theatre 30,000 SF, 1200 seat performance venue. $66 Million Renovation and Expansion. John Anson Ford Theatre renovation and expansion required modeling and coordinating a building about a hundred years old with many potential site issues. Modeling of project including the new building then Navisworks coordination reduced RFI.


EXISTING CONDITIONS MODELING - FORD THEATRE

Lower Level 01

Lower Level 03

3D image of the seating and stage Building plans updated from Architect’s drawings into a 3D BIM document which can then be used for coordination

Loading Dock level


NAVISWORKS COORDINATION - FORD THEATRE Ford Theatre Bim Coordination In Navisworks Remaining Issues Sign-off (Final) Meeting Pankow With Subconctractors

JAFT NAVISWORKS MODEL 01/13/16

MECHANICAL VS FIRE

MECHANICAL VS PLUMBING

ELECTRICAL VS FIRE

MECHANICAL VS ELECTRICAL

ELECTRICAL VS PLUMBING

PLUMBING VS FIRE

ALL TRADES VS AUDIO VISUAL

Remaining clashes are highlighted after 9 months of coordination in the building. Known issues that are left will be resolved in field.


NAVISWORKS COORDINATION - THE EDITION

Rendering of completed building.

Navisworks composite model.

The Edition - West Hollywood 300,000 SF, 13 floors and 148 hotel rooms. $300 Million New Construction. The Edition is built on a challenging site along Sunset boulevard. The tight constraints require constant coordination to make sure the building will be free of time consuming review meetings.


NAVISWORKS COORDINATION - THE EDITION

Typical hallway condition and equipment above and below.

Level 4 of the building. The section is an example of all the systems that are coordinated on the horizontal and vertical planes week to week.

Clash between a beam and HVAC equipment.


NAVISWORKS COORDINATION - THE EDITION

Clash between Mechanical and Electrical equipment. The building is still being coordinated and expected to meet a 2018 completion.

Vertical section through building showing core and parking structure.


NAVISWORKS COORDINATION - KAISER MURRIETA

Rendering of building entrance

Navisworks model John Anson Ford Theatre 80,000 SF, Healthcare building Design-build project fully coordinated between Architect, Engineers, General Contractor and Permitted before construction.


NAVISWORKS COORDINATION - KAISER MURRIETA

Kaiser Murrieta MOB had a 12 month completion time and coordination was vital. Section displaying building systems and equipment under roof.

Section showing Level 1 including work stations

Section of Level 2 with Exam rooms


NAVISWORKS COORDINATION - KAISER MURRIETA - MEPF

Combined MEPF model for the entire building - fully coordinated. Tolerances within half an inch are common throughout the tightly packed building. All of the structural, architectural, MEPF and interior systems were fully coordinated before construction.

Exploded Axon of each system, From top: HVAC, Plumbing, Fire, Framing, Structure, Electrical.


NAVISWORKS COORDINATION - KAISER MURRIETA - MEPF

Fire Suppression

HVAC / Mechanical

Electrical systems

Plumbing and Waste

Framing model

Structural Conxtech

After all the models were coordinated less than two dozen RFI’s reported during construction.


REALITY CAPTURE - EQUIPMENT

Scanner unit, Carrying case, Portable PC, Memory card Faro Focus 3D system is used together with Scene software to create 3D point clouds that record the existing environment of a given space. These point clouds can then be used to coordinate with a new set of changes with enhanced accuracy compared to traditional surveying methods.


REALITY CAPTURE IN OPERATIONS – CITY NATIONAL PLAZA NORTH TOWER (PAUL HASTINGS TOWER) Owner needed as-built survey to study sizing for new passenger elevator. Recorded levels 50-52 with Faro Scanner in 1 day.

Point Cloud Section of Composite scan from levels 50-52 in CNP North building.

Completed renovation of level 52.


REALITY CAPTURE IN OPERATIONS – CITY NATIONAL PLAZA NORTH TOWER (PAUL HASTINGS TOWER)

Sketchup model based on plans and scan of as-built are combined into a single model to preview changes.


