CYAN MAGENTA YELLOW B
CMYK
CMYK
CONSTRUCTION OBSTRUCTION
QING HUANG / THE ADVOCATE
ART DIRECTOR
gmorin.theadvocate@gmail.com
With construction ongoing in the middle of campus, students continue to find themselves adapting to the temporary footpaths to get around from classto-class. Business major Daniel Lee said, “Parking is a high commodity around here. I had to drive around the campus two times just to find a spot close enough to my class.” The approximately $52 million construction of the new three-story classroom building and student activities building, also call the Campus Center, began with the demolition of the 57-year-old Student Activities and Humanities buildings before the 2014 spring semester. Over the summer, Lathrop Construction, Inc. replaced pipes and sewer lines under Castro Street. The installation of these pipes over the summer was an “important” part of the construction since these pipes will be used SEE CONSTRUCTION, PAGE 3
WELCOME CENTER
Welcome/ Transfer Center now open College resource returns to CCC after three years BY Jared Amdahl
The foundation for the new Campus Center and the three-story classroom building will rise in the area soon, but are not due for completion until fall 2016. Students are forced to use alternate footpaths around the site to navigate the campus.
WEDNESDAY l 09.10.14 OUR 65TH YEAR CONTRA COSTA COLLEGE SAN PABLO, CALIF.
GYM ANNEX BUILDING
SQUAD DEFEATS CABRILLO IN FIRST GAME COMETS DOMINATE SEAHAWKS ON THE ROAD IN SEASON OPENER, 36-14
T PAGE 7
Enrollment drops by 1 percent in one year T PAGE 5
STAFF WRITER
jamadahl.theadvocate@gmail.com
In 2011, Contra Costa College eliminated its Transfer Center due to budgetary issues. But now, three years later, the newly installed Welcome/Transfer Center acts as an accessible source of information for students in need of help to become acquainted Resource with college revived life and transWelcome/ ferring. Transfer Center Doris Gray brought back, is just one of beneficial to the students student body. attending CCC who found herself in need of help registering for classes online. The first place she went was the Welcome/Transfer Center located in SSC-111 in the Student Services Center.
Two-story building receives overdue lift
CODY CASARES / THE ADVOCATE
A construction worker sits outside the Gym Annex Building on Monday. An external lift is being installed after spending years in planning limbo due to a lack of state funding.
Gym Annex meets federal law after 42 years BY Lorenzo Morotti EDITOR-IN-CHIEF
lmoroti.theadvocate@gmail.com
edit orial
PAGE 2
WOMEN’S SOCCER SEASON PREVIEWED
SEE CENTER, PAGE 3
T PAGE 6
Access to the north entrance of the Gym Annex Building, adjacent to Comet Stadium, is closed off as construction crews prepare to complete the installation of an external lift by December. Buildings and Grounds Manager Bruce King said the project, which will help students with mobility issues who are unable to navigate the stairs to reach the second floor, began on July 26 and must be completed before Dec. 25. Contra Costa Community College District Chief Facilities Planner Ray Pyle said that about a year ago the district hired Critical Solutions (CS), a project and construction management consultant firm, to help manage the various construction projects on campus. He said the district decided to bring CS on board when it became apparent the GA Building project was stagnated due to a lack of new funding from the state. CS assisted him with securing the $700,000
“
We will not take any shortcuts when it comes to student safety.” John Leary, on site Critical Solutions projects manager
total construction cost from funds left over from the passing of Measure A in 2006. After Pyle spoke with on site CS managers, Ron Johnson and John Leary, he said he feels assured that the lift project will be done prior to the December deadline. King said the development contractor, who won the bid at $500,000, B. Brothers is currently digging out the area where a foundation will be poured to secure the frame that will hold the prefabricated lift that is scheduled to arrive on Oct. 1. Leary said once supporting structure for the pre-fab lift is built and put into place, it would have to undergo three weeks of extensive testing by a Division of the State Architect inspector until it is deemed safe for student use. “We will not take any shortcuts when it comes to student safety,” he said. In the meantime, Athletic Director John Wade’s office, in GA-90, is located right next to the construction on the second floor of the building. He, along
with coaches, professors and students, has had to get used to taking routes around the construction site since July. King Wade said having only one exit and entrance available, on the south side of the GA Building, has caused confusion among students who are unfamiliar with the building’s layout. He said while the building has been crowded because of the construction site blocking foot traffic that normally would pass straight through the building, he has not heard any complaints. Men’s basketball coach Miguel Johnson said getting in and out of the GA Building, so far, has been not been much of an inconvenience. Finding an open parking space during the week, however, has been frustrating. Johnson said faculty parking has been impacted due to conSEE GA LIFT, PAGE 3
CMYK
BY George Morin
CYAN MAGENTA YELLOW B
CMYK