REALITY CAPTURE – FORD THEATRE - AS-BUILT RECORDS

GRAY SCALE PHOTO OF SCANNED AREA OF OS2

3D MODEL OF THE SCAN IN NAVISWORKS SUPERIMPOSED ON CONCRETE MODEL TO BE USED AS A REFERENCE IN COORDINATION

SAME AREA AS ABOVE VIEWED IN 3D POINT CLOUD ENVIRONMENT

As an additional QA/QC measure to go above and beyond standard practices to make sure key areas were thoroughly coordinated. A 3D scan beneath the stage of OS2 was created. This allowed us to accurately locate openings for key MEPFS systems during coordination saving both time and money by allowing us to route systems to the correct locations and elevations per the scan.


REALITY CAPTURE – FORD THEATRE – AS-BUILT RECORDS

Left: Post-pour scan point cloud overlaid on Navisworks model. Aligning the point cloud and models accurately is essential to accurate coordination. Right: Equipment as modeled compared to as-built scan showing a clash between the concrete and pipes. Finding issues like these would be difficult without a point cloud of the existing conditions.


REALITY CAPTURE – FORD THEATRE – INFORMING MODELS

Left: Clash between modeled ducts and actual position of as-built catwalk supports compared to modeled supports. Modeled supports from design documents are shown to be inaccurate compared to the actual condition. Issue was noted and resolved before installation of large ducts. Right: Beam shown was added in after point cloud indicated where it should be. Prior to this there was no beam or it was assumed to be lower. Finding this issue early led to design revisions instead of waiting until installation was underway.


REALITY CAPTURE – FORD THEATRE – TOPOGRAPHIC DATA

South and North elevations of proposed sound wall compared to existing hillside captured from scan. These scans along with the model can help coordinate the project in areas of limited access.


IMPROVING CONCRETE FINISH RESULTS AT KAISER MURRIETA - SCAN SETUP Situation: Client requested an improved process from contractors showing floor flatness results. The solution was using point clouds and third-party apps to create a heat map of the concrete for easy readability.

3D scan capture of column with target. These targets are essential for aligning the scans to the elevation. The elevation is needed for accurate topographic results.

Photo from scanner displaying ground level. The scanner can take photos as well as 3D data. These photos are useful reference documents.


REALITY CAPTURE CONCRETE – PLANNING STAGES Next step is to plan out the scanning process. This scan takes place as the concrete is poured so timing is crucial.

Step 1 – Establish concrete pour plans

Step 2 – Create path of pour for crews

Step 3 – Create line of travel with scanner following pour path

Step 4 – Scan slabs for floor flatness and process results


REALITY CAPTURE - FINISHED CONCRETE - RESULTS

Heat map created with SCENE & Rithm App displaying concrete floor highs in red and lows in blue based on As-builts. Effort required: 4-8 hrs. Now the client has a complete topographic map of the concrete floor flatness of this project for ease of study. Kaiser was very satisfied with the results.


BIM PLANNING - EXECUTION PLANS AND PROJECT SETUP

ARCH BACKGROUNDS AUG/01 LOD MATRIX?

Clockwise from top: level of detail guide for modeling, level of detail matrix provided by each trade for their role in the project, flowchart for implementing models and documents for the bim portion of this project resulting in record models


BIM PLANNING - NAVISWORKS SETUP Typical Navisworks project setup. Each model is meant to be a record of coordination and a form of issue tracking.

1

2

1. MODELS BY TRAIDE AND DISCIPLINE LOADED INTO NAVISWORKS 2. MODEL VIEW AND NAVIGATION AREA – CONFLICTS ARE SHOWN HERE 3. VIEWPOINTS OF ISSUS/CLASHES ASSIGNED TO EACH TRADE – HISTORY OF CONFLICTS AND RESPONSIBLE PARTIES

3


SOFTWARE & APPLICATIONS - TRAINED AND APPLIED IN PRACTICE Here’s the set of software I use to get things done. It’s not an exhaustive list but most shown here I’ve used for years on dozens of projects.


TADEH HAKOPIAN Feel free to contact me if you have questions or requests: LINKEDIN: https://www.linkedin.com/in/thakopian/ EMAIL: thakopian@gmail.com PORTFOLIO: Standard: https://issuu.com/thakopian/docs/sample_portfolio_tadeh_hakopian_092112 Compact: https://issuu.com/thakopian/docs/tadeh_hakopian_revit_sample_2015030


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.